Construction methods for small buildings

Post on 19-Jan-2015

658 views 1 download

description

Construction for small buildings of timber design

Transcript of Construction methods for small buildings

POWERPOINT PRESENTATIONAND REPORT

Alena Homes LTD8 Ohaupo rd

Glenn Hurren

Introduction

Site Plan

Floor Plan

Elevation

Setting Out and Excavationo Strip site of all

vegetation o Extra fill to form the lay of the siteo Setting out of the:

o Location of building o Position from Boundary

o Placing of piles

o Done by erecting timber profiles (min. of 0.9m from building) and using string lines

o Floor plan

Foundations

o 6 meter driven timber piles of specific engineering design

o Transmits loads from the building to the ground

o Resist horizontal and vertical loads acting on a building

o Supports the concrete slab floor and building to prevent settlement.

Formwork and the Concrete Slab

o Temporary timber formwork to the perimeter of the slab.o DPM used as a moisture barrier between the soil and concreteo Reinforcing steel is laid to prevent cracking and improve the ability of the concrete to resist tensile stress. o Bar chairs to hold reo in placeo Edges of slab are thicker to form a footing

o 100mm thick floor slabo Power float finish

Wall Framing

o DPC to btm plate to act as moisture barrier between the concrete floor and timber

o 90x45mm H1.2 treated timber

o Temporary timber bracing to support the framing during construction and to prevent the framing from deforming o M12 bolt fixing to btm plates with additional fixing anchors on external walls o 140 x 35

extra top plate

Roof and Ceiling Framing

o SED roof trusses made up of H1.2 treated timber

o Roof design is a combination of a gable and hip roof

o Trusses braced with diagonally opposed metal straps fixed to top chords

o Purlins span across trusses and provide a surface for roof cladding o Ceiling battens fixed to bottom chord and provide surface for ceiling linings to fix to

Closed In – Roof and Wall Claddings

o Cladding underlay fixed externally to framing as backup to cladding from moisture and water

o NZBC requires that roofing underlay be used under all metal roof claddings

o Hardies Weatherboard cladding to walls with 150x25 H3 timber to form all external corners and facing boards

o Corrugated coloursteel longrun fixed roofing to resist weather conditions

Insulation and Ceiling Lining

o Plumbing and wiring is completed within frames before interior is lined

o R1.8 Batts to walls

o R2.2 Rocwool to ceilings

o Insulation holds the warmth within a room by resisting the transfer of heat

o 13mm Gib Board screw fixed to all ceilings

o Back blocking to sheet end joints

Wall Lining and Bracingo Internal linings provide

fire protection, protection to the framing, wall bracing and also helps contain heat

o 9.5mm GIB Board to wallso 9.5mm Aqualine GIB Board to bathroom walls

o GIB Braceline wall bracing sheet fixed per designers calculations

o Skirting – Colonial 92mm No.1 Pine

o 90 mm Gib-Cove

References

Helen Fenwick and Alena Home Team Nathan Collins Paul Robertshaw

Special Thanks To

http://www.gib.co.nz http://www.branz.co.nz NZ/S 3604 http://www.google.co.nz