7/25/2019 Sample Pages Build Cost
1/34
The Scientific Costing Guide
Building Construction Cost DataBuildCOSTuildOST
Item of Work Cost Database
2014
7/25/2019 Sample Pages Build Cost
2/34
Div. No. Title Page Div. No. Title Page
01 GENERAL REQUIREMENTS 1 06 WOOD, PLASTICS, AND COMPOSITES 43
01 45 Quality Control 3 06 17 Shop-Fabricated Structural Wood 45
01 45 23 Testing and Inspecting Services 3 06 17 53 Shop-Fabricated Wood Trusses 45
02 EXISTING CONDITIONS 5 06 22 Millwork 45
02 32 Geotechnical Investigations 7 06 22 13 Standard Pattern Wood Trim 45
02 32 19 Exploratory Excavations 7 06 26 Board Paneling 46
02 41 Demolition 7 06 26 13 Profi le Board Paneling 46
02 41 13 Selective Site Demolition 7 06 42 Wood Paneling 46
03 CONCRETE 11 06 42 10 Wood Paneling 46
03 05 Common Work Results for Concrete 13 06 43 Wood Stairs and Railings 47
03 05 13 Basic Concrete Materials 13 06 43 13 Wood Stairs 47
03 11 Concrete Forming 13 06 48 Wood Frames 47
03 11 13 Structural Cast-in-Place Concrete Forming 13 06 48 16 Interior Wood Door Frames 47
03 15 Concrete Accessories 15 07 THERMAL AND MOISTURE PROTECTION 49
03 15 05 Concrete Forming Accessories 16 07 11 Dampproofing 51
03 15 13 Waterstops 16 07 11 17 Damp-Proof Course 51
03 21 Reinforcing Bars 17 07 13 Sheet Waterproofing 51
03 21 10 Uncoated Reinforcing Steel 17 07 13 13 Bituminous Sheet Waterproofing 51
03 22 Welded Wire Fabric Reinforcin g 17 07 16 Cementitious And Reactive Waterproofing 52
03 22 05 Uncoated Welded Wire Fabric 17 07 16 16 Crystalline Waterproofing 52
03 31 Structural Concrete 17 07 21 Thermal Insulation 55
03 31 05 Normal Weight Structural Concrete 17 07 21 14 Building Insulation 56
03 35 Concrete Finishing 21 07 22 Roof and Deck Insulation 56
03 35 29 Tooled Concrete Finishing 21 07 22 16 Roof Board Insulation 57
03 41 Precast Structural Concrete 21 07 26 Vapor Retarders 57
03 41 05 Precast Concrete Members 21 07 26 10 Vapor Retarders 57
03 41 16 Precast Concrete Slabs 23 07 32 Roof Tiles 57
03 45 Precast Architectural Concrete 23 07 32 13 Clay Roof Tiles 57
03 45 13 Faced Architectural Precast Concrete 23 07 41 Roof Panels 58
04 MASONRY 25 07 41 13 Metal Roof Panels 58
04 21 Clay Unit Masonry 27 07 41 34 Asbestos Roof Panels 60
04 21 13 Brick Masonry 27 08 OPENINGS 6104 22 Concrete Unit Masonry 31 08 09 Metal Doors, Windows And Frames 63
04 22 10 Concrete Masonry Units 31 08 09 16 Aluminum Doors, Windows and Frames 63
04 23 Glass Unit Masonry 32 08 09 21 Steel Doors, Windows and Frames 63
04 23 13 Vertical Glass Unit Masonry 32 08 12 Metal Frames 64
04 43 Stone Masonry 33 08 12 21 Steel Frames 64
04 43 10 Stone Masonry 33 08 14 Wood Doors 65
05 METALS 39 08 14 50 Wood Shutters 65
05 05 Common Work Results fo r Metals 41 08 33 Coiling Doors and Grilles 69
05 05 23 Metal Fastenings 41 08 33 23 Overhead Coil ing Doors 69
05 12 Structural Steel Framing 41 08 33 33 Side Coiling Doors 69
05 12 23 Structural Steel for Buildings 41 08 44 Curtain Wall and Glazed Assemblies 69
05 51 Metal Stairs 41 08 44 13 Glazed Aluminum Curtain Walls 69
05 51 16 Metal Floor Plate Stairs 41 08 71 Door Hardware 7105 55 Metal Stair Treads and Nosings 42 08 71 20 Hardware 71
05 55 13 Metal Stair Treads 42 09 FINISHES 77
05 73 Decorative Metal Railings 42 09 21 Plaster and Gypsum Board Assemblies 79
05 73 23 Ornamental Rai lings 42 09 21 13 Plaster Assemblies 79
06 WOOD, PLASTICS, AND COMPOSITES 43 09 22 Supports for Plaster & Gypsum Board 79
06 11 Wood Framing 45 09 22 26 Suspension Systems 79
06 11 10 Wood Framing 45
Unit Price Section - Table of Contents
7/25/2019 Sample Pages Build Cost
3/34
Div. No. Title Page Div. No. Title Page
Unit Price Section - Table of Contents
09 FINISHES 77 22 PLUMBING 115
09 23 Gypsum Plastering 80 22 12 Facility Potable-Water Storage Tanks 126
09 23 20 Gypsum Plaster 80 22 12 23 Facility Indoor Potable-Water Storage Tanks 126
09 24 Portland Cement Plastering 80 22 13 Facility Sanitary Sewerage 127
09 24 20 Portland Cement Plaster 80 22 13 16 Sanitary Waste and Vent Piping 127
09 24 26 Pointing On Walls And Floors 82 22 13 23 Sanitary Waste Interceptors 136
09 28 Backing Boards and Underlayments 83 22 33 Electric Domestic Water Heaters 136
09 28 13 Cementitious Backing Boards 83 22 33 30 Residential, Electric Domestic Water Heaters 136
09 30 TILING 84 22 41 Residential Plumbing Fixtures 136
09 30 10 Precast Pre-polished Tiling 84 22 41 13 Residential Water Closets, Urinals, & Bidets 136
09 30 13 Ceramic Tiling 84 22 41 16 Residential Lavatories and Sinks 139
09 30 23 Glass Mosaic Tiling 85 22 41 19 Residential Bathtubs 141
09 30 35 Terrazo Tiling 86 22 41 39 Residential Faucets, Supplies, and Trim 141
09 51 Acoust ical Ceil ings 86 22 42 Commercial Plumbing Fixtures 143
09 51 23 Acoustical Tile Cei lings86
22 42 13 Commercial Water Closets, Urinals, & Bidets143
09 63 Masonry Flooring87
23 HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)145
09 63 13 Brick Flooring 87 23 07 HVAC Insulation 14709 63 30 Marble Flooring 87 23 07 13 Duct Insulation 147
09 63 35 Granite Flooring 93 23 09 Instrumentation and Control for HVAC 148
09 63 40 Stone Flooring94
23 09 33 Electric and Electronic Control System for HVAC148
09 64 Wood Flooring97
23 09 53 Pneumatic and Electric Control System for HVAC151
09 64 16 Wood Block Flooring 97 23 21 Hydronic Piping and Pumps 151
09 65 Resilient Flooring 98 23 21 20 Hydronic HVAC Piping Specialties 151
09 65 16 Resil ient Sheet Flooring 98 23 21 23 Hydronic Pumps 152
09 66 Terrazzo Flooring 98 23 21 24 Hydronic Piping 159
09 66 13 Portland Cement Terrazzo Flooring 98 23 31 HVAC Ducts and Casings 161
09 91 Painting 100 23 31 13 Metal Ducts 161
09 91 13 Exterior Painting 100 23 33 Air Duc t Accessor ies 161
09 91 23 Interior Painting 101 23 33 11 Air Duct Accessories 161
10 SPECIALTIES 105 23 34 HVAC Fans 161
10 14 Signage 107 23 34 11 Fans 161
10 14 53 Traffic Signage 107 23 41 Particulate Air Filtration 164
10 28 Toilet, Bath, and Laundry Accessories 107 23 41 13 Panel Air Filters 164
10 28 16 Bath Accessories 107 23 52 Heating Boilers 165
10 44 Fire Protection Specialties 109 23 52 13 Electric Boilers 165
10 44 13 Fire Extinguisher Cabinets 109 23 52 23 Cast-Iron Boilers 165
10 44 16 Fire Extinguishers 109 23 64 Packaged Water Chillers 166
21 FIRE SUPPRESSION 111 23 64 10 Packaged Water Chi llers 166
21 12 Fire-Suppression Standp ipes 113 23 64 13 Absorption Water Chillers 168
21 12 13 Fire-Suppression Hoses and Nozzles 113 23 65 Cooling Towers 170
21 13 Fire-Suppression Sprinkler Systems 113 23 65 11 Cooling Towers 170
21 13 13 Wet-Pipe Sprinkler Systems 114 23 73 Indoor Central-Station Air-Handling Units 17122 PLUMBING 115 23 73 13 Modular Indoor Central-Station Air-Handling Unit 171
22 05 Common Work Results for Plumbing 117 23 74 Packaged Outdoor HVAC Equipment 172
22 05 23 General-Duty Valves for Plumbing Piping117
23 74 33 Packaged, Outdoor, Heating and Cooling
Makeup Air-Conditioners172
22 05 76 Facility Drainage Piping Cleanouts 119 23 76 Evaporative Air-Cooling Equipment 172
22 11 Facility Water Distribution 120 23 76 13 Direct Evaporative Air Coolers 172
22 11 13 Facility Water Distribution Piping 120 23 81 Decentralized Unitary HVAC Equipment 173
22 11 19 Domestic Water Piping Specialties 126 23 81 19 Self-Contained Air-Conditioners 173
7/25/2019 Sample Pages Build Cost
4/34
Div. No. Title Page Div. No. Title Page
Unit Price Section - Table of Contents
23 HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)145
32 EXTERIOR IMPROVEMENTS249
23 81 Decentralized Unitary HVAC Equipment 173 32 11 Base Courses 251
23 81 26 Split-System Air-Conditioners 173 32 11 23 Aggregate Base Courses 251
23 82 Convection Heating and Cooling Units 174 32 11 26 Asphalt ic Base Courses 251
23 82 16 Air Coils 174 32 12 Flexible Paving 252
23 82 19 Fan Coil Units 175 32 12 16 Asphalt Paving 252
26 ELECTRICAL 177 32 13 Rigid Paving 253
26 05 Common Work Results for Electrical 179 32 13 13 Concrete Paving 253
26 05 13 Medium -Voltage Cables 179 32 14 Unit Paving 253
26 05 19 Low-Voltage Electrical Power Conductors and
Cables185
32 14 13 Precast Concrete Unit Paving253
26 05 26 Grounding & Bonding for Electrical Systems193
32 16 Curbs, Gutters, Sidewalks, And Driveways254
26 05 29 Hangers & Supports for Electrical Systems 194 32 16 13 Curbs And Gutters 254
26 05 33 Raceway and Boxes for Electrical Systems 194 32 31 Fences and Gates 254
26 05 36 Cable Trays for Electrical Systems 196 32 31 13 Chain Link Fences and Gates 254
26 05 90 Residential Wiring 199 33 UTILITIES 257
26 24 Switchboards and Panelboards 219 33 11 Water Utility Distribution Piping 25926 24 13 Switchboards 219 33 11 13 Public Water Utility Distribution Piping 259
26 27 Low-Voltage Distribution Equipment 220 33 36 Utility Septic Tanks 268
26 27 26 Wiring Devices 220 33 36 13 Utility Septic Tank and Effluent Wet Wells 268
26 28 Low-Voltage Circuit Protecti ve Devices 223 33 41 Storm Utility Drainage Piping 269
26 28 16 Enclosed Switches and Circuit Breakers 223 33 41 13 Public Storm Utility Drainage Piping 269
26 41 Facility Lightning Protection 230 33 44 Storm Utilit y Water Drains 271
26 41 13 Lightning Protection for Structures 230 33 44 13 Utility Area Drains 271
26 51 Interior Ligh ting 230
26 51 13 Interior Lighting Fixtures, Lamps, & Ballasts 230
27 COMMUNICATIONS 233
27 15 Communications Horizontal Cabling 235
27 15 10 Special Communications Cabling 235
28ELECTRONIC SAFETY AND SECURITY 23728 31 Fire Detection and Alarm 239
28 31 23 Fire Detection and Alarm Annunciation Panels
and Fire Stations239
31 EARTHWORK 241
31 11 Clearing and Grubbing 243
31 11 10 Clearing and Grubbing 243
31 14 Earth Stripping and Stockpiling 243
31 14 13 Soil Stripping and Stockpiling 243
31 22 Grading 243
31 22 16 Fine Grading 243
31 23 Excavation and Fill 243
31 23 16 Excavation 243
31 23 19 Dewatering 245
31 23 23 Fill 245
31 31 Soil Treatment 246
31 31 16 Termite Control 246
31 50 EXCAVATION SUPPORT and
PROTECTION246
31 50 13 Excavation Support And Protection 246
31 62 Driven Piles 247
31 62 13 Concrete Piles 247
31 63 Bored Piles 247
31 63 23 Bored Concrete Piles 247
