Team 6
Case for Cambodia
Eric Immerfall
Elizabeth Smit
Jordan Johnston
Lisa Andela
Aaron Goodman
Design NormsMaster Plan LayoutAccomplishments and DecisionsObstaclesWhat We Have Learned Questions
Presentation Outline
Cultural Appropriateness: Through the design, materials, and
construction methods of the common Cambodian.
Transparency: Communication about the simplicity and
reliability of the design.Integrity:
Design will facilitate relationships between people and their land.
Design Norms
Design Norms Layout Accomplishments Obstacles Learned Questions
Master Plan Layout
• Well• Solar Pump
• Fish Ponds• Drip
Irrigation
• Common Building
• Sanitary Facilities
Design Norms Layout Accomplishments Obstacles Learned Questions
• Bridge
Common BuildingComputer model started
in Revit Structure 2010First and second floors
and stairs inputModel inserted into Civil
3D site planLayout for first and
second floor completedDesign changed to a
larger sizeStairway designed
Wrapping stair design
Design Norms Layout Accomplishments Obstacles Learned Questions
Layout2nd Floor- 11 dorm roomsTile roof, steel and concrete
1st Floor- Classroom, kitchen, 3 full bathrooms
Design Norms Layout Accomplishments Obstacles Learned Questions
Sanitary Facility3 bathrooms
- sink, toilet, shower in each
Design options- Stabilization Pond- Treatment- Latrine Pit- Septic
Final Choice - Multiple Latrine Pits
http://www.rdic.org
Design Norms Layout Accomplishments Obstacles Learned Questions
Sanitary Facility-Layout
Design Norms Layout Accomplishments Obstacles Learned Questions
ShowerLatrine PitToilet &Sink
Bridge DesignCross Sections made
using data from site
Design changed to include dam Dry season water
supply
Currently Modeling in HEC-RAS and HY – 8 to determine culvert sizes and amounts
Design Norms Layout Accomplishments Obstacles Learned Questions
Bridge Design
Design Norms Layout Accomplishments Obstacles Learned Questions
Area of Dam
Renewable Energy Source
Estimation of Power DemandsDetermined harvestable energyInitial determination of specific componentsPreliminary cost analysis of primary system
Annuity Payments approximately $2200/yr Cost per KW-hour $1.00-$1.30
Design Norms Layout Accomplishments Obstacles Learned Questions
http://cambodia.picosol.nl
Renewable Energy Source – Design Changes
Changed to a multiple system design 2 to 3 systems: building electricity & water
pumps
Design Norms Layout Accomplishments Obstacles Learned Questions
http://cambodia.picosol.nl
Water Distribution and IrrigationDetermining elevation
change of the farm
Drip irrigation system for veggie garden using waste fish water
Storage behind dam to irrigate ESA in dry season
Using AutoCAD Civil 3D for topography
Design Norms Layout Accomplishments Obstacles Learned Questions
www.ide-cambodia.org/
Obstacles Have OvercomeSite DataLocal vendors for
system componentsPreliminary design
Obstacles in Design
Design Norms Layout Accomplishments Obstacles Learned Questions
Obstacles to OvercomeMore modeling of
designsFinal master plan
design
Keep units straight -metricDocument everythingThings change- be able to adaptWe don’t know everything-make assumptionsGetting started is half the battle- where to
startLearned a lot about different aspects of site
developmentCommunication is key between group
members
What We have Learned
Design Norms Layout Accomplishments Obstacles Learned Questions
Questions?
Further questions…email us!…[email protected]
Special Thanks To: Prof DeRooy-Team Advisor Prof Dornbos-Biology Prof Rachel Koopman-Interim Data
CoordinatorInterim Group
Roger Lamer-Industrial Consultant Navy Chann-Chhay & Li Chhay-
ClientFounders of Eden School of
Agriculture
Design Norms Layout Accomplishments Obstacles Learned Questions