Post on 30-May-2018
8/14/2019 CRS Report : Earned Value Management
1/23
Order Code RL34257
Earned Value Management (EVM) as an OversightTool for Major Capital Investments
November 21, 2007
Clinton T. Brass
Analyst in Government Organization and ManagementGovernment and Finance Division
8/14/2019 CRS Report : Earned Value Management
2/23
Earned Value Management (EVM) as an OversightTool for Major Capital Investments
Summary
This report focuses on a technique earned value management (EVM) for
overseeing the cost, schedule, and performance of major capital investments duringthe investment process (e.g., information technology systems, structures, weaponssystems). EVM provides metrics to help inform assessments of whether capitalinvestments are on track from three perspectives: the investments planned cost,time schedule, and functionality. Variance from a projects planned cost, schedule,and functionality might occur due to the inherent complexity and uncertainty of aproject, poor planning or implementation, or, sometimes, simply bad luck. AlthoughEVM attempts to address several significant monitoring and evaluation issues, otherevaluation techniques are typically necessary in order to understand why variancefrom the planned cost, schedule, or functionality might be occurring. In addition,other evaluation methods are typically more useful in assessing other significantquestions, such as whether a project is worth undertaking (or continuing) and, afterthe investment process is completed, whether an investment might be having animpact on achievement of an agencys mission or the success of a public policy,compared with what would have happened without the investment.
EVM may be of increasing salience in executive branch practices and, implicitlyor explicitly, in presentations to Congress. This report begins by putting EVM withina broader context of risk management and how capital investments are oftenevaluated and monitored throughout their life cycles. Next, the report provides anoverview of EVM terminology and concepts by using an example and illustrating afew potential oversight issues and caveats. The report concludes with some potentialoversight questions for Congress. The report will be updated periodically.
8/14/2019 CRS Report : Earned Value Management
3/23
Contents
Oversight of Major Capital Investments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Managing Risks and Evaluating Projects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2Managing Risks of Adverse Events and Forgone Opportunities . . . . . . . . . . 2Monitoring and Evaluating Capital Investments . . . . . . . . . . . . . . . . . . . . . . 3
Increasing Executive Branch Adoption of EVM for Budgeting,Management, and Reporting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5Related Statutory Directives and Requirements . . . . . . . . . . . . . . . . . . . . . . 5Budget Formulation, Management, and Contract Management . . . . . . . . . . 6
Illustrative and Hypothetical Example of EVM Measurements and Issues . . . . . . 8Purpose of Example . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8Hypothetical Example: EVM for Project B . . . . . . . . . . . . . . . . . . . . . . . 10
Explanation ofPlanned Value . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Explanation ofEarned Value and Schedule Variance . . . . . . . . . . . . . 11Explanation ofActual Costand Cost Variance . . . . . . . . . . . . . . . . . . 12EVM as More Useful Tool than Simple Spend Comparisons . . . . . . . 14In Sum: EVM Metrics as Oversight Tools . . . . . . . . . . . . . . . . . . . . . 15
Caveat: EVM Metrics Might Tell Only Part of the Story . . . . . . . . . . . . . . 15
Potential Oversight Questions for Congress . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
List of Figures
Figure 1. Illustrative Activities and Evaluation MethodsDuring Phasesof a Capital Assets Life Cycle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
List of Tables
Table 1. Baseline Plan of Work Units, Project B1 . . . . . . . . . . . . . . . . . . . . . . 10Table 2. Schedule Variance of Work Units, Project B1 . . . . . . . . . . . . . . . . . . 11Table 3. Cost Variance of Work Units, Project B1 . . . . . . . . . . . . . . . . . . . . . 13Table 4. Spend Comparison of Work Units, Project B1 . . . . . . . . . . . . . . . . . 14
8/14/2019 CRS Report : Earned Value Management
4/23
1 For example, see U.S. Congress, Senate Committee on Homeland Security andGovernmental Affairs, Subcommittee on Federal Financial Management, GovernmentInformation, and, International Security,IT Programs at Risk: Is It Too Late to Save $12Billion? hearing, 109th Cong., 2nd sess., Sept. 7, 2006 (Washington: GPO, 2007).
2 This reports purpose is to provide an overview of EVM for a congressional audience andhighlight potential oversight issues, rather than provide a comprehensive overview of themechanics of EVM. Readers with questions about EVM terms, concepts, and proceduresare encouraged to consult with the author, who can answer questions and provide citationsto relevant resources.
Earned Value Management (EVM) as an
Oversight Tool for Major CapitalInvestments
Oversight of Major Capital Investments
For the federal government, capital investments include development andacquisition of major capital assets, such as equipment (e.g., hardware for weaponssystems, satellites, and information technology (IT)); structures (e.g., the CapitolVisitor Center); intellectual property (e.g., software); and combinations thereof. Acapital investment can play a critical role, therefore, in the accomplishment of agencymissions and the success of public policies. Congress has often taken a stronginterest in the performance, cost, and schedule of major capital investments. Inaddition, Congress has taken a strong interest in establishing and maintainingaccountability mechanisms to ensure that the President, Office of Management andBudget (OMB), and agencies fulfill statutory duties, accomplish prescribed publicpolicy goals, report transparently and fully, and act as careful stewards of publicresources.1
Earned Value Management (EVM), which is the subject of this report, is amanagement technique that provides metrics to help inform assessments of whethera capital investment is on track from three perspectives: planned cost, time
schedule, and functionality (the latter concept often referred to as performance,technical performance, capability, scope of work, or planned value). Usingthese three perspectives, EVM compares the planned cost, schedule, and functionalityagainst an (ideally) accurate measurement of what is actually happening.2
Frequently, EVM metrics serve to raise potential issues that require furtherinvestigation or study, rather than provide the full picture of a projects progress andstatus. EVM may be of increasing salience in executive branch practices and,implicitly or explicitly, in presentations to Congress. EVM might also be used as anoversight tool for Congress.
8/14/2019 CRS Report : Earned Value Management
5/23
CRS-2
3 Many years and millions of dollars can be wasted on a large project, with little or nothingother than frustration to show for the effort. For example, the Federal Bureau ofInvestigations (FBIs) Virtual Case File (VCF) IT project, part of the FBIs Trilogy ITinvestment initiative, was abandoned in 2005 after $170 million was spent. See ChrisStrom, FBI Solicits Proposals for New Information System, GovExec.com, Aug. 9, 2005,available at [http://www.govexec.com/dailyfed/080905c1.htm]; and U.S. Department ofJustice, Office of the Inspector General, The Federal Bureau of Investigations Managementof the Trilogy Information Technology Modernization Project, report 05-07, Feb. 2005,available at [http://www.usdoj.gov/oig/reports/FBI/a0507/final.pdf]. Even when a projecthas not necessarily failed, preventable cost, schedule, and performance problems can also
(continued...)
This report provides an overview of EVM terminology and concepts by usinga hypothetical example and illustrating a few potential oversight issues. To placeEVM in context, however, it is necessary to discuss first the risks associated withmajor capital investments, how capital investments are often evaluated andmonitored throughout their life cycles, and how EVM appears to be increasinglyadopted by executive branch agencies. After providing the hypothetical EVM
example and some related caveats, the report concludes with potential oversightquestions for Congress regarding EVM.
Managing Risks and Evaluating Projects
Managing Risks of Adverse Eventsand Forgone Opportunities
The planning and implementation of a major capital investment are not simpletasks. Consequently, major capital projects in both the public and private sectors are
considered to be inherently risky. For purposes of capital asset investment, riskmight be described as the probability that adverse events will occur or favorableopportunities will not be exploited. Unless a project is carefully managed, risk mightincrease substantially in both of these senses. Adverse events that might occurinclude schedule delays, cost overruns, and performance shortfalls or failures.Favorable opportunities that might not be pursued (or noticed) could include chancesto complete a project more quickly, at less cost, and with better than plannedperformance in achieving the mission or one or more goals. In response, agenciesmust make substantial efforts to plan effectively and manage risk in order to achievesuccessful outcomes. Given the complexity and inherent risk of major capitalinvestments, however, it should be noted that problems cannot always be avoided,
even in well-planned and implemented projects.
Many stakeholders including Congress, the President, agency employees, andthe public often take a strong interest in the performance, cost, and schedule ofmajor capital investments. The interest stems directly from the mission-criticalnature of many investments. Furthermore, interest in specific capital investments canbecome heightened when something has gone wrong. Indeed, the consequences ofa poorly managed capital investment project can be significant, and wheninvestments in major capital assets fail, they can fail spectacularly.3
8/14/2019 CRS Report : Earned Value Management
6/23
8/14/2019 CRS Report : Earned Value Management
7/23
CRS-4
5 In a capital investment context, monitoring and evaluation efforts are used to addressseveral challenges, including (1) identifying, analyzing, and proposing investmentopportunities that could improve performance of a policy or agency mission; (2) managing
risk during the capital investments planning, acquisition (and development), andoperational use; (3) facilitating learning, improvement, and achievement of requiredfunctionality during operational use, in support of a policy or agency mission; and (4)providing for transparency and accountability in achieving all of the above.
6 The phases are described (according to OMBs perspective) in U.S. Executive Office ofthe President, Office of Management and Budget, Circular No. A-11, Part 7, Planning,Budgeting, Acquisition, and Management of Capital Assets, July 2007; and Part 7,supplement, Capital Programming Guide, version 2.0, June 2006, both available at[http://www.whitehouse.gov/omb/circulars/a11/current_year/a11_toc.html]. Definitions ofprogram evaluation terms, techniques, and concepts can vary among authors. Nevertheless,some resources can provide initial assistance in understanding how techniques might applyto a capital investment context. See Sandra Mathison, ed.,Encyclopedia of Evaluation
(Thousand Oaks, CA: Sage, 2005); and Michael S. Lewis-Beck, Alan Bryman, and TimFuting Liao, eds., The Sage Encyclopedia of Social Science Research Methods (ThousandOaks, CA: Sage, 2004). Few publications provide an overview of EVM for non-practitioners. For background on EVM intended for a practitioner audience, see Alan Webb,Using Earned Value: A Project Managers Guide (Hants, UK: Gower, 2003). For answersto frequently asked questions about EVM (including a glossary of terms) intended mainlyfor U.S. federal government practitioners, see [http://www.acq.osd.mil/pm/faqs/faq.htm].For discussion of possible congressional roles concerning program evaluation, including aglossary of selected terms and concepts, see CRS Report RL33301, Congress and ProgramEvaluation: An Overview of Randomized Controlled Trials (RCTs) and Related Issues, byClinton T. Brass, Blas Nuez-Neto, and Erin D. Williams.
after disposal.5 Because EVM is intended to inform assessments of whether a capitalinvestment is on track with respect to planned cost, schedule, and functionality, EVMtakes place primarily during the acquisition process for a new asset (or modificationof an existing asset), but can also occur during planning. Figure 1 providesillustrative lists of capital planning and programming activities that agencies oftenundertake during each of the four phases of a capital investments life cycle. The
figure also shows corresponding lists of the monitoring and evaluation activities,including EVM, that are often used to support the agency activities.6
8/14/2019 CRS Report : Earned Value Management
8/23
CRS-5
7 This language was originally enacted in somewhat different form in Title V of the FederalAcquisition Streamlining Act of 1994 (FASA V; P.L. 103-355, 108 Stat. 3351) and was later
(continued...)
Source: CRS analysis.
Increasing Executive Branch Adoption of EVM forBudgeting, Management, and Reporting
Related Statutory Directives and Requirements
Concerns about project risks are not new, nor are efforts to mitigate risks ofmajor capital investments and prevent failures. For example, the first edition ofOMBs Capital Programming Guide for agencies was published in 1997. Before
then, Congress had enacted statutory provisions that were related to major capitalinvestments, including, among others, a provision amending the Federal Property andAdministrative Services Act of 1949 (41 U.S.C. 263(a)), which now declares that[i]t is the policy of Congress that the head of each executive agency should achieve,on average, 90 percent of the cost, performance, and schedule goals established formajor acquisition programs of the agency;7 provisions to require the Secretary of
Figure 1. Illustrative Activities and Evaluation MethodsDuring Phases of a Capital Assets Life Cycle
8/14/2019 CRS Report : Earned Value Management
9/23
CRS-6
7 (...continued)
amended to reach its present form by the National Defense Authorization Act for FiscalYear 1998 (P.L. 105-85, 111 Stat. 1851).
