TarBuster Drill and Case System
www.dril-quip.com
Setting a Global Standard
tm
Tar zones are unpredictable. They can not be seen seismically. A zone can be from several feet to
over 150 feet thick, with various levels of mobility, and it comes as no surprise to operators that tar zones can present major difficulties for drilling. The tar can plastically deform into the wellbore, circulation is lost, increased shock and vibrations occur; the tar sticks to the Bottom Hole Assembly (BHA) and drill pipe, clogs flowlines and soils handling equipment.
The Dril-Quip TarBuster Drill and Case System was designed to deal with the many problems caused by tar zones. The TarBuster System allows for casing shoe or bit and underreamer options to get the casing to the desired depth, and is capable of more aggressive drilling than with casing and reamer shoe. The main components of the TarBuster System are the Liner Hanger Setting Adapter (LHSA), the Liner Hanger Set-ting Adapter Running Tool (LHSART) and the Liner Top Isolation Packer (LTIP). The BHA is attached to the inner string below the LHSA. The LHSA is run on the first trip and the LTIP, with bidirectional slips, is run on the second trip.
TarBusTer™ Drill anD Case SYSTEM
1
Liner Hanger Setting Adapter
Running Tool(LHSART)
Liner Hanger Setting Adapter
(LHSA)
2
Features:• Ream or drill in
• Right- or left-hand torque
• Hydraulic functions are port-isolated to pre-vent premature actuation
• Liner/casing rotation enhances flow-by, help-ing to clear tar and debris from the hydraulic tool and out of the hole
• Reduced length (less than half the length of a standard liner) provides less flow restriction
• Over four times more flow-by than conven-tional running tool; returns are taken up the I.D. annulus of the tool
• Developed with the aid of Computational Fluid Dynamics (CFD) analysis
liner Hanger seTTing aDapTer running Tool
Flow-By Exit Slots
Hydraulic Release Piston
C-Ring Ball Seat
Clutch Profile
Split Load Ring
Secondary Release Housing with Anti-
Rotation Keys
Drill-Down Shoulder
Anti-Rotation Keys for Bidirectional
Connection
Setting Ball Diverter
Drill Pipe Connection
Centralizer Fins
Drill Pipe Connection
Top View of Anti-Rotation Keys
for Bidirectional Connection
Top View of Spline to Mandrel
Top View of Hydraulic
Flow Path
Top View of Centralizer Fins
3
Features:
liner Hanger seTTing aDapTer
Tie-Back Receptacle
Clutch ProfileSplit Load
Ring Profile
Anti-Rotation Slot for Secondary
Mechanical Release
Liner Hanger Setting Adapter Body
Drill-Down Shoulder
Tie-Back Profile for Liner Top
Isolation Packer
Casing Thread
Tie-BackReceptacle
RunningAdapter
Upper BodyLock Ring
Lower BodyLock Ring
UpperSlip Cone
LowerSlip Cone
Split Lock Ringfor Tie-Back to
Liner SettingAdapter
Molded Sealsfor Tie-Back to
Liner SettingAdapter
BidirectionalC-Ring Slip
PusherSleeve
Packer
Packer Cone
4
Tie-Back Receptacle
Running Adapter
Upper Body Lock Ring
Pusher Sleeve
Packer
Packer Cone
Lower Body Lock Ring
Upper Slip Cone
Bidirectional C-Ring Slip
Lower Slip Cone
Molded Seals for Tie-Back to Liner Setting Adapter
Split Lock Ring for Tie-Back to Liner Setting Adapter
Features:
liner Top isolaTion paCker
TarBusTer running proCeDures
Running Procedures to Install Liner Hang-er Setting Adapter (LHSA)
1. After hole interval is drilled, POOH with Bottom Hole Assembly (BHA) while boosting riser.
2. Pump viscous sweeps to help clean hole.
3. Run casing with liner shoe as specified by customer procedure. An open-ended shoe with 45 degree inverted bevel is recommended.
4. Place false rotary on top of last casing connection.
5. Run BHA and inner string.
6. Make up Liner Hanger Setting Adapter Running Tool (LHSART) with LHSA to inner string.
7. Lower TarBuster assembly through rotary and trip into the hole.
8. Turn on pumps once in 13 5/8" cased hole to wash liner down as needed or as per customer procedure.
9. Begin to rotate casing two stands from 13 5/8" casing shoe, with circulation. 30 RPM in cased hole suggested.
10. In open hole, adjust pump rate and weight on bit accord-ing to torque and hole conditions; monitor returns.
11. Continuing to rotate pipe, increase to 60 RPM in open hole. Continue into hole until TD is reached.
12. Rig up Cementing Manifold onto last stand of the landing string.
13. Launch 2" setting ball from the Cementing Manifold.
14. Circulate ball at 1-2 bpm to chase ball down. Shut pumps down before the ball reaches the ball seat to prevent inad-vertently engaging the LHSART.
15. With the setting ball on seat, pressure up to 2,000 psi to hydraulically release LHSART.
16. Pick up LHSART to check for release.
17. While tripping out of the hole with LHSART and BHA, wash liner top in preparation for tieback with Liner Top Isolation Packer (LTIP).
18. Pull out of the hole.
5
Running Procedures to Install Liner Top Isolation Packer (LTIP)
1. Pick up and run the cementing drill pipe, stinger and (Halliburton Fas Drill?) Squeeze Packer, properly spaced out for squeeze job.
