Statewide Transportation Management Center Statewide Transportation Management Center Software Library SystemSoftware Library System
(SunGuide(SunGuideSMSM))
TIM & SunGuideTIM & SunGuideSMSM Coordination Meeting Coordination MeetingOctober 21, 2004October 21, 2004Orlando, FloridaOrlando, Florida
Liang Y, Hsia, P.E.Liang Y, Hsia, P.E.
State Traffic Engineering & Operations OfficeState Traffic Engineering & Operations Office
Florida Department of TransportationFlorida Department of Transportation
2
Goals and ObjectivesGoals and Objectives
FDOT Goals– Improve transportation safety.– Reduce congestion and delays.– Acquire (own) the most technically comprehensive ITS
software.– Establish a software standard at TMCs throughout the
State of Florida.– Reduce multiple TMC software development,
maintenance, and update costs.
SunGuide software goals:– Flexible and expandable to match individual TMC needs.– Respond to traffic incidents in a rapid, accurate, and
effective manner.
3
Release-Oriented Release-Oriented Development ApproachDevelopment Approach
4
T M C SoftwareT M C SoftwareATMS07 - Regional Traffic ControlATMS07 - Regional Traffic Control
5
Advanced Transportation Advanced Transportation Management Systems (ATMS)Management Systems (ATMS)
ATMS04 - Freeway Control ATMS04 - Freeway Control FDOT District 3 – Tallahassee (Planned)FDOT District 3 – Tallahassee (Planned)
6
Road Rangers Road Rangers EM4 - Roadway Service PatrolsEM4 - Roadway Service Patrols
7
Emergency ManagementEmergency ManagementEM1 - Emergency Response EM1 - Emergency Response Emergency Management AgenciesEmergency Management Agencies
8
Emergency ManagementEmergency ManagementEM1 - Emergency Response EOC Emergency Status MonitoringEM1 - Emergency Response EOC Emergency Status Monitoring
9
511511ATIS1 – Broadcast Traveler InformationATIS1 – Broadcast Traveler Information
511 Traveler information telephone service
10
Operation & MaintenanceOperation & MaintenanceMC01-Maintenance and Construction Vehicle TrackingMC01-Maintenance and Construction Vehicle Tracking
11
ITS Data WarehouseITS Data WarehouseAD2 ITS Data WarehouseAD2 ITS Data Warehouse
12
SunGuideSunGuideSMSM Software Deployment Software Deployment
Center-To-Center CommunicationsTxDOT Extensible Markup Language (XML)
Simple Object Access Protocol (SOAP)
13
Center-to-Center (C2C) Center-to-Center (C2C) CommunicationsCommunications
14
SunGuideSunGuideSMSM Software Project Software Project NTCIP 1203 Dynamic Message SignsNTCIP 1203 Dynamic Message Signs
15
SunGuideSunGuideSMSM Software Project Software Project
NTCIP 1204 Environmental System SensorsNTCIP 1204 Environmental System Sensors (RWIS on FDOT Tallahassee Microwave Tower) (RWIS on FDOT Tallahassee Microwave Tower)
16
SunGuideSunGuideSMSM Software Project Software Project NTCIP 1205 Closed-Circuit Television ControlNTCIP 1205 Closed-Circuit Television Control
17
SunGuideSunGuideSMSM Software Project Software Project NTCIP 1207 Ramp Meter ControlNTCIP 1207 Ramp Meter Control
18
SunGuideSunGuideSMSM Software Project Software Project NTCIP 1208 Video SwitchesNTCIP 1208 Video Switches
19
SunGuideSunGuideSMSM Software Project Software Project NTCIP 1209 Transportation System SensorNTCIP 1209 Transportation System Sensor
20
SunGuideSunGuideSMSM Software Project Software Project NTCIP TranslatorNTCIP Translator