8 Originally enacted in FASA V; 108 Stat. 3349 (DOD), 3351 (civilian agencies); currentlycodified at 10 U.S.C. 2220 and 41 U.S.C. 263(a), respectively.
9 40 U.S.C. 11312(b)(6).
10 Ibid., p. 6.
11 U.S. Executive Office of the President, Office of Management and Budget, Circular No.A-11, Part 7, Sec. 300, p. 3. The cited standard is ANSI/EIA-748-A-1998, Earned Value
(continued...)
Defense and heads of all executive agencies to establish cost, performance, andschedule goals for major acquisition programs;8 and the Clinger-Cohen Act of 1996(P.L. 104-106, later codified and amended), which gave OMB and agencies explicitduties for monitoring the progress of information system investments. The dutiesincluded a requirement for agencies to
provide the means for senior management personnel of the executive agency toobtain timely information regarding the progress of an investment in aninformation system, including a system of milestones for measuring progress, onan independently verifiable basis, in terms of cost, capability of the system tomeet specified requirements, timeliness, and quality[.]9
Budget Formulation, Management, and Contract Management
OMB has issued a number of requirements and directions to executive agenciesthat specifically concern EVM. For example, OMB included in its Circular A-11 an annual document that communicates budget formulation and executionrequirements to agencies detailed directions for agencies to use EVM for major
capital assets (Part 7). Among other things, the circular directed agencies to submitan exhibit 300 (Capital Asset Plan and Business Case Summary) for each majorinvestment as part of their annual budget submissions to OMB, for the WhiteHouses use when formulating the Presidents annual budget proposal forcongressional consideration. The circular also said that an exhibit 300 is designedto coordinate OMBs collection of agency information for its reports to the Congressrequired by the Federal Acquisition Streamlining Act of 1994 (FASA Title V) andthe Clinger-Cohen Act of 1996.10 The circular defined EVM as follows, citing anindustry standard to which agencies would be expected to adhere:
Earned value management (EVM) is a project (investment) management tool that
effectively integrates the investment scope of work with schedule and costelements for optimum investment planning and control. The qualities andoperating characteristics of earned value management systems are described inAmerican National Standards Institute (ANSI)/Electronic Industries Alliance(EIA) Standard 748 1998, Earned Value Management Systems, approvedMay 19, 1998. It was reaffirmed on August 28, 2002. A copy of Standard 748is available from Global Engineering Documents (1-800-854-7179). Informationon earned va lue management sys tems i s ava i l ab le a thttp://www.acq.osd.mil/pm.11
8/14/2019 CRS Report : Earned Value Management
10/23
CRS-7
11 (...continued)Management Systems, approved May 19, 1998, reaffirmed Aug. 28, 2002, and is available
for purchase at [http://webstore.ansi.org/]. The standard provides, among other things, 32basic guidelines for companies to use in establishing an integrated Earned ValueManagement System (EVMS), and includes additional discussion as an aid inunderstanding and applying earned value management methods (pp. 3, 9).
12 U.S. Executive Office of the President, Office of Management and Budget, memorandumfrom Karen S. Evans, Administrator, Office of E-Government and Information Technology,Improving Information Technology (IT) Project Planning and Execution, M-05-23, Aug.4, 2005, available at [http://www.whitehouse.gov/omb/memoranda/fy2005/m05-23.pdf].
13 As explained later, the term baseline essentially refers to a capital investment projectsexplicitly planned costs, schedule for completion, and functionality.
14 The memorandum explained what was meant by independentas follows: An independent
assessment may be performed by a qualified source provided such source is not involved inthe projects development, implementation, management, or direct supervision. Providedthey are qualified, such source may include the agency Inspector General, currentindependent verification and validation reviewers, or any other source internal to the agencyor outside the agency including another agency. Agencies currently using IntegratedBaseline Reviews (IBRs), may substitute an IBR for an independent assessment.Reasonable baselines are accurate, relevant, timely, and complete. An IBR has beendefined as [a] joint Government/contractor review to assess the realism and accuracy of theintegrated performance measurement baseline (work, schedule, and budget) (see U.S.Department of Defense,Earned Value Management Implementation Guide, Oct. 2006, p.92, available at [https://acc.dau.mil/CommunityBrowser.aspx?id=19557]).
Citing room for improvement in the execution of our IT projects, OMB hasalso provided directions concerning major IT capital investments to agency ChiefInformation Officers in an August 2005 memorandum.12 The memorandum statedthat, at the time, agencies were already required to meet four principal criteria forIT capital investments. The criteria included, along with two others, (1) theestablishment and validation of a performance measurement baseline with clear cost,
schedule, and performance goals;13
and (2) the management and measurement ofprojects to within 10% of baseline goals through the use of an earned valuemanagement system compliant with the ANSI standard cited in Circular A-11. Thememorandum also added new expectations for agencies, including directions to (1)ensure that cost, schedule, and performance goals for new major IT projects areindependently validated for reasonableness before beginning development; and (2)provide, for all ongoing major IT projects with development efforts, for independentvalidations of then-current cost, schedule, and performance baselines by March 31,2006, and submission of proposed changes of baselines for OMB approval.14
EVM requirements have also been added to executive branch acquisitionregulations. On July 5, 2006, three agencies promulgated a final rule on behalf of theCivilian Agency Acquisition Council and the Defense Acquisition RegulationsCouncil to amend the Federal Acquisition Regulation (FAR). The stated purpose ofthe change was, among other things, to implement earned value management system(EVMS) policy in accordance with OMB Circular A-11, Part 7 and the supplementto Part 7, the Capital Planning [sic] Guide and help standardize the use of EVMSacross the Government for those parts of [an] acquisition where developmental
8/14/2019 CRS Report : Earned Value Management
11/23
CRS-8
15 U.S. Department of Defense, U.S. General Services Administration, and U.S. NationalAeronautics and Space Administration, Federal Acquisition Regulation; FAR Case 2004-019, Earned Value Management System (EVMS), 71 Federal Register38238, July 5, 2006.
