TECHNICAL OVERVIEW: ELECTRICAL, CIVIL AND
COMMISSIONING
June 2017
2
DISCIPLINE STREAMS
• The following technical discipline streams are defined for this Panel:
• Electrical Plant
• General Building and Civil Engineering Work
• Commissioning
• Protection
• Metering
• Telecontrol
• DC
DISCIPLINE STREAMS - SCOPES
• ELECTRICAL PLANT:
(High level only! Refer to NEC document for detail)
• Delivery, storage and installation of electrical equipment for new substations or during refurbishment of substations.
• Substation earthing
• Stringing of busbars and jumpers
• Cable work (MV and LV)
• Yard lighting, plug boxes, junction boxes
• Substation labels
• Installation of panels
3
DISCIPLINE STREAMS - SCOPES
• GENERAL BUILDING AND CIVIL ENGINEERING WORK:
(High level only! Refer to NEC document for detail)
• Geology and Soils
• Excavation
• Survey
• Water Services
• Earthworks and Subgrade treatment
• Drainage
• Embankments
• Access Roads
• Fencing and Gates
• Foundations
• Control Building
• Main Substation Earthing
• Steelwork
4
DISCIPLINE STREAMS - SCOPES
• COMMISSIONING:
(High level only! Refer to NEC document for detail)
Pre-commissioning and Energization phase of commissioning
• PROTECTION: schemes e.g. transformer and OLTC diff scheme, HV
feeder diff and impedance schemes, Bus zone protection, rural feeder
schemes (refer to NEC for more)
• METERING: tariff metering, statistical metering
• DC: batteries, battery charger, AC/DC board
• TELECTRONTROL: Reclosers (Any 2 of the following: Tavrida,
Schneider, Nulec, 4c, Form 5), D20 RTU, D400 RTU
5
TECHNICAL TENDER SUBMISSIONS
• Technical Criteria for each stream is unique, and only relevant to the specific stream.
• Technical Submissions Files can be submitted for any or all of the defined streams.
• A minimum of one stream must be submitted for further consideration on the Panel.
• If no technical submission is received then overall submission will not be considered further.
• The submission will only be considered for the discipline stream it is submitted against. No benefit will be given for other streams.
• That is! Example: If a submission is for Electrical Plant, that submission will not be used to assess compliance to the Civils or Commissioning criteria. It will strictly be used for evaluation against the Electrical Plant criteria.
6
SCORING AND RANKING
• There are 15 slots available in each Discipline Stream
• Electrical Plant: 15
• General Building and Civil Engineering Work: 15
• Commissioning: 15
• What does this mean?
• For each stream, after the technical evaluations are concluded, only 15 submissions will be considered successful and will be processed further.
• The 15 successful submissions will be selected by scoring and ranking all submissions that meet the minimum requirements, and thereafter selecting the TOP 15 highest ranked submissions.
7
SCORING AND RANKING
• Minimum Thresholds have been established for each Discipline Stream.
• If a submission has achieved a score above the minimum threshold, it will be included in the ranking process.
• Scores will be normalized to percentages for the ranking process.
• The Top 15 will be selected from the submissions scoring above the minimum threshold.
8
SUBSTATION PANEL – HOW IT WORKS
9
SUBSTATION PANEL
ELECTRICAL PLANT
TOP 15
1. A
2. B
3. Springbok
4. D
5. E
6. F
7. G
8. H
9. I
10. J
11. Rhino
12. L
13. M
14. N
15. O
CIVIL WORKS
TOP 15
1. Zebra
2. Giraffe
3. Rhino
4. Elephant
5. A
6. Duiker
7. Springbok
8. N
9. Lion
10. Leopard
11. Cheetah
12. Hyena
13. Dragon
14. Godzilla
15. T-Rex
COMMISSIONING
TOP 15
1. Mountain
2. Valley
3. H
4. Grass
5. Sand
6. Water
7. River
8. A
9. Road
10. …
11. …
12. Rhino
13. …
14. …
15. …
ACHIEVING TOP 15
• How to maximize the chance of being in the Top 15 for any Discipline (Electrical Plant, Civil, Commissioning)?
• Follow the Evidence Guidelines – e.g. certify, method statements, CVs etc.
• Use the Submission Packs and organize the evidence correctly per discipline
• Don’t just attempt to meet the minimum score – try to meet the maximum score
10
ELECTRICAL PLANT
TECHNICAL CRITERIA, SCORING, THRESHOLD etc.
11
ELECTRICAL PLANT
• Electrical Plant Criteria has two MAIN Sections:
• GATEKEEPER SECTION
• MANDATORY EVIDENCE SECTION
• Training and Skills
• Tools and Equipment
• Vehicles
• All elements in the criteria have a score allocation. Negative marking applies for non-compliant/not submitted evidence.
• The minimum score for the gatekeeper has to be achieved for the submission to be considered further.
• The minimum score for the mandatory evidence has to be achieved for the submission to achieve the minimum threshold for Ranking.
12
ELECTRICAL PLANT: GATEKEEPER
Evidence of previous experience & associated method statements
• List of Completed Jobs related to Substation Construction and Refurbishment (not older than 7 years, specifically demonstrating the required competencies).
• Competencies (New Build or Refurb):
• Installation of Substation Equipment: Isolators
• Installation of Substation Equipment: Breakers
• Installation of Substation Equipment: Power Transformers
• Stringing of jumpers and busbars
• Laying of Power Cables (MV) and Terminating
• Substation Dismantling
• Installation of substation equipment such as CTs, VTs, Insulators
• Installation of PTM and DC Panels And Junction Boxes
13
ELECTRICAL PLANT: GATEKEEPER
• Gatekeeper Evidence to be submitted:
• General Information required per Completed Job:
• Project Name
• Name Of Customer
• References (Name And Contact Information)
• Project Value
• Project Duration (Start And End Dates)
• Brief scope of work
• Method statements to be included per Competency, with content relevant to the task such as risks, working in live chambers, supervision, tools and equipment, task steps etc
• Can be from 1 or more jobs – if 1 job shows required number of competencies, then 1 is fine… or as many as you need.
14
ELECTRICAL PLANT: GATEKEEPER
• How to successfully submit the Gatekeeper information:
1. Use the Electrical Plant - Tender Submission pack loaded on the tender portal.
2. Use the Gatekeeper Section of the Submission Pack to prepare your submission.
3. Successful evidence will included details of the job completed, confirmation of the tasks that align to the competencies we require and the Method Statements for those competencies.
15
ELECTRICAL PLANT: GATEKEEPER
• How to successfully PASS the Gatekeeper:
• Total / Max Gatekeeper Score = 40 (8 Competencies demonstrated)
• Pass Mark = 20 (4 Competencies demonstrated)
• Points deducted per Competency not demonstrated = 5
• Points deducted if evidence does note demonstrate Project Details, a Competency as stated in the criteria and the associated method statement for that competency!
• Pass with 4 competencies – will allow the submission to be considered further
• GATEKEEPER SCORES ARE INCLUDED IN THE FINAL SCORING.
HIGHER GATEKEEPER SCORES COULD RESULT IN HIGHER FINAL
SCORES AND IMPROVE THE CHANCES OF BEING INCLUDED IN
THE TOP 15!
16
ELECTRICAL PLANT: MANDATORY EVIDENCE
• MANDATORY TRAINING AND SKILLS
17
Criteria Quantity Evidence Evidence requirements Scoring
BASIC
RIGGING
1 Basic Rigging
Training Certificate
1. Copies of the training certificates must be certified by a
commissioner of Oaths, with a signature and date not
older than three months from the issue date of this
tender.
2. Training certificates are to be valid on the date of tender
close. Certificates that have expired prior to this date will
not be accepted as valid evidence.
10
TRUCK
MOUNTED
CRANE
OPERATOR
1 Truck Mounted
Crane Certificate
1. Copies of the training certificates must be certified by a
commissioner of Oaths, with a signature and date not
older than three months from the issue date of this
tender.
2. Training certificates are to be valid on the date of tender
close. Certificates that have expired prior to this date will
not be accepted as valid evidence
10
ORHVS 1 ORHVS Training
Certificates
(Responsible
Person/HVO2
Minimum)
Or Valid
Authorizations
1. Copies of the training certificates/authorizations must be
certified by a commissioner of Oaths, with a signature
and date not older than three months from the issue date
of this tender.
