1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

22
1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015

Transcript of 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

Page 1: 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

1

Corridor Cities Transitway

Presented to:Amberfield HOA

January 15, 2015

Page 2: 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

2

Project History

• I-270/US 15 Multi-Modal Corridor Study– Highway needs too great– Inclusion of the Corridor Cities Transitway– DEIS, AA/EA, SEA– Independent Utility

Page 3: 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

3

Locally Preferred Alternative

• Governor O’Malley: May 11, 2012

• Mode: Bus Rapid Transit– 2 lanes– Exclusive guideway– Hiker/biker trail

• 16 mile alignment– Shady Grove to Metropolitan

Grove (9 mile Phase I)

• Maintenance Facility: Near Metropolitan Grove

• Phased Construction

Page 4: 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

4

What is BRT?

• LRT on Rubber Tires• Modern, low floor vehicles• Multiple door entry • Advanced fare payment• Varied runningways • Stations• Signal priority/preemption• Real-time transit info• High frequency service• Operates on intervals, not a

timetable• Branded – recognizable and distinct

Page 5: 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

5

Operations• CCT Direct Service and CCT via USG• Ridership– 36,000 trips per day in 2035

• Design year headways– 3.5 minutes peak– 6 minutes mid-day– 10 minutes off-peak

• Bus Fleet– 60 ft articulated, low floor, clean diesel hybrid-electric– 39 total buses

Page 6: 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

6

Current Schedule• August 2014 – Draft EA and 15% Design Submittal• August 2015 – 30% Design• September 2015 – FONSI• Winter 2015/2016 – Initiate design activities• Winter 2016/2017 – Begin Right-of Way

Acquisition/ Permitting/ Agreements• Spring 2018 – Begin Construction• 2021 – Begin Service

Page 7: 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

7

Transitway Alignment• Nine miles exclusive right-of-way• Side running along SHA and Montgomery

County roadways• Median running on Montgomery County and

City of Rockville roadways• Limited roadway reconstruction since

alignment is through planned or future developments

Page 8: 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

8

Transitway Alignment

Page 9: 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

9

Transitway Alignment

Page 10: 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

10

Typical Sections

Page 11: 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

11

Follow-up Questions

Rick KiegelMTA Office of Planning and Programming

[email protected]

Page 12: 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

12

Station Architecture

Page 13: 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

13

Station Prototype• Platforms - 150’ X 18’• Entrances - Primary &

Secondary• Canopy - 60% coverage• Amenities – ticketing,

benches, etc.• Ancillary enclosure

Page 14: 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

14

Concept 1: Surface Station

Framework• Establish presence

• Column free platform• Clarity• Safety

• Translucent canopy

• W-section primary frame

• HSS canopy grid

02_PLATFORM VIEW

01_AERIAL VIEW

Page 15: 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

15

Concept 1: Aerial StationFramework• Community Space

• Vertical Circulation

• Establish presence

• Column free platform• Clarity• Safety

• Translucent Canopy

• W-section primary frame

• HSS canopy frame

01_PLAZA LEVEL VIEW

02_STREET LEVEL VIEW

Page 16: 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

16

Concept 2: Surface StationHelix• Contextual influence:

Bioscience

• Helix as generative form

• Translucent Canopy

• Tree Structure• Concrete column• Steel Pipe Frame

02_PLATFORM VIEW

01_AERIAL VIEW

Page 17: 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

17

Concept 2: Aerial StationHelix• Community Space

• Vertical Circulation

• Contextual influence:• Bioscience

• Helix as generative form

• Tree Structure• Concrete column• Steel Pipe Frame

01_PLAZA LEVEL VIEW

02_STREET LEVEL VIEW

Page 18: 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

18

Operations and Maintenance Facility

Page 19: 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

19

Operations and Maintenance Facility• Secure Site• Counter-clockwise

circulation : Site lines• Parking for initial

operations• Efficient & safe

user/bus circulation

01_CIRCULATION DIAGRAM

Page 20: 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

20

Traffic Signals• Total of 37 signal: 19 new, 17 rebuild, and 1

active control• Transit Signal Priority installed corridor wide• Current plans show existing and proposed

above ground elements• Traffic signal plans will be reviewed by SHA,

MCDOT, and City of Rockville

Page 21: 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

21

Traffic Signals• Transit Signal Priority

• Concept of Operations Currently Being Developed:– Focus: maintain correct separation between buses – Priority will be conditional: applied only when issues occur– Potential priority given: green extension at end of cycle or red

truncation at beginning of cycle– Warrant analysis: determine where TSP will be installed

» Based on intersection V/C

Page 22: 1 Corridor Cities Transitway Presented to: Amberfield HOA January 15, 2015.

22

Urban DesignStation Area Concept• Specialized pavement areas• Pedestrian lighting• Crosswalk treatments• Transitway treatment• Community signage

Projectwide• Transitway treatment• Finish for structures: MSE walls,

retaining walls, portals• Crosswalk treatment• Wayfinding signage

01_Metropolitan Grove