RESETTLEMENT IMPLEMENTATION PLAN WAP 2 (Mudhol – Nippani)
June 2012
GOVERNMENT OF KARNATAKA PUBLIC WORKS DEPARTMENT
Karnataka State Highways Improvement Project - II
KARNATAKA STATE HIGHWAYS IMPROVEMENT PROJECT - II
RP946 v3
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
i
Contents
ABBREVIATIONS ..................................................................................................................................... iv
EXECUTIVE SUMMARY .......................................................................................................................... 1
I INTRODUCTION ...................................................................................................................................... 3
Objectives of RIP .................................................................................................................................... 4
Main activities of RIP ............................................................................................................................. 4
Minimization of Impacts and Corridor of Impact ............................................................................... 5
II. LAND ACQUISITION AND RESETTLEMENT IMPACTS ................................................................ 6
Land Acquisition Status ............................................................................................................................ 6
Guidance Value ......................................................................................................................................... 6
Negotiation Committee ............................................................................................................................. 6
Method of Price Negotiation ..................................................................................................................... 7
Records to be submitted by the Land Owners .......................................................................................... 7
Failure of KHA and Appellate Committee ............................................................................................... 8
Conclusion of negotiation ........................................................................ Error! Bookmark not defined.
Valuation of Assets on land under LA ....................................................... Error! Bookmark not defined.
Valuation of Crops .................................................................................................................................. 8
Valuation of other structures/assets .......................................................................................................... 8
Site Requirement for Residential and Commercial impacts ............................................................... 8
Loss of Community Assets ....................................................................................................................... 8
III. BASELINE CENSUS SURVEYS AND CONSULTATIONS ............................................................ 10
Characteristics of displaced households ................................................................................................. 10
Major and Minor Impacts ....................................................................................................................... 11
Vulnerable groups ................................................................................................................................... 12
Consultations........................................................................................................................................... 13
IV. IMPLEMENTATION MECHANISMS ............................................................................................... 16
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
ii
Institutional Arrangements ...................................................................................................................... 16
Extending R & R Assistance to PAPs. .................................................................................................... 16
Implementation support by NGOs .......................................................................................................... 18
IR Activities ............................................................................................................................................ 19
Monitoring and Evaluation support for RAP .......................................................................................... 19
Grievance Redressal mechanism ............................................................................................................ 20
Resettlement Colonies and Vendor Markets ........................................................................................... 20
Protection of RoW .................................................................................................................................. 21
Impacts on Municipal Towns ............................................................................................................... 21
Data Base Management .......................................................................................................................... 21
Co –ordination between R&R and Civil works ...................................................................................... 22
Monitoring and R&R Activities ................................................................. Error! Bookmark not defined.
Additional Impacts .................................................................................................................................. 24
Budget ..................................................................................................................................................... 24
Disclosure ............................................................................................................................................... 24
Annexure 1: Guidance Value as on May 2011 ........................................................................................... 26
Annexure 2: Details of PAFs in link 19A ................................................................................................... 28
Annexure 3: Details of PAFs in link 19B ................................................................................................... 32
Annexure 4 : Details of PAFs in Link 19C ................................................................................................. 36
Annexure 5: Details of PAFS in Link 19D ................................................................................................. 38
Annexure 6: Details of Community Structure ............................................................................................ 43
List of Tables
Table 1- 1: Package Details .......................................................................................................................... 3
Table 1- 2: Summary Tables on Impacts ...................................................................................................... 4
Table 2- 2: Summary Table on Community Assets ...................................................................................... 9
Table 3- 1: Baseline Socio Economic information - for Major impacts (232) ........................................... 10
Table 3- 2: Distribution of PAFs by Major and Minor Impacts for WAP 2 ............................................... 11
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
iii
Table 3- 3: Consultation Summary ............................................................................................................. 13
Table 4- 1: R& R Assistance ...................................................................................................................... 16
Table 4- 2: Time line for Key LA and R & R Activities ............................................................................ 22
Table 4- 3: Time line for LA and R & R Activities ....................................... Error! Bookmark not defined.
Table 4- 4: Monitoring Indicators for Physical Progress ............................................................................ 24
Table 4- 5: Budget ...................................................................................................................................... 24
Table 4- 6: Guidance Value for Link 19A .................................................................................................. 26
Table 4- 7: Guidance Value for Link 19B .................................................................................................. 26
Table 4- 8: Guidance Value for Link 19C .................................................................................................. 26
Table 4- 9: Guidance Value for Link 19D .................................................................................................. 27
Table 4- 10: PAFs Structure details of link 19A ......................................................................................... 28
Table 4- 11: PAF Structure details of link 19B .......................................................................................... 32
Table 4- 12: PAF Structure details of link 19C .......................................................................................... 36
Table 4- 13: PAF Structure details of link 19D .......................................................................................... 38
Table 4- 14: Community Asset Details of link 19A (Mudhol - Mahalingapura ) ....................................... 43
Table 4- 15: Community Asset Details of link 19B (Mahalingapura - Kabbur) ......................................... 44
Table 4- 16: Community Asset Details of link 19C (Kabbur - Chikodi) .................................................... 46
Table 4- 17: Community Asset Details of link 19D (Chikodi - Nippani (NH4)) ....................................... 48
List of Figures
Figure 1- 1: Distribution of PAFs for Package WAP2 ............................................................................... 12
Figure 1- 2: Distribution of PAFS by Major Impact for Package WAP 2 .................................................. 12
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
iv
ABBREVIATIONS
AC Assistant Commissioner
ADSW Assistant Director Social Welfare
CAO Chief Administrative Officer
CPO Chief Project Officer
CPR Common Property Resources
COI Corridor of Impact
DC Deputy Commissioner
DPR Detail Project Report
EWS Economically Weaker Section
EPC Engineering Procurement Contract
GOI Government of India
GOK Government of Karnataka
GRC Grievance Redressal Cell
ID Identity Card
IPDP Indigenous People Development Plan
IR Income Restoration
KHA Karnataka Highways Act
KSHIP Karnataka State Highways Improvement Project
LAA Land Acquisition Act
LAO Land Acquisition Officer
LAP Land Acquisition Plan
NGO Non-Governmental Organization
PAF Project Affected Family
PAG Project Affected Group
PAP Project Affected Person
PIU Project Implementation Unit
PGB Project Governing Body
PWD Public Works Department
PU Pre University
PGB Project Governing Body
RTC Record of Rights
R & R Resettlement and Rehabilitation
RAP Resettlement Action Plan
ROW Right of Way
SIA Social Impact Assessment
SDO Social Development Officer
SDRC Social Development Resettlement Cell
SWI Social Welfare Inspector
SC Scheduled Caste
SR Schedule of Rates
ST Scheduled Tribes
SHG Self Help Group
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
v
SIA Social Impact Assessment
ToR Terms of Reference
UR Upgradation
ZP Zilla Panchayat
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
1
EXECUTIVE SUMMARY
The Karnataka State Highways Improvement Project (KSHIP) – II covers a length of 826.7 kms.
