Building Program Update

February 5th, 2019

Joe Romenick

Catawba Ridge High School

• Opens - August 2019

• Substantial Completion Date – April 23rd, 2019

• Barring any additional weather delays.

• This does not mean building is ready to occupy with full staff.

• Key personnel can occupy.

• Furniture, furnishings & equipment can be installed.

• Furniture Delivery and Install – April 23rd thru May 14th, 2019

• Staff can move in once Certificate of Occupancy (CO) is received from SC Office of School Facilities. Scheduled for Mid-May 2019.

CRHS – on Parkway

CRHS – Hallway w/ Terrazzo

CRHS – Science Classroom

CRHS – Main Street

CRHS – Main Gym

CRHS – Auditorium

CRHS – Commons

CRHS – 3rd Floor Hallway

CRHS – Courtyard / Media Center

CRHS – Spring Athletics

CRHS – Track & Stadium

Aquatics Center

• On schedule to open to public sometime in October 2019

• Substantial Completion Date – September 30th, 2019

• Barring any additional weather delays.

• This does not mean building is ready to occupy with full staff.

• Key personnel can occupy.

• Furniture, furnishings & equipment can be installed

• Furniture, furnishings and equipment installed September 30th thru October 7th, 2019

• Staff can move in once Certificate of Occupancy (CO) is received from SC Office of School Facilities. Scheduled for Early October 2019.

AQUATICS CENTER – First Wall Panel

AQUATICS CENTER – Building Site

AQUATICS CENTER – Parking Lot Area

Elementary # 11 – Parkway

• Opens - August 2020

• Substantial Completion Date – June 1st, 2020

• Barring any additional weather delays.

• This date has already been pushed out 2 weeks because of weather.

• Furniture Delivery and Install – June 1st thru June 15th, 2020

• Staff can move in once Certificate of Occupancy (CO) is received from SC Office of School Facilities. Currently scheduled for mid June 2020.

ES # 11 – Initial Clearing

ES # 11 – Initial Clearing

ES # 11

Elementary # 10 – Masons Bend• Opens - August 2020

• Substantial Completion Date – June 15th, 2020

• Barring any additional weather delays.

• This date has already been pushed out 2 weeks because of weather & permit delay.

• Furniture Delivery and Install – June 15th thru June 30th, 2020

• Staff can move in once Certificate of Occupancy (CO) is received from SC Office of School Facilities. Currently scheduled for late June 2020.

ES # 10 – Initial Clearing

ES # 10 – Initial Clearing

Middle # 6 – White’s Road• Opens to Students - August 2021

• The District will be going out for contractor bids 2nd quarter 2019.

• Construction will begin summer 2019.

• Estimated substantial completion date scheduled for May 2019.

MIDDLE SCHOOL # 6