    Al Sufouh Transit System

    Period Ending: 26 January 2010

    LS 2 WET & DRY SERVICES

    Progress of Works

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    2/71

    Al Sufouh Transit SystemLS 2 WET SERVICES

    Irrigation (dia 500mm A/C)Works Completed

    STATION 10

    Progress of Works

    Drainage Line

    Works Completed

    Irrigation Line

    Temporary Connection Done

    Drainage Line (dia 315 mm)

    Backfilling done.

    Connect to existing mainirrigation line done

    Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10

    Traffic Diversion Completed

    Drainage Line (dia 315 mm) Backfilling done.

    Drainage Line - Manholes

    Base Slab , Side Walls & Top Slab done.Top Cover (Metallic- Balance)

    Drainage Line (dia 315 mm) Connection works in progress

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    3/71

    Al Sufouh Transit SystemLS 2 WET SERVICES

    STATION 11

    Progress of Works

    Irrigation (dia 500mm A/C) - Works Completed

    Drainage line (dia 315 mm) Backfilling in Progress

    Drainage Line

    WorksCompleted

    Drainage Line Backfilling done

    Connect to main

    irrigation line done

    Drainage line (dia 315 mm) Manhole Base done

    Irrigation Line Backfilling done.

    Shutdown executed on 25th Jan10

    Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    4/71

    Al Sufouh Transit SystemLS 2 WET SERVICES

    Progress of Works

    MH H1.14.10 (Sewerage)

    Connection works in progress

    Irrigation (dia 500mm)

    Station 10 to Dubai college Junction: Existing Irrigation line to be removed- Shutdown executed on 25th Jan10

    Washout Chamber (Irrigation) Base Slab done

    Wall Casted Top Slab in progress

    Branch Valve & Air Valve (Irrigation) Base Slab done

    Wall Casted Top Slab Pre casted (to be placed)

    Drainage line (dia 315 mm) Backfilling in Progress

    Drainage line (dia 315 mm) Pipe laid. Backfilling in progress

    Drainage line (dia 315 mm) Excavation done Pipe laying in progress

    Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10

    Sewerage (dia 315mm)

    Works Completed

    Flow meter Chamber (Irrigation)

    Excavation done Blinding in progress

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    5/71

    Al Sufouh Transit SystemLS 2 WET SERVICES

    Progress of Works

    Sewerage (dia 315mm) Future Connection: Top slab done

    Irrigation (dia 500 mm) Line: Excavation done, Pipe Laid, Connection done Flow Meter : Side Walls done. Future Connection: Side Walls done Branch Valve Chamber: Walls in progress.

    Drainage line (dia 315 mm)

    Excavation in Progress

    Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10

    Irrigation (dia 500 mm) Flow Meter : Blinding Done, base slab in progress. Line: Excavation completed.

    Traffic Diversion

    Dubai College Junction (Closure of free right Turn) completed on 25th Jan10

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    6/71

    Al Sufouh Transit SystemLS 2 WET SERVICES

    Progress of Works

    Sewerage Manhole Works Completed

    Only lamination & Connection to be done

    Irrigation (dia 500mm)

    Works Completed

    Sewerage (dia 200mm)

    Works Completed

    Sewerage (dia 315mm) Line: Works Completed

    Auto Irrigation Line (dia 150mm)

    Temporary Diversion Completed

    Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    7/71

    Al Sufouh Transit SystemLS 2 WET SERVICES

    STATION 12

    Progress of Works

    Irrigation (dia 500mm)

    Works Completed

    Water (dia 300mm)Works Completed

    Auto - Irrigation (dia 150mm)

    Diversion Completed

    Drainage line (dia 315 mm)Excavation Completed

    Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    8/71

    Al Sufouh Transit SystemLS 2 DRY SERVICES

    Progress of Works

    Electrical Works:

    All light poles were relocated along this area

    STATION 10

    Etisalat (18 W)Completed

    Etisalat Manhole Base slab doneSide walls done

    Top Slab in progress

    Electrical Line:

    Duct Crossings done

    Etisalat (18W): Backfilling done

    Etisalat (18W):

    Works Stopped

    Electrical cable (6.6/11 kV + 132 kV)Excavation completed

    Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    9/71

    Al Sufouh Transit SystemLS 2 DRY SERVICES

    Progress of Works

    Electrical Works:

    All light poles were relocated along this area

    Electrical Works:

    Slewing & supporting of

    existing HV Cables done

    STATION11

    Etisalat (18 W):

    Completed

    Etisalat (Manhole):

    Base Slab done

    Walls done Mandrill test executed

    Etisalat (18W):

    Concrete Encasement done

    Electrical Line /Duct Crossings:

    Excavation done

    Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10

    DU

    Duct Installation.

