1
Schedule Risk Analysis Mini Masterclass
2
Content
1. Software 2. Schedule Risk Analysis
• Schedule Sense Check • Duration Uncertainty Inputs
• Correlations • Risk Inputs & Modelling
• Distributions
3. Monte Carlo Risk Analysis 4. Results
• What If / Stress Test 5. Benefits
Software Schedule Risk Analysis
4
Software
Palisade @Risk • Excel Based • MSP • SRA Limitations • Cost Focused • Significant
Oracle Primavera Risk Analysis • Primavera, MSP, Others • Manipulate Plan • Large Schedules • Limited Distributions • Limited cost function
Schedule Risk Analysis What is it?
6
Schedule Risk Analysis
• Software
• Schedule • Risk & Uncertainty
Analysis
6
7
Project Schedule • A Project Schedule is a dynamic
representation of the project activities and their execution sequence.
• Dynamic Model – Not a Calendar
• Completion dates should be OUTPUTS not inputs
7
8
Why do we schedule a project? • Plan out activities to understand
realistic targets • Understand resource requirements • Forecast and record performance • Compare performance against
targets (baseline) • Understand dynamics of plan and
identify changes required to meet targets etc
8
9
Build A Schedule
Group Task • Build This Hotel • Less than 10
Activities • Durations • Logic Links
9
Schedule Sense Check What is it?
11
Project Schedule Best Practice
• Define WBS • Set consistent coding strategy • All tasks have dependencies • No constrained dates (or Minimum use if legit) • Activities based on work/durations not dates • Realistic durations • Realistic relationships
• Not date driven • No lags or negative lags
11
12
Schedule issues
• Start to Start with Open End
12
Construction 20
Engineering 20
Design 20
S-S
F-S
S-S
Commissioning 20
Delay
Delay
13
Schedule issues • Finish to Finish with Open End
• Engineering completion becomes constrained by Design and Construction constrained by Engineering
13
Construction
Engineering
Design
F-S
F-S
F-F
Delay
Delay
F-F
14
Constraints
• Often used to set dates • Targets, contract dates, management dates • This is incorrect use and poor planning • ‘looks fine’ but negative float builds up
• Constraints can be legitimate • Date land access is to be granted • Date Vendor/Sub-Con has agreed to start • Resource leveling constraints
• Completion dates are OUTPUTS not inputs
14
Duration Uncertainty Building A Model
16
Duration Uncertainty
• Review Activity Durations • Are they realistic? • Optimistic? Pessimistic? • Durations are not always certain • Activities have natural variance. • 3 point range for better accuracy. Min, Most Likely and Maximum
durations
• Interview/Workshop with Planner, PM, Eng etc
16
17
Risk & Uncertainty
17
Time or Cost
Uncertainty Risk Event
Digging Foundations
Flooding Strike Hard Rock Equipment Failure Archeological Find
100% <100%
5 7
10 11(1) 17
(7)
24 (14)
18
Estimating Impacts
18
19
Group Task
• Build Uncertainty in your durations
19
BASELINE
20
Correlations
Risk Inputs Identify & Quantify
22
Group Task
• Identify Risks
22
Concrete Pour Failure
23
Quantifying Risk Events • Each Risk given a Min, Most Likely & Max impact • Min = Optimistic but realistic outcome
• Most Likely (ML) = Expected most probable outcome • Max = Pessimistic worst case outcome
• Should not include force majeure or project stopping outcome
23
Risk Impact
Num
ber o
f Occ
urre
nces
Min ML Max
Probability Min Most Likely Max
30% 1 week 4 weeks 8 weeks
24
Distributions
25
Distributions
Monte Carlo Schedule Risk Analysis
27
Quantitative Risk Analysis - Distribution
27
2 3 4 5 6 7 8 9 10 11 12
Total 136 264 425 513 703 857 690 600 373 307 132
0200400600800
1000
# O
ccur
ance
s
"Two Dices" - Histogram Simulation (5000x)
What is a Distribution? • Graphical representation of occurrences of a variable, e.g. cost, duration, date,
etc.