The roads have been categorised into two types of contracts EPC and Annuity. It consists of 269.4 kms of
EPC roads consisting of 5 packages and 557.3 kms of roads under annuity contract consisting of 4
packages. Contract package WAP 2, is an Annuity package which covers 108 kms consisting of 4 links.
The details are given in Table 1.1This Resettlement Implementation Plan covers the implementation
requirements for Package WAP 2.
In this package about 77 acres 17 ¾ guntas land has to be acquired, of this about 76 acre 06 ¾
guntas is dry land and 02 guntas plantation and 1 acre 09 guntas is kharab land. As a result of land
acquisition and related impacts 681 PAFs will lose part of their land; and another 298 PAFs lose their
house hold/commercial/ assets /livelihood . In addition, 156 community assets will also be affected. Out
of these impacts, 232 PAFs are in the major impact category losing their houses/shop and livelihood and
753 PAFs in the minor category who loses only part of their land or assets and the remaining land and
assets is sufficient to continue their shelter and livelihoods.
A baseline survey was conducted amongst the affected people which indicated that a large
majority of them are Hindus(77.72 percent), followed by Jains at 6.35 percent and Muslims at 3.81
percent. Distribution of PAPs by occupation indicates that 77.35 percent are in agriculture; agricultural
labourers account for 5.58 percent; commerce and trade supports 11.16 percent. In this package 69.17
percent of population has income less than Rs.26,000. 61.9 percent of the population falls within the age
group of 18-60, which happens to be the working age group. In this package illiterate population
accounts for 24.07 percent; those with primary education account for 11.19 percent and those with
secondary education account for 18.12 percent.
Public consultations were held at 4 important locations in this package in November 2008 and
November 2007 and 256 persons participated in these consultations. The consultations focused on mainly
in explaining the entitlements under the R&R Policy and measures taken to minimize the impacts and
receive the suggestions from participants. The consultations have helped in not only in disseminating the
policy provisions to deal with land acquisition related impacts, but also assisted in gathering suggestions
for mitigation of adverse impacts, improvements in designs and facilitating inputs for resettlements plan
preparation and implementation. During Consultations, a number of issues have been raised. One of the
main issues is the shifting of water pipelines in this package. This issue is under the process of being
resolved by the PIU; in another instance people have asked for over-bridges in all sensitive areas,
however such requests would have been considered if technically feasible; another issue of temples being
affected has been addressed by relocation if it is not possible to retain the temple; other cases where
people said that the affected house/land is under litigation and wanted to know how the project would
deal with it, such cases will be dealt on a case to case basis during implementation; other issues raised
were people wanted to know about the entitlements. Besides this, safety concerns have been addressed by
building footpaths in built up area, providing footpath barricades, school/village signages, rumble strips
and road humps.
The key potential issue is the shifting of the pipelines, which is being resolved by the PIU.
Besides there are realignments proposed to minimize impact, such as in Belagalli village. There are 6
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
2
cross section options adopted in this package to minimize impacts, the COI width varies from 11 m to 26
m.
The GOK has adopted the Resettlement and Rehabilitation (R&R) Policy for KSHIP- II
consistent with NRRP, 2007 and World Bank Policy on Involuntary Resettlement to address adverse
impacts arising out of this project. Land Acquisition will be done through the Karnataka Highways Act
1964. Land acquisition under this Act will help the PAPs to receive the market price/replacement cost of
land as compensation is negotiated through negotiations. Negotiation Committee has been constituted to
negotiate the price of land with the landlord. The minimum negotiated price will be twice the current
guidance value for Bagalkot and Belgaum districts.
Some of the entitlements include payment of compensation through negotiation according to the
Karnataka Highways Act, 1964; additional compensation for those becoming marginal farmers; grant for
replacement of cattle shed; alternative house or developed plot +construction cost for those losing house;
additional 25% compensation for partially affected structures towards reconstruction; support for
purchase of income generating assets; rental allowance for affected tenants; and support for non-title
holders to provide alternative houses or developed plot; construction cost; support for providing alternate
shop or income generating asset to those who are losing commercial structures; employees losing
livelihood will be given a onetime payment; vulnerable groups including physically challenged and those
above 60 years will be assisted to get Government pension, if they are eligible or given a lump sum
amount as assistance; and all community assets will be replaced and reconstructed.
This RIP will be implemented by Karnataka PWD-PIU Social Development Resettlement Cell
with support from the NGO - BIRDS (Bijapur Integrated Rural Development Society). The SDRC is
responsible for monitoring the implementation of all resettlement and rehabilitation activities, including
land acquisition. The Special Deputy Commissioner, Land Acquisition, will be responsible for land
acquisition activities while the Chief Administrative Officer will be responsible for all Resettlement and
Rehabilitation works. A Grievance Redressal Cell with 3 members is constituted with Deputy
Commissioner of the District as the Chairman. An independent agency viz., Samaj Vikas has been hired
for Monitoring and Evaluation support. The SDRC, PIU will facilitate land acquisition and compensation,
relocation and resettlement, distribution of assistance for the PAPs. WAP 2 will be implemented by
KHSIP Division, Belgaum. The SDO and SWIs appointed for the Belgaum division will take care of
R&R activities of this package.