2. Training certificates are to be valid on the date of tender
close. Certificates that have expired prior to this date will
not be accepted as valid evidence
10
ELECTRICAL PLANT: MANDATORY EVIDENCE
• MADATORY TRAINING AND SKILLS
18
Criteria Quantity Evidence Evidence requirements Scoring
MV CABLE JOINTING
AND TERMINATION
1 Training
certificate
1. Copies of the training certificates must be
certified by a commissioner of Oaths, with a
signature and date not older than three
months from the open date of this tender.
10
CONSTRUCTION
TEAM EXPERIENCE:
SITE
SUPERVISOR
CONSTRUCTION
MANAGER
FOREMAN
ELECTRICIAN
1 CV and
related
qualificati
ons
1. CV to demonstrate previous experience in
this specific role for substation related tasks.
1. Proof of registration as a candidate or
confirmation letter from SACPCMP of
registration for the Construction Manager.
(2.5 marks per skill)
10
ELECTRICAL PLANT: MANDATORY EVIDENCE
• TRAINING AND SKILLS – SCORING
• Total / Max Points = 50
• Each Training and Skill criteria is worth 10 points
• Negative Marking Applies
• 10 points deducted if evidence not submitted as per requirements stated
19
ELECTRICAL PLANT: MANDATORY EVIDENCE
• MANDATORY TOOLS/EQUIPMENT
20
No Tool/Equipment 1 Slings (steel, chain and canvas)
2 Conductor grip (steel)
3 Conductor grips (al)
4 Tirfor (winch)
5 Lever hoists
6 D-shackles (containing swl)
7 Snatch block
8 Stringing wheels / conductor pulleys
9 Guide / pilot rope
10 Galvanizing tester
11 Tool boxes – electrical and mechanical
12 Insulation tester
13 Earth resistance tester
14 Continuity tester for ringing out cable
cores
No Tool/Equipment 15 Suitable drills (power)
16 Hole alignment wedge
17 Hand lines or skip rope
18 Hydraulic conductor cutter
19 Cable/conductor drum trestle (braked)
20 Conductor wire brush (al)
21 Gas welding sets
22 Jacks & props
23 Generator
24 Thermometer
25 Crimping (100 ton press + suitable dies)
26 LV Crimper
27 Torque wrench
28 Dynamometer (or sagging tools)
29 Mechanical Compactor
30 Angle Grinder
ELECTRICAL PLANT: MANDATORY EVIDENCE
• MANDATORY TOOLS/EQUIPMENT
• Refer to the Electrical Plant - Tender Submission pack loaded on the tender portal.
• Use the tool list included in the pack for your evidence submission. This is preferred.
• HOW TO SUBMIT THE REQUIRED EVIDENCE:
• Use the Tool List in the tender pack.
• Indicate if the tool is currently OWNED by the Company or being HIRED
• If the tool is owned, indicate the quantity available and if the tools are available for inspection if needed.
• If the tools are being hired, include a letter from the Bona Fide Hiring Company proving the ability to hire the tools. If this letter is not included, points will be deducted for the relevant tools.
21
ELECTRICAL PLANT: MANDATORY EVIDENCE
• MANDATORY TOOLS/EQUIPMENT - SCORING
• Total / Max Points = 30
• Each Tool/Equipment criteria is worth 1 point
• Negative Marking Applies
• 1 point deducted if evidence not submitted as per requirements stated
• A penalty of 2 points will be deducted if 50% (15) or more of tools/equipment is hired.
22
ELECTRICAL PLANT: MANDATORY EVIDENCE
• MANDATORY VEHICLES
23
Criteria Quantit
y
Evidence Evidence requirements Scoring
Bakkie/LDV 1 Proof of
Ownership
Or
Hiring Letter
In order to demonstrate ownership, license documents are to be
submitted, clearly showing the type of vehicle and the owner’s name.
If the vehicle is not in the Company name then submit an affidavit
clarifying the vehicle ownership for consideration.
If the evidence does not adequately demonstrate ownership then the
vehicle will be noted as non-responsive.
Hiring of the Vehicle will be accepted. A hiring letter from a Bona Fide
hiring company will be required as evidence. Hiring from
Electrical/Construction/Other Contractors will not be accepted. If the hiring
letter is not provided or accepted then the vehicle will be noted as non-
responsive.
1
Staff
Transport
Vehicle
1 Proof of
Ownership
Or
Hiring Letter
In order to demonstrate ownership, license documents are to be
submitted, clearly showing the type of vehicle and the owner’s name.
Additional bakkies/ldvs, micro/minibus buses, or similar passenger
vehicles will be accepted.
If the vehicle is not in the Company name then submit an affidavit
clarifying the vehicle ownership for consideration.
If the evidence does not adequately demonstrate ownership then the
vehicle will be noted as non-responsive.
Hiring of the Transport Vehicle will be accepted. A hiring letter from a
Bona Fide hiring company will be required as evidence. Hiring from
Electrical/Construction/Other Contractors will not be accepted. If the hiring
letter is not provided or accepted then the vehicle will be noted as non-
responsive.
1
ELECTRICAL PLANT: MANDATORY EVIDENCE
• MANDATORY VEHICLES
24
Criteria Quantity Evidence Evidence requirements Scoring
5 Ton
Truck with
Crane
1 Proof of
Ownership
with Crane
Load Test
Or
Hiring Letter
In order to demonstrate ownership, license documents are to be submitted, clearly
showing the type of vehicle and the owner’s name.
If the vehicle is not in the Company name then submit an affidavit clarifying the
vehicle ownership for consideration.
The Crane Load test for the crane on the truck must be submitted.
If the evidence does not adequately demonstrate ownership or of the load test is not
accepted/submitted then the vehicle will be noted as non-responsive.
Hiring of the Vehicle will be accepted. A hiring letter from a Bona Fide hiring
company will be required as evidence. Hiring from Electrical/Construction/Other
Contractors will not be accepted. If the hiring letter is not provided or accepted then
the vehicle will be noted as non-responsive.
1
Bucket/
Hydraulic
Lift
1 Proof of
Ownership
Or
Hiring Letter
In order to demonstrate ownership, license documents are to be submitted, clearly
showing the type of vehicle and the owner’s name.
If the vehicle is not in the Company name then submit an affidavit clarifying the
vehicle ownership for consideration.
The Crane Load test for the crane on the truck must be submitted.
If the evidence does not adequately demonstrate ownership or of the load test is not
accepted/submitted then the vehicle will be noted as non-responsive.
Hiring of the Vehicle will be accepted. A hiring letter from a Bona Fide hiring
company will be required as evidence. Hiring from Electrical/Construction/Other
Contractors will not be accepted. If the hiring letter is not provided or accepted then
the vehicle will be noted as non-responsive.
1
ELECTRICAL PLANT: MANDATORY EVIDENCE
• MANDATORY VEHICLES
• HOW TO SUBMIT THE REQUIRED EVIDENCE:
• The Vehicles listed can be OWNED by the Company or HIRED.
• If OWNED:
• Evidence of ownership is needed. Submit evidence such as a Logbook or license documents that show the vehicle type (e.g. bakkie, LDV, micro-bus, dropside etc) and the owners name.
• If the vehicle is not in the companies name, include an affidavit explaining the ownership of the vehicle. The vehicle ownership must be related to the company in a significant way e.g. Company Owner’s name, Shareholders Name etc
• The CRANE TRUCK EVIDENCE must include the evidence above and proof of the crane e.g. installation certificate, load test certificate etc.
• If HIRED: include a letter from the Bona Fide Hiring Company proving the ability to the vehicles. If this letter is not included, points will be deducted for the relevant vehicles.
25
ELECTRICAL PLANT: MANDATORY EVIDENCE
• MANDATORY VEHICLES
• Total / Max Points = 4
• Each Vehicle criteria is worth 1 point
• Negative Marking Applies
• 1 point deducted if evidence not submitted as per requirements stated
26
ELECTRICAL PLANT: FINAL SCORING AND RANKING
• Only applicable if the Gatekeeper pass mark is achieved AND the minimum score for the Mandatory Evidence is achieved:
• Gatekeeper Pass = 20
• Mandatory Evidence Pass = 38***
• ***Mandatory evidence score is determined by combining the scores for Training and Skills, Tools/Equipment and Vehicles. Submitting evidence as per the requirements and minimizing the scores that will be deducted by negative marking will increase the points achieved for the Mandatory Evidence.