16 OMB Circular A-11 says Development/Modernization/Enhancement (DME) means theprogram cost for new investments, changes or modifications to existing systems to improvecapability or performance, changes mandated by the Congress or agency leadership,personnel costs for investment management, and direct support (italics in original). OMBcontrasts DME with another term: Steady State (SS) means maintenance and operationcosts at current capability and performance level including costs for personnel, maintenance
of existing information systems, corrective software maintenance, voice and datacommunications maintenance, and replacement of broken IT equipment. See OMBCircular A-11, Sec. 53.
17 See [http://www.whitehouse.gov/results/agenda/standardsforsuccess08-2007.pdf] forExpanded Electronic Government scorecard criteria that explicitly cite EVM data. Forbackground on the PMA, see CRS Report RS21416, The Presidents Management Agenda:A Brief Introduction, by Virginia A. McMurtry.
18 For discussion, see CRS Report RL32388, General Management Laws: Major Themesand Management Policy Options, by Clinton T. Brass, section titled Making and MeasuringProgress, pp. 19-26.
effort is required.15 The FAR changes required agencies to use an EVMS for certainmajor acquisitions for development,16 in accordance with Circular A-11, andpotentially also for other acquisitions, in accordance with individual agencyprocedures. The new regulations also specified that [t]he qualities and operatingcharacteristics of an earned value management system are described in theANSI/EIA Standard 748 that was cited by Circular A-11 (see the extended Circular
A-11 quotation, above). Under the regulations, agency contracting officers weredirected to, at a minimum, require contractors to submit EVMS monthly reportsfor those contracts for which an EVMS applies.
In addition, OMB says it has used EVM data to determine agency scores underthe George W. Bush Administrations initiative concerning the management ofagencies in the executive branch the Presidents Management Agenda (PMA).17
Although the PMAs standards are publicly available, PMA evaluation practices havenot been fully transparent outside of OMB and the executive agencies.18 Detailedrationales and worksheets behind PMA scores are created, but not publicly availableor independently validated.
Illustrative and Hypothetical Example of EVMMeasurements and Issues
Purpose of Example
Based on published requirements, it appears that the Bush Administration andmost executive branch agencies are widely adopting EVM for major capital assets forpurposes of budgeting, management, and reporting. Specifically, as noted above,EVM has been formally adopted in requirements for preparation of the Presidents
8/14/2019 CRS Report : Earned Value Management
12/23
CRS-9
19 The Department of Defense (DOD) has maintained a website on EVM for many years,including a brief Illustrative Explanation of Earned Value, available at[http://www.acq.osd.mil/pm/faqs/evbasics.htm]. This reports adaptation draws somematerial verbatim from the DOD website. OMBs Circular A-11 and Capital Programming
Guide have also included a nearly identical example for a number of years (App. 3 of theCapital Programming Guide, and some previous versions of the circular). The definition ofEVM in Circular A-11 points to the DOD website ([http://www.acq.osd.mil/pm/]) as a placeto get [a]dditional information on EVMS.
20 EVM practices and terms often differ somewhat from project to project, agency to agency,and type of asset to type of asset. Therefore, the terminology and practices presented herewill not necessarily reflect terminology and practices for specific agencies, projects, or typesof assets. The underlying concepts, however, presumably apply across the board. Exactdefinitions of terms are available from a variety of sources, including Circular A-11, theDOD website, and the ANSI/EIA-748-A-1998, Earned Value Management Systems,standard.
annual budget proposal, agency contract management, and formal scoring criteriaunder the Administrations PMA initiative. It appears, therefore, that EVM metricswill be presented either implicitly or explicitly to Congress in a variety of venues,sometimes packaged along with the Presidents views and representations aboutbudgetary and management priorities. Due to the substantially public nature of thebudget process, the metrics will similarly be presented either implicitly or explicitly
to the public at large, some of whom play a significant role in the budget processthrough provision of information and opinions to elected officials.
It appears, therefore, that a potential ongoing issue for Congress will be judgingwhether underlying EVM metrics are fully, forthrightly, timely, and transparentlyreported. In addition, it appears that a corresponding issue for Congress might beunderstanding, interpreting, and scrutinizing EVM metrics, as potential inputs tocongressional oversight, appropriations of funds, and authorization (orreauthorization) of agency and presidential activities. In each of these situations,EVM information might be relevant to informing Congresss assessments of whetheracquisitions of major capital assets are on track with respect to planned cost,schedule, and functionality and, in turn, inform subsequent decision making.
With these considerations in mind, the following tables and corresponding textpresent a hypothetical example of EVM metrics being applied to the developmentand acquisition of a major capital asset. The purpose of explaining how EVM worksthrough an example, here, is to give concrete illustrations of the types of basicanalyses that can be performed with EVM, as well as to illustrate how EVM can beused to identify potential topics for follow-up investigation and study (e.g., perhapswith congressional oversight or complementary evaluations included in Figure 1).The type of asset described here could be any of those described at the beginning ofthis report, including a weapons system, satellite, structure, IT system, etc. Theexample presented here is adapted from an example that has been published in a
variety of forms for a number of years in federal government websites andpublications,19 but also draws on other resources, as noted below. Some EVM-related terms are italicizedand explained as they are introduced.20
8/14/2019 CRS Report : Earned Value Management
13/23
CRS-10
21 Depending on many factors, a major capital investments work units might be calledmodules, useful segments, components, or other terms. Some of these terms might havespecial definitions in some circumstances.
22 The work breakdown structure might also subdivide the work units listed here into smallercomponents.
23 The baseline is also sometimes referred to as the performance measurement baseline(PMB).
24 Because a project can be re-baselined by changing the plan for cost, schedule, andfunctionality, it is typically always important to be clear regarding what baseline is thesubject of discussion and also the reasons why a project might have been re-baselined.
25 The sum of all budgets established for the contract is sometimes referred to asBudget atCompletion (BAC).
26 The termplanned value is sometimes referred to asBudgeted Cost for Work Scheduled(BCWS).
Hypothetical Example: EVM for Project B
Explanation of Planned Value. For this hypothetical example, Congresshas been presented with EVM data about a major capital investment called ProjectB. The project has sixwork units, represented by the letters A through F, whichare interrelated, but distinct subcomponents of the project.21 For a simple example
relating to a structure, work units might include concrete, framing, roofing, electrical,plumbing, and interior. Collectively, work units A through F are also referred to asthe projects work breakdown structure (WBS).22 In this example, Project B hasbeen underway for a period of time already, and all the work units were planned tobe successfully completed by the time of this EVM report. The original plan forProject Bs costs, schedule for completion, and functionality is referred to as theprojects baseline, identified here as B1 (see Table 1).
