Aqaba LPG Terminal Jordan

21
1 AQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN Company / Owner Marine Contractor Main Contractors - JV

description

Aqaba LPG Terminal Jordan

Transcript of Aqaba LPG Terminal Jordan

Page 1: Aqaba LPG Terminal Jordan

1

AQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN

Company / Owner

Marine Contractor

Main Contractors - JV

Page 2: Aqaba LPG Terminal Jordan

2

OUTLINE:.1Introduction

.2Resources

.3Progress Percentage◦Construction Status

.4Financial Summary

.5Variation Orders

AQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN

Page 3: Aqaba LPG Terminal Jordan

3

The project consists mainly of the detailed design and construction of LPG Jetty which includes:

•Access Trestle & Loading Platform

•2 No. Berthing Dolphins & 4 No. Mooring Dolphins & Catwalks

•Marine Loading Arms (x2)

•LPG and vapour return lines & Cathodic Protection System

•Fire fighting system & Electrical power supply and lighting

•Contractual project dates: 24-Feb-14 24-Oct-14

•Computed Completion Date :21-feb-15

1 .Introduction

AQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN

Page 4: Aqaba LPG Terminal Jordan

4

2 .ResourcesAQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN

Manpower 1-Nov-2014 1-Jan-2015Staff 51 54

Direct Labor 41 64Equipment Quantity Rented/

OwnedBarge 1 Owned

Flexi float barge 1 OwnedTug Boat 1 1 OwnedTug Boat 2 1 Rented

Speed Boat 1 RentedVibro Hammer 1 Owned

Diesel Hammer 1 OwnedCrawler Crane 1 OwnedMobile Crane 3 Rented

Air-Compressor 4 OwnedWelding Machine

20 Owned

Truck Mounted Crane

1 Owned

Page 5: Aqaba LPG Terminal Jordan

5

3. Progress Percentage

AQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN

Status Expected Completion DateTrestle 100% CompletePlatform 100% CompleteLoading Arm 100% CompletePile Static Load Test 100% CompletePipe Line 80% 31-Jan-15Mooring Dolphins 80% 25-Jan-15Berthing Dolphins 75% 31-Jan-15Catwalks 75% 5-Feb-15Abutement & Access 50% 28-Jan-15Electrical 30% 10-Feb-15Marine Furniture (QRH,BAS,Fenders,..) 20% 12-Feb-15Commissioning 4-Feb to 18-Feb-15

Construction

Page 6: Aqaba LPG Terminal Jordan

6

3.1 Construction of Pipe LinesAQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN

Front View

10” FF Pipe4” Vapour Pipe

6” LPG Pipe2.5” Water

Pipe

U-Channel Pipe Support

Concrete Pipe Support

Pipe 13-Jan-15FireFighting 80%Vapour 80%LPG 80%Water 80%

Page 7: Aqaba LPG Terminal Jordan

7

4 .Financial Summary

AQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN

Invoice No.

Description

Initial Amount (JOD)

Agreed Amount (JOD)

Issue Date

Due Date

Settlement Date

Overdue

Period (days)

Status

001Advance payment

10%1,723,255.00 1,723,255.00 5-Feb-14 6-Mar-

14 8-Jun-14 94 Closed

002 IPC-1 2,356,981.61 1,926,073.33 7-May-14 2-Jul-14 19-Aug-14

48 Closed

003 IPC-2 1,092,297.77 969,456.65 7-Jun-14 2-Aug-14 1-Sep-14 30 Closed

004 IPC-3 1,507,114.54 1,245,493.82 12-Jul-14 6-Sep-14 1-Oct-14 25 Closed

005 IPC-4 1,174,215.32 1,583,941.28 11-Aug-14 6-Oct-14 10-Nov-14

35 Closed

006 IPC-5 1,617,218.84 1,006,200.22 8-Sep-14 3-Nov-14 12-Nov-14

9 Closed

007 IPC-6 2,638,679.75 1,919,859.74 7-Oct-14 2-Dec-14 12-Nov-14

  Closed

008 IPC-7 1,571,120.29 1,005,264.70 29-Oct-14 24-Dec-14

30-Nov-14

  Closed

009 IPC-8 1,864,144.68 993,963.07 2-Dec-14 27-Jan-15 Not Yet Open

010 IPC-9 1,366,814.24  1,212,026.19 2-Jan-15 27-Feb-15 Not Yet Open

Issued 14-Jan-2015

Page 8: Aqaba LPG Terminal Jordan

8

.1Steel Water Tank to feed the fire fighting system•Issued on Nov. 17th 2014 (202,425.00) JD, Progress : 30%

.2Firefighting Pumps Room•Issued on 17th 2014 (40,700.0) JD, Progress : 95%

.3LPG and Vapour Return Tie-In to Existing Networks•Issued on 17th 2014 (64,509.61) JD, Progress : 100%

.4Design, Supply and Installation of Main Power cable•Issued on Dec. 24th (18,246.99) JD, Progress : 80%

.5Design, Supply and Installation of a Standby Power Generator•Issued on Dec. 24th (18,198.69) JD, Progress : 80%

5 .Variation Orders (Issued by Employer/CM)

AQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN

Page 9: Aqaba LPG Terminal Jordan

9

General Layout

General Layout

Page 10: Aqaba LPG Terminal Jordan

Trestle Modules

Page 11: Aqaba LPG Terminal Jordan

Pipe Lines on Trestle

Page 12: Aqaba LPG Terminal Jordan

Mooring Dolphins

Page 13: Aqaba LPG Terminal Jordan

13

Firefighting Tank + Pump Room

Page 14: Aqaba LPG Terminal Jordan

14

Static Load Test

Page 15: Aqaba LPG Terminal Jordan

15

Loading Arm PrecommissioningLoading Arm Construction

Page 16: Aqaba LPG Terminal Jordan

16

Firefighting Monitor Towers

Page 17: Aqaba LPG Terminal Jordan

17

Abutment

Page 18: Aqaba LPG Terminal Jordan

18

Tie in at Loading Arm

Page 19: Aqaba LPG Terminal Jordan

19

Tie in Point

Page 20: Aqaba LPG Terminal Jordan

20

Cable Trays onshore + Trestle

Page 21: Aqaba LPG Terminal Jordan

21

Q & AAQABA LIQUIFIED PETROLEUM GAS (LPG) TERMINAL - JORDAN