1
Safety Information………………………………
Installation Tools…………………………………
Installation Modes………………………………
Space Requirements …………………………
Requirements on the Objects for Installation
Installation Procedure……………………………
Preparing for the installation…………………
Installing the RRU on a Metal Pole……………
Installing the RRU on a Wall……………………
Installing the RRU on a U-Steel………………
Installing the RRU on an Angle Steel………
Installing the Cables of the RRU……………
Powering On the RRU…………………………
Reference…………………………………………
2
3
4
5
6
7
7
8
13
15
15
16
29
30
Contents
Copyright © Huawei Technologies Co., Ltd. 2009. All rights reserved.
2
Following All Safety PrecautionsBefore any operation, read the instructions and precautions in this document carefully to minimize the possibility of accidents.The Danger, Caution, and Note items in the documents do not cover all the safety precautions that must be followed. They only provide the generic safety precautions for operations.When operating Huawei products and equipment, you must comply with safety precautions and special safety instructions related to corresponding equipment provided by Huawei. The safety precautions in the document are related to only Huawei products. Huawei is not liable for any consequence that results from the violation of universal regulations for safety operations and safety codes on design, production, and equipment use. Complying with the Local Safety RegulationsWhen operating the device, comply with the local safety regulations. The safety precautions provided in the documents are supplementary. You must comply with the local safety regulations.Qualified Personnel OnlyThe personnel in charge of installation and maintenance must be trained and master the correct operating methods and safety precautions before beginning work.Symbols
Safety of Personnel• The high voltage power supply provides power for running the system. Direct contact with the high voltage power supply or contact through damp objects may result in fatal danger.• Non-standard and improper high voltage operations may result in fire and electric shock.• In a thunderstorm, do not perform operations on high voltage and AC power supply facilities or on a steel tower and mast.• Ground the device before powering on the device. Otherwise, the personnel and device are in danger.• Power off the device before performing operations on the power supply equipment.• High power radio-frequency signals are harmful to human body. Before installing or maintaining an antenna on a steel tower or mast with a large number of transmitter antennas, the operator should coordinate with all parties to ensure that the transmitter antennas are shut down.• When handling optical fibers, do not stand close to, or look into the optical fiber outlet with unaided eyes.• Protect yourself when drilling holes. Flying dust may hurt your eyes or you may inhale the dust.• Power off the batteries before connecting the cables to the batteries. Otherwise, casualties may occur. • When working at a height, be cautious about falling objects.Device Safety• Check the electrical connection of the device before operation and ensure that the device is reliably grounded.• The static electricity generated by the human body may damage the electrostatic sensitive components on the circuit board, such as the large-scale integrated circuit (LIC). Wear an ESD wrist strap or ESD gloves when performing the operation.• When working on batteries, take measures to prevent short circuits in the batteries and electrolyte spill/loss. The electrolyte may erode metal and boards, or even cause rust of the equipment or short circuits in the boards.• When the equipment is unpacked, it must be powered on in 24 hours. The maximum duration of the power-off state of the equipment is 24 hours during maintenance.
Safety Information
Indicates a hazard with a high level of risk, which if not avoided,will result in death or serious injury.DANGER
WARNING
CAUTION
TIP
NOTE
Indicates a hazard with a medium or low level of risk, which if not avoided, could result in minor or moderate injury.Indicates a potentially hazardous situation, which if not avoided,could result in equipment damage, data loss, performance degradation, or unexpected results.
Indicates a tip that may help you solve a problem or save time.
Provides additional information to emphasize or supplement important points of the main text.
