OMAN RAIL PROJECT.SEGMENT 1 TUNNELS WORKS. Sch-S-Annex-6 (a)

A DETAILS OF TEAMS PLANNED TO BE DEPLOYED FOR THE DRILL & BLAST TECHNIQUE Sr. N o Working faces Activity ID

Gantt Ref (Sch-S-Annex-1)Lining Team Remarks.

A-1 Ajran Tunnel (sector A) D&BA-1-1 Portal ORC0104GN010010A-1-2 Main Tunnel ORC0104GN010020 I

A-1-3 Emergency tunnel ORC0104GN020010ORC0104GN020020 IV

A-1-4 C&C ORC0104GA0010 IIA-2 Kitnah Tunnel (Sector A)A-2-1 Portal ORC0104GN030010A-2-2 Main Tunnel ORC0104GN030020 II

A-2-3 Emergency tunnel ORC0104GN040010ORC0104GN040020 IV

A-2-4 C&C ORC0104GA0040 IIIA-3 Humaydah Tunnel (sector B)A-3-1 Portal ORC0204GN010010A-3-2 Main Tunnel ORC0204GN010020 II

A-3-3 Emergency tunnel ORC0204GN020010ORC0204GN020020 IV

A-4 Zurub Tunnel (sector B)A-4-1 Portal ORC0204GN030010A-4-2 Main Tunnel ORC0204GN030020 III

S-Total Total Tunnelling TeamS-Total Total Lining Team IV

* Kitnah C&C (ORC0104GA0040) is been moved sequentially to the to Arjan C&C to obtain a single tunnelling team

11

6

4*

12

1

4

12

1

Tunnelling Team

D&B12

1