7/25/2019 Sample Pages Build Cost
5/34
BuildCOST GENERAL REQUIREMENTS
45 Quality Control01
23 Testing And Inspecting Services UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
4501TOTAL
Pile Test21
Vertical load testing ( INITIAL ) of piles in
accordance with IS 2911 (Part IV) including
installation of loading platform / or reaction pilesand preparation of pile head or construction of
est cap and dismantling of test cap after test
etc. to 150% of designed load, complete, of pile
capacities :
10005 /testupto 50 ton 36,000.00 - - 36,000.00 41,400.0
10010 /testabove 50 ton and upto 100 ton 73,125.00 - - 73,125.00 84,093.7
10015 /test/50 tadd for every additional 50 ton or part thereof 36,000.00 - - 36,000.00 41,400.0
Vertical load testing ( ROUTINE ) of piles in
accordance with IS 2911 (Part IV) including
installation of loading platform / or reaction piles
and preparation of pile head or construction of
est cap and dismantling of test cap after test
etc. to 150% of designed load, complete, of pile
capacities :
10020 /testUpto 50 ton 36,000.00 - - 36,000.00 41,400.0
10025 /testabove 50 ton and upto 100 ton 73,125.00 - - 73,125.00 84,093.7
10030 /test/50 tadd for every additional 50 ton or part thereof 29,812.50 - - 29,812.50 34,284.3
Cyclic vertical load testing of pile in accordance
with IS:2911 (part IV) including preparation of pile
head etc., to 150% of designed load, complete,
of pile capacities :
10035 /testupto 50 ton 36,000.00 - - 36,000.00 41,400.0
10040 /testabove 50 t and upto 100 ton 73,125.00 - - 73,125.00 84,093.7
10045 /test/50 tadd for every additional 50 ton or part thereof 36,000.00 - - 36,000.00 41,400.0
Lateral load testing of single pile in accordance
with IS:2911 (Part IV) to 150% of designed load,
complete, of pile capacities :
10050 /testupto 50 ton 36,000.00 - - 36,000.00 41,400.0
10055 /testAbove 50 ton and upto 100 ton 63,562.50 - - 63,562.50 73,096.8
10060 /test/50 tAdd for every additional 50 ton or part
hereof.
36,000.00 - - 36,000.00 41,400.0
Vertical load testing ( INITIAL ) of piles in
accordance with IS 2911 (Part IV) including
installation of loading plateform / or reaction piles
and preparation of pile head or construction of
est cap and dismantling of test cap after test
etc. to 250% of designed load complete, of pile
capacities :
10065 /testupto 50 ton 36,000.00 - - 36,000.00 41,400.0
10070 /testabove 50 ton and upto 100 ton 73,125.00 - - 73,125.00 84,093.7
10075 /test/50 tadd for every additional 50 ton or part thereof 36,000.00 - - 36,000.00 41,400.0
Vertical load testing ( ROUTINE ) of piles in
accordance with IS 2911 (Part IV) including
installation of loading plateform / or reaction piles
and preparation of pile head or construction ofest cap and dismantling of test cap after test
etc. to 250% of designed load, complete, of pile
capacities :
10080 /testupto 50 ton 36,000.00 - - 36,000.00 41,400.0
10085 /testabove 50 ton and upto 100 ton 59,062.50 - - 59,062.50 67,921.8
10090 /test/50 tadd for every additional 50 ton or part thereof 36,000.00 - - 36,000.00 41,400.0
Testing50
Conducting laboratory tests at approved
laboratory, including preparation and taking of
samples to laboratory, testing of samples and
getting and submitting test results :
3
7/25/2019 Sample Pages Build Cost
6/34
BuildCOST GENERAL REQUIREMENTS
45 Quality Control01
23 Testing And Inspecting Services UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
4501TOTAL
10005 /testCompressive strength test on rock samples 3,150.00 - - 3,150.00 3,622.5
10010 /testChemical analysis of soil samples 2,812.50 - - 2,812.50 3,234.3
10015 /testChemical analysis of water samples 2,812.50 - - 2,812.50 3,234.3
4
7/25/2019 Sample Pages Build Cost
7/34
BuildCOST EXISTING CONDITIONS
32 Geotechnical Investigations02
19 Exploratory Excavations UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
3202TOTAL
Test Pit17
Drilling 150 mm diameter bore holes in all type of
soils by manual auguring, conducting standard
penetration tests, collecting disturbed andundisturbed soil samples, conducting necessary
laboratory tests, recommending suitable type of
foundation and allowable bearing pressure and
submission of report in three copies :
10005 mGround level to 6.0 m or refusal,
whichever is earlier
393.75 - - 393.75 452.8
10010 mOver 6.0 m and upto 10.0 m or refusal,
whichever is earlier
427.50 - - 427.50 491.6
10015 mOver 10.0 m and upto 12.0 m or refusal,
whichever is earlier
506.25 - - 506.25 582.1
Drilling 150 mm diameter bore holes in all type of
soils by Calyx drilling, conducting standard
penetration tests, collecting disturbed and
undisturbed soil samples, conducting necessary
laboratory tests, recommending suitable type of
foundation and allowable bearing pressure andsubmission of report in three copies :
10020 mGround level to 6.0 m or refusal, which is
earlier
900.00 - - 900.00 1,035.0
10025 mOver 6.0 m and upto 10.0 m or refusal,
which is earlier
956.25 - - 956.25 1,099.6
10030 mOver 10.0 m and upto 12.0 m or refusal,
which is earlier
1,012.50 - - 1,012.50 1,164.3
Drilling 100 mm dia bore hole in rock using
double core barrel Diamond/TC including
recovery of cores, wherever possible and
keeping a log of the same :
10035 mWeathered / disintegrated rock 2,025.00 - - 2,025.00 2,328.7
10040 mHard rock 4,725.00 - - 4,725.00 5,433.7
41 Demolition0213 Selective Site Demolition UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
4102TOTAL
Concrete / Rcc / Masonry Demolition21
10005 cumDemolishing lime concrete / cement
concrete in all mixes, in foundations, super
structure and basement, at all heights /
depths, including disposal of unserviceable
materials upto a 50 m lead.
- 203.25 - 203.25 233.7
10010 cumDemolishing RCC work in foundations, super
structure and basement, at all heights /
depths, including cutting, straightening
scrapping, cleaning and stacking of
reinforcement bars and disposal of
unserviceable materials upto a 50 m lead.
- 833.33 - 833.33 958.3
10015 cumDemolishing RB work in foundations, super
structure and basement, at all heights /
depths, including cutting, straightening
scrapping, cleaning and stacking of
reinforcement bars and disposal of
unserviceable materials upto a 50 m lead.
- 757.58 - 757.58 871.2
10020 cumDismantling / Demolishing brick work in
cement / lime mortar in foundations, super
structure and basement, at all heights /
depths, including removing of mortar,
cleaning bricks and stacking of serviceable
materials and disposed of unserviceable
materials upto 50 m lead
- 925.93 - 925.93 1,064.8
7
7/25/2019 Sample Pages Build Cost
8/34
BuildCOST EXISTING CONDITIONS
41 Demolition02
13 Selective Site Demolition UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
4102TOTAL
10025 cumDismantling / demolishing stone rubble
masonry in cement / lime mortar in
foundations, super structure and basement
at all heights / depths including stacking ofserviceable materials and disposal of
unserviceable materials upto a 50 m lead.
- 581.40 - 581.40 668.6
Ceiling Demolition22
Dismantling false ceiling, partitions, wall lining,
etc supported / fixed to wooden / aluminium /
metal frame including dismantling of frame,
stacking of serviceable material and disposal of
unserviceable material upto a 50 m lead, with :
10005 sqmPlaster of Paris /Gypsum / Plywood / Block
board / Particle board / MDF sheets / tiles
- 38.53 - 38.53 44.3
10010 sqmWooden planks - 57.80 - 57.80 66.4
10015 sqmGlass / Mirror / Fabric / Extruded metal - 77.21 - 77.21 88.7
10020 sqmAsbestos cement, celotax or other hard
board
- 38.53 - 38.53 44.3
Flooring Demolition24Dismantling tile work in floors and roofs in
cement mortar/lime mortar including stacking of
serviceable material and disposal of
unserviceable material upto a lead of 50 m, of
hickness :
10005 sqm10 mm to 25 mm - 19.14 - 19.14 22.0
10010 sqmover 25 mm and upto 40 mm - 29.29 - 29.29 33.6
10015 sqmDismantling dry brick pitching in floors,
drains etc, including stacking of serviceable
materials and disposal of unserviceable
materials within a 50 m lead.
- 35.98 - 35.98 41.3
10020 sqmDismantling stone slab flooring in cement
mortar / lime mortar, including stacking of
serviceable materials and disposal of
unserviceable materials within a 50 m lead.
- 62.98 - 62.98 72.4
Demolition of flooring including stacking ofserviceable materials and disposal of
unserviceable materials upto a 50m lead, with :
10025 sqmParquet flooring - 22.00 - 22.00 25.3
10030 sqmPVC flooring - 5.00 - 5.00 5.7
10035 sqmCarpet flooring - 5.00 - 5.00 5.7
Framing Demolition25
Dismantling woodwork in frames, trusses, purlins
and rafters upto a 10 metres span and 5 metres
height including stacking the material within a 50
m lead, of sectional areas :
10005 mupto 4000 sqmm - 4.80 - 4.80 5.5
10010 cumover 4000 sqmm - 1,200.00 - 1,200.00 1,380.0
10015 QuintalDismantling steel work in built up sections at
all heights and depths, in angles, tees, flats,channels and tubes including all gusset
plates, bolts, nuts, cutting rivets, welding
etc. including dismembering and stacking
within 50 m lead.
- 145.00 - 145.00 166.7
10020 QuintalDismantling steel work in single sections at
al l heights and depths including
dismembering and stacking within a 50 m
lead.
- 87.00 - 87.00 100.0
Lining Dismantling26
Dismantling and removing wooden boardings in
lining of walls and partitions, excluding
supporting members, but including stacking
8
7/25/2019 Sample Pages Build Cost
9/34
BuildCOST CONCRETE
05 Common Work Results For Concrete03
13 Basic Concrete Materials UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
0503TOTAL
Admixture, Concrete20
Providing and mixing admixtures, conforming to
IS:9103, in recommended proportions, in
concrete :10005 kgAccelerating admixtures 43.85 5.00 - 48.85 56.1
10010 kgRetarding admixtures 46.54 5.00 - 51.54 59.2
10015 kgAir entraining admixture 43.18 5.00 - 48.18 55.4
10020 kga t e r r e d u c i n g a d m i x t u r e s
(Plasticizer/Super Plasticizer)
64.08 5.00 - 69.08 79.4
Concrete Additives21
10005 kgProviding and mixing water proofing
compound, conforming to IS:2645, in cement
concrete/reinforced concrete works.