23 Later in the life of theproject, it is possible that the project could be re-baselined (baselined again withnew cost, schedule, and functionality plans, in order to, for example, conform to amanagement decision or reflect new circumstances).24
Table 1. Baseline Plan of Work Units, Project B1
BaselineID
MetricWork Units of Project B
TotalA B C D E F
B1 Planned value ($) 10 15 10 25 20 20 100
To summarize the contents of Table 1, the baseline plan B1 for Project B shows thatsix work units (A-F) are planned to be completed at an overall cost of $100 for thetime period covered by this report.25 Each work unit is listed with its own plannedbudget that is, the amount of money that is planned to be spent to successfullybuild and complete the functionality planned for the work unit. Work unit D,therefore, is planned to be successfully completed within the time period covered bythis EVM report at a cost of $25, and work unit E is similarly planned to becompleted at a cost of $20. These numbers have a special name,planned value,26
that this report will also generically call a metric. (Other metrics will be introduced
8/14/2019 CRS Report : Earned Value Management
14/23
CRS-11
27 The term earned value is sometimes referred to asBudgeted Cost for Work Performed(BCWP).
as this section progresses.) In a sense, when the agency that is paying for Project Band the agencys contractor agree to plan that $25 will be spent to successfullycomplete work unit D, it could be said that the functionality that corresponds to workunit D has taken a monetary value of $25. Assigning work unit Ds functionality aquantitative value (denominated in dollars according to the planned budget for thatfunctionality), in turn, will allow a quantitative representation of how much of work
unit D may have been completed at any given point in time, as explained below.
Explanation of Earned Valueand Schedule Variance. Table 2 addstwo rows of EVM data, with two new metrics, to the previous table.
Table 2. Schedule Variance of Work Units, Project B1
BaselineID
MetricWork Units of Project B
TotalA B C D E F
B1 Planned value ($) 10 15 10 25 20 20 100
B1 Earned value ($) 10 15 10 10 20 - 65B1 Schedule variance 0 0 0 -15 0 -20 -35 = -35%
The first row of data in Table 2 shows the same planned value that was portrayed inTable 1 for Project B and its constituent work units, according to the projectsplanned baseline B1. Note that the planned value for Project Bs various work unitscontinues to sum to $100, the overall cost of the contract to the agency. The secondrow is new. This row is intended to show how much functionality has actually beensuccessfully developed by the date this EVM report was produced. Work unit A, forexample, is shown with an earned value (denominated in dollars) of $10. Thismeans that the functionality that was planned for work unit A has been successfully
completed or earned, and becomes earned value,27 not merely value that was planned.As work is successfully performed, therefore, it is earned on the same basis as it wasplanned. Stated differently, work unit A has earned the full functionality that wasplanned, and the work unit and overall project are, therefore, credited with $10 ofvalue that has been earned for purposes of work unit A.
Looking across the table, one sees similar situations with work units B, C, andE. In each case, the functionality that was planned for these work units has beensuccessfully and fully developed, or earned. Work units D and F, however, areanother story. Table 2 shows that work unit D was partially, but not fully,completed, and also that work unit F was never started. Only $10 worth of
functionality, out of work unit Ds planned value of $25, has been accomplished. Inother words, only 40% of the work associated with work unit D has been successfullycompleted, and 60% of the work has not been successfully completed. As a result,work unit D is said to have a schedule variance of -$15 ($10 earned value minus $25planned value equals -$15 schedule variance). With EVM, the term variance,therefore, implicitly means difference from the relevant plan (or baseline). The
8/14/2019 CRS Report : Earned Value Management
15/23
CRS-12
28 U.S. Government Accountability Office, Cost Assessment Guide: Best Practices forEstimating and Managing Program Costs, Exposure Draft, GAO-07-1134SP, July 2007, p.218. Contractor EVM reports often include explanations of the reasons for variances.
29 The term actual costis sometimes referred to asActual Cost of Work Performed(ACWP).
variance is denominated in dollar terms, because dollars (i.e., dollars of plannedvalue) represent the functionality that is planned to be developed and, eventually,either delivered or not delivered. With only $10 of earned value, work unit D is $15behind schedule, compared with the baseline B1 planned value of $25. Or,equivalently expressed in percentage terms, work unit D is 60% behind schedule.Because work unit F was never started, work unit F has a schedule variance of -$20,
and is 100% behind schedule. When work units A through F are summed, out of theplanned value of $100 for Project B, only $65 of the planned functionality has beensuccessfully developed, thanks to work units D and F falling behind schedule.Overall, Project B is therefore said to have an earned value of $65, $35 lower thanthe projects planned value, and is said to have a schedule variance of -$35, or inpercentage terms, a 35% schedule variance (i.e., 35% behind schedule compared towhat was planned to be accomplished). The 35% schedule variance might also beunderstood as a shortfall in the functionality that had been planned to be deliveredwithin the time period of the EVM report.
An explanation of why work units D and F were not successfully completed,however, is not captured with EVM data. To construct such an explanation, otherevaluation and monitoring methods from Figure 1 might need to be explored. Inaddition, it would probably be possible to use qualitative and quantitativeinformation from individuals involved in the project, and potentially also fromstakeholders, to construct interpretations of what might have caused the slip inschedule. As GAO has cautioned, [i]t is important to understand that variances areneither good nor bad. They are merely measures that indicate that work is not beingperformed according to plan and that it must be assessed further to understandwhy.28
The schedule variance metric discussed above (i.e., the difference betweenplanned value and earned value) only captures part of the overall story of Project B:
whether the project is on schedule or behind schedule. One has yet to look atwhether the project is on track with regard to its actual cost, in comparison to thebaseline B1. The question of whether Project B is on track with its planned cost isthe subject ofTable 3, below.