FDOT uses NTCIP translator devices for non-NTCIP DMS and CCTV to save device driver software development costs
21
Status of Release 1 ActivitiesStatus of Release 1 Activities
Project Management:– PM / Meetings / Reviews– Process documents– Interface Control Documents
(ICDs)
Core software framework:– Database– User administration– Executive handler– Status logger– User interface– Map– Data Bus
DMS:– General Subsystem– NTCIP Florida MIB driver– Mark IV version 2.5 driver
CCTV Control:– General Subsystem– NTCIP 1205 driver
Video Switching– General Subsystem– IP Video switching driver
Video Wall– General Subsystem– Barco/Argus video wall driver
Traffic Detection, driver for:– General Subsystem– Bitrans B238-I4 driver– RTMS (EIS and Wavetronix) driver
Incident Management:– GUI– Subsystem
22
Status of Release 2 ActivitiesStatus of Release 2 Activities
Ramp Metering:– Design activities initiated– Initial GUI design completed– High level design completed
Emergency Evacuation:– Requirements refined and
provided to FDOT– Design initiated
Data Archive– Requirements refined– Design initiated
Web Server– Requirements refined– Design initiated
HAR– Requirements refined– Design initiated
Center-to-Center– Requirements refined– Design initiated
RWIS– Requirements refined– Design initiated
Inventory and Maintenance– Requirements to be refined
Optional Service:– iFlorida Data Collection
Process (DCP)
23
License Discussion / Software Baseline
24
License UpdatesLicense Updates
SwRI / FDOT Sublicense– License executed before the contract started.– TxDOT informed SwRI on January 22, 2004 that TransGuide
software was on “hold”.– License amended on April 12, 2004 (to support District 2 and
name change)
For a FDOT / TxDOT partnership to occur two things are needed:
– MOU:• FDOT provided TxDOT with comments and legal opinion on
March 2, 2004
– TxDOT Software License (solves TransGuide license issue)• TxDOT provided FDOT with a license on June 30, 2004
(included previous FDOT requests for content).• FDOT signed license on August 10, 2004.• Waiting for signatures by TxDOT – TxDOT acknowledged the
receiving of the FDOT signed license on August 23, 2004.
25
License Updates - continuedLicense Updates - continued
FDOT / WSDOT Term of Use (TOU):– WSDOT provided FDOT with standard TOU on February 11,
2004.– FDOT provided recommendation on to WSDOT on March
13, 2004.– FDOT provided comments to the WSDOT’s Office of
General Counsel’s August 21, 2004.– WSDOT began working on FDOT’s comments on August
26, 2004.
FDOT / MDX Joint Program Agreement (JPA)– FDOT provided MDX with preliminary JPA on December 3,
2003.– MDX provided FDOT with draft final JPA on June 23, 2004.– FDOT worked on Locally Funded Agreement and MDX JPA.
26
License Updates - continuedLicense Updates - continued
SwRI / FDOT / Lee County Sublicense– Lee County provided FDOT with official letter for participation
on July 27, 2004– FDOT and SwRI started documentation preparation on July
30, 2004– SwRI provided FDOT with draft language on September 10,
2004
FDOT issued iFlorida Data Collection Process (DCP) notice to proceed on September 8, 2004.
GDT License: System Planning Office and Office of Information Systems are finalizing the license agreement on September 14, 2004.