• Submissions not achieving these scores will not be processed further.
• Gatekeeper score and Mandatory evidence score will be added together. This will be the final score for the submission. The final score will be converted to a percentage.
• The % scores will be ordered from highest to lowest, thereby ranking them.
27
ELECTRICAL PLANT: FINAL SCORING AND RANKING
• Threshold for Ranking:
• The TOP 15 submissions achieving a % score of 59% or more will be processed further
• If there are less than 15 submissions with scores greater than or equal to 59%, then the shortfall will be made up from submissions with scores between 58% and 46% (inclusive). The selected submissions will be processed further.
• These submissions will be allocated for Development to resolve the shortfalls related to the Mandatory evidence which resulted in the score achieved.
• Submissions not selected in the Top 15 will not be processed further.
28
GENERAL BUILDING AND CIVIL ENGINEERING WORK
TECHNICAL CRITERIA, SCORING, THRESHOLD etc.
29
GENERAL BUILDING AND CIVIL ENGINEERING WORK
• General Building And Civil Engineering Work Criteria has two MAIN Sections:
• GATEKEEPER SECTION
• MANDATORY EVIDENCE SECTION
• Training and Skills
• Tools and Equipment
• Vehicles
• All elements in the criteria have a score allocation. Negative marking applies for non-compliant/not submitted evidence.
• The minimum score for the gatekeeper has to be achieved for the submission to be considered further.
• The minimum score for the mandatory evidence has to be achieved for the submission to achieve the minimum threshold for Ranking.
30
GENERAL BUILDING AND CIVIL ENGINEERING WORK: GATEKEEPER
Evidence of previous experience & associated method statements
• List of Completed Jobs related to Substation Construction and Refurbishment (not older than 7 years, specifically demonstrating the required competencies).
• Competencies (New Build or Refurb):
• Survey
• Bulk earthworks and layerworks
• Control Room/ Switchroom Building works
• CONTINUED NEXT SLIDE
31
GENERAL BUILDING AND CIVIL ENGINEERING WORK: GATEKEEPER
• Competencies (New Build or Refurb):
• Concrete works:
• If Batching – the contractor needs to provide the following:
Concrete Mix design;
Aggregate to be used;
Location/supplier of aggregate; and
Mixing and testing need to be included in the method statement.
• If Ready mix – the contractor needs to provide the following:
The supplier of Ready mix and the distance from site;
How results will be obtained from the supplier; and
How concrete will be tested on site.
• CONTINUED NEXT SLIDE
32
GENERAL BUILDING AND CIVIL ENGINEERING WORK: GATEKEEPER
• Competencies (New Build or Refurb):
• Surface and Subsurface Drainage
• Steelwork
• Earthmat trenching, installation and backfilling
• Fencing and Gates
• Yardstone and kerbing
• Installation of Control/Switch Room Electrical (Air-conditioner units, 400V
AC DB, 110V DC DB, emergency lighting
• Retaining structures
• Rehabilitation
• Total of 12 competencies listed.
33
GENERAL BUILDING AND CIVIL ENGINEERING WORK: GATEKEEPER
• Gatekeeper Evidence to be submitted:
• General Information required per Completed Job:
• Project Name
• Name Of Customer
• References (Name And Contact Information)
• Project Value
• Project Duration (Start And End Dates)
• Brief scope of work
• Method statements to be included per Competency, with content relevant to the task such as risks, working in live chambers, supervision, tools and equipment, task steps etc.
• Can be from 1 or more jobs – if 1 job shows required number of competencies, then 1 is fine… or as many as you need.
34
GENERAL BUILDING AND CIVIL ENGINEERING WORK: GATEKEEPER
• How to successfully submit the Gatekeeper information:
1. Use the General Building and Civil Engineering Work - Tender Submission pack loaded on the tender portal.
2. Use the Gatekeeper Section of the Submission Pack to prepare your submission.
3. Successful evidence will included details of the job completed, confirmation of the tasks that align to the competencies we require and the Method Statements for those competencies.
35
GENERAL BUILDING AND CIVIL ENGINEERING WORK: GATEKEEPER
• How to successfully PASS the Gatekeeper:
• Total / Max Gatekeeper Score = 60 (12 Competencies demonstrated)
• Pass Mark = 40 (8 Competencies demonstrated)
• Points deducted per Competency not demonstrated = 5
• Points deducted if evidence does note demonstrate Project Details, a Competency as stated in the criteria and the associated method statement for that competency!
• Pass with 8 competencies – will allow the submission to be considered further
• GATEKEEPER SCORES ARE INCLUDED IN THE FINAL SCORING.
HIGHER GATEKEEPER SCORES COULD RESULT IN HIGHER FINAL
SCORES AND IMPROVE THE CHANCES OF BEING INCLUDED IN
THE TOP 15!
36
GENERAL BUILDING AND CIVIL ENGINEERING WORK: MANDATORY EVIDENCE
• MANDATORY TRAINING AND SKILLS
37
Criteria Quantity Evidence Evidence requirements Scoring
BASIC
RIGGING
1 Basic Rigging
Training
Certificate
1. Copies of the training certificates must be certified by a
commissioner of Oaths, with a signature and date not
older than three months from the open date of this tender.
2. Training certificates are to be valid on the date of tender
close. Certificates that have expired prior to this date will
not be accepted as valid evidence.
10
TRUCK
MOUNTED
CRANE
OPERATOR
1 Truck Mounted
Crane Certificate
1. Copies of the training certificates must be certified by a
commissioner of Oaths, with a signature and date not
older than three months from the open date of this tender.
2. Training certificates are to be valid on the date of tender
close. Certificates that have expired prior to this date will
not be accepted as valid evidence
10
ORHVS 1 ORHVS Training
Certificates
(Responsible
Person/HVO2
Minimum)
Or Valid
Authorizations
1. Copies of the training certificates/authorizations must be
certified by a commissioner of Oaths, with a signature and
date not older than three months from the open date of this
tender.
2. Training certificates are to be valid on the date of tender
close. Certificates that have expired prior to this date will
not be accepted as valid evidence
10
GENERAL BUILDING AND CIVIL ENGINEERING WORK: MANDATORY EVIDENCE
• MANDATORY TRAINING AND SKILLS
38
Criteria Quantity Evidence Evidence requirements Scoring
SURVEYOR 1 CV and related
qualifications
1. Site Surveyor CV to demonstrate previous experience in
this role.
2. Qualifications such as a Registered Land Surveyor with
PLATO to be included, and must be in the name of the
identified site Surveyor as per the CV
10
SITE
SUPERVISOR
1 CV and related
qualifications
1. Site Supervisor CV to demonstrate previous experience in
this role.
2. Qualifications such as 4 years’ experience : NQF5- Civil
Engineering Diploma to be included, and must be in the
name of the identified site supervisor as per the CV,
experience in civil projects, contactable references.
10
SITE
SUPERVISOR
1 CV and related
qualifications
1. Site Supervisor CV to demonstrate previous experience in
this role.
2. Qualifications such as 10 years’ experience to be
included, and must be in the name of the identified site
supervisor as per the CV, experience in civil projects,
contactable references.
10
GENERAL BUILDING AND CIVIL ENGINEERING WORK: MANDATORY EVIDENCE
• MANDATORY TRAINING AND SKILLS
39
Criteria Quantity Evidence Evidence requirements Scoring
CONSTRUCTION
MANAGER
1 CV and related
qualifications
1. Construction Manager CV to demonstrate previous
experience in this role.
2. Qualifications such as 5 years’ experience: NQF5- Civil
Engineering Diploma or BSc in Construction Management
or BSc in Civil Engineering) to be included, and must be in
the name of the identified Construction Manager as per the
CV, experience in civil projects, contactable references.
3. Must be registered at least as a candidate with the
SACPCMP.