The civil works for this package is likely to commence in December 2012. The R&R and land
acquisition is targeted to be completed by August 2012. Implementation activities include land
acquisition process, relocation and rehabilitation and monitoring. The budget estimated for land
acquisition and R&R activities for this package is Rs.13.41 Crores which forms a part of the overall
budget approved by the GoK. All cash allowances to be paid to the PAPs is adjusted for inflation for
2012-13 and those who receive the assistance beyond April 2013 will further be adjusted by 10% as
needed.
This RIP will be disclosed through public consultations, Government of Karnataka/PWD
Website. In addition, copies will be kept in: (i) State Government Library at Bangalore; (ii) - District
library of Belgaum and Bagalkot districts; and (iii) in the Panchayat offices along the project roads.
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
3
I INTRODUCTION
1. The Karnataka State Highways Improvement Project (KSHIP) – II Phase-I covers a length of 826.7
kms. In this connection a detailed Resettlement Action plan has been prepared in consultation with
the affected persons, PIU and other stakeholders. This document includes, among other things, legal
frame work and Resettlement Policy Provisions, Land acquisition and compensation payment, Social
impact assessment and base line Socio-Economic characteristic and the implementation arrangement.
The Government approved the Resettlement Action plan vide its order dated 28th July 2010. This has
been published in the PWD web sites in the month of August 2010. This Resettlement
Implementation Plan outlines the steps for resettlement and rehabilitation of PAFs/PAPs losing their
land and structures and relocation of community assets for WAP 2.
2. Contract package WAP 2 covers 108 kms consisting of 4 links. The details about the package are
given in Table 1.1. In the Annexure, the lists of those losing structures are provided, which are
enumerated in 2007-08 and verified by NGO in 2011. Details of those losing land are given in the
Notifications issued under Section 15 of the KHA. The list of vulnerable people will be subsequently
prepared and assistance extended as needed. Any additional people moved into the ROW after the
cut-off date and are not served notices subsequently will be identified through additional verification
by 31st July 2012. The question of extending assistance to them will be examined on case to case
basis. In case of those who are mobile type of shop will not be provided any assistance since, they
keep on changing on regular basis and they can easily find another alternative place to continue their
petty business provided after verification.
Table 1- 1: Package Details
Link Description Length Districts Taluks Cutoff date
19A Mudhol – Mahalingapura 19.17 Bagalakot Mudhol 30.10.2008
19B Mahalingapura – Kabbur 42.34
Bagalkot,
Belgaum
Mudhol, Raibagh,
Chikkodi
04.11.2008
19C Kabbur - Chikodi 18.41 Belgaum Chikkodi 14.11.2008
19D Chikodi - (NH-4 cross)
Nippani 28.01
Belgaum Chikkodi 06.12.2007
3. WAP 2 falls within the Northern Karnataka Plateau. Northern Karnataka Plateau comprises of the
districts of Belgaum and Bagalkot. It is largely composed of Deccan Trap. It represents &
monotonous treeless extensive plateau landscape with a general elevation of 300 to 600 meters from
the mean sea level. However the river plains of the Krishna, the Bhima, the Ghataprabha and the
Malaprabha with the intervening watersheds, the step like landscapes, lateritic scarpments, residual
hills and ridges break the monotony of this extensive plateau. The general slope is towards east and
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
4
this region is largely covered with rich black cotton soils (Expansive Soil). In this region, major crops
grown are Tobacco, Sugar cane, Jawar, Sunflower, Toor, Groundnut, Soya bean and maize
4. The entire package is regarded as a single milestone. All the R&R and land acquisition has to be
completed at the time of handing over of package to the contractor.
5. In this package 77 acres 17 ¼ guntas land has to be acquired, of this 76 acre 6 ¾ guntas is dry land
and 02 guntas is plantation land and 1 acre 09 guntas is kharab land; there are 298 PAFs whose house
hold/commercial structures/ assets/ livelihood is getting affected and 681 PAFs losing land;. There are
165 community assets getting affected. The PAPs listed in this RIP is as recorded during the cut-off
date and further verified by the NGOs.
6. There are no major issues related to land acquisition and resettlement identified in this package.
Objectives of RIP
7. The objective of this RIP is to provide a package specific guideline for implementation for R&R
activities. The implementation plan identifies the persons affected, the type of entitlements to be
provided for specific losses, what are the steps that will be adopted in getting compensation, details of
members of the Negotiation Committee and the GRC members in the package, time table and steps to
be taken by the PIU for protecting right ROW. Overall it provides how the RAP will be implemented
in this particular package.
Main activities of RIP
8. The main activities to be carried out in finalizing the RIP includes, Joint verification, distribution of
ID cards, identification of sites for relocation, identification of income generating options,
identification of vulnerable people who are not getting any assistance from Government, identification
of resettlement centers and vendor markets, negotiations for land acquisition, payment of
compensation, relocation and shifting of community assets. The members of the GRC and Negotiation
committees have to be identified and informed, as mentioned in the RIP. The RIP after finalization
will be disclosed
Table 1- 2: Summary Tables on Impacts
Link
Description LA Pvt Land
Transfer
Major Impact Minor
Impact
Community
Assets
19A Mudhol –
Mahalingapura
6.14 1/2 0.01 41 149 39
19B Mahalingapura –
Kabbur
42.39 1/4 0.23 1/2 75 367 65
19C Kabbur - Chikodi 4.22 - 29 48 26
19D Chikodi - (NH-4 cross)
Nippani
22.12 0.25 1/2 87 189 35
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
5
Minimization of Impacts and Corridor of Impact
9. There are 6 cross section options adopted in this package to minimize impacts. The COI width varies
from 11 m to 26m. Besides this, safety concerns have been addressed by building footpaths in built
up area, providing footpath barricades, school/village signages, rumble strips and road humps.
The different cross sections used are:
1. UR1A Rural Cross section with paved shoulders varying from 18-26 m
2. UR2 Rural Cross section through village width varying from 11m to 22m.
3. UR3 Urban Cross Section in built up area with covered drain with a maximum width of 22m
4. UR4 Urban Dual lane Cross section in built up area with covered drain with a maximum width of
24 m.
5. UR6 Rural Cross section in hilly terrain
6. UR7 Rural cross section cutting
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
6
II. LAND ACQUISITION AND RESETTLEMENT IMPACTS
10. This chapter provides an overview of the extent of land acquisition and the process of land price
negotiations and details of documents to be submitted. It also provides the impacts of the project on
community assets.
11. In this package 77 acres 17 ¼ guntas land has to be acquired, of this 76 acre 6 ¾ guntas is dry land, 2
guntas is plantation and 15 acres 1 acre 9 guntas is kharab land.. The details of the PAFs losing land is
given in Notification issued under section 15 of the KHA 1964 in connection with land acquisition.
There are 199 PAFs who are losing 5 guntas and more of agricultural land.
Land Acquisition Status
12. The Notifications under Section 15 under the KHA for WAP 2 is as follows:
1. 19 A: No. PWD :139: EAP : 2011, Bangalore, dated 19 .10.2011;
2. 19 B: No. PWD :140: EAP : 2011, Bangalore, dated 19 .10.2011;
3. 19 C : No. PWD :141: EAP : 2011, Bangalore, dated 19 .10.2011;
4. 19 D: No. PWD :142: EAP : 2011, Bangalore, dated 19 .10.2011
Guidance Value
13. The Guidance Value of land for different categories of land, for the villages along the project road is
given in Annexure 1 are as of July 2011. This guidance value will be referred to by the Negotiation
Committee.
14. The rates will be revised annually by 10% on the 1st of April every year, in case Government has
not revised it. The guidance value varies from a minimum of Rs. 40,000 per acre in Kothalli village
in Chikkodi Taluk to Rs 3,03,000 per acre in Nippani village in Nippani Taluk..
Negotiation Committee
15. The Replacement Cost of land for consent award will be determined by the Negotiation Committee.
In this package the Negotiation Committee has been constituted vide GO No. PWD 215 EAP 2007
dated 24-10-2009. This Committee consists the following members:
1. Assistant Commissioner of the concerned Sub Division : Chairman
2. Assistant Commissioner of KSHIP : Member Secretary
3. Executive Engineer KSHIP Division, : Member
4. Zilla Panchayat Member of the concerned jurisdiction : Member.
16. The details about the committee members will be updated by 30th June 2012.
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
7
Method of Price Negotiation
1. The concerned Land Acquisition officer who is the member secretary of the Negotiation
Committee will call for a meeting;
2. Dates for price negotiation will be given village wise. Negotiation will be conducted village wise
calling all the land losers together for negotiation. This is to ensure transparency.
3. The PIU will provide information on the guidance value of the land to land losers before
Negotiations.
4. The minimum negotiated price will be twice the current guidance value for Bagalkot and
Belgaum districts.
5. The Negotiation Committee will negotiate the price with the landlord;
6. Based on the decision of the Negotiation Committee the Special Land Acquisition Officer will
initiate action to collect documents after obtaining the approval of competent authority in the
PIU.
7. Compensation will be given within 30 days of receiving all the necessary documents by the
Special LA officer. In case of delay , 9% interest will be given to the beneficiary upto a period of
one year and after which, it will be increased to15% . (This is as per the provisions of the LA
Act).
8. On approval of the award by the Special DC or PD, the Special Land Acquisition Officer will
make the payments accordingly.
9. Possession of Land will be taken vide Section 19, which will be only after the payment of
compensation.
Records to be submitted by the Land Owners
17. As soon as Notification u/s 19 is issued, the NGO shall collect the following documents in respect of
lands to be acquired, before inviting for negotiations.
1. Original copy of RTC for current year;
2. Original or attested copy of mutation in respect of land and Khatha Certificate in respect of site /
building;
3. Encumbrance Certificate for 13 years;
4. No Tenancy Certificate and Certificate regarding 79A, 79B and 66;
5. Bank Account details;
6. Land holding / small / marginal farmers Certificate whenever necessary; and
7. G. Tree.
After negotiations, the NGO shall collect the remaining documents such as –
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
8
1. Attested copy of Sale Deed/Partition Deed/Saguvali Chit/Regrant Order etc., to prove title of
land;
2. Indemnity Bond;
3. Agreement and Affidavit
and submit them to the Assistant Commissioner for processing for compensation. Any fees incurred by
the NGO in obtaining the documents shall be reimbursed by the Executive Engineer of the Division
Failure of KHA and Appellate Committee
18. Even after the minimum negotiation price as per the RAP is offered and the land owner does not
agree for it, then the negotiation will be treated as failed and award will be passed as per the general
LA Act. The price offered and the price demanded by the land owner in such cases will be recorded
in the proceedings. The provisions of the LA amendment bill will be followed when they come into
force.
Valuation of assets on land under LA
19. The valuation of structures and other assets will be carried out by Government approved Valuators
appointed by the Executive Engineer in consultation with PIU. Valuation will be done on the basis
of current PWD Schedule of Rates, without depreciation. Based on the valuation, another 30% will
be given as top up to those who come forward for consent award. Trees will be valued by the
Agriculture/Horticulture/Forest Department.
Valuation of Crops
20. Crop loss will be compensated based on the valuation done by the Agriculture/Horticulture
Department.