60.45 5.00 - 65.45 75.2
11 Concrete Forming03
13 Structural Cast-in-place Concrete
Forming
UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1103
TOTAL
Forms In Place18
Providing and fixing centering and shuttering for
concrete work (plain and reinforced) in following
locations, including strutting, propping, bracing,
bolting tie bolt / spring coil / plastic cone,
wedging, easing, striking, removal etc, complete.
Allow for forming grooves, drips, throats,
chamfers, cut-outs, openings etc. where called
for and for dressing with approved shuttering oil
o prevent adhesion. The works are at all levels .
The floor height is up to 4.00 m :
10005 sqmSides of footings of columns and walls and
sides of base slabs.
68.20 63.00 - 131.20 150.8
10010 sqmFoundation beams, floor channels, kerb
stones and drain walls.
68.20 63.00 - 131.20 150.8
10015 sqmSides of columns, piers and pedestals of any
shape, size and profile.
82.92 199.98 - 282.90 325.3
10020 sqmSides of walls, retaining walls, attached
columns, pilasters.
66.93 180.72 - 247.65 284.7
10025 sqmSoffits and sides of beams, plinth beams,
lintels, ties, ribs, pergolas and such other,
string courses, cornices, corbels.
70.41 144.00 - 214.41 246.5
10030 sqmSides of facias, parapets, railings, planting
boxes and such other vertical elements.
63.50 252.09 - 315.59 362.9
10035 sqmSoffits and sides of suspended slabs, floor
and roof projections, landing slabs,
canopies, chajjas, slabs of planting boxes
and such other horizontal elements, coffer
ribs and slabs.
70.12 199.98 - 270.10 310.6
10040 sqmSoffits and sides of waist slabs of stairs,
sides of risers and stepped waist slabs,spiral staircases, etc.
54.26 218.97 - 273.23 314.2
10045 sqmSides of mullions, suspenders, struts, ties,
slings including flarings or taperings of any
shape and profile.
74.07 413.82 - 487.89 561.0
10050 sqmSoffits of inclined slabs and ramps, folded
plates. ( slopes more than 15o and upto 45o)
72.24 252.09 - 324.33 372.9
10055 sqmArches, archribs, domes, shells, vaults, etc. 321.38 437.90 - 759.27 873.1
10060 sqmWell Steinings 68.61 968.34 - 1,036.95 1,192.4
10065 sqmVertical and horizontal fins individually or
forming boxes
63.50 252.09 - 315.59 362.9
10070 sqmChimney shafts 66.93 180.72 - 247.65 284.7
13
7/25/2019 Sample Pages Build Cost
10/34
BuildCOST MASONRY
21 Clay Unit Masonry04
13 Brick Masonry UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
2104TOTAL
Brick Work, Conventional Bricks46
Providing brick work with bricks of class 75,
oints finished flush/raked to 12 mm depth, cured
including necessary scaffolding complete incement mortar 1:6 with coarse sand, in :
10005 cumFoundations and plinths (1.5 m below and
upto 1.2 m above GL)
2,629.27 699.25 22.50 3,351.02 3,853.6
10010 cumSuperstructures upto 20.0 m above plinth
level.
2,629.27 1,339.85 70.20 4,039.32 4,645.2
10015 cumBasement, under ground water tank and the
like, upto 7.0 m below GL
2,629.27 983.53 38.18 3,650.98 4,198.6
10020 cumArches, vaults, domes, etc., in super
structures/basements and the like in cement
mortar 1:3 with coarse sand including
centering, shuttering, struting, proping,
wedging, bolting and removal, etc.,
complete.
3,713.71 2,037.04 58.32 5,809.07 6,680.4
10025 cumAdd for every additional 4.0 m height or part
hereof for brick work/exposed brick work
beyond 7.0 m below GL
- 187.98 - 187.98 216.1
10030 cumAdd for every additional 20.0 m height or
part thereof for brick work/exposed brick
work beyond 20.0 m above plinth level
- 373.13 - 373.13 429.0
10035 cumAdd for brick work in cement mortar 1:4 in
place of 1:6
182.00 - - 182.00 209.3
10040 cumAdd for brick work in cement mortar 1:3 in
place of 1:6
364.00 - - 364.00 418.6
10045 cumDeduct for brick work in cement mortar with
fine sand in place of coarse sand
99.33 - - 99.33 114.2
10050 cumAdd for brick work/exposed brick work in
square or rectangular pillars
- 256.75 - 256.75 295.2
10055 cumAdd for brick work, curved in plan/elevation,
upto mean radius not exceeding 6.0 m
144.18 223.70 - 367.88 423.0
10060 mAdd for cutting or chamfering the bricks to
required shape in masonry work
- 10.45 - 10.45 12.0
10065 cumDeduct for using bricks of class 50 in place
of class 75
172.28 - - 172.28 198.1
10070 mProviding 70 mm thick and 57 mm projected
string course/ band with bricks of class 75 in
cement mortar 1:4 with coarse sand
11.36 6.59 0.29 18.24 20.9
10075 00 mm/mProviding and making mouldings, cornices &
corbels with bricks of class 75 in cement
mortar 1:4 with coarse sand (girth to be
measured in mm and length in running
metres)
10.56 7.41 0.28 18.25 20.9
Providing brick work with bricks of class 75 in
half brick thick walls in any shape and profile
including curvilinear, laid in cement mortar 1:4
with coarse sand, joints finished flush/raked to 12
mm depth, cured, including scaffolding and flat
reinforcement (25 x 3 mm) at every fourth course
and embedding the same in adjoining
masonry/columns by drilling holes etc complete :
10080 sqmSuper structure upto 20.0 m above plinth
level.
397.39 158.23 5.04 560.65 644.7
10085 sqmBasements, and the like, upto 7.0 m below
GL
397.39 129.39 5.58 532.35 612.2
10090 sqmArches, domes, vaults at all levels in cement
mortar 1:3 with coarse sand including
centring and shuttering strutting, propping,
bolting and removal complete. (Flat iron
reinforcement 25 x 3 mm not to be provided)
653.54 607.37 5.58 1,266.48 1,456.4
10095 sqmAdd for every 4.0 m height or part thereof for - 21.55 - 21.55 24.7
27
7/25/2019 Sample Pages Build Cost
11/34
BuildCOST METALS
05 Common Work Results For Metals05
23 Metal Fastenings UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
0505TOTAL
Bolts & Hex Nuts10
10005 kgProviding and fixing MS bolts upto 300 mm
in length including nuts and washers,
complete.
47.72 22.80 - 70.52 81.1
Welding88
10005 10 mm/mGas welding including mobilization at site,
complete, (for designed structural welding).
236.00 - - 236.00 271.4
10010 10 mmGas welding including mobilization at site,
complete, (for non structural welding).
3.00 - - 3.00 3.4
10015 10 mm/mElectric arc welding including mobilization at
site, complete (for designed structural
welding).
178.00 - - 178.00 204.7
10020 10 mmElectric arc welding including mobilization at
site, complete (for non structural welding).
2.50 - - 2.50 2.8
12 Structural Steel Framing05
23 Structural Steel For Buildings UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1205TOTAL
Structural Steel Built Up Section23
Providing, fabricating and erecting built up steel
ubular trusses, welded and bolted including
special shaped washers, etc. and applying a
primer coat of zinc chromate on duly prepared
surfaces, complete :
10005 kgHot finished, welded tubes 85.74 19.19 - 104.92 120.6
10010 kgHot finished, seamless tubes 110.23 19.19 - 129.42 148.8
10015 kgElectric resistance or induction welded tubes 102.44 19.19 - 121.62 139.8
10020 kgProviding, fabricating and erecting bolted
structural steel built up sections, trusses and
frames and applying a primer coat of zinc
chromate on duly prepared surfaces,
complete.
51.29 13.49 - 64.77 74.4
10025 kgProviding, fabricating and erecting welded
structural steel built up sections in trusses
and frames and applying a primer coat of
zinc chromate on duly prepared surfaces,
complete.
53.73 9.10 - 62.83 72.2
10030 sqmProviding and applying three finish coats of
synthetic enamel paint on steel surfaces,
complete.
2,457.53 47.45 - 2,504.98 2,880.7
Structural Steel Single Section81
10005 kgProviding, fabricating and erecting structural
steel, single sections, and applying a primer
coat of zinc chromate on duly prepared
surfaces, complete.
58.16 7.57 - 65.73 75.5
10010 kgProviding and fixing wind ties of MS section 48.78 6.50 - 55.28 63.5
51 Metal Stairs05
16 Metal Floor Plate Stairs UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
5105TOTAL
Steel Stairs13
Providing, fabricating and erecting MS welded
built up sections/ frames and applying a primer
coat of zinc chromate on duly prepared surfaces,
complete :
10005 kgIn stringers, treads, landings, etc. of
staircases including chequered plates
wherever required, all complete.
69.92 3.83 - 73.75 84.8
41
7/25/2019 Sample Pages Build Cost
12/34
BuildCOST METALS
51 Metal Stairs05
16 Metal Floor Plate Stairs UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
5105TOTAL
10010 kgIn guard bars, ladders, railings, and similar
works.
55.14 22.47 - 77.61 89.2
Providing, fabricating and erecting hand rails by
welding to steel ladders/railings, balcony railings,and staircase railings including primer coat of
zinc chromate on duly prepared surfaces,
complete :
10015 kgMS black tubes 190.77 20.09 - 210.86 242.4
10020 kgERW tubes 207.48 20.09 - 227.56 261.7
10025 kgGalvanised steel pipes 183.33 20.09 - 203.42 233.9
10030 kgStructural steel sections, flats, angles,
channels, etc.
68.45 18.90 - 87.35 100.4
55 Metal Stair Treads And Nosings05
13 Metal Stair Treads UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
5505TOTAL
Stair Treads And Nosing51
10005 kgProviding and fixing MS angles 50 x 50 x 5
mm nosing with lugs of MS flats 10 x 5 mm,
100 mm long and forked at ends, 600 mm
apart (minimum three lugs to be provided)
including necessary welding and applying a
primer coat on exposed surfaces etc.,
complete.
63.52 16.67 - 80.19 92.2
10010 kgProviding and fixing aluminium angles 35 x
35 x 3 mm nosing with lugs of flats 10 x 3
mm, 100 mm long and forked at ends, 600
mm apart (minimum three lugs to be
provided) including necessary welding, etc.,
complete.
307.08 111.83 - 418.91 481.7
Providing and fixing aluminum strip edge to
staircases including fixing with rawl plugs and
stainless steel screws, with under layer of
cement mortar 1:3 with coarse sand, of stripedging of size :
10015 m57 x 12 x 3 mm 186.09 64.48 - 250.57 250.5
10020 m38 x 12 x 3 mm 174.96 64.48 - 239.43 275.3
73 Decorative Metal Railings05
23 Ornamental Railings UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
7305TOTAL
Railings, Ornamental50
Providing, fabricating and erecting MS balusters
in stair flight slabs, landing balconies and similar
other railings, anchored to steps, landings etc.,
all fixing accessories including providing pockets
in concrete/brick works and grouting with ironite
or other equivalent, applying three coats of
synthetic enamel paint over a primer coat of zinc
chromate on duly prepared surfaces, complete.