10
FOREMAN FOR
CIVIL
ENGINEERING
AND BUILDING
ACTIVITIES
1 CV and related
qualifications
1. Grade 10, 10 years of practical experience as a General
Foreman in building, relevant occupational experience to
be included, and must be in the name of the identified site
foreman as per the CV.
2. Trade qualification in concreting/ building or construction.
10
GENERAL BUILDING AND CIVIL ENGINEERING WORK: MANDATORY EVIDENCE
• TRAINING AND SKILLS – SCORING
• Total / Max Points = 80
• Each Training and Skill criteria is worth 10 points
• Negative Marking Applies
• 10 points deducted if evidence not submitted as per requirements stated
40
GENERAL BUILDING AND CIVIL ENGINEERING WORK: MANDATORY EVIDENCE
• MANDATORY TOOLS/EQUIPMENT
41
No Tool/Equipment 1 Galvanizing tester
2 Concrete vibrator
3 Suitable drills including pneumatic drills
4 Excavator
5 TLB
6 Dump truck/ tipper truck
7 Vibratory rollers/ Compactors
8 Water bowser/ tanker
9 Survey equipment
10 Concrete test equipment
11 Troxler tester
12 DCP
13 Scaffolding
14 Shuttering/ Formwork
15 Approved FAS
16 Concrete mixer
GENERAL BUILDING AND CIVIL ENGINEERING WORK: MANDATORY EVIDENCE
• MANDATORY TOOLS/EQUIPMENT
• Refer to the General Building and Civil Engineering Work - Tender Submission pack loaded on the tender portal.
• Use the tool list included in the pack for your evidence submission. This is preferred.
• HOW TO SUBMIT THE REQUIRED EVIDENCE:
• Use the Tool List in the tender pack.
• Indicate if the tool is currently OWNED by the Company or being HIRED
• If the tool is owned, indicate the quantity available and if the tools are available for inspection if needed.
• If the tools are being hired, include a letter from the Bona Fide Hiring Company proving the ability to hire the tools. If this letter is not included, points will be deducted for the relevant tools.
42
GENERAL BUILDING AND CIVIL ENGINEERING WORK: MANDATORY EVIDENCE
• MANDATORY TOOLS/EQUIPMENT - SCORING
• Total / Max Points = 16
• Each Tool/Equipment criteria is worth 1 point
• Negative Marking Applies
• 1 point deducted if evidence not submitted as per requirements stated
• A penalty of 1 points will be deducted if 50% (8) or more of tools/equipment is hired.
43
GENERAL BUILDING AND CIVIL ENGINEERING WORK: MANDATORY EVIDENCE
• MANDATORY VEHICLES
44
Criteria Quantity Evidence Evidence requirements Scoring
Bakkie/LD
V
1 Proof of
Ownership
Or
Hiring Letter
In order to demonstrate ownership, license documents are to be
submitted, clearly showing the type of vehicle and the owner’s name.
If the vehicle is not in the Company name then submit an affidavit
clarifying the vehicle ownership for consideration.
If the evidence does not adequately demonstrate ownership then the
vehicle will be noted as non-responsive.
Hiring of the Vehicle will be accepted. A hiring letter from a Bona Fide
hiring company will be required as evidence. Hiring from
Electrical/Construction/Other Contractors will not be accepted. If the hiring
letter is not provided or accepted then the vehicle will be noted as non-
responsive.
1
Staff
Transport
Vehicle
1 Proof of
Ownership
Or
Hiring Letter
In order to demonstrate ownership, license documents are to be
submitted, clearly showing the type of vehicle and the owner’s name.
Additional bakkies/ldvs, micro/minibus buses, or similar passenger
vehicles will be accepted.
If the vehicle is not in the Company name then submit an affidavit
clarifying the vehicle ownership for consideration.
If the evidence does not adequately demonstrate ownership then the
vehicle will be noted as non-responsive.
Hiring of the Transport Vehicle will be accepted. A hiring letter from a
Bona Fide hiring company will be required as evidence. Hiring from
Electrical/Construction/Other Contractors will not be accepted. If the hiring
letter is not provided or accepted then the vehicle will be noted as non-
responsive.
1
GENERAL BUILDING AND CIVIL ENGINEERING WORK: MANDATORY EVIDENCE
• MANDATORY VEHICLES
45
Criteria Quantity Evidence Evidence requirements Scoring
5 Ton
Truck with
Crane
1 Proof of
Ownership
with Crane
Load Test
Or
Hiring Letter
In order to demonstrate ownership, license documents are to be submitted, clearly
showing the type of vehicle and the owner’s name.
If the vehicle is not in the Company name then submit an affidavit clarifying the
vehicle ownership for consideration.
The Crane Load test for the crane on the truck must be submitted.
If the evidence does not adequately demonstrate ownership or of the load test is not
accepted/submitted then the vehicle will be noted as non-responsive.
Hiring of the Vehicle will be accepted. A hiring letter from a Bona Fide hiring
company will be required as evidence. Hiring from Electrical/Construction/Other
Contractors will not be accepted. If the hiring letter is not provided or accepted then
the vehicle will be noted as non-responsive.
1
Bucket/
Hydraulic
Lift
1 Proof of
Ownership
Or
Hiring Letter
In order to demonstrate ownership, license documents are to be submitted, clearly
showing the type of vehicle and the owner’s name.
If the vehicle is not in the Company name then submit an affidavit clarifying the
vehicle ownership for consideration.
The Crane Load test for the crane on the truck must be submitted.
If the evidence does not adequately demonstrate ownership or of the load test is not
accepted/submitted then the vehicle will be noted as non-responsive.
Hiring of the Vehicle will be accepted. A hiring letter from a Bona Fide hiring
company will be required as evidence. Hiring from Electrical/Construction/Other
Contractors will not be accepted. If the hiring letter is not provided or accepted then
the vehicle will be noted as non-responsive.
1
GENERAL BUILDING AND CIVIL ENGINEERING WORK: MANDATORY EVIDENCE
• MANDATORY VEHICLES
• HOW TO SUBMIT THE REQUIRED EVIDENCE:
• The Vehicles listed can be OWNED by the Company or HIRED.
• If OWNED:
• Evidence of ownership is needed. Submit evidence such as a Logbook or license documents that show the vehicle type (e.g. bakkie, LDV, micro-bus, dropside etc) and the owners name.
• If the vehicle is not in the companies name, include an affidavit explaining the ownership of the vehicle. The vehicle ownership must be related to the company in a significant way e.g. Company Owner’s name, Shareholders Name etc
• The CRANE TRUCK EVIDENCE must include the evidence above and proof of the crane e.g. installation certificate, load test certificate etc.
• If HIRED: include a letter from the Bona Fide Hiring Company proving the ability to the vehicles. If this letter is not included, points will be deducted for the relevant vehicles.
46
GENERAL BUILDING AND CIVIL ENGINEERING WORK: MANDATORY EVIDENCE
• MANDATORY VEHICLES
• Total / Max Points = 4
• Each Vehicle criteria is worth 1 point
• Negative Marking Applies
• 1 point deducted if evidence not submitted as per requirements stated
47
GENERAL BUILDING AND CIVIL ENGINEERING WORK: MANDATORY EVIDENCE
• Only applicable if the Gatekeeper pass mark is achieved AND the minimum score for the Mandatory Evidence is achieved:
• Gatekeeper Pass = 40
• Mandatory Evidence Pass = 40***
• ***Mandatory evidence score is determined by combining the scores for Training and Skills, Tools/Equipment and Vehicles. Submitting evidence as per the requirements and minimizing the scores that will be deducted by negative marking will increase the points achieved for the Mandatory Evidence.
• Submissions not achieving these scores will not be processed further.
• Gatekeeper score and Mandatory evidence score will be added together. This will be the final score for the submission. The final score will be converted to a percentage.
• The % scores will be ordered from highest to lowest, thereby ranking them.
48
GENERAL BUILDING AND CIVIL ENGINEERING WORK: FINAL SCORING AND RANKING
• Threshold for Ranking:
• The TOP 15 submissions achieving a % score of 58% or more will be processed further
• If there are less than 15 submissions with scores greater than or equal to 58%, then the shortfall will be made up from submissions with scores between 57% and 50% (inclusive). The selected submissions will be processed further.
