Post on 19-Jan-2016
description
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
1
Capacity Development for CDM
General Description of the Project Cycle
Tunis, 27-29 August 2004
Samir Amous, APEX, TunisiaSamir Amous, APEX, TunisiaRegional Centre for North Africa and Middle-EastRegional Centre for North Africa and Middle-East
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
2
1. Project identification & formulation
CDM Project cycle
2. National approval
P.D.Document
OE (A)
3. Validation / registration
4. Project financing & implementation
5.Monitoring
6. Verification /Certification
7. Issuance of CERs
Investors
Project participants
EB registry
Ver & Cert reportRequest for CERs
Monitoring Report
OE (B)
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
3
1. Project design& formulation
Step 1
ACTIONS-Project identification- project description- baseline methodology- GHG emissions- monitoring methods/plan- SD impacts- statement of env. impacts- stakeholder comments
PROCESS-National consultations-Internal project preparation-National/International tenders
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
4
Project Design Document*
A. general description of project activity B. Baseline methodology C. Duration of the project activity
crediting/crediting period D. Monitoring methodology and plan E. Calculation of GHG emission by sources F. Environmental impacts G. Stakeholders comments
* CDM website UNFCCC secretariat
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
5
1. Project design& formulation
Step 1
RESPONSIBILITIES-National Agencies- Private Consultants- Researchers- Unilateral preparation
DNA INVOLVEMENT-Identifying projects-Promoting consultations among stakeholders-Mobilizing resources for PDD preparation-Liaising with CDM investors
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
6
1. Project design& formulation
Step 1
RESOURCES-Financial- Organisational- Human-
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
7
Step 2
2. National approval
ACTIONS-Project Review- National Consultation- Assessement as regards to contribution to SD-No négative side-effects-No major opposition fromother parties
PROCESS/ROLES-National consultations-Review National CDM Authority -Legitimacy of the decisions tobe made by the DNA members-Who issues the formal approval-Time limits (e.g. 4 weeks)
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
8
2. NationalApproval
Step 2
RESOURCES-Institutional-Organisational- Human capacities
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
9
3. Validation& Registration
Step 3ACTIONS-Designation of an Accredited DOE see sectoral scope-Projects to be reviewedby the DOE-Feedbacks form NGOs and Local communities-DOE to validate the projectand to notify EB for Registration-Registration by EB: within 8 weeks
PROCESS-DNA to designate a DOE-Project developper designate a DOE while informing DNA
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
10
3. Validation& Registration
Step 3
RESPONSIBILITIES-DOE- EB
DNA INVOLVEMENT-Identifying DOE-Facilitate contracting DOE-Responding to any DNAquestions-Keeping record of the Registrations
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
11
3. Validation& Registration
Step 3
RESOURCES-DOE: variable- Registration: Us$ 5,000 to US$ 30,000
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
12
a
4. Project Financing
Step 4 ACTIONS-Estimate of Financing needed: -Identification of Potentialsources of financing-Contacts with donors-Finalization of the funding scheme-No Diversion of ODA-Signature of the CDM contractPROCESS-Marketing Policy-Communication with donors:
•Forum, seminars, website, study tour, etc.•Signature of MOU
Can be started fromthe early process
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
13
4. Project Financing
Step 4
RESPONSIBILITIES-Ministries-National Agencies- Project Developers
DNA INVOLVEMENT-Organizing events-Posting project Portfolio (Website)-Promoting the country in the Carbon Market
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
14
4. Project Financing
Step 4
RESOURCES-Communication-Organisational- Financial
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
15
a
5. ProjectImplementation and Monitoring
Step 5
ACTIONS-Implementing and managing the project-Establishing and executing the Monitoring Procedures-Producing monitoring reports
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
16
Step 5
RESPONSIBILITIES-Project Proponents-Sub-contractors
DNA INVOLVEMENT-Ensuring that Monitoring is appropiately implemented-Consulted for the DOE designation
5. ProjectImplementation and Monitoring
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
17
Step 5
RESOURCES-Financial-Human
5. ProjectImplementation and Monitoring
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
18
a
6. Verification/Certification
Step 6 ACTIONS-Contracting a DOE b-sending the monitoring reports to Doe for review-Getting evaluated through field review by DOE (GHG emissions, quality of the monitoring procedures, consistency withe the Monitoring Plan, etc.-Certification by DOE (written assurance by DOE)
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
19
Step 6
RESPONSIBILITIES- DOE
DNA INVOLVEMENT-Consulted for the DOE designation-Getting in touch with the DOE
6. Verification/Certification
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
20
Step 6
RESOURCES-Financial6. Verification/
Certification
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
21
a
7. Issuance ofCERs
Step 7ACTIONS-EB receiving the notification for Certification from DOE-EB issuing CERS within 15 days-EB to keep a registry of CERs
-2% CERs adaptation
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
22
Step 7
RESPONSIBILITIES- EB
DNA INVOLVEMENT-Liaise with the EB for theissuance of CERs
7. Issuance of CERs
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
23
Step 7
RESOURCES-None-Project proponent to money from CDMinvestors accordingto contractual modalities
7. Issuance of CERs
Capacity Development for CDM - RW4 Tunis, 27-29 August 2004
24