Valuation of other structures/assets
21. The valuation of structures and other assets will be carried out as mentioned above. However, this
will be verified and approved by the concerned Executive Engineer.
Site Requirement for Residential and Commercial impacts
22. Actual requirement of sites in each package, has been indicated in the Joint Verification report of
NGO. In this package 13 sites are required for non - titleholders. Verification for titleholders is
under progress. As for as possible, Government land will be identified for formation of sites and
allotted to the eligible PAFs/PAPs. Where Government land is not available then the PIU, KSHIP
shall examine alternatives such as - cash in lieu of sites or purchase of private land - on case to case
basis, based on local factors.
Loss of Community Assets
23. In the contract package WAP 2, 165 community Assets getting affected.
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
9
Table 2- 1: Summary Table on Community Assets
Sl.
No. Type of Community Asset No
1. Temple/Shrines 30
2. Aralikatte 2
3. Bus Shelters 23
4. Hand Pumps 29
5. MWS/Water supply tanks 18
6. Borewells 17
7. Others 46
Total 165
24. All community assets on Government land will be shifted by PIU. All assets on private land will be
shifted with assistance of NGO.
25. For Temple/shrine, Aralikatte, new site has to be identified by NGO in coordination with
SDO/SWIs at the Divisional level. This site should be a Gramathana land or land given as donation.
For land that is donated the concerned Engineer has to take a site consent letter from the donor of
the site in prescribed format which will be prepared by NGO. The format will have Donor name and
address, Site details(Survey nos, place, boundary) with measurement, the signatures of atleast 3
persons from the village is necessary on the letter for evidence. The donor has to also sign on the
consent letter. The letter will be submitted to the Executive Engineer of the division. The EE will
then have to construct the new community structure/Temple/Shrine/ Aralikatte etc. After the
construction of the new structure the SDO/SWIs and NGO will jointly convince the concerned
village people to demolish the existing structure, and shift the activities to the new place.
26. Bus shelters, Hand pump, MWS tanks, Bore wells and other community assets will be relocated and
reconstructed. The KSHIP divisional staff will be taking necessary action with assistance of
SDO/SWIs. The chainage wise community assets details are given in Annexure 6.
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
10
III. BASELINE CENSUS SURVEYS AND CONSULTATIONS
Characteristics of displaced households
27. This chapter outlines the characteristics of displaced households. As a part of the project, a census
survey of Project Affected Families / Persons (PAFs and PAPs) was carried out in the month of
Dec.2007-Nov.2008. The findings of the census survey provided the magnitude of social impacts
on the PAFs and PAPs. In this chapter, baseline socio-economic analysis has been done separately
for the major impacted families.
28. Among religious groups, Hindus dominate with 77.72 percent followed by Jains at 6.35 percent and
Muslims at 3.81 percent. Distribution of PAPs by occupation indicates that 77.35 percent are in
agriculture; agricultural labourers account for 5.58 percent; commerce and trade supports 11.16
percent. In this package 69.17 percent of population has income less than Rs.26,000. 61.9 percent
of the population falls within the age group of 18-60, which happens to be the working age group.
In this package illiterate population accounts for 24.07; those with primary education account for
11.19 percent; those with secondary education account for 18.12 percent. Average land holding size
is 5.36 acres. A look at the ownership of household assets indicate 57.92 percent own televisions;
30.13 percent own 2/4 wheelers; 15.90 percent own cooking gas; while only 8.48 percent own
refrigerators. Some of the baseline parameters identified for those with major impacts are given in
the table below. The details of the PAPs losing structures are given in Annexure 2,3.4.and 5.
Table 3- 1: Baseline Socio Economic information - for Major impacts (232)
1. Losing total house 13
2. Average area 30.16 sq.m
3. % of houses electrified 2.15%
4. % of houses having water supply 0.11%
5. Average earning Rs. 39,811/-
6. % of earners 26.78%
7. % of PAPs earning less than Rs.26,000* 14.58%
8. Average land holding (A-G) 5.36 Acres
9. % of Farmers having less than 2.20 acres of holding 28.30%
10. % of PAPs in agriculture 2.03%
11. % of PAPs working as agriculture labour 1.24%
12. % of PAPs in the service sector 0.34%
13. % of PAPs in Commerce and Trade 25.31%
14. Loss of commercial structures 219
15. Type of commercial structure 1 Pucca 3.20%
2. Semi pucca 12.79%
3. Kutcha 84.02%
16. Average area of commercial structure 6.73 sqm
17. Type of shops affected (majority)
1. Pan/cigarette – 34.25%
2. Tea shop/hotel - 11.42%
3. Barber- 11.42%
18. Average monthly turnover of shops
1. Rs.13,000
19. Ownership of Household assets 1. Television - 51.29%
2. Refrigerator – 5.17%
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
11
3. Telephone – 16.38%
4. Cooking Gas – 20.26%
5. 2/4 wheeler - 11.64%
Note : * Rs.26,000 has been taken as the cut off for BPL
Major and Minor Impacts
29. The list of major and minor impacts for this package is given below.
Table 3- 2: Distribution of PAFs by Major and Minor Impacts for WAP 2
Sl.
No. Extent of Loss Owner Tenant Squatter Encroacher Total
Major Impact
1 Losing Total House 3 0 7 3 13
2 Losing Total Com. Struc. 2 0 213 4 219
3 Losing Total House and Com. Struc. 0 0 0 0 0
4 Tenants Losing Total Livelihood 0 0 0 0 0
Total Major Impact 5 0 220 7 232
Minor Impact
1 Losing only Part of House 1 0 5 36 42
2 Losing Part of Com. Struc. 1 0 11 12 24
3 Losing Part of House and Com.
Struc. 0 0 0 1
1
4 Partial Plot 0 0 0 0 0
5 Total Boundary Wall 0 0 0 0 0
6 Partial Boundary Wall 0 0 0 0 0
7 Total Cattle shed 4 0 0 1 5
8 Farmers 681 0 0 0 681
9 Others 0 0 0 0 0
Total Minor Impact 687 0 16 50 753
Total (Major & Minor Impacts) 692 0 236 57 985
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
12
Figure 1- 1: Distribution of PAFs for Package WAP2
Figure 1- 2: Distribution of PAFS by Major Impact for Package WAP 2
Vulnerable groups
30. Based on the Census survey, there are 1115 PAPs who come within the purview of vulnerable
group. The categories include 185 widows; 828 persons above the age of 60 and 102 persons with
disabilities. However this is only an enlistment of all persons coming under the vulnerable category.