• These submissions will be allocated for Development to resolve the shortfalls related to the Mandatory evidence which resulted in the score achieved.
• Submissions not selected in the Top 15 will not be processed further.
49
COMMISSIONING
TECHNICAL CRITERIA, SCORING, THRESHOLD etc.
50
COMMISSIONING
• Commissioning has ONE MAIN Section made up of 4 subsections:
• MANDATORY EVIDENCE SECTION
• Experience
• Skills
• Tools/ Test Equipment
• Vehicles
• All elements in the criteria have a score allocation. Negative marking applies for non-compliant/not submitted evidence.
• THERE IS NO GATEKEEPER!
• The minimum score for the mandatory evidence for Experience and Tools/ Test Equipment has to be achieved for the submission to processed further.
51
COMMISSIONING
• How it works for Commissioning:
• The Technical Tender Criteria is unique for each discipline – Protection, Metering, Telecontrol, DC.
• To be consider for Commissioning, a technical file must be submitted for at least 1 of the 4 commissioning disciplines.
• The same company can apply for any or all of the Commissioning disciplines.
• Minimum Thresholds have been established for each Discipline of Commissioning.
• If a submission achieved a score above the minimum threshold for that Commissioning Discipline, it will be included in the ranking process FOR THAT DISCIPLINE.
• The Top 15 will be selected from the submissions scoring above the minimum threshold FOR THAT DISCIPLINE.
52
COMMISSIONING – DETERMINING THE TOP 15
• To reiterate, scoring and ranking will be applied for each submission under each discipline. The top 15 as per the defined Ranking rules will be determined for each discipline.
• All submissions achieving a top 15 ranking under any discipline will be processed further to determine a Top15 ranking for Commissioning.
53
Protection
Top 15
Metering
Top 15
Telecontrol
Top 15
DC
Top 15
COMMISSIONING
FINAL TOP 15
COMMISSIONING – DETERMINING THE TOP 15
• The maximum score achievable for Commissioning is 100%.
• If a Tenderer was ranked in the top 15 for only one discipline then the score achieved will be utilized with no normalization applied.
• If a Tenderer was ranked in the top 15 for any two disciplines then the two scores achieved will be combined and divided by 2 in order to determine a score out of 100%.
• If a Tenderer was ranked in the top 15 for any three disciplines then the three scores achieved will be combined and divided by 3 in order to determine a score out of 100%.
• If a Tenderer was ranked in the top 15 for all four disciplines then the four scores achieved will be combined and divided by 4 in order to determine a score out of 100%.
• All normalized scores will be ranked and the top 15 highest scores will be processed further.
54
PROTECTION
TECHNICAL CRITERIA, SCORING, THRESHOLD etc.
55
PROTECTION: MANDATORY CRITERIA
• MANDATORY EXPERIENCE
• Commissioning Records/Portfolio of Evidence/Training Certificates demonstrating experience for the following:
• Transformer + OLTC - diff scheme
• Sub transmission (66kV upwards) Feeder Bay - diff scheme
• Sub transmission (66kV upwards) Feeder Bay - impedance, no comms
• Sub transmission (66kV upwards) Feeder Bay - impedance, with comms
• Sub transmission (66kV upwards) Feeder Bay - combined diff + impedance
• Under Frequency load shedding SchemeHV Bus Zone Protection
• MV Buszone Protection
• Rural Feeder - O/H Line
• Rural Feeder - Cable Feeder (RMS Relay)
• Rural Feeder - Cable Feeder with Diff
• Busbar Arc Protection -
• HV Cap Bank (132 or 88kV or 66kV)
• MV Cap Bank (11 or 22kV or 33kV)
• Buscoupler Protection
• Section Breaker incl Telecontrol
56
PROTECTION: MANDATORY CRITERIA
• MANDATORY EXPERIENCE
• Evidence is:
• Commissioning Records/Portfolio of Evidence/Training Certificates demonstrating experience for the following:
• Refer to the Protection Commissioning - Tender Submission pack loaded on the tender portal.
• Use the Commissioning Experience Interleaf to indicate which Mandatory Experience is available.
• Then include the evidence to support this.
• DO NOT SUBMIT THE RESOURCE’S ENTIRE PORTFOLIO OF EVIDENCE – ONLY THE SHEETS RELEVANT THAT DEMONSTRATE THE EXPERIENCE LISTED.
• Copies of training certificates are to be certified (certification must be signed and dated, no older than 3 months)
57
PROTECTION: MANDATORY CRITERIA
• MANDATORY EXPERIENCE - SCORING
• Total / Max Points = 75
• Each Experience criteria is worth 5 points
• Negative Marking Applies
• 5 point deducted if evidence not submitted as per requirements stated
• A minimum score of 35 must be achieved for Mandatory Experience for the submission to be processed further.
58
PROTECTION: MANDATORY CRITERIA
• MANDATORY SKILLS
59
MANDATORY SKILLS
CRITERIA EVIDENCE EVIDENCE REQUIREMENTS Scorin
g
ECSA
Registered
Resource
ECSA Registration -
Pr Eng / Pr Tech
Professional
Registration
Copy of registration certificate - certified by a
commissioner of Oaths, with a signature and date not
older than three months from the issue date of this
tender.
1
PROTECTION: MANDATORY CRITERIA
• MANDATORY SKILLS – SCORING
• Total / Max Points = 1
• The Skill criteria is worth 1 point
• Negative Marking Applies
• 1 point deducted if evidence not submitted as per requirements stated
60
PROTECTION: MANDATORY CRITERIA
• MANDATORY TOOLS/EQUIPMENT
61
No Tool/Equipment
1 AC Current clamp: 0-5A
2 AC Current clamp: 0-1000A
3 Current injection test set
4 Single Phase variac
5 Digital multi-meter 4 ½ Digit true
RMS
6 Digital multi-meter 3 ½ Digit true
RMS
7 Insulation tester 500V
8 Insulation tester 5kV
9 Laptop with 3G capability
10 Relay communication cables
No Tool/Equipment
11 Secondary Injection test set
12 Primary Injection test set
13 Universal panel keys
14 GPS unit for End to end
15 Clamp meter with a high resolution
16 Three phase generator.
17 Test Blocks
18 RS232 to RS485 convertors eg.
MOXA Convertor
19 Phase Rotation Meter
20 Insulated hand tools rated 1000v
PROTECTION: MANDATORY CRITERIA
• MANDATORY TOOLS/EQUIPMENT
• Refer to the Protection Commissioning - Tender Submission pack loaded on the tender portal.
• Use the tool list included in the pack for your evidence submission. This is preferred.
• HOW TO SUBMIT THE REQUIRED EVIDENCE:
• Use the Tool List in the tender pack.
• Indicate if the tool is currently OWNED by the Company or being HIRED
• If the tool is owned, indicate the quantity available and if the tools are available for inspection if needed.
• If the tools are being hired, include a letter from the Bona Fide Hiring Company proving the ability to hire the tools. If this letter is not included, points will be deducted for the relevant tools.
62
PROTECTION: MANDATORY CRITERIA
• MANDATORY TOOLS/EQUIPMENT - SCORING
• Total / Max Points = 20
• Each Tool/Equipment criteria is worth 1 point
• Negative Marking Applies
• 1 point deducted if evidence not submitted as per requirements stated
• A minimum score of 10 must be achieved for Mandatory Tools/Equipment for the submission to be processed further.
63
PROTECTION: MANDATORY CRITERIA
• MANDATORY VEHICLES
64
Criteria Quantity Evidence Evidence requirements Scoring
Bakkie/
LDV
1 Proof of
Ownership
Or
Hiring Letter
In order to demonstrate ownership, license documents are to be
submitted, clearly showing the type of vehicle and the owner’s
name.
If the vehicle is not in the Company name then submit an affidavit
clarifying the vehicle ownership for consideration.
If the evidence does not adequately demonstrate ownership then the
vehicle will be noted as non-responsive.
Hiring of the Vehicle will be accepted. A hiring letter from a Bona
Fide hiring company will be required as evidence. Hiring from
Electrical/Construction/Other Contractors will not be accepted. If the
hiring letter is not provided or accepted then the vehicle will be noted
as non-responsive.
