Al Sufouh Transit System
Period Ending: 26 January 2010
LS 2 WET & DRY SERVICES
Progress of Works
8/14/2019 26 01 10 Weekly Progress Presentation FINL
2/71
Al Sufouh Transit SystemLS 2 WET SERVICES
Irrigation (dia 500mm A/C)Works Completed
STATION 10
Progress of Works
Drainage Line
Works Completed
Irrigation Line
Temporary Connection Done
Drainage Line (dia 315 mm)
Backfilling done.
Connect to existing mainirrigation line done
Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10
Traffic Diversion Completed
Drainage Line (dia 315 mm) Backfilling done.
Drainage Line - Manholes
Base Slab , Side Walls & Top Slab done.Top Cover (Metallic- Balance)
Drainage Line (dia 315 mm) Connection works in progress
8/14/2019 26 01 10 Weekly Progress Presentation FINL
3/71
Al Sufouh Transit SystemLS 2 WET SERVICES
STATION 11
Progress of Works
Irrigation (dia 500mm A/C) - Works Completed
Drainage line (dia 315 mm) Backfilling in Progress
Drainage Line
WorksCompleted
Drainage Line Backfilling done
Connect to main
irrigation line done
Drainage line (dia 315 mm) Manhole Base done
Irrigation Line Backfilling done.
Shutdown executed on 25th Jan10
Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10
8/14/2019 26 01 10 Weekly Progress Presentation FINL
4/71
Al Sufouh Transit SystemLS 2 WET SERVICES
Progress of Works
MH H1.14.10 (Sewerage)
Connection works in progress
Irrigation (dia 500mm)
Station 10 to Dubai college Junction: Existing Irrigation line to be removed- Shutdown executed on 25th Jan10
Washout Chamber (Irrigation) Base Slab done
Wall Casted Top Slab in progress
Branch Valve & Air Valve (Irrigation) Base Slab done
Wall Casted Top Slab Pre casted (to be placed)
Drainage line (dia 315 mm) Backfilling in Progress
Drainage line (dia 315 mm) Pipe laid. Backfilling in progress
Drainage line (dia 315 mm) Excavation done Pipe laying in progress
Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10
Sewerage (dia 315mm)
Works Completed
Flow meter Chamber (Irrigation)
Excavation done Blinding in progress
8/14/2019 26 01 10 Weekly Progress Presentation FINL
5/71
Al Sufouh Transit SystemLS 2 WET SERVICES
Progress of Works
Sewerage (dia 315mm) Future Connection: Top slab done
Irrigation (dia 500 mm) Line: Excavation done, Pipe Laid, Connection done Flow Meter : Side Walls done. Future Connection: Side Walls done Branch Valve Chamber: Walls in progress.
Drainage line (dia 315 mm)
Excavation in Progress
Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10
Irrigation (dia 500 mm) Flow Meter : Blinding Done, base slab in progress. Line: Excavation completed.
Traffic Diversion
Dubai College Junction (Closure of free right Turn) completed on 25th Jan10
8/14/2019 26 01 10 Weekly Progress Presentation FINL
6/71
Al Sufouh Transit SystemLS 2 WET SERVICES
Progress of Works
Sewerage Manhole Works Completed
Only lamination & Connection to be done
Irrigation (dia 500mm)
Works Completed
Sewerage (dia 200mm)
Works Completed
Sewerage (dia 315mm) Line: Works Completed
Auto Irrigation Line (dia 150mm)
Temporary Diversion Completed
Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10
8/14/2019 26 01 10 Weekly Progress Presentation FINL
7/71
Al Sufouh Transit SystemLS 2 WET SERVICES
STATION 12
Progress of Works
Irrigation (dia 500mm)
Works Completed
Water (dia 300mm)Works Completed
Auto - Irrigation (dia 150mm)
Diversion Completed
Drainage line (dia 315 mm)Excavation Completed
Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10
8/14/2019 26 01 10 Weekly Progress Presentation FINL
8/71
Al Sufouh Transit SystemLS 2 DRY SERVICES
Progress of Works
Electrical Works:
All light poles were relocated along this area
STATION 10
Etisalat (18 W)Completed
Etisalat Manhole Base slab doneSide walls done
Top Slab in progress
Electrical Line:
Duct Crossings done
Etisalat (18W): Backfilling done
Etisalat (18W):
Works Stopped
Electrical cable (6.6/11 kV + 132 kV)Excavation completed
Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10
8/14/2019 26 01 10 Weekly Progress Presentation FINL
9/71
Al Sufouh Transit SystemLS 2 DRY SERVICES
Progress of Works
Electrical Works:
All light poles were relocated along this area
Electrical Works:
Slewing & supporting of
existing HV Cables done
STATION11
Etisalat (18 W):
Completed
Etisalat (Manhole):
Base Slab done
Walls done Mandrill test executed
Etisalat (18W):
Concrete Encasement done
Electrical Line /Duct Crossings:
Excavation done
Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10
DU
Duct Installation.