Explanation of Actual Costand Cost Variance. Table 3 presents twoadditional EVM metrics that are necessary to assess whether a project is experiencingcost overruns or coming in under budget compared to the baseline. For each workunit, the table compares the value of the functionality that was successfully delivered(earned value, which was discussed above) with the amount of money that wasactually spent to achieve that functionality (actual cost, the first of the two new
metrics).29
By subtracting the actual cost from the earned value, one calculates thesecond new metric: cost variance.
8/14/2019 CRS Report : Earned Value Management
16/23
CRS-13
30 Recall that in Tables 1 and 2, work unit A was planned to be delivered at a cost of $10,and therefore had a planned value of $10. Full delivery of that functionality would,therefore, result in $10 of earned value.
31 However, simply because a cost overrun has occurred does not necessarily mean the workunit or project was mismanaged. As discussed earlier in this report, many factors mightcause problems (cost overruns, schedule slips, and functionality shortfalls or failures) fora major capital investment.
32 Stated differently, work unit Ds overall planned value was $25, and the planned value of(continued...)
Table 3. Cost Variance of Work Units, Project B1
BaselineID
MetricWork Units of Project B
TotalA B C D E F
B1 Earned value ($) 10 15 10 10 20 - 65
B1 Actual cost ($) 9 22 8 30 22 - 91
B1 Cost variance 1 -7 2 -20 -2 0 -26 = -40%
Some illustrations provide intuition for understanding cost variance forindividual work units and also the overall project. In Table 3, the first row of EVMdata shows that work unit A was successfully delivered, creating earned value of$10.30 The second row of EVM data shows that the actual cost of work unit A wasonly $9, or $1 under the earned value. Subtracting the $9 actual cost from the $10earned value results in a $1 cost variance. A positive number for cost variance,therefore, means something was delivered under budget. Work unit C similarly camein under budget, as shown by its positive cost variance.
Work units B, D, and E, by contrast, show that cost overruns have occurred.31
A negative cost variance means that a work unit (or portion of a work unit) wasdelivered over budget: more money was spent for the work successfullyaccomplished than was planned. To achieve the full functionality that was deliveredfor work unit B (represented by the work units earned value), the actual cost was$22, considerably higher than the original budget (planned value). The cost variancefor work unit B is -$7, representing a cost overrun. In percentage terms, the costoverrun can be calculated by dividing the cost variance (i.e., -$7, the excess amountspent over the budgeted amount) by the earned value (i.e., $15, the value of thefunctionality that was delivered). The cost overrun was, therefore, nearly -47%.
For work unit D, the picture looks even worse. In developing the functionalityrepresented by $10 of earned value (only a portion of the hoped-for functionalityrepresented by $25 in planned value), the actual cost was $30. That is, only 40% ofwork unit Ds planned functionality was delivered successfully, but at a cost thatexceeded the budget for the entire work unit. Work unit Ds cost variance is -$20($10 earned value minus $30 actual cost), or -200%. The intuition behind the -200%figure is as follows. Only a portion of work unit D was successfully delivered (i.e.,$10 out of work unit Ds overall planned value of $25 was successfully delivered,becoming $10 in earned value).32 Looking at work unit D, overall, the portion of the
8/14/2019 CRS Report : Earned Value Management
17/23
CRS-14
32 (...continued)the work that was successfully completed was $10.
33 A 200% cost overrun means that costs were triple what was planned, a 100% cost overrunmeans that costs were twice what was planned, etc.
34 A portion of a work unit has a planned value, therefore, that is only a portion of the workunits overall planned value.
35 See [http://www.acq.osd.mil/pm/faqs/evbasics.htm].
work units functionality that was delivered successfully ended up costing three timesmore than what was planned ($30 actual cost instead of $10), which is a 200%overrun for that portion of work unit D that was successfully completed.33
Finally, one might assess work unit F. Because work unit F was not started, nomoney was spent on the work unit, resulting in a cost variance of zero.
Looking at Project B overall, in terms of its B1 baseline, the earned value for themajor capital investment is $65 (nearly two-thirds of the planned functionality). Inachieving $65 in earned value, however, $91 was spent. Stated differently, theportion of the overall project that was performed successfully (i.e, the $65 earnedvalue) was, by definition, originally planned to cost $65 (i.e., the portion had aplanned value of $65), but in the end, was completed at an actual, overall cost of$91.34 These metrics result in an overall cost variance for the project of -$26 (earnedvalue of $65 minus an actual cost of $91), or exactly -40% (-$26 cost variancedivided by the earned value of $65). Project B, therefore, could be said to haveexperienced a 40% cost overrun on the capability that has been successfullydelivered. The capability that was successfully delivered in the time period of theEVM report, in turn, was substantially less than the capability that was planned to bedelivered in the time period (-35%, the schedule variance, which shows a scheduleslip and corresponding functionality shortfall).
EVM as More Useful Tool than Simple Spend Comparisons. EVMtutorials often compare EVM metrics with an oversight tool that is often considerednot useful: the spend comparison.35 The typical spend comparison approach,whereby contractors report actual expenditures against planned expenditures, isunrelated to the functionality that was successfully delivered (see Table 4).
Table 4. Spend Comparison of Work Units, Project B1
BaselineID
MetricWork Units of Project B
TotalA B C D E F
B1 Planned spend ($) 10 15 10 25 20 20 100
B1 Actual spend ($) 9 22 8 30 22 - 91
B1 Spend variance 1 -7 2 -5 -2 20 9 = 9%
Table 4 shows a simple comparison of planned spending and actual spending,which is unrelated to work performed and, therefore, potentially misleading and not
8/14/2019 CRS Report : Earned Value Management
18/23
CRS-15
36 See [http://www.acq.osd.mil/pm/faqs/evbasics.htm].
37 A large number of other EVM metrics are used to manage projects and contracts and arenot discussed in this report. See the third question and answer at [http://www.acq.osd.mil/pm/faqs/faq.htm] for more information.
a very useful comparison. The fact that the overall amount spent was $9 less thanplanned for this period is not useful for most purposes, because the metrics lackcomparisons of spending with the functionality that was successfully delivered.