3
Installation Tools
ESD glovesPercussion drill(Ø14) Vacuum cleaner
Heat gun Phillips screwdriver (M2 toM6) Flat-head screwdriver (M2 to M6)
Claw hammer Knife Cable peeler
Power cable crimping pliers Wire cutter
Adjustable wrench
(with the diameter of at least 32 mm)
Level bar Torque screwdriver
Combination wrench
(21mm to 21mm) for pole installation(17mm to17mm) for wall installation
Multimeter
Marking pen
(with the diameter of no more than 10 mm) Long measuring tape
4
Installation Modes
On a metal pole (three RRUs)
On a metal pole (in Ordinary Mode)
On a metal pole (in contrary mode)
On a metal pole (in back-to-back mode)
On a metal pole (four RRUs)
On a metal pole (six RRUs)
On a U-steel On an angle steel On a wall
5
Space Requirements (Unit: mm)a RRU Dimensions b Recommended Clearance
for a Single RRU
c Minimum Clearance for a Single RRU
d Clearance for Two Combined RRUs
eRecommended Clearance for Multiple Centralized RRUs
f Minimum Clearance for Multiple Centralized RRUs
6
Requirements on the Objects for Installation
The following figure describes the specifications for the metal pole, angle steel, and U-steel where the RRU is installed.
Metal pole Angle steel U-steel
Angle steel or U-steel
As shown in the figure, the angle between the vertical direction and the angle steel or U-steel where the RRU is installed must be less than 10 degrees.
• A maximum of two RRUs can be installed on a metal pole with a diameter of 60 mm to 76 mm, and the installation mode must be standard mode. Three or more RRUs must be installed on a metal pole with a diameter of 76 mm to 114 mm in a centralized way.• It is recommended that only one RRU be installed on a U-steel or angle steel.• When installed on a tower, one RRU can be installed only in standard mode or reverse mode rather than side-mounted. Two RRUs cannot be installed in back-to-back mode.
When the RRU is installed on a wall, the requirements are as follows:• For one RRU, the wall has a weight-bearing capacity of 68 kg.• The fastening torque of the expansion bolt reaches 30 N·m, the expansion bolt works properly, and no damages such as cracks are on the wall.
The brackets cannot be combined when the RRUs are installed on the wall.
7
Installation Procedure
Preparing for the installation
Fixture assembly for installing the RRU Front of the RRU Back of the RRU
Cover plate Attachment plate
Auxiliary fixture
Dual-nut boltMain fixture
• Place the foam pad or cardboard under the RRU to prevent any damage to the housing of the RRU.• The weight-bearing capacity of the RF ports at the bottom of the RRU is low. Do not place the RRU at its bottom.
8
Installing the RRU on a Metal PoleInstalling a Single RRU in Ordinary Modea
1、Install the main fixture,
2、Install the auxiliary fixture between the nuts of the dual-nut boltassembly on the main fixture。
Arrow
Dual-nut bolt assembly
Ensure that the arrow on the auxiliary fixture is upward.
You can fit the auxiliary fixture on one of the dual-nut bolt assemblies before the installation. Thus, you can simply install the auxiliary fixture by fitting the other end of it on the other dual-nut bolt assembly.
1. Before installing the main fixture, ensure that the contact piece on the fixture is fixed.2. When installing the main fixture, keep the arrow on the main fixture upward.
It is recommended that the bottom of the main fixture be 1200 mm to 1600 mm above the ground for easy maintenance.
9
Installing the RRU on a Metal PoleInstalling a Single RRU in Ordinary Modea
4、Install the RRU on the main fixture.
3、Use an adjustable wrench (with the diameter of at least 21 mm) to tighten the dual-nut bolt assemblies. In this way, the main and auxiliary fixtures are securely mounted on the pole.
This screw is fastened only if the RRU needs to be removed.
Tighten the two dual-nut bolts synchronously during the operation.
40N•m
10
4.8N•m
M6X16
Installing the RRU on a Metal PoleInstalling Two RRUs in Back-To-Back Modeb
4、Fit the tabs on the attachment plate on the second RRU into the anchor slots on the main fixture.
3、Reinstall the attachment plate and cover plate on the second RRU byinterchanging their positions.
1、Install an RRU first. For details, see page 8 Installing a Single RRU in Ordinary Mode.
