Primary Construction

Route

Park Access

Park Access

PublicParking

Secondary Construction

Route

www.houriganconstruction.com www.cbf.org

Park Access

CONSTRUCTION ENTRANCE AND DELIVERY SIGN & PROJECT RENDERING

SAFETY RULES SIGN

& SECURITY GATE

SECURITY CAMERA

CONSTRUCTION PARKING

HOURIGAN & CBF PROJECT TRAILERS

SECURED STORAGE

CONSTRUCTION-USE SOLAR ARRAY

RECYCLE/LOADING AREA SECURITY LIGHTING

DIRECTION OF CONSTRUCTION

SECURITY LIGHTING

SECURITY LIGHTING

EROSION AND SEDIMENT FENCE

TEMPORARY POWER/SANITARY FACILITIES

BROCK ENVIRONMENTAL CENTER SITE UTILIZATION PLAN

EXISTING SWING-GATE TO REMAIN DURING CONSTRUCTION

STRUCTURAL ERECTION ROAD -

8’ STONE WITH GEO TEXTILE FABRIC

www.houriganconstruction.com www.cbf.org

Construction Means and Methods

www.houriganconstruction.com www.cbf.org

Noise Reduction•Activitiesproducinghigherlevelsofnoisewillbeperformedbetweenthehoursof9:00amand3:30pmMondaythroughFriday

Green Construction Processes Utilized to Reduce Carbon Footprint•Onsitewatermanagement•Noonsiteconstructionparking•Solarpanelarrayfortemporaryconstructionpower•Waterwellfortemporaryconstructionwater•Pollutionreductionmethodsutilizedonequipment•Containmentareasaroundtemporarytoilets•Minimizeuseoffossilfuelequipment

Public Parking and Access to Park•ParkingattheCitypumphouseorMarlinBayDrive•Accesstoparkidentifiedviasignage

Construction Traffic•Primaryconstructionroute:ShoreDr.toE.Stratford•Constructionhours:MondaythroughFriday6:30am–5:00pm•ConstructionparkingattheCitypumphouse•Dustcontrolmethods

Safety & Security•6’tallsecurityfence•Motionsensorlighting•Webbasedsecuritycamera

Construction Schedule (as of July 16, 2013)

Brock Environmental Center

Construction Activity Start Date Completion DateTotal Construction 08/05/13 07/30/14

Fencing & Gates 08/05/13 08/16/13Construction Trailers 08/12/13 08/16/13Clearing & Construction Roads 08/19/13 08/30/13Concrete Structure 08/28/13 10/18/13Site Utilities 09/02/13 10/25/13Steel Structure 10/28/13 11/29/13Interior Construction 12/30/13 04/04/14Pier 01/01/14 05/01/14Site Work 02/17/14 04/11/14Chesterfield Road Waterline 04/07/14 04/18/14Marlin Bay Path 05/01/14 08/01/14Complete Construction 07/30/14 07/30/14

CBF Occupancy Late Summer Early Fall