AfterConstruction

Birgitta FosterSSA/Sandia National Labs

Page 2: Winter Bim Forum Bim After Construction Final

1945 : Sandia was created

1979 :Sandia was made a national laboratory.

Mission :Nuclear stockpile stewardshipHomeland security

Antiterrorism/Aviation securityTech Transfer

Page 3: Winter Bim Forum Bim After Construction Final

www.sandia.gov

Page 4: Winter Bim Forum Bim After Construction Final

Four sites ( ~ 1100 bldg, 7M GSF)

NM (Albuquerque ) CA (Livermore) NV (Tonopah) HI (Kauai)

Sandia NM

891 Bldgs 6M GSF 8700 acres

Construction : $80 M /YR

Page 5: Winter Bim Forum Bim After Construction Final

BIM = Information

BIM is a database of Building Information.

Stores InformationLinks to informationALSO….Extracts informationExchange information

Page 6: Winter Bim Forum Bim After Construction Final

BIM after Construction

Space Planning

Safety/Security

Facility Management System - ( FMS)

Facility Control Systems - (FCS)

Asset Management applications

Operation & Maintenance

Page 7: Winter Bim Forum Bim After Construction Final

Building InformationSpecifications

Submittal InformationEquipment dataPerformance dataWarranty

Finishes Information

O&M manuals

Panel Schedules

FCS

Page 8: Winter Bim Forum Bim After Construction Final

Building Information Applications

Page 9: Winter Bim Forum Bim After Construction Final

BIM : Facilities Management (6D)

Page 10: Winter Bim Forum Bim After Construction Final

BIM (6D) : Exchanges Information

Equipment data

Asset info

Room Info

FMS : Tririga/ Maximo

Page 11: Winter Bim Forum Bim After Construction Final

BIM: Untapped SavingsIn

form

atio

n Va

lue

TimePlanning

ConstructionDesign

Operation

$$$$

$$$

Page 12: Winter Bim Forum Bim After Construction Final

BIM : Due Diligence Investigation

Shadow project Partnerships

Software

Pulsing Industry

O&M Planning

Data Integration

Page 13: Winter Bim Forum Bim After Construction Final

Accurate As Built Models

Retrofits

Migration to BIM

Attracting new Customers

BIM : Laser scanning

Page 14: Winter Bim Forum Bim After Construction Final

BIM (6D): Bldg Operations Training

Pantex complex Amarillo, Texas. (CH2M-Hill)

Page 15: Winter Bim Forum Bim After Construction Final

BIM : Untapped Savings

Inefficiency Costs : $15B/yr

66% borne by Owners

Unit cost : $ 0.20/SFT (existing space)

Est. Costs for Sandia : 6.0 M GSF ~$1.2M / yr

Page 16: Winter Bim Forum Bim After Construction Final

BIM : Untapped Savings

NIST Study Validation: “View of the Future “ videoIn-House Planner Survey

ResultsSaves 2 hours per work order (WO)

(2 hrs x $50/hr ) x 24,000 WO

Cost Savings : $2.4 M/year Annual Budget : $14M/yr

Page 17: Winter Bim Forum Bim After Construction Final

BIM (6D) :Closing the Information Gap

Paper-based

Inherent Inefficiencies Reentry data Multiple databases Handoffs Locating Information

But what if it could be like this…………

Page 18: Winter Bim Forum Bim After Construction Final
Page 19: Winter Bim Forum Bim After Construction Final

BIM: 6DHow to get started

Start with O&M group What information is needed IT and O&M meeting

FMS Import options Selected preferred import format Determine fields

Use on Pilot project

Page 20: Winter Bim Forum Bim After Construction Final

BIM: What’s holding Owners back?

What Owners want : Save moneyCentralized Data repositorySeamless integration with FMS applications Save money $$$

Concerns :Education on BIM

Updating Model information

O&M Savings are not immediate

Model sharing

Page 21: Winter Bim Forum Bim After Construction Final

BIM:Owners next steps

Get to know your O&M team

Investigate integration withFacilities Mgt systems Building Control systemsAsset Management system

Require 6D BIM as a deliverable

Determine Owner Information needsDefine 6D BIM data requirements

Page 22: Winter Bim Forum Bim After Construction Final

BIM : Sandia Facilities

FMSINTERFA

CE(Excel -Manual)

6D Integrat

edMODEL

INTERFACE(Excel –

Extracted)

PHASE A

PHASE C

PHASE B

SEAMLESS

Integrated 6D model Software

Migration plan ( Road map)

Internal processes BIM team Model Management

Meeting with IT and O&M FMS Import options Selected preferred import formatDetermine fields

Use on Pilot project

Migration plan in process Seamless integration – bi

directional Receiving Integrated 6D

models O&M with models

Menu

Page 23: Winter Bim Forum Bim After Construction Final

BIM After Construction

QUESTIONS ?Birgitta Foster

[email protected]

Page 24: Winter Bim Forum Bim After Construction Final

BIM: 6DHow to get started

Determine what you need