Blinding in progress
8/14/2019 26 01 10 Weekly Progress Presentation FINL
10/71
Al Sufouh Transit SystemLS 2 DRY SERVICES
Progress of Works
Electrical Works:
Slewing of existing HV
Cables done = 130mts
Electrical Works:
Slewing of
existing HV Cables
done
Etisalat Manhole Walls Done
Etisalat (18 W) Excavation , duct laying done. Concrete Encasement done.
Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10
Etisalat (12 W) 14 m
Concrete Encased
8/14/2019 26 01 10 Weekly Progress Presentation FINL
11/71
8/14/2019 26 01 10 Weekly Progress Presentation FINL
12/71
Al Sufouh Transit SystemLS 2 DRY SERVICES
Progress of Works
Etisalat (18W):
Backfilling in progress
Exposed 11kV & 33kVCable Protection Works Done
Etisalat Manhole
Completed
Etisalat (18W):
Concrete Encasement Done
Etisalat (18W): Backfilling in progress
Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10
Etisalat (12 W) 8 mConcrete Encased
8/14/2019 26 01 10 Weekly Progress Presentation FINL
13/71
Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES
Progress of Works
8/14/2019 26 01 10 Weekly Progress Presentation FINL
14/71
8/14/2019 26 01 10 Weekly Progress Presentation FINL
15/71
Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES
Progress of Works
8/14/2019 26 01 10 Weekly Progress Presentation FINL
16/71
Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES
Progress of Works
8/14/2019 26 01 10 Weekly Progress Presentation FINL
17/71
Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES
Progress of Works
8/14/2019 26 01 10 Weekly Progress Presentation FINL
18/71
Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES
Progress of Works
8/14/2019 26 01 10 Weekly Progress Presentation FINL
19/71
Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES
Progress of Works
8/14/2019 26 01 10 Weekly Progress Presentation FINL
20/71
Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES
Progress of Works
8/14/2019 26 01 10 Weekly Progress Presentation FINL
21/71
Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES
Progress of Works
8/14/2019 26 01 10 Weekly Progress Presentation FINL
22/71
Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES
Progress of Works
8/14/2019 26 01 10 Weekly Progress Presentation FINL
23/71
Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES
Progress of Works
8/14/2019 26 01 10 Weekly Progress Presentation FINL
24/71
Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES
Progress of Works
8/14/2019 26 01 10 Weekly Progress Presentation FINL
25/71
Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES
Progress of Works
8/14/2019 26 01 10 Weekly Progress Presentation FINL
26/71
8/14/2019 26 01 10 Weekly Progress Presentation FINL
27/71
Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES
Progress of Works
8/14/2019 26 01 10 Weekly Progress Presentation FINL
28/71
Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES
Progress of Works
8/14/2019 26 01 10 Weekly Progress Presentation FINL
29/71
Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES
Progress of Works
8/14/2019 26 01 10 Weekly Progress Presentation FINL
30/71
Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES
Progress of Works
8/14/2019 26 01 10 Weekly Progress Presentation FINL
31/71
Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES
Progress of Works
8/14/2019 26 01 10 Weekly Progress Presentation FINL
32/71
8/14/2019 26 01 10 Weekly Progress Presentation FINL
33/71
Al Sufouh Transit SystemLS 3 Road Works & Traffic Diversion
Progress of Works
All Works suspended from 12th Nov09
l f h i
8/14/2019 26 01 10 Weekly Progress Presentation FINL
34/71
Al Sufouh Transit SystemLS 3 Road Works & Traffic Diversion
Progress of Works
STATION 7
Asphalt done.