2、Install the main fixture of anotherRRU. Ensure that the main andauxiliary fixtures are perfectly matched.
In ordinary mode
In reverse mode
This screw is fastened only if the RRU needs to be removed.
There are four screws at the front
There are three screws at the back
Cabling cavities
When two RRUs are installed in back-to-back mode, it is recommended that the cabling cavities of the RRUs face the same direction for future maintenance.
11
Installing Multiple RRUs in Centralized Modec
Installing the RRU on a Metal Pole
4、Install the second main fixture.
5、Fit the tabs on the attachment plate onthe second RRU into the anchor slots onthe second main fixture.
3、Fit the tabs on the attachment plate on the RRU into the anchor slots on the main fixture.
2、Relocate the attachment plate.
1、Install the main fixture and the auxiliary fixture ,For details, see page 8 Installing a Single RRU in Ordinary Mode.
4.8N•m
M6X16
There are three screws at the back
There are three screws at the back
This screw is fastened only if the RRU needs to be removed.
12
Installing the RRU on a Metal PoleInstalling Multiple RRUs in Centralized Modec
6、Install the third main fixture.
7、Install the third RRU.
Four RRUs Six RRUs
This screw is fastened only if the RRU needs to be removed.
The installations of four RRUs and six RRUs are as follows:
13
Installing the RRU on a WallInstalling a Single RRUa
2. Drill holes at the anchor points and then install the expansion bolt assembly.
1. Place the auxiliary fixture at the installation position. Use the level bar to check that the auxiliary fixture is placed horizontally. Then, mark the anchor points by using a marking pen.
It is recommended that the auxiliary fixture be 1200 mm to 1600 mm above the ground.
Level
RRU1,200 mm to 1,600 mm
52~60mm
90°
Ø14
20~30mm
After the expansion bolt is removed, dispose of the plastic tube.
When the RRU is installed on a wall, the requirements are as follows:• For one RRU, the wall has a weight-bearing capacity of 68 kg.• The fastening torque of the expansion bolt reaches 30 N·m, the expansion bolt works properly, and no damages such as cracks are on the wall.
Bolt M10x65
Flat washer 10
Spring washer 10
Expansion tube
Plastic tube
14
Installing the RRU on a WallInstalling a Single RRUa
5、Install the RRU.
4、Install the main fixture.3、Fit the auxiliary fixture on the expansionbolts downward, and then tighten the boltsby using a combination wrench (with thediameter of at least 17 mm).
This screw is tightened only when the RRU needs to be removed.
30N•m
M10X65
15
Installing the RRU on a U-Steel
The procedure for installing the RRU on a U-steel is the same as that on a metal pole.
Installing the RRU on an Angle Steel
The procedure for installing the RRU on an angle steel is the same as that on a metal pole.
U-Steel
Top view
Top view
Angle steel
16
Installing the Cables of the RRUConnections of a Single RRU Cablesa
Ant
enna
External power supply
BBU
PGND cablePower cableFeeder jumperFeederAISG multi-wire cableAISG extensionCPRI optical cableAlarm cable
abcdefgh
Install the AISG multi-wire cable and extension cable(optional)
Install the feeder jumper
Install the power cable
Start
End
Install the PGND cable
Install the CPRI optical cable
Install the alarm cable(optional)
17
Connections of Two RRUs Cablesb
The above figure shows the scenario where the cascaded CPRI optical cables and interconnect jumper are used.Determine the routing of the CPRI optical cables for the RRU according to field requirements.
Ant
enna
Ant
enna
PGND cablePower cableInterconnect jumperCPRI optical cable
Installing the Cables of the RRU
abcd
18
Installing the Cables of the RRU
Cable Connector Type Connected to…
OT or 2-hole terminal (16 mm²-M6) Grounding bolt on the RRU
OT or 2-hole terminal (16 mm² )
Select an appropriate size based on the grounding screws on the grounding bar.