Only after verification by the NGO it will be confirmed whether these people are vulnerable. If so it
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
13
will be verified further whether they are already receiving pension / assistance from the
Government. If the person is already receiving pension / assistance, then this offer will not be
extended. Only after such verification will the person be entitled to assistance under this category. li
Consultations
31. Four consultations were carried out in this package. The outcome of the consultation are
summarized below
Table 3- 3: Consultation Summary
Section Details Issued Raised Response of project Authority
19A Date: 21.11.2008
Place: Ranna
Belagali
No. of
Participants: 53
People wanted to know the road formation
width in village limit and outside.
People wanted to know whether equal widening
is possible within village limits
People asked to construct over bridge in
school, hospital and religious sensitive places.
It was also informed that about 23000 meters of
panchayat water supply pipeline will get
affected. The people wanted to know who will
take responsibility to shift the pipeline
People losing their commercial structure
wanted to know what assistance will be given
by the project
A likely affected Tenant wanted know what is
the provisions making in the project for tenants
BPL squatter losing their house asked for
alternative site and construction cost of the
house from the project.
People wanted to know what provisions are
there for community assets getting affected.
There were two temples which the people did
not want the project to affect. The
Mahalingeshwara temple and Mallikarjuna
temple Mahadwara in belagali village
It was informed that outside the village limit
11 mt. from the existing center line and within
village limit 8 mt. from the existing center
line, and also informed that the proposed road
design have prepared on the basis of field
condition.
It was explained that if existing road was
straight it will take both side equally from the
center, in the curve situation as per availability
of width will considered.
It was informed that all type of public utilities
including water supply pipeline will be
shifting by project authority before execution
of civil work
It was informed that the project will provide
10x15” commercial site for each BPL
commercial squatter PAF accordingly project
policy. If more than 20 BPL commercial
squatter PAF’s are going to affect within 2 km
project authority will construct commercial
complex and allotted the rooms for them.
It was informed that if any legal tenant is
going to be affected in this project those who
will be getting three month rental allowance
which is determined by project policy .
It was explained that all the residential BPL
squatters will be getting EWS houses and
shifting and subsistence allowance from the
project
As for as possible we try to retain the temple
and other community assets as it is, in case it
is not able to save that assets panchayat people
would identify the alternative land/site outside
of COI in your village limit, after that project
authority will construct better Temple and all
the community assets .
19 B Date: 21.11.2008
Place:
He wanted to know the PWD road boundary
and new road formation width in village limit
and outside
It was informed that according to Karnataka
State highway Gazette PWD boundary is in
village limit is total 30 mt. and outside the
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
14
Section Details Issued Raised Response of project Authority
Kankanawadi
No. of
Participants: 58
He was asked if owner structure is getting
affected how to fix the compensation rate.
He is losing his commercial shop. He asked
after getting the assistance from the project,
whether he can shift to remaining PWD land or
out ROW
He asked if any private trees will getting
affected weather project will compensate or
not.
She is losing her residential house and she
asked alternative site and house as
compensation.
He is a Tenant PAP, he wanted know what the
provisions in the project are for tenants.
What to do when the Temple, Community
assets are affected in the village? And he asked
to people to give cooperation to project
implement officials.
village limit total 45 mt. The new road
formation width is outside the village limit 11
mt. from the existing center line (Total
22mtr)and within village limit 8 mt. from the
existing center line(Total 16 mt.), and also
informed that the proposed road design have
prepared on the basis of field condition
It was explained that if any owner structure
will getting affected in this project authority
will make valuation as per current PWD SR
rate for structure, and site cost valued by
project price fixation committee negotiation on
basis of local sub-registrar guidance value
It was informed that if he receives assistance
then he should shift out of ROW.
It was informed that any type private trees will
affecting by project compensation would be
given accordingly agriculture department
valuation.
It was informed that project authority will give
EWS house for BPL residential squatters
It was informed that if any legal tenant is
going to be affected in this project those who
will be getting three month rental allowance
which is determined by project policy .
As for as possible we try to retain the temple
and other community assets as it is, in case it
is not able to save the assets panchayat people
would identify the alternative land/site
outside of COI within village limit, after that
project authority will construct the affected
Temple and any other affected community
assets.
19 C Date: 21.11.2008
Place:
Nagaramunnoli
No. of
Participants: 32
He asked if panchayat water supply pipeline will
getting affected, who will take responsible to shift
the pipeline
He is losing his commercial shop. He asked what
type compensation will be paid by project.
He is losing his commercial shop. He asked more
compensation because no site will not available for
20.000 Rs in their village
He asked if any private trees will getting affected
weather project will compensate or not?
It was informed that all type of public utilities
including water supply pipeline will be
shifting by project authority before execution
of civil work.
The project will provide alternate IGA or a
shop
It was informed that this matter will bring to
notice to higher authority after that they will
take decision
It was informed that any type private trees will
affecting by project compensation would be
given accordingly agriculture department
valuation
It was informed that if any legal tenant is
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
15
Section Details Issued Raised Response of project Authority
He is a Tenant PAP, he wanted know what the
provisions in the project for tenants.
What to do when the Temple, Community assets are
affected in the village? He demanded upto 50.000 Rs
for commercial site purchase for commercial
squatters .And he asked to people to give
cooperation to project implement officials
going to be affected in this project those who
will be getting three month rental allowance
which is determined by project policy
As for as possible we try to retain the temple
and other community assets as it is, in case it
is not able to save that assets panchayat people
would identify the alternative land/site outside
of COI in your village limit, after that project
authority will construct better Temple and all
the community assets . More assistance for
commercial squatters matter will be reported
to higher authority for consideration.
19D Date: 19.12.2007
Place: Pattankudi
No. of
Participants: 113
People asked for proper compensation and also
wanted to know the mode of compensation.
People wanted to know the road cross sections
and how compensation would be paid.
A Handicapped person losing her shop wanted
to know what additional assistance would be
provided to her.
In Nippani Town the people requested the COI
to be reduced to 9 mts on either side of the
centre line.
An affected person had just taken a loan to
build his house, which is likely to get affected.
He wanted to know how he would be
compensated.
Another point raised was a person losing his
agriculture land; his land is under dispute and
the matter is pending in court; he wanted to
know how the project would compensate him.
Another affected person losing open land
wanted to know whether the project would give
another site as compensation.
The project will pay compensation for
agricultural land according to KHA. Structure compensation will be according to the current
PWD SR. Assistance for squatters will be
according to the Project Policy.
Handicapped persons will be provided
assistance according to Project Policy and
RAP.
The cross section at Nippani will be looked
into.
If a person’s house has been affected by the
project he will get compensation according to
the project policy .
For cases pending with the court , the matter
will be looked onto on case to case basis
during implementation and will be taken up
with the DCs office.
It was explained the project did not have an
option of land for land. But compensation will
be paid for any land acquired by the project.
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
16
IV. IMPLEMENTATION MECHANISMS
Institutional Arrangements
32. This chapter outlines the implementation mechanism specifically for this package, including the
tasks of the NGO and the GRC. It also outlines the assistance to be paid to affected persons and
provides the tasks to be completed before the start of civil works.
33. The SDRC, PIU will facilitate land acquisition and compensation, relocation and resettlement,
distribution of assistance for the PAPs. The SDRC is responsible for monitoring the implementation
of all resettlement and rehabilitation activities, including land acquisition. WAP 2 will be
implemented by KSHIP Division, Belgaum. The SDO and SWI appointed for the Belgaum division
will take care of R&R activities of this package. The SDRC will be supported by the NGO for
implementation of RAP.
Extending R & R Assistance to PAPs.
34. R& R assistance will be disbursed according to the R&R Policy. The NGO will verify the PAPs and
ensure that they get the assistance in accordance with their entitlements. The entitlements given
here are accurate as far as possible, however, because only preliminary notification for land losers
has been given at this stage, the exact details about entitlements need to be updated at the time of
paying R&R assistance. The cash allowances are updated for 2012-13 and will be further adjusted
as needed for 2013-14 and beyond. The exact number of disbursements made for each year will be
computed after all assistance is given. The annually revised amounts are mentioned in the
Implementation Manual.
35. Table 4- 1: R& R Assistance Entitlement
Category
Category of loss Entitlement
1a 681 PAF losing
land Negotiation as per Karnataka State Highway Act, 1964;
Amount equivalent to current stamp duty and registration charges
on compensation amount;
**Additional 25% compensation in case remaining land is severed;
Crop/tree damage compensation as assessed by concerned
Departments;
*In case land owners becomes landless or marginal families, the
following additional entitlements will be offered: (a) subsistence
allowance of Rs.36,300 for land less and marginal; and, (b)
assistance for creating Income generation asset valued upto
Rs.90,750 for those becoming marginal farmers and landless only;
Additional amount of Rs.24,2001 will be restricted to those who
loose narrow stretch of land as additional compensation in lieu of
all other benefits. Additional amount of Rs 24,200 to those who
1 Narrow stretch of land is defined as persons losing upto 5 guntas of land.
*These entitlements will be applicable only when the farmers submit the landholding/ marginal farmer document,
and if found applicable.
** This will be verified after Section. 19.
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
17
Entitlement
Category
Category of loss Entitlement
lose more than a narrow stretch and are not eligible for any other
additional benefits.
*For those becoming landless and all marginal farmers training
assistance will be provided for income generating vocational
training and skill upgradation options as per affected persons choice
;
Employment opportunity for affected persons as per his skills and
availability of suitable work in road construction work.
Ib 3owners losing total
residential structure
Compensation at current PWD scheduled rates without
depreciation and 30% solatium
Alternative houses in resettlement colony or developed plot2 and
construction cost of Rs. 60,000 linked to construction progress.
Shifting assistance of Rs. 12,100
Subsistence allowance of Rs. 36,300
1b 1owner1 losing
partial residential
structures
Compensation at current PWD scheduled rates without
depreciation and 30% solatium
Additional 25% compensation for partially affected structures
towards reconstruction
Ic 2 owners losing
commercial
structure
Compensation at current PWD scheduled rates without
depreciation and 30% solatium
Alternative shop or assistance for income generation asset valuated
upto Rs. 90,750
Shifting assistance of Rs. 12,100
Subsistence allowance of Rs. 36,300
1c 1owner PAFs
losing partial
commercial
Compensation at current PWD scheduled rates without
depreciation and 30% solatium
Additional 25% compensation for partially affected structures
towards reconstruction
1a 4 owners losing
cattle shed
A grant of Rs. 15,000 for replacement of Cattle shed;
IIIa 7 Squatter s losing
residential
structure
House in resettlement colony or developed plot and construction
cost of Rs. 60,000 linked to construction progress.
Subsistence allowance of Rs.15,000;
Shifting Allowance of Rs.5000.
