Brock Environmental Center - Presentation from July 16, 2013 Open House
-
Upload
chesapeake-bay-foundation -
Category
News & Politics
-
view
1.507 -
download
1
description
Transcript of Brock Environmental Center - Presentation from July 16, 2013 Open House
Primary Construction
Route
Park Access
Park Access
PublicParking
Secondary Construction
Route
www.houriganconstruction.com www.cbf.org
Park Access
CONSTRUCTION ENTRANCE AND DELIVERY SIGN & PROJECT RENDERING
SAFETY RULES SIGN
& SECURITY GATE
SECURITY CAMERA
CONSTRUCTION PARKING
HOURIGAN & CBF PROJECT TRAILERS
SECURED STORAGE
CONSTRUCTION-USE SOLAR ARRAY
RECYCLE/LOADING AREA SECURITY LIGHTING
DIRECTION OF CONSTRUCTION
SECURITY LIGHTING
SECURITY LIGHTING
EROSION AND SEDIMENT FENCE
TEMPORARY POWER/SANITARY FACILITIES
BROCK ENVIRONMENTAL CENTER SITE UTILIZATION PLAN
EXISTING SWING-GATE TO REMAIN DURING CONSTRUCTION
STRUCTURAL ERECTION ROAD -
8’ STONE WITH GEO TEXTILE FABRIC
www.houriganconstruction.com www.cbf.org
Construction Means and Methods
www.houriganconstruction.com www.cbf.org
Noise Reduction•Activitiesproducinghigherlevelsofnoisewillbeperformedbetweenthehoursof9:00amand3:30pmMondaythroughFriday
Green Construction Processes Utilized to Reduce Carbon Footprint•Onsitewatermanagement•Noonsiteconstructionparking•Solarpanelarrayfortemporaryconstructionpower•Waterwellfortemporaryconstructionwater•Pollutionreductionmethodsutilizedonequipment•Containmentareasaroundtemporarytoilets•Minimizeuseoffossilfuelequipment
Public Parking and Access to Park•ParkingattheCitypumphouseorMarlinBayDrive•Accesstoparkidentifiedviasignage
Construction Traffic•Primaryconstructionroute:ShoreDr.toE.Stratford•Constructionhours:MondaythroughFriday6:30am–5:00pm•ConstructionparkingattheCitypumphouse•Dustcontrolmethods
Safety & Security•6’tallsecurityfence•Motionsensorlighting•Webbasedsecuritycamera
Construction Schedule (as of July 16, 2013)
Brock Environmental Center
Construction Activity Start Date Completion DateTotal Construction 08/05/13 07/30/14
Fencing & Gates 08/05/13 08/16/13Construction Trailers 08/12/13 08/16/13Clearing & Construction Roads 08/19/13 08/30/13Concrete Structure 08/28/13 10/18/13Site Utilities 09/02/13 10/25/13Steel Structure 10/28/13 11/29/13Interior Construction 12/30/13 04/04/14Pier 01/01/14 05/01/14Site Work 02/17/14 04/11/14Chesterfield Road Waterline 04/07/14 04/18/14Marlin Bay Path 05/01/14 08/01/14Complete Construction 07/30/14 07/30/14
CBF Occupancy Late Summer Early Fall