1 LAHORE WASTE MANAGEMENT COMPANY. Expression of Interest Published in July 22, 2013 in local and...

Post on 16-Jan-2016

213 views 0 download

Tags:

Transcript of 1 LAHORE WASTE MANAGEMENT COMPANY. Expression of Interest Published in July 22, 2013 in local and...

1

LAHORE WASTE MANAGEMENT COMPANY

Expression of Interest Published in July 22, 2013 in local and international press Published in Gulf international, Zamaan Turkey,

Daily China & international websites and Pakistani newspapers

EOI Validity was till September 15, 2013 Seventy (70) companies were contacted by

the LWMC Twenty Nine (29) companies submitted their

EOIs.

2

List of Companies

Twenty (20) companies are being shortlisted and Letter of acceptance are sent to all

20 companies as yet. These companies are called for meeting

with MD LWMC for further proceedings.

3

4

5

Sr. #

Name of company

Technology

Generation of Power

Amount of waste (tons/day)

Estimated cost (US$ Million)

1. Reality Renewables, Manchester UK(BOO)

Pyrolysis Mr. Neil and Kevin visited LWMC, landfill site, Signing of MOU in

process, Technical team will visit LWMC after MOU

2. EAWC, Technologies, Miami USA(Rep visited LWMC, Skype conf.)

Plasma 1 MW 12 4

3. IMPACT GLOBAL EMISSION

SOLUTIONS, London UK

Pyrolysis

30 MW 800 -

6

Sr. #

Name of company

Technology

Generation of Power

Amount of waste (tons/day)

Estimated cost (US$ Million)

4 COWI, Denmark (Turn Key project)

Incineration 25 MW 1500 -

5 Hitz, Hitachi Zosen corp. Tokyo Japan(DBO)

Incineration 6.6 MW 420 -

6 Mumtaz Construction Company with Naanovo energy Inc., Ottawa Canada (BOT or BOO)

Mass burn /Incineration

30 MW 2000 -

7

Sr. #

Name of company Technology

Generation of Power

Amount of waste (tons/day)

Estimated cost (US$ Million)

7 Omega/ GTS energy private Ltd., Oregon USA(BOO)

Plasma Arc/gasification

3.9 250 -

8 Vinci Environnement / Technical Assosiate Pakistan Pvt Ltd

Inceneration

- - -

9 Salman & Associates with Energy Projeckt i Serverige AB, Sweden

Incineration

0.5 to 4 MW

100 -

10 Global Green International, Singapore

Pyrolysis 2 MW/h 20 -

8

Sr. #

Name of company Technology

Generation of Power

Amount of waste (tons/day)

Estimated cost (US$ Million)

11AFCO Enterprises Gasification

4 MW 100 -

12 AL - WASEH INTERNATIONAL CO, JV (BMEI & Co) TIAJIN DESIGN & RESEARCH

INSTITUTE OF ELECTRIC DRIVE CO.

Ltd

Incineration

- - -

13 Swede Tech International (Pvt) Ltd

Incineration - - -

9

Sr. #

Name of company Technology Generation of Power

Amount of waste (tons/day)

Estimated cost (US$ Million)

14 DESCON ENGINEERING PVT Ltd., A Group Of

CnimMass -Burn

- - -

15 CONSORTIUM OF EUROCONSULT -46 K-I Model Town Lahore

Anaerobic Digestion

- - -

16Albario Engineering

Pvt Ltd

Inineration/ Gasification

- - -

17Se Group Rebuilding

Society

Pyrolysis 37 1000

10

Sr. #

Name of company

Technology

Generation of Power

Amount of waste (tons/day)

Estimated cost (US$ Million)

18Satarem A.G -

20-60 - -

19K-axis Engineering

(incineration)

- - -

20Escorts Pakistan

biomass energy

- 1500-2000

-

11

Mr. Neil Vaughan Jones, and Mr. Kevin King of M/s Reality Renewables meeting

with LWMC on 12-09-2013

Eight (08) Consultants/companies have shown interest in WtE project in Lahore and submitted their Proposals. Technical evaluation of all the consultants is done.

BOD of LWMC principally approved in its meeting held on 16-09-2013 to build the capacity of LWMC for WTE projects and hiring of consultants

12

13

Professor Nickolas J Themelis has been

selected

His services will be backed by the firm

M/s Ecoair

Vast experience of WTE projects

US $ 27,500/- for four weeks of

assignment Consultant is expected to be mobilized in

2nd week of October 2013.

TORs

CV

Review and Screening of EOIs for WTE Technologies

by 3rd week of October 2013

Int. consultant on board by 2nd Week of October

2013.

Preparation of technical feasibility by January 2014

Start of construction of project by June 2014

Start of production of electricity by April 2015

14

Production of 1 MW from 100 tons/day with US$ 1.5 to 2 million with huge Environmental emissions – as per Indian Model

Technical Feasibility to be conducted by the consultant

Efficient options available from current EOIs with possibility of investor

Companies from Japan, Denmark, China etc., provide incineration technology

15

State of the art Thermal waste Treatment plant – Grate fired incineration

Maximum output of 11.4 MW

600 tons of feedstock per day

Total investment of US$ 3,600,000 Commissioning start October 2015 First waste fire January 2016

16

State of the art Combustion plant Maximum output of 4 MW

100 tons of feedstock per day

Total investment of 3.75 Million €

17

Decision on upfront tariff for waste to energy projects

Investment subsidy on capital investment

Capacity building for Implementation of WTE project

18