1
PROTECTION: MANDATORY CRITERIA
• MANDATORY VEHICLES
• HOW TO SUBMIT THE REQUIRED EVIDENCE:
• The Vehicles listed can be OWNED by the Company or HIRED.
• If OWNED:
• Evidence of ownership is needed. Submit evidence such as a Logbook or license documents that show the vehicle type (e.g. bakkie, LDV, micro-bus, dropside etc) and the owners name.
• If the vehicle is not in the companies name, include an affidavit explaining the ownership of the vehicle. The vehicle ownership must be related to the company in a significant way e.g. Company Owner’s name, Shareholders Name etc
• The CRANE TRUCK EVIDENCE must include the evidence above and proof of the crane e.g. installation certificate, load test certificate etc.
• If HIRED: include a letter from the Bona Fide Hiring Company proving the ability to the vehicles. If this letter is not included, points will be deducted for the relevant vehicles.
65
PROTECTION: MANDATORY CRITERIA
• MANDATORY VEHICLES
• Total / Max Points = 1
• Vehicle criteria is worth 1 point
• Negative Marking Applies
• 1 point deducted if evidence not submitted as per requirements stated
66
PROTECTION: MANDATORY CRITERIA
• Only applicable if the minimum score for the Mandatory Evidence is achieved as follows:
• Mandatory Experience = 35
• Mandatory Tools/Equipment = 10
• Submitting evidence as per the requirements and minimizing the scores that will be deducted by negative marking will increase the points achieved for the Mandatory Evidence.
• If these scores are not achieved the submission will not be processed further.
• This will be the final score for the submission in this Discipline of commissioning. The final score will be converted to a percentage.
• The % scores will be ordered from highest to lowest, thereby ranking them.
67
PROTECTION: MANDATORY CRITERIA
• Threshold for Ranking:
• The TOP 15 submissions achieving a % score of 69% or more will be processed further
• If there are less than 15 submissions with scores greater than or equal to 69%, then the shortfall will be made up from submissions with scores between 68% and 46% (inclusive). The selected submissions will be processed further.
• These submissions will be allocated for Development to resolve the shortfalls related to the Mandatory evidence which resulted in the score achieved.
• Submissions not selected in the Top 15 will not be processed further to determine the COMMISSIONING Top 15.
68
METERING
TECHNICAL CRITERIA, SCORING, THRESHOLD etc.
69
METERING: MANDATORY CRITERIA
• MANDATORY EXPERIENCE
• Commissioning Records/Portfolio of Evidence/Training Certificates demonstrating experience for the following:
• Tariff Metering
• Statistical Metering
• Modems
70
METERING: MANDATORY CRITERIA
• MANDATORY EXPERIENCE
• Evidence is:
• Commissioning Records/Portfolio of Evidence/Training Certificates demonstrating experience for the following:
• Refer to the Metering Commissioning - Tender Submission pack loaded on the tender portal.
• Use the Commissioning Experience Interleaf to indicate which Mandatory Experience is available.
• Then include the evidence to support this.
• DO NOT SUBMIT THE RESOURCE’S ENTIRE PORTFOLIO OF EVIDENCE – ONLY THE SHEETS RELEVANT THAT DEMONSTRATE THE EXPERIENCE LISTED.
• Copies of training certificates are to be certified (certification must be signed and dated, no older than 3 months)
71
METERING: MANDATORY CRITERIA
• MANDATORY EXPERIENCE - SCORING
• Total / Max Points = 45
• Each Experience criteria is worth 15 points
• Negative Marking Applies
• 15 point deducted if evidence not submitted as per requirements stated
• A minimum score of 15 must be achieved for Mandatory Experience for the submission to be processed further.
72
METERING: MANDATORY CRITERIA
• MANDATORY SKILLS
73
MANDATORY SKILLS
CRITERIA EVIDENCE EVIDENCE REQUIREMENTS Scoring
ECSA
Registered
Resource
ECSA Registration -
Pr Eng / Pr Tech
Professional
Registration
Copy of registration certificate - certified by a
commissioner of Oaths, with a signature and date not
older than three months from the issue date of this
tender.
1
METERING: MANDATORY CRITERIA
• MANDATORY SKILLS – SCORING
• Total / Max Points = 1
• The Skill criteria is worth 1 point
• Negative Marking Applies
• 1 point deducted if evidence not submitted as per requirements stated
74
METERING: MANDATORY CRITERIA
• MANDATORY TOOLS/EQUIPMENT
75
No Tool/Equipment
1 AC Current clamp: 0-5A
2 AC Current clamp: 0-1000A
3 Current injection test set
4 Digital multi-meter
5 Insulation tester 500V
6 Insulation tester 5kV
7 Laptop
8 Capacitive Load box
9 CT accuracy test set
10 Meter test set
11 Optical eye: Universal type
12 Injection set and reference meter
13 PK 2 4 way test handles.
14 Insulated tools
METERING: MANDATORY CRITERIA
• MANDATORY TOOLS/EQUIPMENT
• Refer to the Metering Commissioning - Tender Submission pack loaded on the tender portal.
• Use the tool list included in the pack for your evidence submission. This is preferred.
• HOW TO SUBMIT THE REQUIRED EVIDENCE:
• Use the Tool List in the tender pack.
• Indicate if the tool is currently OWNED by the Company or being HIRED
• If the tool is owned, indicate the quantity available and if the tools are available for inspection if needed.
• If the tools are being hired, include a letter from the Bona Fide Hiring Company proving the ability to hire the tools. If this letter is not included, points will be deducted for the relevant tools.
76
METERING: MANDATORY CRITERIA
• MANDATORY TOOLS/EQUIPMENT - SCORING
• Total / Max Points = 14
• Each Tool/Equipment criteria is worth 1 point
• Negative Marking Applies
• 1 point deducted if evidence not submitted as per requirements stated
• A minimum score of 7 must be achieved for Mandatory Tools/Equipment for the submission to be processed further.
77
METERING: MANDATORY CRITERIA
• MANDATORY VEHICLES
78
Criteria Quantity Evidence Evidence requirements Scoring
Bakkie/
LDV
1 Proof of
Ownership
Or
Hiring Letter
In order to demonstrate ownership, license documents are to be
submitted, clearly showing the type of vehicle and the owner’s
name.
If the vehicle is not in the Company name then submit an affidavit
clarifying the vehicle ownership for consideration.
If the evidence does not adequately demonstrate ownership then the
vehicle will be noted as non-responsive.
Hiring of the Vehicle will be accepted. A hiring letter from a Bona
Fide hiring company will be required as evidence. Hiring from
Electrical/Construction/Other Contractors will not be accepted. If the
hiring letter is not provided or accepted then the vehicle will be noted
as non-responsive.
1
METERING: MANDATORY CRITERIA
• MANDATORY VEHICLES
• HOW TO SUBMIT THE REQUIRED EVIDENCE:
• The Vehicles listed can be OWNED by the Company or HIRED.
• If OWNED:
• Evidence of ownership is needed. Submit evidence such as a Logbook or license documents that show the vehicle type (e.g. bakkie, LDV, micro-bus, dropside etc) and the owners name.
• If the vehicle is not in the companies name, include an affidavit explaining the ownership of the vehicle. The vehicle ownership must be related to the company in a significant way e.g. Company Owner’s name, Shareholders Name etc
• The CRANE TRUCK EVIDENCE must include the evidence above and proof of the crane e.g. installation certificate, load test certificate etc.
• If HIRED: include a letter from the Bona Fide Hiring Company proving the ability to the vehicles. If this letter is not included, points will be deducted for the relevant vehicles.
79
METERING: MANDATORY CRITERIA
• MANDATORY VEHICLES
• Total / Max Points = 1
• Vehicle criteria is worth 1 point
• Negative Marking Applies
• 1 point deducted if evidence not submitted as per requirements stated
80
METERING: MANDATORY CRITERIA
• Only applicable if the minimum score for the Mandatory Evidence is achieved as follows:
• Mandatory Experience = 15
• Mandatory Tools/Equipment = 7
• Submitting evidence as per the requirements and minimizing the scores that will be deducted by negative marking will increase the points achieved for the Mandatory Evidence.
• If these scores are not achieved the submission will not be processed further.
