AQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN

Company / Owner

Marine Contractor

Main Contractors - JV

2

OUTLINE:.1Introduction

.2Resources

.3Progress Percentage◦Construction Status

.4Financial Summary

.5Variation Orders

AQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN

3

The project consists mainly of the detailed design and construction of LPG Jetty which includes:

•Access Trestle & Loading Platform

•2 No. Berthing Dolphins & 4 No. Mooring Dolphins & Catwalks

•Marine Loading Arms (x2)

•LPG and vapour return lines & Cathodic Protection System

•Fire fighting system & Electrical power supply and lighting

•Contractual project dates: 24-Feb-14 24-Oct-14

•Computed Completion Date :21-feb-15

1 .Introduction

AQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN

4

2 .ResourcesAQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN

Manpower 1-Nov-2014 1-Jan-2015Staff 51 54

Direct Labor 41 64Equipment Quantity Rented/

OwnedBarge 1 Owned

Flexi float barge 1 OwnedTug Boat 1 1 OwnedTug Boat 2 1 Rented

Speed Boat 1 RentedVibro Hammer 1 Owned

Diesel Hammer 1 OwnedCrawler Crane 1 OwnedMobile Crane 3 Rented

Air-Compressor 4 OwnedWelding Machine

20 Owned

Truck Mounted Crane

1 Owned

5

3. Progress Percentage

AQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN

Status Expected Completion DateTrestle 100% CompletePlatform 100% CompleteLoading Arm 100% CompletePile Static Load Test 100% CompletePipe Line 80% 31-Jan-15Mooring Dolphins 80% 25-Jan-15Berthing Dolphins 75% 31-Jan-15Catwalks 75% 5-Feb-15Abutement & Access 50% 28-Jan-15Electrical 30% 10-Feb-15Marine Furniture (QRH,BAS,Fenders,..) 20% 12-Feb-15Commissioning 4-Feb to 18-Feb-15

Construction

6

3.1 Construction of Pipe LinesAQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN

Front View

10” FF Pipe4” Vapour Pipe

6” LPG Pipe2.5” Water

Pipe

U-Channel Pipe Support

Concrete Pipe Support

Pipe 13-Jan-15FireFighting 80%Vapour 80%LPG 80%Water 80%

7

4 .Financial Summary

AQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN

Invoice No.

Description

Initial Amount (JOD)

Agreed Amount (JOD)

Issue Date

Due Date

Settlement Date

Overdue

Period (days)

Status

001Advance payment

10%1,723,255.00 1,723,255.00 5-Feb-14 6-Mar-

14 8-Jun-14 94 Closed

002 IPC-1 2,356,981.61 1,926,073.33 7-May-14 2-Jul-14 19-Aug-14

48 Closed

003 IPC-2 1,092,297.77 969,456.65 7-Jun-14 2-Aug-14 1-Sep-14 30 Closed

004 IPC-3 1,507,114.54 1,245,493.82 12-Jul-14 6-Sep-14 1-Oct-14 25 Closed

005 IPC-4 1,174,215.32 1,583,941.28 11-Aug-14 6-Oct-14 10-Nov-14

35 Closed

006 IPC-5 1,617,218.84 1,006,200.22 8-Sep-14 3-Nov-14 12-Nov-14

9 Closed

007 IPC-6 2,638,679.75 1,919,859.74 7-Oct-14 2-Dec-14 12-Nov-14

  Closed

008 IPC-7 1,571,120.29 1,005,264.70 29-Oct-14 24-Dec-14

30-Nov-14

  Closed

009 IPC-8 1,864,144.68 993,963.07 2-Dec-14 27-Jan-15 Not Yet Open

010 IPC-9 1,366,814.24  1,212,026.19 2-Jan-15 27-Feb-15 Not Yet Open

Issued 14-Jan-2015

8

.1Steel Water Tank to feed the fire fighting system•Issued on Nov. 17th 2014 (202,425.00) JD, Progress : 30%

.2Firefighting Pumps Room•Issued on 17th 2014 (40,700.0) JD, Progress : 95%

.3LPG and Vapour Return Tie-In to Existing Networks•Issued on 17th 2014 (64,509.61) JD, Progress : 100%

.4Design, Supply and Installation of Main Power cable•Issued on Dec. 24th (18,246.99) JD, Progress : 80%

.5Design, Supply and Installation of a Standby Power Generator•Issued on Dec. 24th (18,198.69) JD, Progress : 80%

5 .Variation Orders (Issued by Employer/CM)

AQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN

9

General Layout

General Layout

Trestle Modules

Pipe Lines on Trestle

Mooring Dolphins

13

Firefighting Tank + Pump Room

14

Static Load Test

15

Loading Arm PrecommissioningLoading Arm Construction

16

Firefighting Monitor Towers

17

Abutment

18

Tie in at Loading Arm

19

Tie in Point

20

Cable Trays onshore + Trestle

21

Q & AAQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN