SUSTAINABLE AIRPORT MASTER PLAN

12

Sustainable Airport Master Plan (SAMP)Master Plan stages

• Inventory

• Forecasts

• Facility requirements

• Planning alternatives

• Environmental review

• Implementation plan

• Plan of Finance

• Airport Layout Plan approval

SAMP BODY OF WORK

Page 2: SAMP BODY OF WORK SUSTAINABLE AIRPORT MASTER …SAMP BODY OF WORK 2018 2019 Planning Open Houses 5/30, 6/14, 6/20 Start scoping process noti˜cation: July 23 Winter 2019 • FAA NEPA

www.portseattle.org

SUSTAINABLE AIRPORT MASTER PLANEnvironmental Scoping Public Comment Milestones

SAMP BODY OF WORK

2018 2019

Planning Open Houses5/30, 6/14, 6/20

Start scoping processnoti�cation: July 23

Winter 2019• FAA NEPA Decision• Port of Seattle SEPA DeterminationAgency and public scoping meetings

• Week of Sept. 10• Comment period closes: Sept. 21

Environmental AnalysisSummer 2018 – Summer 2019

Draft NEPA EA/SEPA EIS – Summer 2019

NEPA EA/SEPA EIS comment period Fall 2019

Final NEPA EA/SEPA EIS – Winter 2019Agency & Public Scoping Process

Page 3: SAMP BODY OF WORK SUSTAINABLE AIRPORT MASTER …SAMP BODY OF WORK 2018 2019 Planning Open Houses 5/30, 6/14, 6/20 Start scoping process noti˜cation: July 23 Winter 2019 • FAA NEPA

www.portseattle.org

DEVELOPMENT CONSTRAINTS AND KEY FUNCTIONAL AREAS

13

Development Constraints & Key Functional Areas

SAMP BODY OF WORK

Page 4: SAMP BODY OF WORK SUSTAINABLE AIRPORT MASTER …SAMP BODY OF WORK 2018 2019 Planning Open Houses 5/30, 6/14, 6/20 Start scoping process noti˜cation: July 23 Winter 2019 • FAA NEPA

www.portseattle.org

PHASED APPROACHPlanning Status Update

7

• Airfield/airspace constraints result in major congestion (aircraft delays) as activity nears 59 million passengers (2029)

• Phased approach required to advance SAMP – Identify projects to accommodate near-term demand within existing

constraints – Near-Term projects– Conduct environmental review of Near-Term projects

– Follow-on planning study to address airfield/airspace constraints

• Near-Term projects– Near-Term projects can accommodate 2027 market demand– Approximately 56 million annual passengers

Phased approach required to meet future demand

Phased approach required to meet future demand

• Airfield/airspace constraints result in major congestion beyond 2027

• Phased approach required to advance SAMP–Identify projects to accommodate near-term demand within existing constraints –Near-Term projects–Conduct environmental review of Near-Term projects–Follow-on planning study to address airfield/airspace constraints–Resolve constraints in the future phase

• Near-Term projects–Near-Term projects can accommodate 2027 market demand–Approximately 56 million annual passengers and 480,000 annual operations

SAMP BODY OF WORK