27
Software Software Baseline Baseline
Information: Information: Significant Significant Reuse Of Reuse Of Existing Existing SoftwareSoftware
Legend: E- Existing M – Modified N - New
28
Software Software Baseline Baseline
Information: Information: OwnershipOwnership
29
Budget / Work Plan
30
Release-Oriented Release-Oriented Development ApproachDevelopment Approach
Release 1 Release 2a Release 2b not in scope
31
Budget for SunGuideBudget for SunGuideSMSM Effort: Effort: Release 1Release 1
Source: SwRI BAFO
Budget Amount: $3,208,052
32
Budget for SunGuideBudget for SunGuideSMSM Effort: Effort: Release 2aRelease 2a
Source: SwRI BAFO
Budget Amount: $2,074,276
33
Budget for SunGuideBudget for SunGuideSMSM Effort: Effort: Release 2bRelease 2b
Source: SwRI BAFO
Budget Amount: $245,311
34
Budget for SunGuideBudget for SunGuideSMSM Effort: Effort:Deployment and SupportDeployment and Support
Source: SwRI BAFO
35
SunGuideSunGuideSMSM Budget in Budget in Ten-Year ITS Cost Feasible PlanTen-Year ITS Cost Feasible Plan
(Programmed Dollars in Millions)
Funding Source FY 03-04 FY 04-05 FY 05-06 FY06-07 FY07-08
1. STMCSLS* 5.01 0.75 0.75 0.17 0.17
2. District 6 0.50 (Ramp Metering)
3. MDX
36
SunGuideSunGuideSMSM Budget in Budget in Ten-Year ITS Cost Feasible PlanTen-Year ITS Cost Feasible Plan
(Programmed Dollars in Millions)
Funding Source FY 08-09 FY 09-10 FY 10-11 FY11-12
1. STMCSLS* 0.18 0.18 0.19 0.19
2. District 6 (Ramp Metering)
3. MDX
*Note: Total $8.09 Million
37
SunGuideSunGuideSMSM Software and TIM Software and TIM
TIM Applications
38
Scan Traffic ConditionsScan Traffic Conditions Map Colors Indicate Traffic Conditions
– Mouse over Roadway for Details
– Select Closest Camera
– Drag Camera to Display on Monitor
– PTZ Camera to Examine Traffic Conditions
Check DMS Messages
– Congestion Warning
39
Traffic ConditionsTraffic Conditions
40
Incident ManagementIncident Management Auto-Detected
– Alarm Raised by TSS– Confirmed by Operator– Review, Complete, Modify & Execute Plan
Manual (911 / 511)– Enter Incident Management Data– Review, Complete, Modify & Execute Plan
41
SunGuideSunGuideSM Software and TIM Software and TIM
AMBER Alert Handling
42
Amber Alert HandlingAmber Alert Handling
Pre-planning– DMS Standard Groups– Standard Message Templates (license plate, make,
model, color, etc.)– Notification Information
Deployment– Compose Message– Set Time Limit– Display Message– Check DMS Status
43
Amber Alert DMS Group SelectionAmber Alert DMS Group Selection
44
DMS ControlDMS Control
45
SunGuideSunGuideSM Software and TIM Software and TIM
Special Events
46
Special EventSpecial Event
Pre-plan Messages for DMS– Ingress to ALLTEL Stadium– Egress from ALLTEL Stadium– Alternate Plans
Deploy Messages with Duration Event Management
– Check Traffic Conditions– Check Message Deployment– Adjust Traffic Diversion Messages
47
SunGuideSunGuideSMSM Software and TIM Software and TIM
Emergency Evacuation
48
Emergency EvacuationEmergency Evacuation
Web based information tool:– Evacuation Guidance– Evacuation Travel Information– Evacuation Traffic Management– Evacuation Planning Support – Resource Sharing– Shelter Location & Available Spacing (Future
Feature) Combine with the SunGuide software to provide
evacuation services
49
SunGuideSunGuideSMSM Software Deployment Software Deployment
Transportation Management Centers Applications and Deployments
50
District 4 Broward County RTMCDistrict 4 Broward County RTMC
51
District 4 Broward County RTMCDistrict 4 Broward County RTMC
52
District 4 ScheduleDistrict 4 Schedule
September 2004 District 4 moves equipment to new TMC
October 12, 2004 SunGuideSM Software Team performs Milestone Demonstration
December 2004 SunGuideSM Software Team provides TMC operators with software training
January 2005 SunGuideSM Software Team sets upthe District 4 software
53
District 4 ScheduleDistrict 4 Schedule
December 2004 I95/I595 Video Monitoring Project Starts.
