1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

Post on 26-Dec-2015

218 views 3 download

Tags:

Transcript of 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

1

Corridor Cities Transitway

Presented to:Amberfield HOA

January 15, 2015

2

Project History

• I-270/US 15 Multi-Modal Corridor Study– Highway needs too great– Inclusion of the Corridor Cities Transitway– DEIS, AA/EA, SEA– Independent Utility

3

Locally Preferred Alternative

• Governor O’Malley: May 11, 2012

• Mode: Bus Rapid Transit– 2 lanes– Exclusive guideway– Hiker/biker trail

• 16 mile alignment– Shady Grove to Metropolitan

Grove (9 mile Phase I)

• Maintenance Facility: Near Metropolitan Grove

• Phased Construction

4

What is BRT?

• LRT on Rubber Tires• Modern, low floor vehicles• Multiple door entry • Advanced fare payment• Varied runningways • Stations• Signal priority/preemption• Real-time transit info• High frequency service• Operates on intervals, not a

timetable• Branded – recognizable and distinct

5

Operations• CCT Direct Service and CCT via USG• Ridership– 36,000 trips per day in 2035

• Design year headways– 3.5 minutes peak– 6 minutes mid-day– 10 minutes off-peak

• Bus Fleet– 60 ft articulated, low floor, clean diesel hybrid-electric– 39 total buses

6

Current Schedule• August 2014 – Draft EA and 15% Design Submittal• August 2015 – 30% Design• September 2015 – FONSI• Winter 2015/2016 – Initiate design activities• Winter 2016/2017 – Begin Right-of Way

Acquisition/ Permitting/ Agreements• Spring 2018 – Begin Construction• 2021 – Begin Service

7

Transitway Alignment• Nine miles exclusive right-of-way• Side running along SHA and Montgomery

County roadways• Median running on Montgomery County and

City of Rockville roadways• Limited roadway reconstruction since

alignment is through planned or future developments

8

Transitway Alignment

9

Transitway Alignment

10

Typical Sections

11

Follow-up Questions

Rick KiegelMTA Office of Planning and Programming

410-767-1380rkiegel@mta.maryland.gov

12

Station Architecture

13

Station Prototype• Platforms - 150’ X 18’• Entrances - Primary &

Secondary• Canopy - 60% coverage• Amenities – ticketing,

benches, etc.• Ancillary enclosure

14

Concept 1: Surface Station

Framework• Establish presence

• Column free platform• Clarity• Safety

• Translucent canopy

• W-section primary frame

• HSS canopy grid

02_PLATFORM VIEW

01_AERIAL VIEW

15

Concept 1: Aerial StationFramework• Community Space

• Vertical Circulation

• Establish presence

• Column free platform• Clarity• Safety

• Translucent Canopy

• W-section primary frame

• HSS canopy frame

01_PLAZA LEVEL VIEW

02_STREET LEVEL VIEW

16

Concept 2: Surface StationHelix• Contextual influence:

Bioscience

• Helix as generative form

• Translucent Canopy

• Tree Structure• Concrete column• Steel Pipe Frame

02_PLATFORM VIEW

01_AERIAL VIEW

17

Concept 2: Aerial StationHelix• Community Space

• Vertical Circulation

• Contextual influence:• Bioscience

• Helix as generative form

• Tree Structure• Concrete column• Steel Pipe Frame

01_PLAZA LEVEL VIEW

02_STREET LEVEL VIEW

18

Operations and Maintenance Facility

19

Operations and Maintenance Facility• Secure Site• Counter-clockwise

circulation : Site lines• Parking for initial

operations• Efficient & safe

user/bus circulation

01_CIRCULATION DIAGRAM

20

Traffic Signals• Total of 37 signal: 19 new, 17 rebuild, and 1

active control• Transit Signal Priority installed corridor wide• Current plans show existing and proposed

above ground elements• Traffic signal plans will be reviewed by SHA,

MCDOT, and City of Rockville

21

Traffic Signals• Transit Signal Priority

• Concept of Operations Currently Being Developed:– Focus: maintain correct separation between buses – Priority will be conditional: applied only when issues occur– Potential priority given: green extension at end of cycle or red

truncation at beginning of cycle– Warrant analysis: determine where TSP will be installed

» Based on intersection V/C

22

Urban DesignStation Area Concept• Specialized pavement areas• Pedestrian lighting• Crosswalk treatments• Transitway treatment• Community signage

Projectwide• Transitway treatment• Finish for structures: MSE walls,

retaining walls, portals• Crosswalk treatment• Wayfinding signage

01_Metropolitan Grove