In Sum: EVM Metrics as Oversight Tools. Considered together, Tables1, 2, and 3 cover central aspects of EVM: comparing the planned cost, time schedule,
and functionality for a major capital investment against the actual cost, timeschedule, and functionality of what was successfully delivered. Many observersemphasize that EVM might help facilitate the correction of problems during theinvestment process. For example, as one prominent federal agency website asserts,from a practitioner perspective, [t]he benefits to project management of the earnedvalue approach come from the disciplined planning conducted and the availability ofmetrics which show real variances from plan in order to generate necessary correctiveactions.36
Another potential benefit of EVM, from an oversight perspective, is to providea picture of the status of a major capital investment at a snapshot in time. EVM
calculations might enable project managers, contractors, program managers,overseers, and outside stakeholders to see quickly and simply whether or not a projectis on track with its baseline plan. A negative schedule variance or cost varianceindicates a schedule slip or cost overrun, whereas positive variances indicate a projectis ahead of schedule or under budget. EVM metrics might, thereby, suggest the needfor additional analysis in targeted ways to explain the root causes of problems andwhat could be done, if anything, to get a project back on track,37 or even provideevidence of more fundamental management, resource, and oversight problems. EVMmetrics do not, however, necessarily tell the whole story, as discussed below.
Caveat: EVM Metrics Might Tell Only Part of the Story
The story that EVM tells can be a significant one. Once the basic jargon andconcepts of EVM are understood, EVM provides a visually simple picture, on aperiodic basis, of whether or not a project is on track with plans. For oversightpurposes, EVM can thereby flag outliers and signal the potential need to ask furtherquestions. The prospect of this scrutiny might, in turn, provide incentives to OMBand agencies to, among other things (1) closely monitor the progress of major capitalinvestments; and, more fundamentally, (2) build the capacity (e.g., resources, staff,skills, management attention and discipline, and processes) for OMB and agenciesto properly manage investment-related activities and evaluations.
Nonetheless, without further evaluation of a project, EVM metrics might tell
only a partial story. For example, even when EVM metrics are accurately capturedand portrayed, the metrics typically will not reveal why a project might beexperiencing schedule or cost variances. A process or implementation evaluationmight be necessary to address such questions (e.g., to verify and complement
8/14/2019 CRS Report : Earned Value Management
19/23
CRS-16
38 Independent validation of cost, schedule, functionality, and benefit estimates might bolsterthe confidence of some estimates, albeit with additional cost to perform any suchevaluations.
39 For more on perverse incentives, see Steve Kerr, On the Folly of Rewarding A, WhileHoping for B,Academy of Management Journal, vol. 18, no. 4, 1975, pp. 769-783.
explanations that are provided by contractors). In addition, other evaluation methods(see Figure 1) are typically used to assess other significant and, sometimes, morefundamental questions, including (1) whether a project is worth undertaking (orcontinuing); and (2) after the investment process is completed, what impact aninvestment might be having on achievement of an agencys mission or the successof a public policy, compared to what would have happened without the investment.
In addition, a projects baseline plan and corresponding EVM data might notaccurately represent the cost and schedule that are most likely necessary for a projectto achieve a particular functionality. Cost, schedule, and functionality plans are, ofcourse, made in the context of complexity and uncertainty, which oftentimes canguarantee that a capital investment project will not proceed according to plan.Alternatively, estimates of a projects costs, schedule, functionality, and benefitsmight be based on insufficient research and analysis.38 Furthermore, the use ofmetrics can create powerful incentives, including perverse incentives.39 One projectmanagement reference presents a humorous and skeptical, albeit seriously intended,scenario to caution against too quickly accepting EVM metrics at face value as
accurate representations of the full picture. The scenario is worth excerpting atlength not as a portrayal of what is typical but rather as an illustration of anoverseer interpreting EVM metrics; thinking about incentives; and confronting theissue of what a reasonable plan should be for a projects cost, schedule, andfunctionality. Specifically, the author posits a scenario showing a
project is [quite substantially] ahead of schedule and underspent.... At firstglance, this looks wonderful. But ask yourself how the variance happened.There are three possible explanations for how this project manager achieved theresults shown:1. Actual labor [costs] were considerably lower than expected and/or the
people were more efficient than anticipated.
2. The project team had a lucky break. The team had expected to have towork really hard to solve a problem, but it turned out to be very easy.3. The project manager sandbagged his estimates. He padded everything,
playing it safe.If you believe situation 1, you will believe anything. It is unlikely that both
variances would happen at the same time. Situation 2 happens occasionally.When all the planets are aligned about once in a zillion years, you say. Youbet!
Situation 3 is the most likely explanation. The project manager was playingit safe. And he would tell you that there is no problem. After all, if he continuesalong this course, the project will come in ahead of schedule and underspent,which means a manager will give money back to the company. No problem.
But is that true? First of all, I can almost guarantee that the project
manager wont give any money back. He will find a way to spend it byadding bells and whistles to the project, by buying unplanned equipment and
8/14/2019 CRS Report : Earned Value Management
20/23
CRS-17
40 James P. Lewis, The Project Managers Desk Reference, 2nd ed. (Boston: McGraw-Hill,2000), pp. 208-211.
supplies, or by throwing one huge party! No sane project manager wants to givethe money back, because he knows that his next project will be cut.
However, suppose the manager did give back the money. Would that beokay? No. The reason is that the organization would have lost the opportunityto use the money to fund some other project.... But the money is available. It istied up in the under-budget project. If that project were rescheduled andrebudgeted, the money would be available to keep the other project going,
assuming that the [return on investment] is still justified.The question is, naturally, What is reasonable? We certainly cannot
expect to have zero variances in a project. And this is true. It all depends on thenature of our [commercial sector] business. Well-defined construction projectscan be held to very small tolerances as small as plus-or-minus 3 to 5 percent.Research and development projects are likely to run higher tolerances, perhapsin the range of 15 to 25 percent. Each organization has to develop acceptabletolerances from experience.40
Whether the authors scenario and rules of thumb are fully applicable to federalgovernment projects generally, much less in specific policy and technology domains,is debatable. Nevertheless, his scenario illustrates some of the psychological and
implementation phenomena that might be at play in the context of major capitalinvestments. In a federal government context, phenomena like these might be at playwith any participating actor (e.g., advocate, critic, project manager, funder,contractor, overseer) at any point in the process of researching, proposing, funding,executing, operating, and evaluating major capital investments.
