Torrance Unified School District
Bond Measure YBond Measure Z
Quarterly Construction UpdateSeptember 30, 2009
Measure Y/Z Bond Management Team
Program/Construction Management
Torrance Unified School District
Modernization Projects Two New School FacilitiesFields & Modernization Projects
OVERVIEW
Measure Z:Update on progress of new field construction
Measure Y/Z:Progress reports for modernization projects at
South High School, Magruder Middle School, and Walteria Elementary School
Measure Y/Z:Progress reports for the new construction projects at Hull Middle School and Fern Elementary School
Measure ZImmediate Bond Money at Work
Sports Fields – North & West HS
Where We Are:• Field Construction Complete
• Closeout / Punchlist Completion
• Bleacher Design and Assessment in Progress
Where We Are Going:• Bleacher Replacement Late Spring / Summer 2010
SOUTH HS
• Where We Are• Demolition is complete.• Construction has started and is approximately 60% complete.• Synthetic turf has begun and is schedule to be completed on July 28th.• Bleacher installation is scheduled to start Aug 3rd and will be completed by Sept 11th.
•Where We Are Going:• Restroom upgrades will be scheduled for Jan – Feb 2010.
Sports Fields – South & Torrance HS
Where We Are:• Field & Bleacher Construction Complete
• Closeout / Punchlist Completion
• Restroom Plans approved by DSA
Where We Are Going:• Restroom Renovations January/ February 2010
Measure Y/ZSchool Modernizations
Where We Are:
• Surveying Complete
• Geological Report Complete
• Construction Documents
⁻ Campus Visual Enhancements
⁻ Quad/Assembly Area Developed
⁻ Classroom Wing Development
⁻ Covered Walkways Designed
Magruder Middle School
Where We Are Going:• Community Meeting #2 – October 2009
• Board Approval of Design
• DSA Submittal- Late October 2009
• Final Cost Estimates
• Bidding - Late Spring
• Construction Begins - Summer 2010
Magruder Middle School
Where We Are:DISTRICT MASTER STANDARDS
•Master Standards 90% complete•Prototype Classroom and Lab Design Complete
CONSTRUCTION DOCUMENTS•Final User Group Scope Meeting•Resolution of Drainage Issues and Site Circulation
•Final Design of an Improved Learning Environment with new Finishes, Lighting, Millwork, Windows/Doors, Roofing, Mechanical, and Fire Alarm System
South High School
South High SchoolWhere We Are Going:September 2009
•Test Classroom Flooring complete•Master Standards complete
October 2009•Community Meeting #1•50% Construction Documents Package for District Review
November 2009•Board Approval of Design•Construction Documents Complete•Division of the State Architect Submission
Summer 2010-Early 2012•Construction Start and Finish
Walteria Elementary SchoolWhere We AreDISTRICT STANDARDS MEETINGS
• Master Standards 90% Complete
CONSTRUCTION DOCUMENTS• Detailing an Enhanced Learning Environment via: ‐A New Campus Entry‐Reconfiguration of the Admin. Interior‐Relocation of existing and new Portable Classrooms‐A new Classroom wing, Library, Kindergarten Quad‐Covered Walkways‐Site Amphitheater to solve Grading Issues
Walteria Elementary SchoolWhere We Are Going:September 2009
•Detailing of Drawings, Finishes, Materials, Products, and Specifications
October 2009•Community Meeting #2•District Review of 50% Construction Documents
November 2009•Board Approval of Design•Construction Documents Complete•Division of the State Architect Submission
Summer 2010 - Fall 2011•Construction Start and Finish
New Construction
Where We Are:
DEMOLITION: Complete end of August
OIL WELLS:• Wells tested and no methane detected or methane remediation required
SOLAR STUDY:
• Analysis of campus energy use begun• Report due October
SUBMISSIONS:• 50% Construction Documents – early October
Hull Middle School
Where We Are Going:• Site Plan:
⁻ 28 Teaching Spaces⁻ Multi-purpose Bldg. & Food Services⁻ Media Center⁻ Administration⁻ Gym, (Alternate)
• Community Meeting #2 Late October 2009• Playfield: Separate Bid November 2009• Recap Torrance #4 Well• Board Approval of Design• DSA Submittal: Nov. 2009
Hull Middle School
Where We Are:
• No petro. or hydrocarbon lines in the street
• Interim housing plan complete
• Geotechnical report complete
• Site Committee meeting #4 held on September 15, 2009.
• 50% Construction Documents submission early October
Fern Elementary School
Fern Elementary School
Where We Are Going:• Site Plan:
⁻ 15 New Classrooms⁻ New Multi-purpose Building⁻ New Food Services
• Community Meeting #2 – October 2009
• Board Approval of Design
• DSA Submittal: November 2009
QuestionsAnd
Closing Remarks
Moving Forward