• This will be the final score for the submission in this Discipline of commissioning. The final score will be converted to a percentage.
• The % scores will be ordered from highest to lowest, thereby ranking them.
81
METERING: MANDATORY CRITERIA
• Threshold for Ranking:
• The TOP 15 submissions achieving a % score of 67% or more will be processed further
• If there are less than 15 submissions with scores greater than or equal to 67%, then the shortfall will be made up from submissions with scores between 66% and 36% (inclusive). The selected submissions will be processed further.
• These submissions will be allocated for Development to resolve the shortfalls related to the Mandatory evidence which resulted in the score achieved.
• Submissions not selected in the Top 15 will not be processed further to determine the COMMISSIONING Top 15.
82
TELECONTROL
TECHNICAL CRITERIA, SCORING, THRESHOLD etc.
83
TELECONTROL: MANDATORY CRITERIA
• MANDATORY EXPERIENCE
• Commissioning Records/Portfolio of Evidence/Training Certificates demonstrating experience for the following:
• Reclosers (Any 2 of the following: Tavrida, Schneider, Nulec, 4c, Form 5)
• D20 RTU
• D400 RTU
84
TELECONTROL: MANDATORY CRITERIA
• MANDATORY EXPERIENCE
• Evidence is:
• Commissioning Records/Portfolio of Evidence/Training Certificates demonstrating experience for the following:
• Refer to the Telecontrol Commissioning - Tender Submission pack loaded on the tender portal.
• Use the Commissioning Experience Interleaf to indicate which Mandatory Experience is available.
• Then include the evidence to support this.
• DO NOT SUBMIT THE RESOURCE’S ENTIRE PORTFOLIO OF EVIDENCE – ONLY THE SHEETS RELEVANT THAT DEMONSTRATE THE EXPERIENCE LISTED.
• Copies of training certificates are to be certified (certification must be signed and dated, no older than 3 months)
85
TELECONTROL: MANDATORY CRITERIA
• MANDATORY EXPERIENCE - SCORING
• Total / Max Points = 45
• Each Experience criteria is worth 15 points
• Negative Marking Applies
• 15 point deducted if evidence not submitted as per requirements stated
• A minimum score of 15 must be achieved for Mandatory Experience for the submission to be processed further.
86
TELECONTROL: MANDATORY CRITERIA
• MANDATORY SKILLS
87
MANDATORY SKILLS
CRITERIA EVIDENCE EVIDENCE REQUIREMENTS Scoring
ECSA
Registered
Resource
ECSA Registration -
Pr Eng / Pr Tech
Professional
Registration
Copy of registration certificate - certified by a
commissioner of Oaths, with a signature and date not
older than three months from the issue date of this
tender.
1
TELECONTROL: MANDATORY CRITERIA
• MANDATORY SKILLS – SCORING
• Total / Max Points = 1
• The Skill criteria is worth 1 point
• Negative Marking Applies
• 1 point deducted if evidence not submitted as per requirements stated
88
TELECONTROL: MANDATORY CRITERIA
• MANDATORY TOOLS/EQUIPMENT
89
No Tool/Equipment 1 Laptop PC with Serial port and USB
ports
2 Electrical or DC Drill
3 GSM Installer's friend
4 Digital Multi meter
5 Milli Amp Injector
6 Megger Earth Resistance tester
7 Tool Box with wire strippers, Crimpers
etc all insulated tools 1000V
8 Soldering and De-Soldering Station
9 Relevant test boxes and test
equipment for Section Breakers
(Schnieder and Tavrida)
TELECONTROL: MANDATORY CRITERIA
• MANDATORY TOOLS/EQUIPMENT
• Refer to the Telecontrol Commissioning - Tender Submission pack loaded on the tender portal.
• Use the tool list included in the pack for your evidence submission. This is preferred.
• HOW TO SUBMIT THE REQUIRED EVIDENCE:
• Use the Tool List in the tender pack.
• Indicate if the tool is currently OWNED by the Company or being HIRED
• If the tool is owned, indicate the quantity available and if the tools are available for inspection if needed.
• If the tools are being hired, include a letter from the Bona Fide Hiring Company proving the ability to hire the tools. If this letter is not included, points will be deducted for the relevant tools.
90
TELECONTROL: MANDATORY CRITERIA
• MANDATORY TOOLS/EQUIPMENT - SCORING
• Total / Max Points = 9
• Each Tool/Equipment criteria is worth 1 point
• Negative Marking Applies
• 1 point deducted if evidence not submitted as per requirements stated
• A minimum score of 5 must be achieved for Mandatory Tools/Equipment for the submission to be processed further.
91
TELECONTROL: MANDATORY CRITERIA
• MANDATORY VEHICLES
92
Criteria Quantity Evidence Evidence requirements Scoring
Bakkie/
LDV
1 Proof of
Ownership
Or
Hiring Letter
In order to demonstrate ownership, license documents are to be
submitted, clearly showing the type of vehicle and the owner’s
name.
If the vehicle is not in the Company name then submit an affidavit
clarifying the vehicle ownership for consideration.
If the evidence does not adequately demonstrate ownership then the
vehicle will be noted as non-responsive.
Hiring of the Vehicle will be accepted. A hiring letter from a Bona
Fide hiring company will be required as evidence. Hiring from
Electrical/Construction/Other Contractors will not be accepted. If the
hiring letter is not provided or accepted then the vehicle will be noted
as non-responsive.
1
TELECONTROL: MANDATORY CRITERIA
• MANDATORY VEHICLES
• HOW TO SUBMIT THE REQUIRED EVIDENCE:
• The Vehicles listed can be OWNED by the Company or HIRED.
• If OWNED:
• Evidence of ownership is needed. Submit evidence such as a Logbook or license documents that show the vehicle type (e.g. bakkie, LDV, micro-bus, dropside etc) and the owners name.
• If the vehicle is not in the companies name, include an affidavit explaining the ownership of the vehicle. The vehicle ownership must be related to the company in a significant way e.g. Company Owner’s name, Shareholders Name etc
• The CRANE TRUCK EVIDENCE must include the evidence above and proof of the crane e.g. installation certificate, load test certificate etc.
• If HIRED: include a letter from the Bona Fide Hiring Company proving the ability to the vehicles. If this letter is not included, points will be deducted for the relevant vehicles.
93
TELECONTROL: MANDATORY CRITERIA
• MANDATORY VEHICLES
• Total / Max Points = 1
• Vehicle criteria is worth 1 point
• Negative Marking Applies
• 1 point deducted if evidence not submitted as per requirements stated
94
TELECONTROL: MANDATORY CRITERIA
• Only applicable if the minimum score for the Mandatory Evidence is achieved as follows:
• Mandatory Experience = 15
• Mandatory Tools/Equipment = 5
• Submitting evidence as per the requirements and minimizing the scores that will be deducted by negative marking will increase the points achieved for the Mandatory Evidence.
• If these scores are not achieved the submission will not be processed further.
• This will be the final score for the submission in this Discipline of commissioning. The final score will be converted to a percentage.
• The % scores will be ordered from highest to lowest, thereby ranking them.
95
TELECONTROL: MANDATORY CRITERIA
• Threshold for Ranking:
• The TOP 15 submissions achieving a % score of 67% or more will be processed further
• If there are less than 15 submissions with scores greater than or equal to 67%, then the shortfall will be made up from submissions with scores between 66% and 35% (inclusive). The selected submissions will be processed further.
• These submissions will be allocated for Development to resolve the shortfalls related to the Mandatory evidence which resulted in the score achieved.
• Submissions not selected in the Top 15 will not be processed further to determine the COMMISSIONING Top 15.
96
DC
TECHNICAL CRITERIA, SCORING, THRESHOLD etc.
97
DC: MANDATORY CRITERIA
• MANDATORY EXPERIENCE
• Commissioning Records/Portfolio of Evidence/Training Certificates demonstrating experience for the following:
• Batteries
• Battery Chargers
• AC/DC Distribution Boards
98
DC: MANDATORY CRITERIA
• MANDATORY EXPERIENCE
• Evidence is:
• Commissioning Records/Portfolio of Evidence/Training Certificates demonstrating experience for the following:
• Refer to the DC Commissioning - Tender Submission pack loaded on the tender portal.