10005 kgSolid sections 172.73 66.45 - 239.18 275.0
10010 kgHollow sections 178.03 66.45 - 244.48 281.1
42
7/25/2019 Sample Pages Build Cost
13/34
BuildCOST WOOD, PLASTICS, AND COMPOSITES
11 Wood Framing06
10 Wood Framing UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
1106TOTAL
Ceiling Framing12
Providing, fabricating and fixing in position
selected quality seasoned and chemically treat
ed wood work in frames of false ceilings,partitions, etc., complete :
10005 cumIst class Deodar wood. 47,709.24 3,750.00 - 51,459.24 59,178.1
10010 cum2nd class Deodar wood. 46,516.19 3,750.00 - 50,266.19 57,806.1
10015 cumSal wood 27,546.49 3,750.00 - 31,296.49 35,990.9
10020 cum2nd class Kail wood 20,984.64 3,750.00 - 24,734.64 28,444.8
10025 cumHollock wood 29,336.09 3,750.00 - 33,086.09 38,049.0
Wall Framing40
Providing and fixing wooden frame with 50 mm x
50 mm battens, fixed at 600 mm centre to centre
(both ways). Allow for solignum treatment to the
imber framework :
10005 sqmSal wood 327.58 121.74 - 449.32 516.7
10010 sqm2nd class CP teak Wood 609.93 121.74 - 731.67 841.4
Providing and fixing wooden framework with 50mm x 75 mm battens, fixed at 600 mm centre to
centre(both ways). Allow for solignum treatment
o the timber framework :
10015 sqmSal wood 455.49 177.17 - 632.66 727.5
10020 sqm2nd class CP Teak Wood 879.03 177.17 - 1,056.19 1,214.6
17 Shop-fabricated Structural Wood06
53 Shop-fabricated Wood Trusses UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
1706TOTAL
Roof Trusses10
Providing, fabricating and fixing in position
selected quality seasoned & chemically treated
wrought wood work in trusses, rafters, runners
posts, struts, walls plates etc. of size and profile
in inclind roofs including anchoring to concrete
members with holding down bolts, fixing
accessories & all incidental works (Flat, angles,
other steel sections and holding down bolts used
in connections will be paid separately), complete
:
10005 cum2nd class CP teak wood 59,339.52 5,172.45 - 64,511.97 74,188.7
10010 cumIst class Deodar wood 44,620.53 5,172.45 - 49,792.98 57,261.9
10015 cum2nd class Deodar wood 43,229.76 5,172.45 - 48,402.21 55,662.5
10020 cumSal wood 26,424.63 5,172.45 - 31,597.08 36,336.6
10025 cumHollock wood 27,235.92 5,172.45 - 32,408.37 37,269.6
22 Millwork06
13 Standard Pattern Wood Trim UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
2206TOTAL
Mouldings12
Providing and fixing select quality seasoned and
chemically treated wooden moulded beadings to
door and window frames with mild steel
screws/headless nails and a primer coat on
unexposed surface, etc. complete, of beading
sizes :
Burma teak wood :
10005 m30 x 12 mm 33.10 43.70 - 76.80 88.3
45
7/25/2019 Sample Pages Build Cost
14/34
BuildCOST WOOD, PLASTICS, AND COMPOSITES
22 Millwork06
13 Standard Pattern Wood Trim UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
2206TOTAL
10010 m40 x 12 mm 46.04 43.70 - 89.74 103.2
10015 m40 x 20 mm 73.07 43.70 - 116.77 134.2
10020 m50 x 12 mm 56.29 43.70 - 99.99 114.9
10025 m50 x 20 mm 89.97 43.70 - 133.67 153.7
2nd class CP teak wood :
10030 m30 x 12 mm 26.60 43.70 - 70.30 80.8
10035 m40 x 12 mm 36.50 43.70 - 80.20 92.2
10040 m40 x 20 mm 57.17 43.70 - 100.87 116.0
10045 m50 x 12 mm 44.37 43.70 - 88.07 101.2
10050 m50 x 20 mm 79.94 43.70 - 123.64 142.1
Ghana teak wood :
10055 m30 x 12 mm 23.36 43.70 - 67.06 77.1
10060 m40 x 12 mm 31.76 43.70 - 75.46 86.7
10065 m40 x 20 mm 57.96 43.70 - 101.66 116.9
10070 m50 x 12 mm 38.45 43.70 - 82.15 94.4
10075 m50 x 20 mm 60.22 43.70 - 103.92 119.5
2nd class Deodar wood :
10080 m30 x 12 mm 21.48 43.70 - 65.18 74.9
10085 m40 x 12 mm 35.95 43.70 - 79.65 91.5
10090 m40 x 20 mm 44.62 43.70 - 88.32 101.5
10095 m50 x 12 mm 35.75 43.70 - 79.45 91.3
10100 m50 x 20 mm 64.32 43.70 - 108.02 124.2
Rubber wood :
10105 m30 x 12 mm 15.39 43.70 - 59.09 67.9
10110 m40 x 12 mm 20.06 43.70 - 63.76 73.3
10115 m40 x 20 mm 29.77 43.70 - 73.47 84.4
10120 m50 x 12 mm 23.82 43.70 - 67.52 77.6
10125 m50 x 20 mm 35.85 43.70 - 79.55 91.4
26 Board Paneling06
13 Profile Board Paneling UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
2606TOTAL
Paneling, Boards10
Providing and fixing in wall lining flat pressed
hree layer & graded (medium density) particle
boards, prelaminated, one side decorative
lamination and on other side balancing
lamination, grade I, Type II, conforming to
IS:12823, with necessary fixing arrangements
and screws etc. complete, of thicknesses :
10005 sqm12 mm 1,788.85 96.33 - 1,885.18 2,167.9
10010 sqm18 mm 2,294.13 96.33 - 2,390.46 2,749.0
Pre-finished Paneling1110005 sqmProviding and fixing 9 mm thick laminated
wall panelling made of melamine
impregnated MDF board having tonge and
groove jointing system, complete with
accessories like wall base skirting and other
profiles complete.
2,166.69 141.59 1.80 2,310.08 2,656.5
42 Wood Paneling06
10 Wood Paneling UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
4206TOTAL
46
7/25/2019 Sample Pages Build Cost
15/34
BuildCOST THERMAL AND MOISTURE PROTECTION
11 Dampproofing07
17 Damp-proof Course UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
1107TOTAL
Damp-proof Course10
Providing and laying damp-proof course with
cement concrete 1:2:4 with graded stone
aggregate 12.5 mm nominal size, including sideshuttering, compacting etc., complete.
10005 sqm40 mm thick 155.50 78.62 9.90 244.02 280.6
10010 sqm50 mm thick 192.82 87.08 10.98 290.88 334.5
10015 kg/50kgProviding and mixing waterproofing material
in cement concrete work @ 1.0 kg per 50 kg
bag of cement used in the mix.
60.45 5.00 - 65.45 75.2
10020 sqmApplying a cost of residual petroleium
bitumen of penetration 80/100 @ 1.70 kg/sq.
on damp-proof course.
67.35 12.68 - 80.02 92.0
13 Sheet Waterproofing07
13 Bituminous Sheet Waterproofing UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
1307TOTAL
Built-Up Sheet Waterproofing13Providing and laying vapour barrier of low density
polythene film (700 microns), laid in blown grade
bitumen at 1 kg. per. sqm, over a coat of primer
at 400 gms per sqm and finished with a coat of
bitumen at 1 kg per sqm as per specifications,
complete :
10005 sqmOver RCC roof surfaces. 312.92 19.50 - 332.42 382.2
10010 sqmOn external wall surfaces. 312.92 22.75 - 335.67 386.0
Providing and laying vapour barrier of aluminium
foil 0.075 mm thick, laid in blown grade bitumen
at 2 kg per sqm over a coat of primer at 400 gms
per sqm and finished with a coat of bitumen at 1
kg per sqm as per specifications, complete :
10015 sqmOver RCC roof surfaces 379.67 26.00 - 405.67 466.5
10020 sqmOn external wall surfaces 379.67 26.00 - 405.67 466.5
10025 sqmAdd for aluminum foil of thickness 0.1 mm
instead of 0.075 mm
25.84 - - 25.84 29.7
10030 sqmPainting top of roof surface with 80 / 100
penetration bitumen @ 1.7 kg per sqm
impregnated with coarse sand, 6 mm thick,
including cleaning of slab surface with brush
and finally with a cloth soaked in kerosene
oil.
73.95 24.70 - 98.65 113.4
10035 sqmProviding and laying damp-proofing
reatment comprising a primer coat, one
layer of aluminium foil 0.1 mm thick and two
layers of bitumen at the rate of 2 kg per sqm
per layer to ground floor/paving, complete.
487.08 26.00 - 513.08 590.0
10040 sqmProviding and laying waterproofing treatment
o roof slabs comprising of Primer coat, one
layer of fibre glass RP tissue, one layer ofaluminium foil 0.10 mm thickness, three
layers of bitumen at the rate of 2 Kg per sqm
per layer, sealing of edges and corners as
called for, complete.
683.90 39.00 - 722.90 831.3
10045 sqmProviding and laying damp-proofing
reatment comprising a primer coat, one
layer of fibre-glass RP tissue and two layers
of bitumen at the rate 2 kg per sqm per layer
in toilets and other areas including side and
end laps, etc., complete.
406.26 39.00 - 445.26 512.0
10050 sqmAdd for additional layer of aluminium foil,
(0.10 mm thick) and additional layer of
276.58 13.00 - 289.58 333.0
51
7/25/2019 Sample Pages Build Cost
16/34
BuildCOST THERMAL AND MOISTURE PROTECTION
13 Sheet Waterproofing07
13 Bituminous Sheet Waterproofing UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
1307TOTAL
bitumen at the rate of 2 kg per sqm in roof
surface treatment.
10055 sqmProviding and laying at roof ridges and other
locations, where called for, waterproofingreatment consisting of one layer of blown
grade bitumen at 1 kg per sqm followed by
one layer of fibreglass tissue laid and
finished with one layer of bitumen at 1 kg per
sqm.
237.68 26.00 - 263.68 303.2
10060 sqmAdd for finishing the waterproofing treatment
with 6 mm pea-size gravel at the rate of 1
cum per 100 sqm (bitumen layer for laying
gravel included in waterproofing item).
6.68 1.70 - 8.38 9.6
10065 sqmAdd for providing polymeric polythene felt
membrane instead of fibre-glass RP tissue.
49.62 - - 49.62 57.0
10070 sqmDeduct for providing hessian based self
finish bitumen felt instead of fibre-glass RP
issue.
-105.06 - - -105.06 -120.8
10075 sqmAdd for every additional coat of blown /
residual bitumen applied hot @ 2 kg persqm.
171.29 13.00 - 184.29 211.9
10080 sqmAdd for every additional layer of fibre-glass
RP tissue and bitumen @ 2 kg per sqm.
196.28 19.50 - 215.78 248.1
16 Cementitious And Reactive Waterproofing07
16 Crystalline Waterproofing UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
1607TOTAL
Cementitious Waterproofing20
10005 sqmBrick bat coba waterproofing treatment to
erraces, terrace gardens, roof surfaces and
such other locations where called for, by
providing an even base layer of minimum 20
mm thick cement mortar 1:4 with coarse
sand admixed with acrylic waterproofingcompound, brick bats of size ranging from
40 mm to 100 mm, laid with gaps of 10 to 15
mm between them and grouted with cement
mortar 1:4 with coarse sand and admixed
with acrylic waterproofing compound, laid to
slope of 1:120 or as specified and a
protective coat of 20 mm thick cement
mortar 1:4 with coarse sand admixed with
acrylic waterproofing compound, fixing of
rough Kotah stone of 18-20 mm thickness
over a bed of cement mortar 1:4 with coarse
sand admixed with acrylic waterproofing
compound and joints grouted to full depth of
stone with cement slurry admixed with
acrylic waterproofing compound. Kotah
stone shall be fixed within 48 hours of
completing and laying the protective coat tobrick coba treatment. Treatment to vertical
faces of parapets, walls, beams, etc. will
comprise 20 mm thick cement plaster 1:4
with coarse sand admixed with acrylic
waterproofing compound and finished neet
upto a height of 300 mm (only horizontal
reatment area shall be measured for
payment). The average thickness, excluding
he Kotah stone and its bedding mortar, shall
be 120 mm. The minimum thickness at
khurra, excluding the Kotah stone and its
bedding mortar, shall be 80 mm.
