Bartow Repowering Project

2

The Bartow Repowering Project

Project needed to increase generation capacityOther Project Benefits

Reduces air emissionsIncreases efficiencyIncreases system reliability Cost effective growthNo new land required

3

The Bartow Repowering Project

Project includes 3 “pieces”Natural Gas Pipeline (Gulfstream)Combined-cycle Power Plant (Progress Energy)Transmission Upgrades (Progress Energy)

4

The Bartow Repowering Project

Fuel Supply Pipeline17.5 miles of 20 inch pipeline155,000 dekatherms daily firm capacity23 years guaranteed supplyProject beginning now

5

The Bartow Repowering Project

6

The Bartow Repowering Project

Combined-Cycle Power PlantNatural gas as primary fuelCapability to also run on distillate oilHighly efficient 4x4x1 designSimple cycle bypass dampers and stacks1,260MW @ ISO conditionsHeat Rate of 7,060 BTU/kWhr

7

The Bartow Repowering Project

Combined Cycle Power Plant4 Siemens 501FD combustion turbine generators equipped with evaporative coolers and power augmentation 4 triple pressure heat recovery steam generators with simple cycle bypass stacks, duct firing and SCR 1 Mitsubishi Steam Turbine Generator

8

The Bartow Repowering ProjectCombined Cycle Process

9

The Bartow Repowering Project

10

The Bartow Repowering Project

Riviera Bay Gandy Causeway

Observation Tower - lower Observation Tower – upper

Visual Impact Analysis

11

The Bartow Repowering Project

Transmission UpgradeExtension to existing Bartow 230kV substation4.5 miles of new 230kV underground transmissionUpgrades to several other 230kV substations

12

The Bartow Repowering Project

Transmission Line Route

13

The Bartow Repowering Project

TimetableConstruction begins = DEC 2006Commercial Operation = JUN 2009

14

Thank you for your time.

Questions?