January 2005 District 4 TMC Grand Opening.
January 2005 Complete I 95/I 595 Video Monitoring andDetector System
54
District 4 Milestone DemonstrationDistrict 4 Milestone Demonstration
55
District 4 Milestone DemonstrationDistrict 4 Milestone Demonstration
56
District 6 RTMCDistrict 6 RTMC
57
District 6 ScheduleDistrict 6 Schedule
June 25, 2004 New TMC Grand Opening
July 2005 I-95 Package B project completion
April 2005 Ramp metering subsystem to be installed and tested
June 2005 SunGuideSM Software Release 2deployment includes Ramp metering system
58
Miami-Dade Expressway (MDX) AuthorityMiami-Dade Expressway (MDX) Authority
59
MDX ScheduleMDX Schedule
April 7, 2003 MDX sent letter to ITS Office aboutparticipating in SunGuideSM Project
April 25, 2003 FDOT Responded, Welcoming MDX’s
participation
December 3, 2003 FDOT provided MDX with a draft Joint Program Agreement
June 2005 SunGuideSM Software Release 2 deployment at MDX
October 2005 MDX TMC Operational
60
District 7 RTMCDistrict 7 RTMC
November 2005 Building Construction FinishApril 2006 SunGuideSunGuideSM Software Deployment
61
District 2 RTMCDistrict 2 RTMC
FY 2004FY 2004 I-95 N ITS ImprovementI-95 N ITS ImprovementFY 2006FY 2006 SunGuideSunGuideSM Deployment (Tentative)Deployment (Tentative)
62
District 5 RTMCDistrict 5 RTMC
FY 2004FY 2004 Orlando RTMC retrofit and upgrade Orlando RTMC retrofit and upgrade FY 2004-2005FY 2004-2005 iFlorida C2C between Districts 2 and 5iFlorida C2C between Districts 2 and 5
63
Turnpike RTMCTurnpike RTMC
64
Turnpike ScheduleTurnpike Schedule
March 2004 SunNav 1.1 Test
April 2004 SunNav 1.2 Development
September 2005 Observation of D 4, D 6, MDX C2C Deployment
65
District 1District 1
December 2006 December 2006 SunGuideSunGuideSM Deployment at Ft. Myers RTMC Deployment at Ft. Myers RTMC FY 2011 (2005) Sarasota RTMCFY 2011 (2005) Sarasota RTMC
66
District 3District 3
FY 2007 Pensacola RTMC FY 2007 Pensacola RTMC FY 2008 Tallahassee RTMCFY 2008 Tallahassee RTMC
67
Broward CountyBroward CountyLee County Lee County Bridge Incident ManagementBridge Incident Management
July 27, 2004 Lee County Public Works will apply SunGuide Software
68
C2C ScheduleC2C Schedule
February 16, 2004 SunGuideSM and C2C Project Team completed Interface Control
Document (ICD)
February 20, 2004 SunGuideSM and C2C Project Coordination Teleconference
March 9, 2004 SunGuideSM & C2C Project Coordination Meeting
June, 2005 C2C deployment among Districts 4,6, and MDX
69
Schedule Summary Schedule Summary
SunGuideSM Software Development Team:– Notice to Proceed: October 7, 2003– Release 1: September 2004, or 5.75 months
after May 6, 2004, Notice To Proceed for Engineering Change Order No. 2
– Release 2: June 2005
– Three Milestone Demonstrations Demo 1: October 12, 2004 at District 4Demo 2: March 2005 at District 6
Demo 3: To be determined at District 7
70
TIM Requirements TIM Requirements
Statewide Summary Report for performance measurement
Change management
New requirements
District TIM & SunGuideSM coordination
71
Project Web SiteProject Web Site
http://sunguide.datasys.swri.edu
72
Questions?