921.23 684.79 11.70 1,617.71 1,860.3
52
7/25/2019 Sample Pages Build Cost
17/34
BuildCOST OPENINGS
09 Metal Doors, Windows And Frames08
16 Aluminum Doors, Windows And
Frames
UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
0908TOTAL
Aluminum Doors, Windows And
Frames
10
Providing, fabricating and fixing aluminium doors,windows and ventilators with sections (IS 733
and IS 1825), 60 microns pure polyster coated,
25 microns colour nutred anodised (IS 1868), of
grade AC 25, fixed with rawl plugs and screws /
fixing clips / expansion hold fasteners and filling
gaps with PVC / Neoprene felt along with
aluminium snap beadings, CP brass/stainless
steel screws for glazing / panelling complete
(cost of glazing / panelling not included)
(payment will be made for weight of aluminium
used in the work).
10005 kgFixed portion 343.31 15.00 - 358.31 412.0
10010 kgShutters of doors, windows and ventilators
including providing and fixing hinges/pivots
and making provision for fixing of fittings
including PVC/neoprene gasket, complete(cost of fitting not included).
362.21 20.00 - 382.21 439.5
21 Steel Doors, Windows And Frames UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
0908TOTAL
Steel Doors, Windows And Frames10
Providing and fixing MS glazed doors, windows
and ventilators of standard heavy rolled steel
sections, conforming to IS 7452-1990, joints
mitred and welded with 15 x 3 mm lugs, 100 mm
long, embedded in cement concrete blocks 150 x
100 x 100 mm of 1:3:6 with coarse sand or with
wooden plugs and screws or rawl plugs and
screws/ with fixing clips/ with bolts and nuts as
required, incluing providing and fixing of 4 mm
hick glass panes with glazing clips and special
metal sash putty including three coats of
synthetic enamel paint over a primer coat of zinc
chromate on duly prepared surfaces excluding
he cost of metal beading and other fittings
except necessary hinges or pivot as required,
complete :
10005 sqmDoors 4,934.06 260.44 0.90 5,195.40 5,974.7
10010 sqmWindows fixed 4,509.86 260.44 0.90 4,771.20 5,486.8
10015 sqmWindows-side hung 4,934.06 260.44 0.90 5,195.40 5,974.7
10020 sqmVentilators-top hung 4,934.06 260.44 0.90 5,195.40 5,974.7
10025 sqmVentilators-centre hung 4,934.06 260.44 0.90 5,195.40 5,974.7
In composite units of doors, windows and
ventilator :
10030 sqm(For overall portion treated as fixed) 4,509.86 260.44 0.90 4,771.20 5,486.8
Add for side hung portion :
10035 sqmDoors 424.20 - - 424.20 487.8
10040 sqmWindows 424.20 - - 424.20 487.8
10045 sqmAdd for top hung portion. 424.20 - - 424.20 487.8
10050 sqmAdd for centre hung portion. 424.20 - - 424.20 487.8
10055 mAdd for providing vertical coupling, mullion
bar, or horizontal coupling mullion bar (when
openable windows are to be coupled above
fixed ones or between two fixed windows) or
horizontal coupling mullion bar (where
windows are not exposed to weather).
99.26 10.08 - 109.34 125.7
10060 mExtra for providing horizontal coupling
mullion bar or weather bar (especially used
126.84 12.88 - 139.72 160.6
63
7/25/2019 Sample Pages Build Cost
18/34
BuildCOST OPENINGS
09 Metal Doors, Windows And Frames08
21 Steel Doors, Windows And Frames UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
0908TOTAL
when the coupled unit is exposed to rain).
10065 mAdd for providing and fixing stainless steel /
aluminium beading of approved shape and
section with SS screws instead of glazingclips and metal sash putty in steel doors,
windows, ventilators and composite units.
62.73 6.30 - 69.03 79.3
11 Metal Doors And Frames08
13 Hollow Metal Doors And Frames UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
1108TOTAL
Hollow Metal Doors and Frames11
10005 sqmProviding, fabricating and fixing 1 mm thick
MS sheet door with hollow MS section frame
of 40 x 40 x 3 mm and 3 mm gussets at the
unctions and corners with necessary fittings
and three coats of synthetic enamel paint
over a primer coat of zinc chromate on duly
prepared surfaces, complete.
7,183.00 803.09 - 7,986.09 9,184.0
10010 sqmProviding, fabricating and fixing 1 mm thick
MS sheet door with MS angle 40 x 40 x 6
mm frame, and 3 mm gussets at the
unctions and corners with necessary fittings,
hree coats of synthetic enamel paint over a
primer coat of zinc chromate on duly
prepared surfaces, complete.
7,184.11 803.09 - 7,987.19 9,185.2
10015 sqmAdd for MS angles 40 x 40 x 6 mm for
diagonal braces.
1,053.02 182.22 - 1,235.24 1,420.5
10020 sqmAdd for MS flats 30 x 6 mm for diagonal
braces and central cross piece.
505.20 175.39 - 680.58 782.6
12 Metal Frames08
21 Steel Frames UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
1208TOTAL
Steel Frames13
10005 kgProviding and fixing MS frames for doors,
w i n d o w s a n d v e n t i l a t o r s w i t h
Tee/angle/fabricated-sections, joints mitred
and welded with 15 x 3 mm lugs 100 mm
long embedded in cement concrete blocks
150 x 100 x 100 mm 1:3:6 with coarse sand
or with wooden plugs and screws or rawls
plugs and screws/with fixing clips/with bolts
and nuts as required including fixing of butt
hinges and screws and applying three coats
of synthetic enamel paint over a primer coat
of zinc chromate on duly prepared surfaces,
complete.
194.71 11.46 0.00 206.16 237.0
Providing and fixing pressed steel door frames,
manufactured from commercial mild steel sheet
of 1.25 mm thickness, including hinges jamb,
lock jamb, bead, and required threshold of mild
steel flat of section 30 x 3 mm/8 mm round or
square bar welded or rigidly fixed together by
mechanical means, adjustable lugs with split end
ail to each jamb including steel butt hinges 2.5
mm thick with mortar guards, lock strike - plate
and shock absorbers and applying three coats of
synthetic enamel paint over a primer coat of zinc
chromate on duly prepared surfaces i/c filling
hollows of the frame with CC 1:3:6, complete :
10010 mProfile A 1,262.65 44.20 0.72 1,307.57 1,503.7
64
7/25/2019 Sample Pages Build Cost
19/34
BuildCOST FINISHES
21 Plaster And Gypsum Board Assemblies09
13 Plaster Assemblies UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
2109TOTAL
Expansion Control With Chicken
Mesh
13
10005 sqmProviding and fixing galvanized chicken wire
mesh (24 gauge 12 mm size) to junctions of
concrete and masonry work and other
locations including cutting to required sizes ,
side laps of minimum 75 mm and fixing in
position with galvanized iron wire nails,
complete.
117.36 120.00 2.00 239.36 275.2
22 Supports For Plaster And Gypsum Board09
26 Suspension Systems UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
2209TOTAL
Aluminium Frame Work14
Providing and fixing frame work for suspended
ceiling with anodised aluminium 15 microns
coating/Polyester pre-coated (50 microns), main
runner T-sections 35 x 35 x 1.5 mm thicksuspended from ceiling with 6 mm dia MS
adjustable hangers, fixed to ceiling with MS cleat
25 x 25 x 5 mm and 50 mm long, fixed to RCC
surface with expandable fasteners 12.5 x 40 mm,
intermediate T-section 23.5 x 19 x 1.5 mm thick
fixed to main runner and perimeter angle 35 x 15
x 1.5 mm thick fixed to wall/beam with cadmium
plated steel screws with rawl plug @ 450 mm
etc., all complete, for panel sizes (cost of
hangers with cleat to be paid for separately) :
10005 sqm1220 x 610 mm 486.05 146.38 - 632.43 727.3
10010 sqm610 x 610 mm 549.62 146.38 - 696.00 800.4
10015 sqmAdd for providing and making arrangement
for fixing light, fixture grills and diffusers in
he frame work.
437.59 146.25 - 583.84 671.4
Ms Frame Work15
Providing and fixing frame work for suspended
ceiling, made from 0.55 mm thick GS sheet
section consisting of GS channel main runner
suspended from ceiling with 6 mm dia MS
adjustable hanger fixed to ceiling with MS angle
of 25 x 25 x 5 mm thick and 50 mm long with
expandable fastners 12.5 x 40 mm, intermediate
T - sections fixed to main runner, and perimeter
channel section fixed to wall with cadmium
plated steel screw with rawl plug @ 450 mm
centre to centre, complete, for panel size (cost of
hangers with cleat to be paid for separately).
10005 sqm1220 x 610 mm 502.23 146.38 - 648.61 745.9
10010 sqm610 x 610 mm 594.31 146.38 - 740.69 851.7
10015 sqmAdd for providing and making arrangementfor fixing light fixture grills and diffusers in the
frame work.
594.31 146.25 - 740.56 851.6
Ceiling Supports, Suspension16
10005 EachProviding and fixing level adjusting hangers
of 6 mm dia. MS Rods fixed to roof slabs by
means of MSangle ceiling cleats 40 x 40 x 5
mm size, 40 mm long and expansion hold
fastners 12.5 mm dia. 40 mm long including
applying a primer coat of zinc chromate,
complete.
57.26 9.65 - 66.91 76.9
79
7/25/2019 Sample Pages Build Cost
20/34
BuildCOST SPECIALTIES
14 Signage10
53 Traffic Signage UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
1410TOTAL
Traffic Signs20
10005 EachProviding and fixing Cats Eye (Glow studs),
heavy duty integral stem, reflective,
aluminium dia cast with elegant finish, ofsize 100 x 100 mm and 20 mm high, having
a stem of 50 mm screwed / nailed with 12
mm dia 90 mm long nail to fix into the road
surface or at the nosing of the central verge .
The road studs should have reflectors fitted
on one side of the studs, complete.
524.77 19.98 - 544.75 626.4
28 Toilet, Bath, And Laundry Accessories10
16 Bath Accessories UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
2810TOTAL
Bath Accessories10
Providing and fixing stainless steel curtain rods
with stainless steel brackets, complete, of size :
10005 m25 mm outer dia 320.19 130.00 - 450.19 517.7
10010 m32 mm outer dia 349.70 130.00 - 479.70 551.6
10015 mProviding and fixing CP brass curtain rod
with CP brass brackets 25 mm outer dia,
complete.
1,201.21 130.00 - 1,331.21 1,530.8
10020 SetProviding and fixing CP brass brackets for
curtain rods 25 mm outer dia, complete.
523.28 97.44 - 620.72 713.8
Providing and fixing angular/bent grab bars
fabricated from 32 mm dia. seamless stainless
steel tubes with peened non-slip gripping
surface, polished flanges firmly fixed, to be fully
safe, with heavy duty anchor fastener having
finish/capping similar to the grab bar, complete,
including cutting and making good the
walls/floors for :
10025 Eachall-mounted /floor-mounted for European
ype water closet - 830 mm high
794.79 195.20 - 989.99 1,138.4
10030 EachBath tub - 1320 mm long 958.31 195.20 - 1,153.50 1,326.5
10035 EachWash basin and shower - 610 mm long 1,094.57 195.20 - 1,289.77 1,483.2
10040 EachProviding and fixing fully automatic "NO
TOUCH" hand driers of stainless steel body
suitable to operate on 230 V, single ph 50
Hz, AC power supply including brackets for
fixing on wall including cutting and making
good the walls, etc., complete.
