Session #6 - EPCC 15 Sponsors/Vendors Panel
Demonstration of real time probabilistic risk assessment for power system operation and planning of operation.
Promaps Realtime
• What is it: Tool for probabilistic risk evaluation in near real-time• Risk:Probability and consequences of disturbances in the power system measured in EENS [MWh/h]• Security of supply
What does it look like
•Client
•Unit model editor
•Dashboard
•Database with results
Unit model editor
Promaps Realtime Client
• Load flow
•Parameters
•Results
•Risk
• Study mode
Dashboard – Main views
• Overview• Area detail• Substation overview• Substation view• Contingency view
Closer look at region view
Region view• Ranked
contingencies• Weather map• Risk in the region• Demand and
production• Risk indicators• Operator
messages
Dashboard
• Plots from within a region
• Showing risk vs. Security of supply
• Both parameters are relevant for system operators
Demand[MW]
Risk[MWh/h]
Security of supply: [min]
• Example weather impacting the security of supply.• Green markers indicating info
updates from TSO• There are disturbances in the grid,
some causing reduced security of supply while other have lesser impact.
Dashboard – Contingency list
• Dynamic list of highest ranked contingencies within a region.• Probability and
consequences • Delta rank
(indictor for contingency rank placement)
Why use Promaps Realtime
Users of Promaps can:• Reduce uncertainty related to operating the grid.Ultimately • Reduce outages experienced by end user• Reduce cost of reinvestments in the power system• Reduce cost of maintanence
Thank you for your attention