    Blinding in progress

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    10/71

    Al Sufouh Transit SystemLS 2 DRY SERVICES

    Progress of Works

    Electrical Works:

    Slewing of existing HV

    Cables done = 130mts

    Electrical Works:

    Slewing of

    existing HV Cables

    done

    Etisalat Manhole Walls Done

    Etisalat (18 W) Excavation , duct laying done. Concrete Encasement done.

    Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10

    Etisalat (12 W) 14 m

    Concrete Encased

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    11/71

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    12/71

    Al Sufouh Transit SystemLS 2 DRY SERVICES

    Progress of Works

    Etisalat (18W):

    Backfilling in progress

    Exposed 11kV & 33kVCable Protection Works Done

    Etisalat Manhole

    Completed

    Etisalat (18W):

    Concrete Encasement Done

    Etisalat (18W): Backfilling in progress

    Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10

    Etisalat (12 W) 8 mConcrete Encased

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    13/71

    Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES

    Progress of Works

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    14/71

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    15/71

    Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES

    Progress of Works

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    16/71

    Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES

    Progress of Works

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    17/71

    Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES

    Progress of Works

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    18/71

    Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES

    Progress of Works

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    19/71

    Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES

    Progress of Works

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    20/71

    Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES

    Progress of Works

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    21/71

    Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES

    Progress of Works

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    22/71

    Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES

    Progress of Works

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    23/71

    Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES

    Progress of Works

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    24/71

    Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES

    Progress of Works

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    25/71

    Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES

    Progress of Works

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    26/71

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    27/71

    Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES

    Progress of Works

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    28/71

    Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES

    Progress of Works

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    29/71

    Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES

    Progress of Works

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    30/71

    Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES

    Progress of Works

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    31/71

    Al Sufouh Transit SystemLS 2 UTILITIES & SERVICES

    Progress of Works

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    32/71

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    33/71

    Al Sufouh Transit SystemLS 3 Road Works & Traffic Diversion

    Progress of Works

    All Works suspended from 12th Nov09

    l f h i

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    34/71

    Al Sufouh Transit SystemLS 3 Road Works & Traffic Diversion

    Progress of Works

    STATION 7

    Asphalt done.

    Prime Coat Done (MC -70).

    Removal of existing kerbstone done.

    Road Diversion (Existing Road Median)

    Existing Gantry Removed

    Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10

    Traffic Diversion (Stage 2B)

    All Street lights relocated.

    Traffic Diversion (Stage 2A): Road remedial works in progress

    TrafficDiversion(Stage2A)Op

    enedon 26Nov09

    Al S f h T i S

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    35/71

    Al Sufouh Transit SystemLS 3 Road Works & Traffic Diversion

    Progress of Works

    Existing paving tiles removed

    STATION8

    Traffic Diversion (Stage 3A) opened on 30th Dec09

    Road Diversion (Existing Island corner of Media city): Road Base done. Sub grade Preparation done Removal of kerb stones & barrier (concrete) done. Removal of Traffic Signals & panel boards (RTA & Lighting) done. Excavation of existing soil up to sub grade levelling done. Removal of existing tiles done.

    Traffic Diversion (Stage 2A) opened on 26th Nov09

    Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10

    Traffic Diversion (Stage 2A & 3A) Road Remedial Works in Progress

    Al S f h T it S t

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    36/71

    Al Sufouh Transit SystemLS 3 Road Works & Traffic Diversion

    Progress of Works

    Road Diversion: Removal of existing kerbstone & tiles in progress.

    Excavation up to formation level in progress

    STATION8

    Road Diversion (Existing Median Island) Asphalt Done

    Road Base Done. Light pole shifting done.

    Existing Gantry Removed

    Existing Gantry Removed

    Road Diversion Works

    Asphalt Done

    Removal of paving tiles done.

    Shifting of 1 No of light pole done.