12,092.10 195.20 - 12,287.30 14,130.3
10045 EachProviding and fixing bevelled edge mirrors
5.5 mm thick of float glass, complete with 6
mm thick marine ply board backing, fixed
with CP brass screws and washers,
complete, of size 450 x 600 mm.
1,761.16 227.31 - 1,988.47 2,286.7
Providing and fixing float glass mirror 5.5 mm
hick with plastic moulded frame and 6 mm thickmarine ply board backing, complete, of outer
dimensions :
10050 EachCircular shape 450 mm dia 455.33 227.31 - 682.64 785.0
10055 EachRectangular shape 453 x 357 mm 371.28 227.31 - 598.59 688.3
10060 EachOval shape 450 x 350 mm 371.89 227.31 - 599.19 689.0
10065 EachRectangular shape 1500 x 450 mm 894.13 292.83 - 1,186.96 1,365.0
10070 sqmProviding and fixing rectangular float glass
mirror 5.5 mm thick of any size with 6 mm
hick marine ply board backing, supported on
clips fixed with CP brass screws and
washers, complete.
805.50 325.00 - 1,130.50 1,300.0
107
7/25/2019 Sample Pages Build Cost
21/34
BuildCOST FIRE SUPPRESSION
12 Fire-suppression Standpipes21
13 Fire-suppression Hoses And Nozzles UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
1221TOTAL
Fire Hose And Equipment52
10005 EachProviding and fixing stand post fire hydrants
Type A, conforming to IS:908, with 63 mm
dia. outlet f itted with gunmetalinstantaneous type coupling, 80 mm dia.
inlet, one number cast iron double flanged
sluice valve, CI duck foot bends and flanged
riser, painting with one coat of ready mixed
red oxide primer and two coats of synthetic
enamel paint of fire red colour, finished to an
even shade, complete, excluding the cost of
brick chamber.
17,672.88 419.08 - 18,091.96 20,805.7
10010 EachProviding and fixing gun metal, under ground
ype fire hydrants, conforming to IS-909, with
control valve and 63 mm dia single outlet
fitted with instantaneous type coupling,
conforming to IS-901 for connection to hose
and 80 mm dia inlet and chained cap,
complete, excluding the cost of brick
chamber.
24,386.18 195.20 - 24,581.37 28,268.5
Providing and fixing gunmetal, hand wheel
operated fire hydrant valves Type A, conforming
o IS:5290, with 63 mm dia outlet fitted with
instantaneous female coupling, conforming to
IS:901, and 80 mm dia inlet, complete, with
blank caps and chains with :
10015 EachSingle outlet 8,355.95 65.00 - 8,420.95 9,684.0
10020 EachDouble outlet 16,104.70 78.00 - 16,182.70 18,610.1
10025 EachProviding and fixing first aid hose reels, of
heavy duty mild steel construction, with CI
brackets, wall mounted, swinging type, fitted
with 19 mm dia., 36.5 m long high pressure
hose, conforming to IS-5132, with 5 mm dia
outlet gunmetal nozzle and shut off valve,
conforming to IS 884-1967, complete.
12,082.83 285.00 - 12,367.83 14,223.0
10030 EachProviding and fixing 63 mm dia, 15 m longreinforced rubber lined hoses, conforming to
IS:636, including gunmetal male and female
instantaneous type coupling, conforming to
IS: 903, machine wound with galvanised
steel wire, complete.
6,752.41 20.00 - 6,772.41 7,788.2
10035 EachProviding and fixing standard short size
gunmetal branch pipes, conforming to
IS-903, with 16 mm dia. outlet gunmetal
nozzle, suitable to fit with standard
instantaneous type 63 mm coupling along
with nozzle spanner, complete.
3,119.82 20.00 - 3,139.82 3,610.7
10040 EachProviding and fixing standard firemans axes
with heavy insulated rubber handle,
conforming to IS:926, complete.
649.98 20.00 - 669.98 770.4
Providing and fixing gunmetal fire brigade
connections, conforming to IS-905, with 63 mmdia. instantaneous type inlet and 150 mm dia
flanged outlet with built in check valves for fire
risers complete in all respects :
10045 EachTwo-way 9,816.21 97.44 - 9,913.65 11,400.7
10050 EachThree-way 13,763.86 110.57 - 13,874.43 15,955.5
10055 EachProviding and fixing 25 mm size single acting
air valves with SCR inlet, conforming to
IS-12992, complete.
806.22 130.00 - 936.22 1,076.6
13 Fire-suppression Sprinkler Systems21
113
7/25/2019 Sample Pages Build Cost
22/34
BuildCOST PLUMBING
05 Common Work Results For Plumbing22
23 General-duty Valves For Plumbing
Piping
UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
0522TOTAL
Valve, Ball23
Providing, fixing and testing brass ball valve,
SCR lever operated, complete, of size:
10005 Each8 mm 207.45 32.50 - 239.95 275.9
10010 Each10 mm 207.45 45.50 - 252.95 290.8
Providing, fixing and testing brass ball valves
with carbon steel lever, complete of size :
10015 Each15 mm 294.01 45.50 - 339.51 390.4
10020 Each20 mm 833.56 45.50 - 879.06 1,010.9
10025 Each25 mm 1,321.30 52.00 - 1,373.30 1,579.3
10030 Each32 mm 1,822.97 52.00 - 1,874.97 2,156.2
10035 Each40 mm 1,974.63 65.00 - 2,039.63 2,345.5
10040 Each50 mm 2,495.58 65.00 - 2,560.58 2,944.6
Providing, fixing and testing brass ball valves
with aluminium alloy lever of size :
10045 Each15 mm 532.60 45.50 - 578.10 664.8
10050 Each20 mm 806.5445.50 -
852.04 979.810055 Each25 mm 1,007.01 52.00 - 1,059.01 1,217.8
10060 Each32 mm 1,958.80 52.00 - 2,010.80 2,312.4
10065 Each40 mm 2,777.87 65.00 - 2,842.87 3,269.3
10070 Each50 mm 4,377.46 65.00 - 4,442.46 5,108.8
Valve, Balancing24
Providing, fixing and testing CI balancing valve,
body conforming to IS:210, with companion
flanges (IS:6392), complete, of size:
10005 Each80 mm 7,714.48 81.25 - 7,795.73 8,965.0
10010 Each100 mm 12,095.16 95.00 - 12,190.16 14,018.6
10015 Each125 mm 17,177.16 118.73 - 17,295.89 19,890.2
10020 Each150 mm 23,275.56 150.03 - 23,425.59 26,939.4
10025 Each200 mm 46,652.76 200.00 - 46,852.76 53,880.6
10030 Each250 mm 73,079.16 250.00 - 73,329.16 84,328.5
10035 Each300 mm 101,538.36 324.65 - 101,863.01 117,142.4
Providing, fixing and testing G/Met balancing
valve SCR, conforming to IS:778, etc., complete,
of size:
10040 Each25 mm 1,375.92 52.00 - 1,427.92 1,642.1
10045 Each32 mm 1,684.07 61.75 - 1,745.82 2,007.6
10050 Each40 mm 2,078.21 71.50 - 2,149.71 2,472.1
10055 Each50 mm 3,511.46 78.00 - 3,589.46 4,127.8
10060 Each65 mm 6,377.96 89.64 - 6,467.60 7,437.7
10065 Each80 mm 8,519.24 104.00 - 8,623.24 9,916.7
Valve, Check27
Providing, fixing and testing CI check valve with
flanges, conforming to IS:9338 etc., complete, ofsize:
10005 Each40 mm 3,189.53 32.50 - 3,222.03 3,705.3
10010 Each50 mm 4,151.92 35.10 - 4,187.02 4,815.0
10015 Each65 mm 5,677.89 39.00 - 5,716.89 6,574.4
10020 Each80 mm 7,709.58 42.25 - 7,751.83 8,914.6
10025 Each100 mm 10,200.56 95.00 - 10,295.56 11,839.9
10030 Each125 mm 15,179.01 118.73 - 15,297.74 17,592.4
10035 Each150 mm 21,178.56 150.03 - 21,328.59 24,527.8
10040 Each200 mm 33,714.09 200.00 - 33,914.09 39,001.2
10045 Each250 mm 43,423.81 250.00 - 43,673.81 50,224.8
117
7/25/2019 Sample Pages Build Cost
23/34
BuildCOST PLUMBING
05 Common Work Results For Plumbing22
23 General-duty Valves For Plumbing
Piping
UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
0522TOTAL
Providing, fixing and testing G/Met vertical check
valve, integral seat, flanged female connection,
conforming to IS:778, complete, of size:
10225 Each25 mm 845.80 27.30 - 873.10 1,004.0
10230 Each32 mm 1,237.60 29.90 - 1,267.50 1,457.6
10235 Each40 mm 1,632.89 32.50 - 1,665.39 1,915.2
10240 Each50 mm 2,291.14 35.10 - 2,326.24 2,675.1
10245 Each65 mm 3,973.99 37.05 - 4,011.04 4,612.7
10250 Each80 mm 6,471.98 42.25 - 6,514.23 7,491.3
10255 Each100 mm 11,817.68 94.35 - 11,912.03 13,698.8
Valve, Gate31
Providing, fixing and testing brass gate valves
with CI Wheel, conforming to IS:778, secrewed
ends, complete, of nominal size :
10005 Each25 mm 782.82 32.50 - 815.32 937.6
10010 Each32 mm 928.93 32.50 - 961.43 1,105.6
10015 Each40 mm 1,428.2732.50 -
1,460.77 1,679.810020 Each50 mm 1,997.34 32.50 - 2,029.84 2,334.3
10025 Each65 mm 4,856.94 39.00 - 4,895.94 5,630.3
10030 Each80 mm 6,041.53 39.00 - 6,080.53 6,992.6
Providing, fixing and testing G/Met gate valve,
non-rising stem SCR, conforming to IS:778,
complete, of size:
10035 Each15 mm 670.94 13.00 - 683.94 786.5
10040 Each20 mm 871.02 16.25 - 887.27 1,020.3
10045 Each25 mm 1,507.90 18.20 - 1,526.10 1,755.0
10050 Each32 mm 2,120.94 20.80 - 2,141.74 2,463.0
10055 Each40 mm 2,650.54 22.75 - 2,673.29 3,074.2
10060 Each50 mm 4,351.73 25.35 - 4,377.08 5,033.6
10065 Each65 mm 7,800.94 27.30 - 7,828.24 9,002.4
10070 Each80 mm 11,062.82 32.50 - 11,095.32 12,759.6
10075 Each100 mm 20,312.07 32.50 - 20,344.57 23,396.2
Valve, Plastic60
Providing, fixing and testing PTMT stop cocks,
complete, of nominal size :
10005 Each15 mm 123.76 32.50 - 156.26 179.6
10010 Each20 mm 140.53 32.50 - 173.03 198.9
76 Facility Drainage Piping Cleanouts UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
0522TOTAL
Cleanouts10
10005 EachProviding and fixing 100 mm dia. flanged
clean-out plugs with CI flanged tail pieces,
blind flanges conforming to IS-1538 fixed
with necessary neoprene washers,galvanised fasteners, complete, (excluding
cost of tail piece and its joints).