Grounding bar
DIN connector Ports labeled ANT_TX/RXA and ANT_RXB at the bottom of the RRU
DIN connector Feeder or antenna
Two OT terminals (6 mm²-M4 )
The OT terminal on the blue wire is connected to the NEG(-) port on the cabling cavity of the RRU. The OT terminal on the black wire is connected to the RTN(+) port on the cabling cavity of the RRU.
Connect the fiber tails labeled 2A and 2B to one of the CPRI0 to CPRI3 ports on the WBBP
Connect the fiber tails labeled 1A and 1B to the CPRI_W port on the RRU
DLC connector
Connect the CPRI_E port on the RRU 0 to CPRI_W port on RRU 1
CPRI optical cable
Bare wire
Select an connector of appropriate type and size based on the external power supply. Use a cable with the diameter of 6 mm².
External power supply
Power cable
Antenna jumper
PGND cable
Cable Listc
19
Installing the Cables of the RRU
Cable Connector Type Connected to…
Waterproof DB9 connector
Port labeled RET/PWR_SRXU at the bottom of the RRU
Standard AISG female connector
AISG extension cable or RCU
AISG multi-wire cable
DB15 connector labeled RS485/EXT_ALM in the RRU cabling cavity
Cord end terminals External device
Alarm cable
2W2 connector Port labeled RX_IN/OUT at the bottom of the RRU
2W2 connector Port labeled RX_IN/OUT at the bottom of the RRU
Standard AISG male connector
Standard AISG female connector of the AISG multi-wire cable port
Standard AISG female connector
RCU
AISG extension cable
Interconnect jumper
c Cable List
The figures are for illustration purposes only and may not reflect actual cables.
20
Installing the Cables of the RRU
e RRU Cabling Cavity
d Opening the Cover Plate of the RRU Cabling Cavity
Waterproof filler
Cable trough for the optical cable
Cable trough for the power cable
Cable trough for the alarm cable
Cabling cavity
Cover plate of the cabling cavity
Label for preparing the power cable
21
Installing the Cables of the RRUf Installing the Cables of the RRU
CPRI optical cableAlarm cable
Shielding layer of the power cable
First wrap the joint with the waterproof tape and then wrap the joint with the PVC insulating tape
Power cable
• For details on how to add OT terminals to the power cable of the RRU, see pages 32 to 34 "Adding OT Terminals to the Power Cable of the RRU".• When wrapping the waterproofing tape, apply even force to extend the tape until the width of the tape is 1/2 of the original width.• Wrap the joint spirally upward, downward, and then upward again. In other words, the joint is wrapped by three layers of the tape. Ensure that the two immediate layers overlap with each other about half the width of the tape. For details, see page 35 “Waterproofing Outdoor Cables”.
• Use the power cable clip to press the shielding layer tightly and ensure that the lower part of the shielding layer does not exceed the position shown in the preceding figure.• Ground the shielding layer at the other end of the power cable.• After the cables are installed on the RRU, insert the waterproofing fillers into the idle cable troughs.• Do not remove the dustproof cap from the idle antenna port, and use the waterproofing tape to wrap the joint.
• The screws on the cover plate should be tightened until the fastening torque is 1.4 N·m.• Tighten the screws on the cover plate of the cabling cavity in the sequence shown in the figure.