• Use the Commissioning Experience Interleaf to indicate which Mandatory Experience is available.
• Then include the evidence to support this.
• DO NOT SUBMIT THE RESOURCE’S ENTIRE PORTFOLIO OF EVIDENCE – ONLY THE SHEETS RELEVANT THAT DEMONSTRATE THE EXPERIENCE LISTED.
• Copies of training certificates are to be certified (certification must be signed and dated, no older than 3 months)
99
DC: MANDATORY CRITERIA
• MANDATORY EXPERIENCE - SCORING
• Total / Max Points = 55
• Battery and Battery Charger Experience criteria is worth 20 points
• AC/DC Board Experience criteria is worth 15 points
• Negative Marking Applies
• Relevant point deducted if evidence not submitted as per requirements stated
• A minimum score of 20 must be achieved for Mandatory Experience for the submission to be processed further.
100
DC: MANDATORY CRITERIA
• MANDATORY SKILLS
101
MANDATORY SKILLS
CRITERIA EVIDENCE EVIDENCE REQUIREMENTS Scoring
ECSA
Registered
Resource
ECSA Registration -
Pr Eng / Pr Tech
Professional
Registration
Copy of registration certificate - certified by a
commissioner of Oaths, with a signature and date not
older than three months from the issue date of this
tender.
1
DC: MANDATORY CRITERIA
• MANDATORY SKILLS – SCORING
• Total / Max Points = 1
• The Skill criteria is worth 1 point
• Negative Marking Applies
• 1 point deducted if evidence not submitted as per requirements stated
102
DC: MANDATORY CRITERIA
• MANDATORY TOOLS/EQUIPMENT
103
No Tool/Equipment
1 Mini Clamp Meter
2 Digital Multimeter Basic
3 Digital Multimeter Advanced
4 Digital Clamp On Current Meter
5 Temperature gun
6 Hydrometer
7 Thermometer
8 Conductivity meter
9 AC/DC mini clamp meter
10 Discharge Unit
No Tool/Equipment
11 Voltage Unit
12 Digital hydrometer
13 State-of-Health tester: Impedance or
conductance tester
14 Scopemeter
15 Cadmium stick
16 Earth leakage tester
17 Safety gloves
18 Laptop
19 Portable Earth Leakage Unit
20 Portable variable power supply
21 Portable 5kVA generator
DC: MANDATORY CRITERIA
• MANDATORY TOOLS/EQUIPMENT
• Refer to the DC Commissioning - Tender Submission pack loaded on the tender portal.
• Use the tool list included in the pack for your evidence submission. This is preferred.
• HOW TO SUBMIT THE REQUIRED EVIDENCE:
• Use the Tool List in the tender pack.
• Indicate if the tool is currently OWNED by the Company or being HIRED
• If the tool is owned, indicate the quantity available and if the tools are available for inspection if needed.
• If the tools are being hired, include a letter from the Bona Fide Hiring Company proving the ability to hire the tools. If this letter is not included, points will be deducted for the relevant tools.
104
DC: MANDATORY CRITERIA
• MANDATORY TOOLS/EQUIPMENT - SCORING
• Total / Max Points = 21
• Each Tool/Equipment criteria is worth 1 point
• Negative Marking Applies
• 1 point deducted if evidence not submitted as per requirements stated
• A minimum score of 12 must be achieved for Mandatory Tools/Equipment for the submission to be processed further.
105
DC: MANDATORY CRITERIA
• MANDATORY VEHICLES
106
Criteria Quantity Evidence Evidence requirements Scoring
Bakkie/
LDV
1 Proof of
Ownership
Or
Hiring Letter
In order to demonstrate ownership, license documents are to be
submitted, clearly showing the type of vehicle and the owner’s
name.
If the vehicle is not in the Company name then submit an affidavit
clarifying the vehicle ownership for consideration.
If the evidence does not adequately demonstrate ownership then the
vehicle will be noted as non-responsive.
Hiring of the Vehicle will be accepted. A hiring letter from a Bona
Fide hiring company will be required as evidence. Hiring from
Electrical/Construction/Other Contractors will not be accepted. If the
hiring letter is not provided or accepted then the vehicle will be noted
as non-responsive.
1
DC: MANDATORY CRITERIA
• MANDATORY VEHICLES
• HOW TO SUBMIT THE REQUIRED EVIDENCE:
• The Vehicles listed can be OWNED by the Company or HIRED.
• If OWNED:
• Evidence of ownership is needed. Submit evidence such as a Logbook or license documents that show the vehicle type (e.g. bakkie, LDV, micro-bus, dropside etc) and the owners name.
• If the vehicle is not in the companies name, include an affidavit explaining the ownership of the vehicle. The vehicle ownership must be related to the company in a significant way e.g. Company Owner’s name, Shareholders Name etc
• The CRANE TRUCK EVIDENCE must include the evidence above and proof of the crane e.g. installation certificate, load test certificate etc.
• If HIRED: include a letter from the Bona Fide Hiring Company proving the ability to the vehicles. If this letter is not included, points will be deducted for the relevant vehicles.
107
DC: MANDATORY CRITERIA
• MANDATORY VEHICLES
• Total / Max Points = 1
• Vehicle criteria is worth 1 point
• Negative Marking Applies
• 1 point deducted if evidence not submitted as per requirements stated
108
DC: MANDATORY CRITERIA
• Only applicable if the minimum score for the Mandatory Evidence is achieved as follows:
• Mandatory Experience = 20
• Mandatory Tools/Equipment = 12
• Submitting evidence as per the requirements and minimizing the scores that will be deducted by negative marking will increase the points achieved for the Mandatory Evidence.
• If these scores are not achieved the submission will not be processed further.
• This will be the final score for the submission in this Discipline of commissioning. The final score will be converted to a percentage.
• The % scores will be ordered from highest to lowest, thereby ranking them.
109
DC: MANDATORY CRITERIA
• Threshold for Ranking:
• The TOP 15 submissions achieving a % score of 66% or more will be processed further
• If there are less than 15 submissions with scores greater than or equal to 66%, then the shortfall will be made up from submissions with scores between 65% and 41% (inclusive). The selected submissions will be processed further.
• These submissions will be allocated for Development to resolve the shortfalls related to the Mandatory evidence which resulted in the score achieved.
• Submissions not selected in the Top 15 will not be processed further to determine the COMMISSIONING Top 15.
110
COMMISSIONING FINAL RANKING
111
Protection
Top 15
Metering
Top 15
Telecontrol
Top 15
DC
Top 15
COMMISSIONING
FINAL TOP 15
ACHIEVING TOP 15
• How to maximize the chance of being in the Top 15 for any Discipline (Electrical Plant, Civil, Commissioning)?
• Follow the Evidence Guidelines – e.g. certify, method statements, CVs etc.
• Use the Submission Packs and organize the evidence correctly per discipline
• Don’t just attempt to meet the minimum score – try to meet the maximum score
112
SUBMISSION PACKS
• Examples of the submission packs will now be demonstrated
• Tender Discipline Selection
• Example 1: Electrical Plant
• Example 2: Protection Commissioning
113
AT CONTRACT AWARD
• Electrical Plant:
• Department of Labour Registration as an Electrical Contractor – in the name of the tendering company and valid at the time of contract award.
• Proof of registration as a candidate or confirmation letter from SACPCMP of registration for the Construction Manager.
• Assessments may be carried out by Eskom prior to Contract Award. This will include resource verification, project assessments and referee interviews. The outcome of the assessment will be the final result, and supersede all previous results.
• General Building and Civil Engineering Work
• Department of Labour Registration as a Civil and Building Contractor – in the name of the tendering company and valid at the time of contract award.
• Proof of registration as a candidate or confirmation letter from SACPCMP of registration for the Construction Manager.
• Assessments may be carried out by Eskom prior to Contract Award. This will include resource verification, project assessments and referee interviews. The outcome of the assessment will be the final result, and supersede all previous results.
114
AT CONTRACT AWARD
• Commissioning:
• Assessments may be carried out by Eskom prior to Contract Award. This will include resource verification, project assessments and referee interviews. The outcome of the assessment will be the final result, and supersede all previous results.
115