CAMPUS DRIVE / ADMIN CIRCLE & S. ACADEMIC MALL …

Post on 03-May-2022

4 views 0 download

Transcript of CAMPUS DRIVE / ADMIN CIRCLE & S. ACADEMIC MALL …

CAMPUS DRIVE / ADMIN CIRCLE &

S. ACADEMIC MALL

IMPROVEMENTS

Campus Stakeholders

May 15, 2020Raymond Pankopf, NCARB

Director, Architectural & Engineering Services

University of Idaho Facilities

LONG RANGE CAMPUS DEVELOPMENT PLAN (LRCDP)

• Coordinates with

UI Strategic Plan

• Guides all campus

development

• Provides a

framework for

stewardship and

preserving the

campus legacy in

concert with

moving forward

LONG RANGE CAMPUS DEVELOPMENT PLAN (LRCDP)

• The first campus comprehensive plan was prepared by John Charles Olmsted in 1908

• The plan had a clear and reverent sense of what a “university” should be

• The plan respected the setting and environment and celebrated work and residence

• Today, these principles are still aliveand vital to creating a high quality,residential campus environment

LONG RANGE CAMPUS DEVELOPMENT PLAN (LRCDP)

The LRCDP is organized into 9 Goals – Each Goal is supported by a Discussion, Objectives, and Defined

Actions in a results-oriented language & format.

▪ Land Use

▪ Transportation & Parking

▪ Open Space

▪ Preserve and enhance campus open space and landscape as a signature characteristic of the University of Idaho.

▪ Compact Academic Core

▪ Maintain and strengthen a compact, pedestrian priority academic core.

▪ Residential Campus

▪ Preserve and enhance the residential campus environment to advance UI’s vision/values and to support the Strategic

Plan.

Figuratively “growing more ivy”

▪ Residential Facilities

▪ Utility Infrastructure

▪ Space

▪ Effective LRCDP Policies

DESIGN & CONSTRUCTION TEAM

Project Administration

▪ State of Idaho Division of Public Works Design & Construction Agency

Gary Groff, Civil Engineer, DPW Project Manager

Mark Schlickenmeyer, DPW Construction Phase Field Representative

Architect / Engineers

▪ Bernardo Wills Architects Lead A/E Firm & Landscape Architect

Dell Hatch, Landscape Architect, Design Team Lead & Lead Landscape Architect

▪ Welch-Comer Engineers Civil Engineer

Matt Gillis, Civil Engineer, Design Team Lead Engineer

University of Idaho

▪ Architectural & Engineering Services Agency Representative

Raymond Pankopf, Architect, UI AES Project Manager

Richard Rader, UI AES Construction Manager

Matthew Proctor, UI AES Construction Inspector

General Contractor

▪ A & R Construction, Lewiston, Idaho General Contractor

PROJECT MILESTONES

Design Phase

▪ Funding Request Submitted, FY2019 State PBF Process August 1, 2017

▪ Funding Approved, 2018 Legislative Session Mar 2018

▪ Funds “Green” July 1, 2018

▪ A/E Selection Dec 2018

▪ Programming & Preliminary Design Phase Jan - Mar 2019

▪ Preliminary Approval Presentation to PBFAC April 2, 2019

▪ Design Development Phase Apr – Aug 2019

▪ Design Development Presentations Aug - Sep 2019

▪ Construction Document Phase Sep – Dec 2019

▪ Final Presentation to PBFAC / Construction Authorization Jan 2020

Bidding, Award, and Construction Phases

▪ Advertisement & Bidding Phase Jan – Feb 2020

▪ Bid Reconciliation & Award Phase Feb – Apr 2020

▪ Break Ground / Notice to Proceed (NTP) May 15, 2020

▪ Construction Phase May – Sep 2020

▪ Substantial Completion Oct 2020

PROJECT COSTS

University of Idaho Funds

000 – Project Support $ 5,000.00

State of Idaho Permanent Building Funds A & R Category, FY19 & FY20

100 - Professional / Design Fees $ 145,966.00

200 - Professional Services $ 25,700.00

▪ Site Survey $ 13,900

▪ Soils $ 6,800

▪ Testing During Construction $ 5,000

300 - Construction Costs: Contracted $ 1,431,255.00

▪ Construction Contract Budgeted Allowance $ 1,363,100

▪ Construction Contingency $ 68,155

400 - Misc. & Project Contingency $ 70,879.00

Total PBF Funds $ 1,673,800.00

Alle

y

Sites: Admin Circle portion of Campus Drive, East of the Administration Building & South Academic Mall, University Ave. Mall to Shattuck Arboretum, wrapping around the south side of PEB to Lot 39.

Sou

th A

cad

emic

Mal

l

Cam

pu

s D

rive

University Ave Pedestrian Mall

Park

ing

Lot

39

Swim Center

PEB

AAN

EHHS

Albertsons

Ad

min

Bld

g.

Sou

th A

cad

emic

Mal

l

Parking Lot 40

EXISTING CONDITIONS / SITE PHOTOS

South Academic Mall Campus Drive / Administration Circle

Concept, Campus Drive / Administration Circle

Note 15 May 20: This was the Conceptual Plan and describes the general intent and character of the project. The final, as-builtcondition will reflect minor changes which occurred during the design process.

Fencing and Access Plan, Campus Drive / Administration Circle

Note 15 May 20: This Fencing and Access Plan is taken from the Construction Documents and was intended to provide the contractor with a general set of scope parameters upon which they could base a bid. It is subject to change as needs and circumstances might require.

East entrance to the Administration Building will be closed. North, south and west entries will remain open.

Concept, South Academic Mall, Master Plan for Full Build-out

Concept, South Academic Mall, Currently Contracted Scope

Note 15 May 20: This was the Conceptual Plan and describes the general intent and character of the project. The final, as-builtcondition will reflect minor changes which occurred during the design process.

Fencing and Access Plan, South Academic Mall

Note 15 May 20: This Fencing and Access Plan is taken from the Construction Documents and was intended to provide the contractor with a general set of scope parameters upon which they could base a bid. It is subject to change as needs and circumstances might require.

Questions?