Post on 19-Jan-2015
description
POWERPOINT PRESENTATIONAND REPORT
Alena Homes LTD8 Ohaupo rd
Glenn Hurren
Introduction
Site Plan
Floor Plan
Elevation
Setting Out and Excavationo Strip site of all
vegetation o Extra fill to form the lay of the siteo Setting out of the:
o Location of building o Position from Boundary
o Placing of piles
o Done by erecting timber profiles (min. of 0.9m from building) and using string lines
o Floor plan
Foundations
o 6 meter driven timber piles of specific engineering design
o Transmits loads from the building to the ground
o Resist horizontal and vertical loads acting on a building
o Supports the concrete slab floor and building to prevent settlement.
Formwork and the Concrete Slab
o Temporary timber formwork to the perimeter of the slab.o DPM used as a moisture barrier between the soil and concreteo Reinforcing steel is laid to prevent cracking and improve the ability of the concrete to resist tensile stress. o Bar chairs to hold reo in placeo Edges of slab are thicker to form a footing
o 100mm thick floor slabo Power float finish
Wall Framing
o DPC to btm plate to act as moisture barrier between the concrete floor and timber
o 90x45mm H1.2 treated timber
o Temporary timber bracing to support the framing during construction and to prevent the framing from deforming o M12 bolt fixing to btm plates with additional fixing anchors on external walls o 140 x 35
extra top plate
Roof and Ceiling Framing
o SED roof trusses made up of H1.2 treated timber
o Roof design is a combination of a gable and hip roof
o Trusses braced with diagonally opposed metal straps fixed to top chords
o Purlins span across trusses and provide a surface for roof cladding o Ceiling battens fixed to bottom chord and provide surface for ceiling linings to fix to
Closed In – Roof and Wall Claddings
o Cladding underlay fixed externally to framing as backup to cladding from moisture and water
o NZBC requires that roofing underlay be used under all metal roof claddings
o Hardies Weatherboard cladding to walls with 150x25 H3 timber to form all external corners and facing boards
o Corrugated coloursteel longrun fixed roofing to resist weather conditions
Insulation and Ceiling Lining
o Plumbing and wiring is completed within frames before interior is lined
o R1.8 Batts to walls
o R2.2 Rocwool to ceilings
o Insulation holds the warmth within a room by resisting the transfer of heat
o 13mm Gib Board screw fixed to all ceilings
o Back blocking to sheet end joints
Wall Lining and Bracingo Internal linings provide
fire protection, protection to the framing, wall bracing and also helps contain heat
o 9.5mm GIB Board to wallso 9.5mm Aqualine GIB Board to bathroom walls
o GIB Braceline wall bracing sheet fixed per designers calculations
o Skirting – Colonial 92mm No.1 Pine
o 90 mm Gib-Cove
References
Helen Fenwick and Alena Home Team Nathan Collins Paul Robertshaw
Special Thanks To
http://www.gib.co.nz http://www.branz.co.nz NZ/S 3604 http://www.google.co.nz