• Example: “Two Dice”
Sum Dice#1 + Dice#2
# Occurrences Dice#1 + Dice#2 Combinations # Comb.
2 136 1+1 1 3 264 1+2; 2+1 2 4 425 1+3; 3+1; 2+2 3 5 513 1+4; 4+1; 2+3; 3+2 4 6 703 1+5; 5+1; 2+4; 4+2; 3+3 5 7 857 1+6; 6+1; 2+5; 5+2; 3+4; 4+3 6 8 690 2+6; 6+2; 3+5; 5+3; 4+4 5 9 600 3+6; 6+3; 4+5; 5+4 4
10 373 4+6; 6+4; 5+5 3 11 307 5+6; 6+5 2 12 132 6+6 1
Grand Total 5000
28
Schedule Risk Analysis (SRA)
• Risk Mapping to Plan
• Can be multiple activities • Entering Schedule Delay impacts (Min, ML, Max)
28
29
Schedule Risk Analysis (SRA) • Duration Uncertainty + Assigned Risks
29
30
Schedule Risk Analysis (SRA) • Montecarlo Analysis plots potential finish dates for each activity/milestone
over 1000 iterations and creates an S-curve of probabilistic outcomes.
30
03/02/2023 22/08/2023 09/03/2024
Distribution (start of interval)
0.0
10.0
20.0
30.0
40.0
50.0
Hits
0% 10/06/2023
5% 17/09/2023
10% 17/10/2023
15% 04/11/2023 20% 19/11/2023
25% 01/12/2023
30% 12/12/2023
35% 21/12/2023
40% 27/12/2023
45% 04/01/2024 50% 11/01/2024
55% 20/01/2024
60% 29/01/2024
65% 05/02/2024
70% 14/02/2024
75% 25/02/2024
80% 06/03/2024 85% 17/03/2024
90% 29/03/2024
95% 14/04/2024
100% 06/06/2024
Cumu
lative
Freq
uenc
y
Production Drilling: Mishrif (Pre-mitigated)Entire Plan : Finish Date
31
Schedule Risk Analysis (SRA)
• Analysis calculates the probabilistic (Not actual) completion dates of milestones/activities
• Therefore P50, P90 etc are created from statistical outputs of 5000 different randomly generated outcomes based on input data.
31
Baseline Risk Impact
Deterministic Finish
P50 or P90 Finish
32
Schedule Risk Analysis (SRA) • Top Risks & Top sensitive Activities Identified
• These can then be areas of focus for improvement and mitigation • These can named or omitted on Insurance policies
32
33
Schedule Risk Analysis (SRA) • “What If” Scenarios
• Tool to understand effect of mitigations and schedule changes
• Change Risk Profile and Run analysis to understand effect of mitigation of key risks
• Omitted risks etc
• Value Management • Option Selection/analysis • Identify key activities (Critical and Duration) • Change Schedule (parallel working, additional resource, reduced scope etc) • Reduce Schedule
33
34
Post Mitigated / Target • Pre and Post mitigated probabilistic S-Curves
34
30/10/19
30/8/19 15/5/19
24/6/19
13%
Benefits Projects
36
Project Benefits • Key to ensuring project success
• Identification of project interdependencies
• Management of Risk to allow project completion of time and on budget
• Helps control the cost of a project
• Validation of Project Information
• Fosters a Clear Understanding of Challenges ahead
• Improved Project Communication
• Improved Schedule / Cost Performance
36
37
Content
1. Software 2. Schedule Risk Analysis
• Project Schedule Review • Duration Uncertainty Inputs
• Correlations • Risk Inputs & Modelling
• Distributions
3. Monte Carlo Risk Analysis 4. Results
• What If / Stress Test 5. Benefits
38
Training Courses - Project Risk Management
- Quantitative Risk
(Cost & Schedule)
- @Risk Software
Public & In House
Thank you
Top Related