Case Studies. Centrica York Module. Client : Heerema Fabrication Duration: In progress Services : Onshore and Offshore access utilising scaffolding, roped access to facilitate the painting of the module and jacket. Location: Hartlepool. Arklow Wind Farm. - PowerPoint PPT Presentation

Transcript of Case Studies

Case Studies

Centrica York Module

Client: Heerema FabricationDuration: In progressServices: Onshore and Offshore access utilising scaffolding, roped access to facilitate the painting of the module and jacket.Location: Hartlepool

Arklow Wind Farm

Client: Smulders BV Arklow Offshore Wind Farm. Duration: Feb – August 2008.Services: Specialist scaffolding to support the coatings refurbishment of the main towers belonging to the Arklow Offshore Wind Power Farm.Location: Irish Sea, 10km off the east coast of County Wicklow, Republic of Ireland. All materials were transported to and from the Arklow using special shallow draught vessels.

During

Before

After

Sheringham Shoal Modules

Client: Heerema FabricationDuration: 2010 - 2011Services: Scaffolding, painting and containment of two (2) substation platform topsides belonging to the Sheringham Shoal Offshore Wind Farm. Situated 17 – 23 km north of the Norfolk coast.Location: Hartlepool and Greater Wash.

Walney Island

Before

After

Client: ArevaDuration: 2010 - 2011Services: Utilising roped access to facilitate the complete re preservation of coatings, situated 15 km off Walney Island, Cumbria.Location: Irish Sea.

Greater Gabbard

Client: Heerema FabricationDuration: 2010 - 2011Services: Utilising roped access to facilitate painting, situated 25 km off Suffolk coast.Location: North Sea.

Centrica Ensign

Client: Heerema FabricationDuration: 2010 - 2011Services: Onshore and Offshore access utilising scaffolding, roped access to facilitate the painting of the module and jacket. Situated 80 km east of the Norfolk coast.Location: North Sea.

BP Andrew Module

Client: Heerema FabricationDuration: In progressServices: Onshore and Offshore access utilising scaffolding, roped access to facilitate the painting of the module and jacket.Location: 230 km NE of Aberdeen