seabed-to-surface
SCM ISSUES IN WEST AFRICALOCAL CONTENT DEVELOPMENT
JUNE 2006
slide 2
seabed-to-surfaceSubsea UK June 1st 2006
What we doSURF Conventional Trunklines IMR
slide 3
seabed-to-surfaceSubsea UK June 1st 2006
Africa & Mediterranean : Countries of operation
40% of ACERGY worldwide activity : circa 750 MUSD in 2005.
45% of which is related to procurement of Projects : 350 MUSD
450 MUSD foreseen in 2006 & 2007.
Projects in the Gulf of Guinea Nigeria Angola Equatorial Guinea Congo
Regional permanent implantation in
Angola, Nigeria and Gabon.
slide 4
seabed-to-surfaceSubsea UK June 1st 2006
SCM Issues 1/2
Weak and critical point :• Risky
• Remote environment
• Uncontrolled planning
InstallationDelivery on site
Logistic
Fabrication Transport CustomsEngineering
slide 5
seabed-to-surfaceSubsea UK June 1st 2006
SCM Issues 2/2
How to succeed the installation ?
Engineering : - over design => secure installation and in service lifeFabrication : - zero default => high QA/QC capabilities
How to succeed the delivery on site ?
Ensure good structure for logistics : - Availability of transport (flexible planning)- Very good knowledge of local regulations which are constantly
changing- Strong set up and full control of local logistics from shore to site.
slide 6
seabed-to-surfaceSubsea UK June 1st 2006
West African Top Priority : Local Content = Constraint but also an Opportunity
1. Constraint : • Access to local Human Resources
- Engineers (Engineering)
- Workers (Fabrication)
• Control of Quality
2. Opportunity : • Transport and Customs are cleared Upstream
- Improve Float on planning
- Less complex nature of goods to import.
Installation
Engineering
Transport Customs
FabricationDelivery on site
slide 7
seabed-to-surfaceSubsea UK June 1st 2006
West Africa : A region with high “Country Specifics”C
APE
X \
In
vest
men
t
Technology / Complexity
Pipe fabrication
(Steel mill)
Flexible
Umbilicals
Forging
Engineering
Local logistic
Coating
Yard
long-product base
(Jacket-piles
/double joint)
low high
high
low
slide 8
seabed-to-surfaceSubsea UK June 1st 2006
SOME LOCAL REALISATIONS
slide 9
seabed-to-surfaceSubsea UK June 1st 2006
Nigeria : Warri Yard & Angola : Lobito Yard
slide 10
seabed-to-surfaceSubsea UK June 1st 2006
HRT in Lobito
slide 11
seabed-to-surfaceSubsea UK June 1st 2006
Manifolds in Lobito
slide 12
seabed-to-surfaceSubsea UK June 1st 2006
APL offloading Buoy
slide 13
seabed-to-surfaceSubsea UK June 1st 2006
YOKRI Deck fabrication in Warri
slide 14
seabed-to-surfaceSubsea UK June 1st 2006
Warri Fabrication Yard: Jacket - Suction Piles
slide 15
seabed-to-surfaceSubsea UK June 1st 2006
Warri Fabrication Yard: Jacket - Suction Piles
slide 16
seabed-to-surfaceSubsea UK June 1st 2006
Common objective for main Contractors and Suppliers :
- Localisation in country with guaranteed quality and delivery
Strong and relationship / partnership required
Conclusion