2. Pick up the LTIP with LTIP Running Tool and make up to cementing drill pipe.
3. Make up landing string to LTIP Running Tool and trip into the hole per pipe tally.
4. Inside casing, wash and clean the hole per operator's procedures.
5. Wash and clean the liner top at 200 to 300 GPM, prior to stabbing into liner top to avoid damaging seals.
6. Tag LHSA to locate latch ring.
7. Slack off 60,000 lbs at the tool to expand load ring into profile in tieback and lock load ring.
8. Pick up 100,000 lbs over drill pipe weight to verify that load ring is engaged into tieback.
9. Slack off to neutral weight.
10. Rig up cementing manifold.
11. Drop 3" setting ball from surface and circulate to running tool.
12. With setting ball on seat, pick up 100,000 lbs over drill pipe weight to put liner in tension.
13. Pressure to 1,000 psi to set bidirectional slip and suspend liner in tension.
14. Slack off 60,000 lbs at the tool, then pick up 60,000 lbs over drill pipe weight to aid in setting the slip. Repeat, increasing setting load to 100,000 lbs.
15. Slack off 40,000 lbs at the tool onto the slip.
16. Pressure to 2,000 psi to release running tool from LTIP, then release pressure to 500 psi and hold.
17. Pick up running string and check that running tool is released from the packer. If running tool is released you will note pressure drop in drill pipe within 4-6" of pipe movement at the running tool.
18. Pick up running tool's Packer Setting Assembly (PSA) above the liner top.
19. Slack off PSA back into the Tieback of the LTIP to trip and "arm" the Packer Setting Ring on the PSA.
20. Pick up running tool's PSA above the liner top a second time to release Packer Setting Ring.
21. Slowly slack off 100,000 lbs at the tool to set the packer seal. Add slow rotation of the drill pipe while slacking off to aid in working down the drill pipe weight.
22. Pressure down annulus to 1,000 psi to test packer seal; hold test pressure for 5 minutes.
23. Bleed off pressure.
24. Pick up running tool above the liner top.
25. Rotate drill string to set the Halliburton Fas Drill Squeeze Packer to isolate the drill pipe annulus to squeeze the liner shoe.
26. Pump and displace cement per operator’s procedure.
27. Pull stinger out of the Halliburton Fas Drill Squeeze Packer and circulate per operator’s procedure.
28. Pull out of the hole with the running tool and stinger.
6
www.dril-quip.com
Worldwide Sales & ServiceDRIL-QUIP WESTERN HEMISPHERE DRIL-QUIP, INC. World Headquarters6401 North Eldridge Pkwy.Houston, Texas 77041Tel (713) 939 7711Fax (713) 939 8063
DRIL-QUIP do Brasil, LTDA.Macaé, BrazilTel (55) 22 2791 8950Fax (55) 22 2791 8989
DRIL-QUIP New OrleansNew Orleans, LouisianaTel (504) 522 5566Fax (504) 522 4426
DRIL-QUIP ASIA PACIFIC
DRIL-QUIP Asia Paci�c Pte. Ltd.No. 80 Tuas West DriveSingapore, 638417Tel (65) 6861 0600Fax (65) 6861 5700DRIL-QUIP ChinaShekou, P. R. ChinaTel (86) 75 5268 97137Fax (86) 75 5268 97134
DRIL-QUIP Oil�eld Services(Tianjin) Co., Ltd.Tanggu, Tianjin, P. R. ChinaTel (86) 22 2580 7466Fax (86) 22 2580 7130
DRIL-QUIP MalaysiaKuala Lumpur, MalaysiaTel (60) 3 2168 4308Fax (60) 3 2168 4201
D.Q. Holdings Pty., Ltd.Perth, AustraliaTel (61) 8 9322 8600Fax (61) 8 9322 8500
DRIL-QUIP QatarDoha, QatarTel (974) 44389715Fax (974) 44417041
DRIL-QUIP IndonesiaJakarta, IndonesiaTel (62) 21 720 0612Fax (62) 21 720 1513
DRIL-QUIP Egypt Zahraa El-Maadi, Cairo, EgyptTel (20) 22 753 8809Fax (20) 22 753 8907
Alexandria, EgyptTel (20) 3 450 0507Fax (20) 3 450 0508
DRIL-QUIP Nigeria, Ltd.Port Harcourt, NigeriaTel (234) 84 463866Fax (234) 84 463649
DRIL-QUIP (Ghana) Ltd.Takoradi, GhanaTel: (233) 312 5384
DRIL-QUIP EASTERN HEMISPHERE
DRIL-QUIP (Europe), Ltd.Stoneywood Park, DyceAberdeen, Scotland, UK AB21 7DZTel (44) 1224 727000Fax (44) 1224 727070DRIL-QUIP LondonHigh Wycombe, Bucks, EnglandTel (44) 1494 601086Fax (44) 1494 601094
DRIL-QUIP NorwayStavanger, NorwayTel (47) 51 443700Fax (47) 51 443701
DRIL-QUIP The NetherlandsBeverwijk, The NetherlandsTel (31) 251 22 9250Fax (31) 251 22 0044
DRIL-QUIP DenmarkEsbjerg, DenmarkTel (45) 7518 0944Fax (45) 7518 0640
072214T © 2014 Dril-Quip, inc. Printed in the USA