Prime Coat Done (MC -70).
Removal of existing kerbstone done.
Road Diversion (Existing Road Median)
Existing Gantry Removed
Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10
Traffic Diversion (Stage 2B)
All Street lights relocated.
Traffic Diversion (Stage 2A): Road remedial works in progress
TrafficDiversion(Stage2A)Op
enedon 26Nov09
Al S f h T i S
8/14/2019 26 01 10 Weekly Progress Presentation FINL
35/71
Al Sufouh Transit SystemLS 3 Road Works & Traffic Diversion
Progress of Works
Existing paving tiles removed
STATION8
Traffic Diversion (Stage 3A) opened on 30th Dec09
Road Diversion (Existing Island corner of Media city): Road Base done. Sub grade Preparation done Removal of kerb stones & barrier (concrete) done. Removal of Traffic Signals & panel boards (RTA & Lighting) done. Excavation of existing soil up to sub grade levelling done. Removal of existing tiles done.
Traffic Diversion (Stage 2A) opened on 26th Nov09
Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10
Traffic Diversion (Stage 2A & 3A) Road Remedial Works in Progress
Al S f h T it S t
8/14/2019 26 01 10 Weekly Progress Presentation FINL
36/71
Al Sufouh Transit SystemLS 3 Road Works & Traffic Diversion
Progress of Works
Road Diversion: Removal of existing kerbstone & tiles in progress.
Excavation up to formation level in progress
STATION8
Road Diversion (Existing Median Island) Asphalt Done
Road Base Done. Light pole shifting done.
Existing Gantry Removed
Existing Gantry Removed
Road Diversion Works
Asphalt Done
Removal of paving tiles done.
Shifting of 1 No of light pole done.
Shifting of Palm tree (1 No.) done.
Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10
Al S f h T it S t
8/14/2019 26 01 10 Weekly Progress Presentation FINL
37/71
Al Sufouh Transit System
Progress of Works
Drainage line (dia. 900 mm)
Sheet Piling in progress
Road Diversion (1A & 1B) opened
Existing paving tiles removed
Traffic Diversion (Stage 3A):Opened on 30th Dec09
Road Remedial works in progress
In front of Arjaan Hotel
Embankment removal completed
Trial Pit excavation in progress.
Removal of existing automatic irrigation system.
Existing Palm Trees, Tiles & Horticulture removed.
Existing paving tiles removed.
LS 3 Road Works & Traffic Diversion
Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10
l S f h i S
8/14/2019 26 01 10 Weekly Progress Presentation FINL
38/71
Al Sufouh Transit System
Progress of Works
STATION 9
Road Diversion 1A & 1B opened
Road Diversion
Asphalting works done.
Diversion opened for traffic
LS 3 Road Works & Traffic Diversion
Gravel & Geo-textile (48 m). Concrete Surround done (60 m). Pipe laid. Sheet Piling done.
Sheet Piling Done. Excavation in Progress.
Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10
Blinding Done
Drainage line (dia. 900 mm)
Site Clearance works in progress
Al S f h T it S t
8/14/2019 26 01 10 Weekly Progress Presentation FINL
39/71
Al Sufouh Transit System
Progress of Works
Irrigation Line (dia 500 mm)
Backfilling in progress
LS3 SECTION 7
LS 3 Utilities & Services
Irrigation Line (dia 500 mm) Pipe Laying done Backfilling in progress
Drainage Line (dia 315 mm)
Pipe laid
Drainage Line (dia 315 mm)
Pipe Laid
Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10
Al S f h T it S t
8/14/2019 26 01 10 Weekly Progress Presentation FINL
40/71
Al Sufouh Transit SystemLS 3 Site Clearance
Progress of Works
Al S f h T it S t
8/14/2019 26 01 10 Weekly Progress Presentation FINL
41/71
Al Sufouh Transit SystemLS 3Road Works & Traffic Diversion
Progress of Works
Al S f h T it S t
8/14/2019 26 01 10 Weekly Progress Presentation FINL
42/71
Al Sufouh Transit SystemLS 3 Road Works & Traffic Diversion
Progress of Works
8/14/2019 26 01 10 Weekly Progress Presentation FINL
43/71
Al Sufouh Transit System
8/14/2019 26 01 10 Weekly Progress Presentation FINL
44/71
Al Sufouh Transit System
Progress of Works
LS 3Road Works & Traffic Diversion
8/14/2019 26 01 10 Weekly Progress Presentation FINL
45/71
Al Sufouh Transit System
8/14/2019 26 01 10 Weekly Progress Presentation FINL
46/71
Al Sufouh Transit SystemLS 3Road Works & Traffic Diversion
Progress of Works
Al Sufouh Transit System
8/14/2019 26 01 10 Weekly Progress Presentation FINL
47/71
Al Sufouh Transit SystemLS 3Road Works & Traffic Diversion
Progress of Works
8/14/2019 26 01 10 Weekly Progress Presentation FINL
48/71
Al Sufouh Transit System
8/14/2019 26 01 10 Weekly Progress Presentation FINL
49/71
Al Sufouh Transit SystemLS 3Utilities & Services
Progress of Works
Al Sufouh Transit System
8/14/2019 26 01 10 Weekly Progress Presentation FINL
50/71
Al Sufouh Transit SystemLS 3 Utilities & Services
Progress of Works
Al Sufouh Transit System
8/14/2019 26 01 10 Weekly Progress Presentation FINL
51/71
Al Sufouh Transit SystemLS 3 Utilities & Services
Progress of Works
Al Sufouh Transit System
8/14/2019 26 01 10 Weekly Progress Presentation FINL
52/71
Al Sufouh Transit SystemLS2 - Utilities & Services
Progress of Works
Utilities & Services - Status as on 25th
Jan'09LS2 - Utilities & Services
Utility/Service Scope Of Works (inLm)
Total Executed (inLm)
% Complete Remarks
Wet Water
Dia 300 mm 155 155 100%
Drainage
Dia 315 mm 1848 977 53%
Sewerage
Dia 315mm 325 325 100%
Dia 200mm 310 165 53%
Irrigation
Dia 500 mm 1761 1387 79%
Dry Etisalat
Duct (18 W) 1045 885 85%
Electrical
132 kV Pilot cable 1459 300 m Excavation done in Sec -1
33 kV Pilot cable 1145 300 m Excavation done in Sec -1
33 kV Power cable 2294 300 m Excavation done in Sec -1
11 kv Cable 8627 300 m Excavation done in Sec -1
8/14/2019 26 01 10 Weekly Progress Presentation FINL
53/71
Al Sufouh Transit System
8/14/2019 26 01 10 Weekly Progress Presentation FINL
54/71
Al Sufouh Transit SystemLS 4 Civil Works
Progress of Works
Period Ending: 26 January 2010
8/14/2019 26 01 10 Weekly Progress Presentation FINL
55/71
Al Sufouh Transit System
8/14/2019 26 01 10 Weekly Progress Presentation FINL
56/71