1.4 N·m
g Closing the Cover Plate of the RRU Cabling Cavity
22
Installing the Cables of the RRUg RRU + APM30/APM30H
RRU power cable
CPRI optical cable
RRU Power Cable
• Connect the RRU power cable to the LOAD4 to LOAD9 terminals on the PDU.• Strip a small part of the jacket off the RRU power cable, press the shielding layer on the grounding clip, and then connect the PGND cable on the grounding clip to the nearby grounding bolt at the side of the cabinet, •as shown in , , and .a b c
PGND
Shielding layer (25 mm)
23
Installing the Cables of the RRUh RRU + APM30(+24V)
RRU power cable
CPRI optical cable
a
b
c
Shielding layer (25 mm)
RRU Power Cable
PGND
• Connect the RRU power cable to the LOAD4 to LOAD9 terminals on the PDU.• Strip a small part of the jacket off the RRU power cable, press the shielding layer on the grounding clip, and then connect the PGND cable on the grounding clip to the nearby grounding bolt at the side of the cabinet, •as shown in , , and .a b c
24
Installing the Cables of the RRUi RRU + TMC/TMC11H
RRU power cable
CPRI optical cable
a
b
c
PGND
Shielding layer (25 mm)
RRU power cable
• Strip a small part of the jacket off the RRU power cable, press the shielding layer on the grounding clip, and then connect the PGND cable on the grounding clip to the nearby grounding bolt at the side of the cabinet, •as shown in , , and .• Connect the RRU power cable to the LOAD0 to LOAD5 terminals on the DCDU-03C.
a b c
25
Installing the Cables of the RRUj RRU + OMB
–48 V DC input (DCDU-03C installed in the OMB cabinet)
a
b
c
PGND
Shielding layer (25 mm)
RRU power cable
RRU power cable
CPRI optical cable
• Strip a small part of the jacket off the RRU power cable, press the shielding layer on the grounding clip, and then connect the PGND cable on the grounding clip to the nearby grounding bolt at the side of the cabinet, •as shown in , , and .• Connect the RRU power cable to the LOAD0 to LOAD5 terminals on the DCDU-03C.
a b c
26
Installing the Cables of the RRUk RRU + PS4890
RRU power cable
CPRI optical cable
Shielding layer of RRU power cable
1. When connecting the RRU power cable to the DCDU-03B, you must add an OT terminal to the shielding layer. Then, fix the OT terminal to the corresponding GND terminal of the DCDU-03B. For details on how to add an OT terminal, see pages 31 to 33 Adding OT Terminals to the Power Cable of the RRU.2. The RRU power cable is connected to one of the LOAD0 to LOAD5 terminals of the DCDU-03C.
27
Installing the Cables of the RRUl RRU + Wall-Mounted BBU
1. When connecting the RRU power cable to the DCDU-03B, you must add an OT terminal to the shielding layer. Then, fix the OT terminal to the corresponding GND terminal of the DCDU-03B. For details on how to add an OT terminal, see pages 32 to 34 Adding OT Terminals to the Power Cable of the RRU.2. The RRU power cable is connected to one of the LOAD0 to LOAD5 terminals of the DCDU-03C.
Shielding layer of RRU power cable
RRU power cableCPRI optical cableBBU power cablePGND cable of DCDU-03C
28
Checking the RRU Hardware Installation
SN Item
1 The position for each equipment conforms to the engineering design and meets the space requirement. Sufficient space is reserved for equipment maintenance.
2 The RRU is securely installed.
3 The cover plate is securely installed on the cabling cavity of the RRU.
4 Waterproof fillers are installed in the idle cable troughs of the cabling cavity of the RRU, and the cover plate of the cabling cavity is securely installed. In addition, the idle RF ports are covered with waterproof caps and waterproofed.
5 There are no connectors or joints on the power cable or PGND cable.
6 The terminals at both ends of the power cable or PGND cable are securely soldered or crimped.
7 All the power cables and PGND cables are not short-circuited or reversely connected. In addition, no damaged or broken parts exist.
8 The power cable and PGND cable are separately bound from other cables.
9 The operating grounding and protection grounding of the NodeB and the lightning protection grounding of the building share one group of grounding conductors.
10 The connector of the signal cable is intact and securely linked, and no damaged or broken parts exist on the cable.
11 Labels are correct, legible, and complete on both ends of each cable.
29
Powering On the RRU
After the RRU is unpacked, it must be powered on in 24 hours. If the RRU should be powered off for maintenance, the duration of the power-off state cannot exceed 24 hours.
The power switch must be set to OFF. Then, check the input voltage and ensure that the voltage ranges from -36 V DC to -57 V DC if -48 V DC power is supplied or 150 V AC to 300 V AC if AC power is supplied.