For example, who says the budget and planned functionality corresponding toa proposed project are accurate? What analyses are the judgments based upon? Arecost and benefit estimates reasonable? Who might have the capacity andindependence to make such an assessment? Do agencies, inspectors general, orOMB have the staff resources to perform adequately the necessary analytical and
monitoring tasks for major capital investments? Are the President, politicalappointees, and career civil service executives making decisions based on, or in spiteof, reasonable and objective analysis and monitoring? What are the real reasons aproject is under or over budget, or ahead of or behind schedule? How much scrutinyis too much? What perverse incentives and consequences might be created whenproject managers make good faith attempts to estimate costs, schedules, andfunctionality, but variances inevitably occur, perhaps due to uncertainty or bad luck,bringing high levels of distracting scrutiny to a project and its sponsoring agency oragencies?
Questions such as these are difficult to answer, but suggest that answers and
corresponding lessons might be learned for specific policy areas and types ofinvestments over time and with experience. This observation raises two furtherquestions. For each type of actor involved in planning, funding, implementing,evaluating, and overseeing major capital investments (e.g., project managers,program managers, political appointees, career executives, congressional staff,Members of Congress, and the President), what are the necessary prerequisites to
8/14/2019 CRS Report : Earned Value Management
21/23
CRS-18
41 For background on that law, see CRS Report RL33680, The Federal FundingAccountability and Transparency Act: Background, Overview, and Implementation Issues ,
by Garrett L. Hatch.42 For discussion intended for the federal audit community, see U.S. GovernmentAccountability Office, Cost Assessment Guide: Best Practices for Estimating and ManagingProgram Costs, Exposure Draft, GAO-07-1134SP, generally and also chap. 18.
43 See U.S. Presidents Council on Integrity and Efficiency, U.S. Executive Council onIntegrity and Efficiency, Fiscal Years 2006 and 2007 Assessments of Federal AgenciesExhibit 300s: A Compilation Prepared for the Office of Management and Budget, Mar.2007, available at [http://www.ignet.gov/randp/rpts1.html]; and U.S. GovernmentAccountability Office,Information Technology: Agencies Need to Improve the Accuracy
(continued...)
learning these lessons from experience? That is, what capacities and processes needto be in place in order to learn from experience? How many of these prerequisitecapacities and processes are currently in place?
Potential Oversight Questions for Congress
Major capital investments give rise to many actual or potential issues forCongress. Issues that are potentially related to EVM are a significant subset of thislarger picture. With the increasing emergence of EVM as a tool for gauging thestatus and progress of major capital investments, potential congressional oversightissues appear likely to continue emerging, as well. This report culminates with asampling of potential oversight questions for Congress that draw on the report andother resources, as noted.
! In light of what appears to be more widespread adoption of EVMpractices for major capital investments by executive agencies and
their contractors, what might be the advantages, disadvantages,costs, and benefits of legislatively requiring more formal, periodic,and publicly accessible agency reporting of EVM metrics for some,most, or all major capital investments?
! To what extent might recent congressional efforts to increase budgetand financial transparency for example, the establishment of asearchable website for federal contracts and grants required by theFederal Funding Accountability and Transparency Act of 2006(FFATA; P.L. 109-282; 120 Stat. 1186) be viewed as anillustration of what could be done with EVM information?41 What
would be the advantages and disadvantages?
! The usefulness of EVM metrics depends upon the quality andreliability of the cost, schedule, and functionality data that underlieboth a projects baseline plan and its reports on work performed.42
Given concerns that have been raised about the quality of agencycapital investment business cases that are used to justify budgetrequests,43 as well as concerns that have been raised about the quality
8/14/2019 CRS Report : Earned Value Management
22/23
CRS-19
43 (...continued)and Reliability of Investment Information, GAO-06-250, Jan. 2006.
44 For example, see U.S. Department of Education, Office of Inspector General,Effectiveness of the Departments Financial Management Support System Oracle 11i Re-Implementation, ED-OIG/A11F0005, June 26, 2007, available at [http://www.ed.gov/about/offices/list/oig/auditreports/a11f0005.doc].
45 U.S. Chief Information Officers Council, Information Technology (IT) WorkforceCapability Assessment Survey (2004), Analysis of Survey Results, Dec. 2004, available at[http://www.cio.gov/index.cfm?function=specdoc&id=545&category=11].
of agency project management,44 what might be options for Congressto cause OMB and agencies to improve any deficiencies in theunderlying analyses and data that support capital investment decisionmaking and reporting?
! What might be the advantages and disadvantages of requiring
independent, publicly accessible assessments includingverification and validation, as appropriate of the underlyingquality of EVM data, including cost estimates and assessments ofthe functionality that is delivered in comparison with what wasplanned?
! What might be the advantages and disadvantages of requiringindependent, publicly accessible assessments of the capacity ofagencies to manage the capital planning and investment control(CPIC) process (e.g., agency capacity to research, formulate, plan,propose, develop, report on, operate, and evaluate major capitalinvestments), which is arguably more fundamental as a driver ofEVM data quality? Would assessments of key capabilities beamenable to systematic oversight through the use of scorecards,similar to those used under the Bush Administrations PresidentsManagement Agenda, albeit with transparency outside the executivebranch and independent validation? To the extent that OMBcurrently identifies gaps in agency capabilities, to what extent doannual budget requests (submitted to Congress by the President) andperformance plans (produced by agencies under the GovernmentPerformance and Results Act of 1993, or GPRA; P.L. 103-62)address the gaps?
! Processes that support the capital investment process includingdevelopment of capital investment business cases, projectmanagement, EVM, contract oversight, management auditing, andevaluation depend for success, in large part, upon adequate staffand skill resources in agencies.45 Have agencies allocated sufficientstaff and financial resources to successfully undertake major capitalinvestments? How might such judgments be made? Also, doagencies have sufficient ability to recruit, retain, and train personnelin disciplines including project management, risk management,contract management and oversight, information technology, and
8/14/2019 CRS Report : Earned Value Management
23/23
CRS-20
program evaluation? If so, what are their track records in recruiting,retaining, training, and allocating staff in sufficient number andcompetency in the management and oversight of major capitalinvestments? If not, what could be done?
! What might be the advantages, disadvantages, costs, and benefits of
applying EVM-related requirements to major capital investments, asappropriate, pursued by agencies in the legislative and judicialbranches?