Al Sufouh Transit SystemLS 4 Civil Works
Progress of Works
STATION 1
Sheet Piling - 100%
Excavation - 100%
Duct Bank P0W
CH. 1888-1535 = 353m
LV Duct BankCh 1888 1535 = 353 m
APS Cast 20 m
Track Slab Cast
(1600-1590) - 10 m LEGEND:
Progress till 18 Jan10
Progress from 19 Jan10 to 25 Jan10
Pulling Chambers 9 No. Completed
DCS Masts 2 No. Completed
Works Suspended w.e.f. 11th Jan10
8/14/2019 26 01 10 Weekly Progress Presentation FINL
57/71
Al Sufouh Transit System
8/14/2019 26 01 10 Weekly Progress Presentation FINL
58/71
Al Sufouh Transit SystemLS 1 Civil Works
VIADUCT Pile P1 to Station 3
PROGRESS OF WORKS FOR LS1-VIADUCT
PILE P1 TO STATION 3
19-Jan-2010 To 25-Jan-2010
SITE PROGRESS CUMULATIVE UP TO 25-Jan-2010
SITE PROGRESS 19-Jan-2010 TO 25 JAN-2010
SEGMENT PRECASTING CUMULATIVE UP TO 25-Jan-2010
SEGMENT PRECASTING: 19-Jan-2010 TO 25-JAN-2010
Al Sufouh Transit System
8/14/2019 26 01 10 Weekly Progress Presentation FINL
59/71
Al Sufouh Transit SystemLS 1 Civil Works
VIADUCT Station 3 to Station 4
SITE PROGRESS CUMULATIVE UP TO 25.-Jan-2010
SITE PROGRESS 19-Jan-2010 TO 25-Jan-2010
SEGMENT PRECASTING CUMULATIVE UP TO 25-Jan-2010
SEGMENT PRECASTING: 19-Jan-2010 TO 25-Jan-2010
PROGRESS OF WORKS FOR LS1-VIADUCT
STATION 3 To STATION 4
19-Jan-2010 To 25-Jan-2010
Al Sufouh Transit System
8/14/2019 26 01 10 Weekly Progress Presentation FINL
60/71
Al Sufouh Transit SystemLS 1 Civil Works
VIADUCT Station 4 to Station 5
SITE PROGRESS CUMULATIVE UP TO 25-Jan-2010
SITE PROGRESS 19-Jan-2010 TO 25-Jan-2010
SEGMENT PRECASTING CUMULATIVE UP TO 25-Jan-2010
SEGMENT PRECASTING: 19-Jan-2010 TO 25-Jan-2010
PROGRESS OF WORKS FOR LS1-VIADUCT
STATION 4 To STATION 5
19-Jan-2010 To 25-Jan-2010
Al Sufouh Transit System
8/14/2019 26 01 10 Weekly Progress Presentation FINL
61/71
Al Sufouh Transit SystemLS1 Civil Works
VIADUCT Station 5 to Station 6
SITE PROGRESS CUMULATIVE UP TO 25-Jan-2010
SITE PROGRESS 19-Jan-2010 TO 25-Jan-2010
SEGMENT PRECASTING CUMULATIVE UP TO 25-Jan-2010
SEGMENT PRECASTING: 19-Jan-2009 TO 25-Jan-2010
PROGRESS OF WORKS FOR LS1-VIADUCT
STATION 5 To STATION 6
19-Jan-2010 To 25-Jan-2010
8/14/2019 26 01 10 Weekly Progress Presentation FINL
62/71
8/14/2019 26 01 10 Weekly Progress Presentation FINL
63/71
46 of 74 Piers 62.2%
8/14/2019 26 01 10 Weekly Progress Presentation FINL
64/71
684 of 849 Segments 80.6%
8/14/2019 26 01 10 Weekly Progress Presentation FINL
65/71
31of 93 Spans 33.3%
Al Sufouh Transit System
8/14/2019 26 01 10 Weekly Progress Presentation FINL
66/71
Al Sufouh Transit SystemLS 1 Civil Works
Progress of Works
Al Sufouh Transit System
8/14/2019 26 01 10 Weekly Progress Presentation FINL
67/71
Al Sufouh Transit SystemLS 1 Civil Works
Progress of Works
Al Sufouh Transit System
8/14/2019 26 01 10 Weekly Progress Presentation FINL
68/71
Al Sufouh Transit SystemLS 1 Civil Works
Progress of Works
Al Sufouh Transit System
8/14/2019 26 01 10 Weekly Progress Presentation FINL
69/71
Al Sufouh Transit SystemLS 1 Civil Works
Progress of Works
Al Sufouh Transit System
8/14/2019 26 01 10 Weekly Progress Presentation FINL
70/71
Al Sufouh Transit SystemLS 1 Civil Works
Progress of Works
8/14/2019 26 01 10 Weekly Progress Presentation FINL
71/71
Al Sufouh Transit System
THE END...