    Shifting of Palm tree (1 No.) done.

    Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10

    Al S f h T it S t

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    37/71

    Al Sufouh Transit System

    Progress of Works

    Drainage line (dia. 900 mm)

    Sheet Piling in progress

    Road Diversion (1A & 1B) opened

    Existing paving tiles removed

    Traffic Diversion (Stage 3A):Opened on 30th Dec09

    Road Remedial works in progress

    In front of Arjaan Hotel

    Embankment removal completed

    Trial Pit excavation in progress.

    Removal of existing automatic irrigation system.

    Existing Palm Trees, Tiles & Horticulture removed.

    Existing paving tiles removed.

    LS 3 Road Works & Traffic Diversion

    Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10

    l S f h i S

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    38/71

    Al Sufouh Transit System

    Progress of Works

    STATION 9

    Road Diversion 1A & 1B opened

    Road Diversion

    Asphalting works done.

    Diversion opened for traffic

    LS 3 Road Works & Traffic Diversion

    Gravel & Geo-textile (48 m). Concrete Surround done (60 m). Pipe laid. Sheet Piling done.

    Sheet Piling Done. Excavation in Progress.

    Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10

    Blinding Done

    Drainage line (dia. 900 mm)

    Site Clearance works in progress

    Al S f h T it S t

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    39/71

    Al Sufouh Transit System

    Progress of Works

    Irrigation Line (dia 500 mm)

    Backfilling in progress

    LS3 SECTION 7

    LS 3 Utilities & Services

    Irrigation Line (dia 500 mm) Pipe Laying done Backfilling in progress

    Drainage Line (dia 315 mm)

    Pipe laid

    Drainage Line (dia 315 mm)

    Pipe Laid

    Progress till 18 Jan10 Progress from 19 Jan10 to 25 Jan10

    Al S f h T it S t

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    40/71

    Al Sufouh Transit SystemLS 3 Site Clearance

    Progress of Works

    Al S f h T it S t

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    41/71

    Al Sufouh Transit SystemLS 3Road Works & Traffic Diversion

    Progress of Works

    Al S f h T it S t

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    42/71

    Al Sufouh Transit SystemLS 3 Road Works & Traffic Diversion

    Progress of Works

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    43/71

    Al Sufouh Transit System

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    44/71

    Al Sufouh Transit System

    Progress of Works

    LS 3Road Works & Traffic Diversion

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    45/71

    Al Sufouh Transit System

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    46/71

    Al Sufouh Transit SystemLS 3Road Works & Traffic Diversion

    Progress of Works

    Al Sufouh Transit System

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    47/71

    Al Sufouh Transit SystemLS 3Road Works & Traffic Diversion

    Progress of Works

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    48/71

    Al Sufouh Transit System

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    49/71

    Al Sufouh Transit SystemLS 3Utilities & Services

    Progress of Works

    Al Sufouh Transit System

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    50/71

    Al Sufouh Transit SystemLS 3 Utilities & Services

    Progress of Works

    Al Sufouh Transit System

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    51/71

    Al Sufouh Transit SystemLS 3 Utilities & Services

    Progress of Works

    Al Sufouh Transit System

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    52/71

    Al Sufouh Transit SystemLS2 - Utilities & Services

    Progress of Works

    Utilities & Services - Status as on 25th

    Jan'09LS2 - Utilities & Services

    Utility/Service Scope Of Works (inLm)

    Total Executed (inLm)

    % Complete Remarks

    Wet Water

    Dia 300 mm 155 155 100%

    Drainage

    Dia 315 mm 1848 977 53%

    Sewerage

    Dia 315mm 325 325 100%

    Dia 200mm 310 165 53%

    Irrigation

    Dia 500 mm 1761 1387 79%

    Dry Etisalat

    Duct (18 W) 1045 885 85%

    Electrical

    132 kV Pilot cable 1459 300 m Excavation done in Sec -1

    33 kV Pilot cable 1145 300 m Excavation done in Sec -1

    33 kV Power cable 2294 300 m Excavation done in Sec -1

    11 kv Cable 8627 300 m Excavation done in Sec -1

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    53/71

    Al Sufouh Transit System

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    54/71

    Al Sufouh Transit SystemLS 4 Civil Works

    Progress of Works

    Period Ending: 26 January 2010

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    55/71

    Al Sufouh Transit System

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    56/71

    Al Sufouh Transit SystemLS 4 Civil Works

    Progress of Works

    STATION 1

    Sheet Piling - 100%

    Excavation - 100%

    Duct Bank P0W

    CH. 1888-1535 = 353m

    LV Duct BankCh 1888 1535 = 353 m

    APS Cast 20 m

    Track Slab Cast

    (1600-1590) - 10 m LEGEND:

    Progress till 18 Jan10

    Progress from 19 Jan10 to 25 Jan10

    Pulling Chambers 9 No. Completed

    DCS Masts 2 No. Completed

    Works Suspended w.e.f. 11th Jan10

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    57/71

    Al Sufouh Transit System

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    58/71

    Al Sufouh Transit SystemLS 1 Civil Works

    VIADUCT Pile P1 to Station 3

    PROGRESS OF WORKS FOR LS1-VIADUCT

    PILE P1 TO STATION 3

    19-Jan-2010 To 25-Jan-2010

    SITE PROGRESS CUMULATIVE UP TO 25-Jan-2010

    SITE PROGRESS 19-Jan-2010 TO 25 JAN-2010

    SEGMENT PRECASTING CUMULATIVE UP TO 25-Jan-2010

    SEGMENT PRECASTING: 19-Jan-2010 TO 25-JAN-2010

    Al Sufouh Transit System

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    59/71

    Al Sufouh Transit SystemLS 1 Civil Works

    VIADUCT Station 3 to Station 4

    SITE PROGRESS CUMULATIVE UP TO 25.-Jan-2010

    SITE PROGRESS 19-Jan-2010 TO 25-Jan-2010

    SEGMENT PRECASTING CUMULATIVE UP TO 25-Jan-2010

    SEGMENT PRECASTING: 19-Jan-2010 TO 25-Jan-2010

    PROGRESS OF WORKS FOR LS1-VIADUCT

    STATION 3 To STATION 4

    19-Jan-2010 To 25-Jan-2010

    Al Sufouh Transit System

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    60/71

    Al Sufouh Transit SystemLS 1 Civil Works

    VIADUCT Station 4 to Station 5

    SITE PROGRESS CUMULATIVE UP TO 25-Jan-2010

    SITE PROGRESS 19-Jan-2010 TO 25-Jan-2010

    SEGMENT PRECASTING CUMULATIVE UP TO 25-Jan-2010

    SEGMENT PRECASTING: 19-Jan-2010 TO 25-Jan-2010

    PROGRESS OF WORKS FOR LS1-VIADUCT

    STATION 4 To STATION 5

    19-Jan-2010 To 25-Jan-2010

    Al Sufouh Transit System

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    61/71

    Al Sufouh Transit SystemLS1 Civil Works

    VIADUCT Station 5 to Station 6

    SITE PROGRESS CUMULATIVE UP TO 25-Jan-2010

    SITE PROGRESS 19-Jan-2010 TO 25-Jan-2010

    SEGMENT PRECASTING CUMULATIVE UP TO 25-Jan-2010

    SEGMENT PRECASTING: 19-Jan-2009 TO 25-Jan-2010

    PROGRESS OF WORKS FOR LS1-VIADUCT

    STATION 5 To STATION 6

    19-Jan-2010 To 25-Jan-2010

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    62/71

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    63/71

    46 of 74 Piers 62.2%

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    64/71

    684 of 849 Segments 80.6%

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    65/71

    31of 93 Spans 33.3%

    Al Sufouh Transit System

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    66/71

    Al Sufouh Transit SystemLS 1 Civil Works

    Progress of Works

    Al Sufouh Transit System

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    67/71

    Al Sufouh Transit SystemLS 1 Civil Works

    Progress of Works

    Al Sufouh Transit System

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    68/71

    Al Sufouh Transit SystemLS 1 Civil Works

    Progress of Works

    Al Sufouh Transit System

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    69/71

    Al Sufouh Transit SystemLS 1 Civil Works

    Progress of Works

    Al Sufouh Transit System

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    70/71

    Al Sufouh Transit SystemLS 1 Civil Works

    Progress of Works

  • 8/14/2019 26 01 10 Weekly Progress Presentation FINL

    71/71

    Al Sufouh Transit System

    THE END...

    THANK YOU!!!