Download - SPL Integration Layout Impact on cryo and vacuum sectorisation

Transcript
Page 1: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

SPL Integration LayoutImpact on cryo and vacuum sectorisation

◊ Underground obstacles, constraints on slope and length of the SPL

◊ Continuous cryostat and warm magnet options

◊ Location of the surface buildings and of the main service shaft

◊ Preliminary integration, impact of the position of the couplers

Sylvain Weisz – SPL Cryogenic and vacuum sectorisation – 9 Nov 2009

Page 2: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

Linac 4

SPL tunnel

Material access and services shaftPersonnel and material access shaft

Klystron gallery

Emergency exit shaft

Transfert line to PS2

Personnel passage

Emergency exit shaft

Personnel passage

Personnel passage

Page 3: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

Computer Center

n_TOF target

TI2 injection line

Underground obstacles

Page 4: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

Computer Center

RP requires a shielding of 6.9m of earth to keep Bld 513 a non designated area sets the altitude of Linac4

A. Kosmicki & M. Poehler

Page 5: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

n_TOF target area

160µSr/h in Klystron gallerie for 7 1012 ppp on n_TOF target

(20 GeV, 0.33Hz)

A. Kosmicki & M. Poehler

Page 6: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

TI2 injection line to LHC

SPL tunnel or SPL to PS2 transfert line crosses TI2 from above

A. Kosmicki & M. Poehler

Page 7: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

Linac 4

Computer Center

n_TOF target area

TI2 injection lineSPL tunnel – slope = 1.7%

Transfert line to PS2 – slope = 8.4%

~550m

Constraints on slope and length of the SPL

Page 8: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

10 x β=.65 moduleslength = 121 m

4 Gev version (LP): 18 x β=1 modules + 2 de-modulator modules

extraction regions to Isolde and Eurisol

5 Gev version (HP): 23 x β=1 modules + 2 de-modulator modules

extraction regions to Isolde and Eurisol SPL length = 527.38 m

SPL length = 452.58 m

SPL "baseline" layout

Cold continuous cryostat

T. Renaglia

Page 9: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

"Compact" version (gain on interconnections):

5 Gev version (HP): SPL length = 485.14 m (-42.24 m with respect to "baseline")

"Warm quadrupole" version (with separate cryoline):

5 Gev version (HP): SPL length = 535.92 m (+8.54 m with respect to "baseline")

Continuous cryostat and warm magnet options

Page 10: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

SPL tunnel

Material access and services shaftPersonnel and material access shaft

Klystron gallery

~150m

~170m

Location of the surface buildings and of the main service shaft

Page 11: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

Downstream limit ofmain service shaft

A. Kosmicki & M. Poehler

Too far, assume 320m max.

Page 12: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

SPLTunnel Machine & Tunnel Services

JMB 03-07-2009

Very preliminary integration issue: Position of the power couplers

Preferred to initial model if we have many waveguide between the two tunnels

J-M. Bianco

Page 13: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

Couplers from above would be accessible

Waveguide network would block access to couplers from below (+ probes, controls,water cooling pipes, etc…)Would need a larger tunnel to access from the other side of the modules (Compatibility with cryoline?)

J-M. Bianco

Page 14: SPL  Integration Layout Impact on  cryo  and vacuum sectorisation

Summary◊ SPL would have a 1.7% slope ◊ 550m should be considered as a maximum length

(including debuncher and vertical bend to PS2)◊ A warm magnet option just fits in the footprint◊ Surface buildings and main shafts can be located

around the mid-point of the SPL◊ It would be a big advantage to install the power

couplers from above