451.43 81.25 - 532.68 612.5
Providing and fixing cast brass clean-out plugs
with suitable inset keys for opening, and
galvanised steel bends including fixing to
galvanised steel / sand cast iron/ centrifugally
spun pipes with lead joint, of nominal dia :
10010 Each50 mm 872.94 125.00 - 997.94 1,147.6
10015 Each75 mm 1,381.39 125.00 - 1,506.39 1,732.3
10020 Each100 mm 2,139.84 187.40 - 2,327.24 2,676.3
10025 Each150 mm 4,538.13 187.40 - 4,725.53 5,434.3
119
7/25/2019 Sample Pages Build Cost
24/34
BuildCOST HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
07 Hvac Insulation23
13 Duct Insulation UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
0723TOTAL
Duct Insulation11
Providing and fixing, fiber-glass insulation,
bonded by resin conforming to IS:8183, for
ducts, etc., with 0.5 mm thick aluminium sheetcladding having 50 mm overlap at joints etc.,
complete, of following thickness and density:
10005 sqm25 mm thick 16kg per cum 617.02 170.10 - 787.12 905.1
10010 sqm25 mm thick 24 kg per cum 659.37 170.10 - 829.47 953.8
10015 sqm25 mm thick 32 kg per cum 704.01 170.10 - 874.11 1,005.2
10020 sqm50 mm thick 16 kg per cum 742.18 170.10 - 912.28 1,049.1
10025 sqm50 mm thick 24 kg per cum 825.74 170.10 - 995.84 1,145.2
10030 sqm50 mm thick 32 kg per cum 917.30 170.10 - 1,087.40 1,250.5
Providing and fixing, rigid polyurethane foam
(PUF) slab for thermal insulation, conforming to
IS:12436, paper laminated/ unfaced, complete,
of following thickness and density:
10035 sqm15 mm thick 32 kg per cum 383.17 130.00 - 513.17 590.1
10040 sqm20 mm thick 32 kg per cum489.21 130.00 - 619.21 712.1
10045 sqm25 mm thick 32 kg per cum 619.55 130.00 - 749.55 861.9
10050 sqm30 mm thick 32 kg per cum 724.08 130.00 - 854.08 982.1
10055 sqm40 mm thick 32 kg per cum 978.82 130.00 - 1,108.82 1,275.1
10060 sqm50 mm thick 32 kg per cum 1,207.57 130.00 - 1,337.57 1,538.2
Providing and fixing, polyurethane rigid foam
insulation pipe section, conforming to IS:12436
and density 36 kg per m3 with 0. 5 mm thick
aluminium sheet cladding having 50 mm overlap
on joints and supports, complete, of following
hickness and nominal bo
25 mm thickness :
10065 m20 mm 249.44 20.00 - 269.44 309.8
10070 m25 mm 278.05 20.00 - 298.05 342.7
10075 m32 mm 311.16 20.00 - 331.16 380.8
10080 m40 mm 336.80 20.00 - 356.80 410.3
10085 m50 mm 378.99 20.00 - 398.99 398.9
10090 m65 mm 424.21 20.00 - 444.21 510.8
10095 m80 mm 464.89 30.00 - 494.89 569.1
10100 m100 mm 540.19 30.00 - 570.19 655.7
10105 m125 mm 644.21 30.00 - 674.21 775.3
10110 m150 mm 725.57 30.00 - 755.57 868.9
10115 m200 mm 900.40 30.00 - 930.40 1,069.9
10120 m250 mm 1,106.99 30.00 - 1,136.99 1,307.5
10125 m300 mm 1,257.58 40.00 - 1,297.58 1,492.2
10130 m350 mm 1,627.94 40.00 - 1,667.94 1,918.1
10135 m400 mm 1,858.82 40.00 - 1,898.82 2,183.6
30 mm thickness :10140 m20 mm 293.30 20.00 - 313.30 360.3
10145 m25 mm 332.33 20.00 - 352.33 405.1
10150 m32 mm 362.52 20.00 - 382.52 439.9
10155 m40 mm 392.65 20.00 - 412.65 474.5
10160 m50 mm 443.93 20.00 - 463.93 533.5
10165 m65 mm 484.61 20.00 - 504.61 580.3
10170 m80 mm 534.38 30.00 - 564.38 649.0
10175 m100 mm 624.77 30.00 - 654.77 752.9
10180 m125 mm 731.82 30.00 - 761.82 876.0
147
7/25/2019 Sample Pages Build Cost
25/34
BuildCOST ELECTRICAL
05 Common Work Results For Electrical26
13 Medium-Voltage Cables UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
0526TOTAL
Cable End Terminations With
Compression Glands
20
Providing and making end termination with single
compression brass gland and aluminium lugs forPVC insulated and PVC sheathed / XLPE
aluminium conductor cable of 1.1 kV grade,
complete, of size :
10005 Set1 core 300 sqmm 278.40 162.50 - 440.90 507.0
10010 Set1 core 400 sqmm 476.03 162.50 - 638.53 734.3
10015 Set1 core 500 sqmm 517.88 195.20 - 713.07 820.0
10020 Set1 core 630 sqmm 582.37 195.20 - 777.56 894.2
10025 Set2 core 6 sqmm 58.37 65.00 - 123.37 141.8
10030 Set2 core 10 sqmm 59.49 78.00 - 137.49 158.1
10035 Set2 core 16 sqmm 81.27 78.00 - 159.27 183.1
10040 Set2 core 25 sqmm 134.84 78.00 - 212.84 244.7
10045 Set2 core 35 sqmm 136.97 78.00 - 214.97 247.2
10050 Set2 core 50 sqmm 141.51 78.00 - 219.51 252.4
10055 Set2 core 70 sqmm 152.61 78.00 - 230.61 265.2
10060 Set3 core 10 sqmm 82.59 78.00 - 160.59 184.6
10065 Set3 core 16 sqmm 136.14 78.00 - 214.14 246.2
10070 Set3 core 25 sqmm 138.18 78.00 - 216.18 248.6
10075 Set3 core 35 sqmm 141.38 78.00 - 219.38 252.2
10080 Set3 core 50 sqmm 148.19 78.00 - 226.19 260.1
10085 Set3 core 70 sqmm 248.36 104.00 - 352.36 405.2
10090 Set3 core 95 sqmm 251.49 104.00 - 355.49 408.8
10095 Set3 core 120 sqmm 435.62 162.50 - 598.12 687.8
10100 Set3 core 150 sqmm 449.29 162.50 - 611.79 703.5
10105 Set3 core 185 sqmm 502.31 162.50 - 664.81 764.5
10110 Set3 core 240 sqmm 721.62 162.50 - 884.12 1,016.7
10115 Set3 core 300 sqmm 773.50 162.50 - 936.00 1,076.4
10120 Set3 core 400 sqmm 972.41 214.50 - 1,186.91 1,364.9
10125 Set3 core 25 sq. mm 140.84 78.00 - 218.84 251.6
10130 Set3 core 35 sqmm 144.04 104.00 - 248.04 285.2
10135 Set3 core 50 sqmm 151.53 104.00 - 255.53 293.8
10140 Set3 core 70 sqmm 252.77 104.00 - 356.77 410.2
10145 Set3 core 95 sqmm 258.17 162.50 - 420.67 483.7
10150 Set3 core 120 sqmm 445.63 162.50 - 608.13 699.3
10155 Set3 core 150 sqmm 497.27 162.50 - 659.77 758.7
10160 Set3 core 185 sqmm 513.36 162.50 - 675.86 777.2
10165 Set3 core 240 sqmm 737.09 162.50 - 899.59 1,034.5
10170 Set3 core 300 sqmm 912.19 214.50 - 1,126.69 1,295.6
10175 Set3 core 400 sqmm 1,187.31 214.50 - 1,401.81 1,612.0
10180 Set4 core 10 sq. mm 84.80 78.00 - 162.80 187.2
10185 Set4 core 16 sqmm 138.81 78.00 - 216.81 249.3
10190 Set4 core 25 sqmm 141.51 104.00 - 245.51 282.3
10195 Set4 core 35 sqmm 145.78 104.00 - 249.78 287.2
10200 Set4 core 50 sqmm 245.06 104.00 - 349.06 401.4
10205 Set4 core 70 sqmm 244.02 162.50 - 406.52 467.5
10210 Set4 core 95 sqmm 277.78 162.50 - 440.28 506.3
10215 Set4 core 120 sqmm 378.07 162.50 - 540.57 621.6
Cable End Termination Kit, Cast
Resin Compound
22
179
7/25/2019 Sample Pages Build Cost
26/34
BuildCOST ELECTRICAL
05 Common Work Results For Electrical26
13 Medium-Voltage Cables UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
0526TOTAL
Providing and making indoor/outdoor cable end
ermination with heat shrinkage jointing kit, with
all accessories including lugs for XLPE
aluminium conductor cable of 33 kV (E) grade,
complete, of size :
Outdoor,
10005 Each2 core 25 sqmm 322.23 240.76 - 562.99 647.4
10010 Each2 core 35 sqmm 324.37 240.76 - 565.13 649.9
10015 Each2 core 50 sqmm 328.91 240.76 - 569.67 655.1
10020 Each2 core 70 sqmm 369.83 240.76 - 610.59 702.1
10025 Each3 core 25 sqmm 325.57 240.76 - 566.33 651.2
10030 Each3 core 35 sqmm 328.77 240.76 - 569.53 654.9
10035 Each3 core 50 sqmm 369.86 325.00 - 694.86 799.0
10040 Each3 core 70 sqmm 379.84 325.00 - 704.84 810.5
10045 Each3 core 95 sqmm 433.11 520.00 - 953.11 1,096.0
10050 Each3 core 120 sqmm 446.37 520.00 - 966.37 1,111.3
10055 Each3 core 150 sqmm 460.04 520.00 - 980.04 1,127.0
10060 Each3 core 185 sqmm 673.66 565.24 - 1,238.90 1,424.7
10065 Each3 core 240 sqmm 861.10 650.00 - 1,511.10 1,737.7
10070 Each3 core 300 sqmm 912.98 650.00 - 1,562.98 1,797.4
10075 Each3 core 400 sqmm 1,143.06 730.34 - 1,873.40 2,154.4
10080 Each3 core 25 sqmm 332.45 240.76 - 573.21 659.1
10085 Each3 core 35 sqmm 365.70 325.00 - 690.70 794.3
10090 Each3 core 50 sqmm 373.20 427.64 - 800.83 920.9
10095 Each3 core 70 sqmm 434.39 427.64 - 862.02 991.3
10100 Each3 core 95 sqmm 439.79 520.00 - 959.79 1,103.7
10105 Each3 core 120 sqmm 456.37 520.00 - 976.37 1,122.8
10110 Each3 core 150 sqmm 668.62 565.24 - 1,233.86 1,418.9
10115 Each3 core 185 sqmm 684.71 565.24 - 1,249.95 1,437.4
10120 Each3 core 240 sqmm876.57 650.00 - 1,526.57 1,755.5
10125 Each3 core 300 sqmm 933.00 730.34 - 1,663.34 1,912.8
10130 Each3 core 400 sqmm 1,168.10 783.12 - 1,951.22 2,243.9
10135 Each4 core 25 sqmm 328.91 325.00 - 653.91 752.0
10140 Each4 core 35 sqmm 367.45 427.64 - 795.08 914.3
10145 Each4 core 50 sqmm 376.54 427.64 - 804.17 924.8
10150 Each4 core 70 sqmm 439.99 427.64 - 867.62 997.7
10155 Each4 core 95 sqmm 444.17 520.00 - 964.17 1,108.7
10160 Each4 core 120 sqmm 461.84 520.00 - 981.84 1,129.1
Indoor,
10165 Each3 core 70 sqmm 1,278.30 325.00 - 1,603.30 1,843.7
10170 Each3 core 95 sqmm 1,281.43 325.00 - 1,606.43 1,847.4
10175 Each3 core 120 sqmm 1,478.39 520.00 - 1,998.39 2,298.1
10180 Each3 core 150 sqmm 1,492.05 520.00 - 2,012.05 2,313.810185 Each3 core 185 sqmm 1,507.10 520.00 - 2,027.10 2,331.1
10190 Each3 core 240 sqmm 1,794.07 650.00 - 2,444.07 2,810.6
10195 Each3 core 300 sqmm 1,845.95 650.00 - 2,495.95 2,870.3