Power off the RRU
Start
Power on the RRU
End
Whether the RUN LED on the RRU is ON for 1s and OFF for 1s and ALM LED
is OFF?
Rectify the fault
Yes
No
30
Reference
Lifting the RRU and Installation Components to the Towera
• When lifting the RRU to the tower, avoid collision of the RRU with the tower.• Lift the RRU to the tower before installing it on the metal pole, angle steel, or U-steel.
1. Route the lifting rope along the bottom of the attachment plate, lead it through the RRU handle, and knot the lifting rope. Then, tie the steering rope to the RRU handle, as shown in the following figure.
Bottom of the attachment plate
Do not lift the RRU to the tower by tying only one rope to the handle.
Steering rope
Lifting rope
31
ReferenceLifting the RRU and Installation Components to the Towera
2. Lead the rope binding the RRU and installation components through the fixed pulley, and then lift them up to the tower.
1. Installer A climbs onto the tower. Then, fixes the pulley to the support on the tower platform and leads the lifting rope through the pulley. 2. Installer C uses a lifting rope to bind the RRU and installation components as shown in the figure above and then ties a knot on the steering rope at the RRU handle.3. Installer B pulls the lifting rope downwards, and at the same time, installer C pulls the steering rope away from the tower to prevent the RRU and installation components from colliding with the tower.4. Installers A holds the RRU and installation components and unties the ropes.
A
B C
Lifting rope
Fixed pulley
Steering rope
32
Label for preparing the power cable
Reference
1、Add two OT terminals to one end of the power cable.
To add the OT terminals, perform the following steps:
Adding OT Terminals to the Power Cable of the RRUb
Determine lengths of power cables for different operations according to the scales on the cover plate of the cabling cavity.
Based on the determined lengths, remove the jacket and shielding layer from the power cable.
Remove the jacket of a specified length from each wire.
Add an OT terminal to each wire.
Remove about 15 mm jacket from the power cable. The shielding layer is exposed.
Shielding lay
-48V DC power cable -48V power wire
OT terminals
GND wire
33
ReferenceAdding OT Terminals to the Power Cable of the RRUb
2、Add an OT terminal to the end of the input power cable.
34
Reference
Pin Assignment for the Wires of the Alarm CablecDB15 connector
Signal name of DB15 connector
Cord End Terminal
Wire Color Wire Type Label
X1.2 SWITCH_INPUT0+
GND
SWITCH_INPUT1+
GND
RS485_TX-
RS485_TX+
RS485_RX-
RS485_RX+
X2 White/blue SWITCH_INPUT0+
X1.3 X3 Blue GND
X1.6 X4 White/orange
SWITCH_INPUT1+
X1.7 X5 Orange GND
X1.10 X6 White/green APM RX-
X1.11 X7 Green APM RX+
X1.13 X8 White/brown APM TX-
X1.14 X9 Brown APM TX+
Twisted pair
Twisted pair
Twisted pair
Twisted pair
PVC insulating tape
Adding OT Terminals to the Power Cable of the RRUb
OT terminal on the shielding layer
35
Changes in the RRU3804 Installation Guide
This part describes the changes in the RRU3804 Installation Guide.
07 (2009-06-30)This is the seventh commercial release.Compared with issue 06 (2009-02-26) of V200, the figures of RRU fixtures are modified.
06 (2009-02-26)
This is the sixth commercial release.Compared with issue 05 (2009-02-05) of V200, the description of power cable grounding method in the TMC+RRU scenario is modified. In addition, the description related to installation modes and requirements for installation support structure is also modified.
05 (2009-02-05)
This is the fifth commercial release.
Compared with issue 04 (2009-01-23) of V200, the description of RRU power cable grounding is modified.
HUAWEI TECHNOLOGIES CO., LTD.Huawei Industrial Base Bantian Longgang
Shenzhen 518129People’s Republic of China
www.huawei.com