10200 Each3 core 400 sqmm 2,332.73 730.34 - 3,063.07 3,522.5
Outdoor,
10205 Each3 core 70 sqmm 3,103.21 325.00 - 3,428.21 3,942.4
10210 Each3 core 95 sqmm 3,106.34 325.00 - 3,431.34 3,946.0
10215 Each3 core 120 sqmm 3,801.34 520.00 - 4,321.34 4,969.5
10220 Each3 core 150 sqmm 3,815.00 520.00 - 4,335.00 4,985.2
180
7/25/2019 Sample Pages Build Cost
27/34
BuildCOST ELECTRICAL
05 Common Work Results For Electrical26
13 Medium-Voltage Cables UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
0526TOTAL
10225 Each3 core 185 sqmm 3,830.05 520.00 - 4,350.05 5,002.5
10230 Each3 core 240 sqmm 4,715.19 650.00 - 5,365.19 6,169.9
10235 Each3 core 300 sqmm 4,767.07 650.00 - 5,417.07 6,229.6
10240 Each3 core 400 sqmm 5,464.43 730.34 - 6,194.77 7,123.9
Cable End Termination Kit, Cold
Shrinkage
24
Providing and making indoor/outdoor cold shrink
ermination including aluminium lugs and all
other jointing materials for XLPE aluminium
conductor cable of 11 kV (E) grade, complete, of
size:
Indoor,
10005 Each3 core 70 sqmm 11,704.18 260.00 - 11,964.18 13,758.8
10010 Each3 core 95 sqmm 11,707.31 260.00 - 11,967.31 13,762.4
10015 Each3 core 120 sqmm 12,670.61 427.64 - 13,098.25 15,062.9
10020 Each3 core 150 sqmm 12,684.28 427.64 - 13,111.92 15,078.7
10025 Each3 core 185 sqmm 12,699.32 427.64 - 13,126.96 15,096.0
10030 Each3 core 240 sqmm 14,908.07 520.00 - 15,428.07 17,742.2
10035 Each3 core 300 sqmm 14,959.95 520.00 - 15,479.95 17,801.9
10040 Each3 core 400 sqmm 15,040.20 650.00 - 15,690.20 18,043.7
Outdoor,
10045 Each3 core 70 sqmm 20,183.70 260.00 - 20,443.70 23,510.2
10050 Each3 core 95 sqmm 20,186.83 260.00 - 20,446.83 23,513.8
10055 Each3 core 120 sqmm 22,694.06 427.64 - 23,121.70 26,589.9
10060 Each3 core 150 sqmm 22,707.73 427.64 - 23,135.37 26,605.6
10065 Each3 core 185 sqmm 22,722.77 427.64 - 23,150.41 26,622.9
10070 Each3 core 240 sqmm 25,222.40 520.00 - 25,742.40 29,603.7
10075 Each3 core 300 sqmm 25,274.28 520.00 - 25,794.28 29,663.4
10080 Each3 core 400 sqmm 25,354.52 650.00 - 26,004.52 29,905.2
Providing and making indoor/outdoor cold shrink
ermination including aluminium lugs and all
other jointing materials for XLPE aluminium
conductor cable of 33 kV (E) grade, complete, of
size:
Indoor,
10085 Each3 core 50 sqmm 31,394.28 325.00 - 31,719.28 36,477.1
10090 Each3 core 70 sqmm 31,404.26 427.64 - 31,831.90 36,606.6
10095 Each3 core 95 sqmm 31,407.39 427.64 - 31,835.03 36,610.2
10100 Each3 core 120 sqmm 31,420.65 520.00 - 31,940.65 36,731.7
10105 Each3 core 150 sqmm 35,351.04 520.00 - 35,871.04 41,251.6
10110 Each3 core 185 sqmm 35,366.08 650.00 - 36,016.08 41,418.4
10115 Each3 core 240 sqmm 35,419.27 650.00 - 36,069.27 41,479.6
10120 Each3 core 300 sqmm 38,737.08 730.34 - 39,467.42 45,387.5
Outdoor,
10125 Each3 core 50 sqmm 41,745.47 325.00 - 42,070.47 48,381.0
10130 Each3 core 70 sqmm 41,755.45 427.64 - 42,183.08 48,510.5
10135 Each3 core 95 sqmm 41,931.98 427.64 - 42,359.61 48,713.5
10140 Each3 core 120 sqmm 41,945.23 520.00 - 42,465.23 48,835.0
10145 Each3 core 150 sqmm 41,958.90 520.00 - 42,478.90 48,850.7
10150 Each3 core 185 sqmm 41,973.94 650.00 - 42,623.94 49,017.5
10155 Each3 core 240 sqmm 46,217.01 650.00 - 46,867.01 53,897.0
10160 Each3 core 300 sqmm 46,268.89 730.34 - 46,999.23 54,049.1
181
7/25/2019 Sample Pages Build Cost
28/34
BuildCOST COMMUNICATIONS
15 Communications Horizontal Cabling27
10 Special Communications Cabling UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
1527TOTAL
Cable, Telephone25
Providing and drawing PVC insulated, PVC
sheathed, tinned copper conductor telephone
cable in the existing surface/recessed, PVC/steelconduit/PVC casing and capping, of size :
0.51 mm dia,
10005 m1 pair 7.40 24.00 - 31.40 36.1
10010 m2 pair 14.36 24.00 - 38.36 44.1
10015 m3 pair 20.89 24.00 - 44.89 51.6
10020 m5 pair 32.64 24.00 - 56.64 65.1
10025 m10 pair 62.07 24.00 - 86.07 98.9
10030 m20 pair 119.72 24.00 - 143.72 165.2
10035 m50 pair 289.99 27.00 - 316.99 364.5
0.61 mm dia,
10040 m1 pair 9.49 24.00 - 33.49 38.5
10045 m2 pair 19.24 24.00 - 43.24 49.7
10050 m3 pair28.26 24.00 - 52.26 60.1
10055 m5 pair 44.72 24.00 - 68.72 79.0
10060 m10 pair 86.01 24.00 - 110.01 126.5
10065 m20 pair 164.15 24.00 - 188.15 216.3
10070 m50 pair 414.94 27.00 - 441.94 508.2
0.71 mm dia,
10075 m1 pair 11.24 24.00 - 35.24 40.5
10080 m2 pair 30.33 24.00 - 54.33 62.4
10085 m3 pair 46.00 24.00 - 70.00 80.5
10090 m5 pair 75.66 24.00 - 99.66 114.6
10095 m10 pair 151.14 24.00 - 175.14 201.4
10100 m20 pair 300.08 24.00 - 324.08 372.6
10105 m50 pair 652.58 27.00 - 679.58 781.5
235
7/25/2019 Sample Pages Build Cost
29/34
BuildCOST ELECTRONIC SAFETY AND SECURITY
31 Fire Detection And Alarm28
23 Fire Detection And Alarm
Annunciation Panels And Fire
Stations
UNIT TOTAL INCL
OHP
BARE COST
Material Labour Equipment
3128TOTAL
Fire Detection And Fire Alarm
System
10
P r o v i d i n g , i n s t a l l a t i n g , t e s t i n g a n d
commissioning of standard fire detection and
alarm control panel in 16 SWG sheet steel
enclosure duly painted, consisting of power
supply, automatic control battery charger, control
and zone cards, duplex talk back facility etc (but
without PA system) for operation on 24 V, DC,
complete with 2 numbers 12 V Lead Acid storage
batteries of suitable capacity, for :
10005 Each2 zones 14,946.23 978.28 - 15,924.51 18,313.1
10010 Each4 zones 18,273.17 1,007.46 - 19,280.63 22,172.7
10015 Each6 zones 21,600.11 1,038.48 - 22,638.59 26,034.3
10020 Each8 zones 24,927.05 1,097.58 - 26,024.63 29,928.3
10025 Each10 zones 28,255.13 1,125.00 - 29,380.13 33,787.1
10030 Each12 zones 31,582.07 1,153.86 - 32,735.93 37,646.3
Providing and fixing heat detector, conforming to
IS:2175, including making connections, of type :
10035 EachRate of rise (ROR) 1,662.43 36.00 - 1,698.43 1,953.2
10040 EachFixed temperature 1,487.57 36.00 - 1,523.57 1,752.1
10045 EachRate of rise - cum - fixed temperature 1,662.43 36.00 - 1,698.43 1,953.2
Providing and fixing smoke detector, conforming
o IS:11360, including making connections, of
ype :
10050 EachIonisation 1,924.72 36.00 - 1,960.72 2,254.8
10055 EachPhoto-electric/optical 1,839.54 72.00 - 1,911.54 2,198.2
10060 EachProviding and fixing spot (response) indicator
including making connection.
108.44 84.00 - 192.44 221.3
Providing and fixing sounder including making
connections, of intensity :
10065 EachLow 835.25 30.00 - 865.25 995.0
10070 EachHigh 1,252.25 30.00 - 1,282.25 1,474.5
10075 EachProviding and fixing manual call box,
complete with cover, switch including making
connections.
1,051.18 84.00 - 1,135.18 1,305.4
P r o v i d i n g , i n s t a l l a t i n g , t e s t i n g a n d
commissioning addressable fire detection and
alarm control panel in 16 SWG sheet steel
enclosures, duly painted, consisting of power
supply, automatic control battery charger, loop
cards, fire / fault event recorder, duplex talk back
facility etc. (but without PA system), suitable for
operation on 24V, DC, complete with 2 numbers
12 V Lead Acid storage batteries of suitable
capacity, for :
10080 Each2 loop 250,343.141,125.00 -
251,468.14 289,188.310085 Each4 loop 375,112.48 1,273.56 - 376,386.04 432,843.9
10090 Each6 loop 541,469.71 1,421.08 - 542,890.79 624,324.4
10095 Each8 loop 666,239.05 1,588.23 - 667,827.28 768,001.3
10100 Each10 loop 832,597.41 1,730.76 - 834,328.17 959,477.4
10105 Each12 loop 998,955.78 1,875.00 - 1,000,830.78 1,150,955.3
Providing and fixing, addressable heat detector ,
conforming to IS:2175, including making
connections, of type :
10110 EachRate of rise (ROR) 3,745.22 36.00 - 3,781.22 4,348.4
10115 EachFixed temperature 3,246.40 36.00 - 3,282.40 3,774.7
239
7/25/2019 Sample Pages Build Cost
30/34
BuildCOST EARTHWORK
11 Clearing And Grubbing31
10 Clearing And Grubbing UNIT TOTAL INCLOHP
BARE COST
Material Labour Equipment
1131TOTAL
Clear And Grub10
10005 100 sqmClearing jungle including uprooting of rank
vegetation, grass, brush wood, trees and
saplings of girth upto 300 mm (measured ata height of 1.0 m above GL) and removal of
rubbish up to a distance of 50 m outside the
periphery of the area cleared, complete.
- 416.68 - 416.68 479.1
Felling trees including cutting of trunks and
branches, removing the roots, stacking of
serviceable materials and disposal of
unserviceable materials within a 50 m lead,
complete, of girths (measured at a height of 1.0
m above GL.) :
10010 Eachover 300 mm and upto 600 mm - 125.00 - 125.00 143.7
10015 Eachover 600 mm and upto 1200 mm - 568.18 - 568.18 653.4
10020 Eachover 1200 mm and upto 2400 mm - 2,500.00 - 2,500.00 2,875.0
10025 Eachover 2400 mm - 5,000.00 - 5,000.00 5,750.0