IIIb 213 Squatter losing
commercial
structures
Alternative shop of 100 sq.ft or assistance for income generation
asset value upto Rs. 36,300;
Subsistence allowance of Rs.18,150
Shifting Allowance of Rs. 6,050
1encroacher losing
cattle shed A grant of Rs. 15,000 for replacement of Cattle shed;
16 Squatter losing
partial assets This needs to be further verified
IIIc 57 encroachers Replacement cost of affected structure calculated at current PWD
scheduled rates without depreciation
2 Developed plot will be restricted to those who do not have any homestead land.
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
18
Implementation support by NGOs
36. The work of the NGO will include consultations and counseling of PAPs, encouraging PAPs for
productive utilization of compensation and rehabilitation grants, facilitating PAP access to income
generating assets, increasing the social acceptability, ensuring effectiveness of training programs
organized for PAPs electing participation in self employment schemes etc.
37. The NGO will work as a link between the PIU - SDR Cell and the affected community. For this
section the NGO is: BIRDS (Bijapur Integrated Rural Development Society). The division office of
this NGO is located in Dharwad. They will educate the PAPs on the need to implement the Project,
on aspects relating to LA and R&R measures and ensure proper utilization of various compensations
extended to the PAPs under the R&R entitlement package. The tasks of the NGO will be to facilitate
the resettlement process. The responsibilities of the NGOs include
1. Identification, verification and updating of PAP Census, includes verification of properties of
PAPs and estimation of their type and level of losses;
2. Educate PAPs on their rights, entitlements, and obligations under the RAP; Assist the PAPs to
identify suitable alternate land for resettlement purposes;
3. Preparation and Distribution of Entitlement cum Identity Card. All eligible project affected
families will be issued Identity Cards, giving details of the type of losses and type of entitlements.
4. Ensure that PAPs receive their full entitlements; Where options are available, the NGO will
provide advice to PAPs on benefits of each option; Ensure proper utilization by the PAPs of
various compensations available under the R&R package; Assist the PAPs in getting benefits
from various government development programs;
5. Rehabilitation of Affected Families and restoration of Income and Livelihood. The NGO will
help the communities derive maximum benefits out of the project without losing their livelihoods
and the least impact on socio-cultural aspects of their lives.
6. Assist PAPs on grievance redressal through the established system; and
7. Will relocate PAPs. Assist PIU in making arrangements for the smooth relocation of the PAPs;
No Physical relocation from agriculture land, residential units, commercial establishments or
other immovable properties will begin before alternate arrangements are made.
8. Any other responsibility that may be assigned by the PIU for the welfare of the affected
communities.
38. In order to carry out the above tasks, NGO staff will be stationed in the site office at Nippani.
Besides contacting the PAPs on an individual basis to regularly update the baseline information,
group meetings and village-level meetings will be conducted by the support agency on a regular
basis. The frequencies of such meetings will depend on the requirements of the PAPs but should
occur at least once a month. The support agency will have to encourage participation of individual
APs in such meeting by discussing their problems regarding LA, R&R and other aspects relating to
their socio-economic lives. Such participation will make it easier to find a solution acceptable to all
involved.
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
19
IR Activities
39. There are two types of IR activities, i.e. short term and long term. Process of identifying income
generating options for those losing commercial structures is under progress.
40. Short Term IR activities: Short-term IR activities mean restoring APs’ income during periods
immediately before and after relocation. For this, the NGO shall ensure that: compensation and
R&R assistance as provided in the entitlement matrix such as subsistence allowance and shifting
allowance are provided to the PAPs. Other works of the NGO include facilitating employment to the
PAPs in the project construction activities, depending on their skill and other allied activities.
41. Long Term IR Activities: This includes provision of shops for those losing their total livelihood to
re-establish their commercial activities. It also includes providing of a shop plot in a commercial
block or purchase of income generating assets upto Rs.36,300 in case of commercial squatters.
42. The steps to be followed for income restoration include:
Step 1: Identification of Target Groups – NGOs need to identify the affected persons;
Step 2: Identification of IR Activities - Prepare a list of possible and feasible income restoration
options. While identifying IR options, the following factors shall also be considered: (i) Education
level of APs; (ii) Skill possession;(iii)Likely economic activities in the post displacement period;
(iii) Extent of land left; (iii) Suitability of economic activity to supplement the income; (iv)Market
potential and marketing facilities. Based on socio-economic characteristics and options preferred by
APs, the NGO may have to re-assign trades to PAPs. Options include (i) petty trade (iii) skill
related schemes and loans for pumps, bore wells, bullock carts etc to increase productivity. The
NGO will assist PAPs in identifying appropriate alternative economic rehabilitation schemes
through counseling and consultation.
Step 3: Training: Option for training for skill enhancement for those losing their livelihood has been
provided in the Entitlement Matrix for owners losing commercial structure and employees losing
their livelihood.
Step 4: Identification of Trainers / Training Institutes: Based on trades selected, NGO shall have to
identify master trainer and/or training institute for different trades / activities who can provide on the
job training.
Step 5: Training Arrangement: NGO shall make different groups of PAPs as per trades selected and
make all the arrangements such as fixing the venue etc.
Step 6: Monitoring of APs: After training the NGO shall monitor the PAPs in order to take mid-term
correction measures, if required.
Monitoring and Evaluation support for RAP
43. An external monitoring and evaluation agency, Samaj Vikas, has been appointed to concurrently
monitor and evaluate R&R activities on periodical basis with NGOs. The role of such an agency will
facilitate process of R&R and thus provide support in the proper implementation of rehabilitation
programmes. And the M&E Consultant will ensure and certify that the stretch is free from all
encumbrances related R&R measures, at every stage prior to issue of bids, prior to signing
concession agreement, prior to appointed date and prior to hand over of the second Milestone
stretches to the developer. The end evaluation will be carried out through independent consultants
not associated with the implementation as to how the R&R objectives are realized and the changes
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
20
in the living conditions of the PAPs which will be compared with the baseline data on key impact
indicators related to income, occupation, assets, housing conditions, land ownership pattern, etc.
Grievance Redressal mechanism
44. The project will establish a Grievance Redressal process with district-level committees. The
following persons constitute the District Level Grievance Redressal Cell :
1. Deputy Commissioner of the District – Chairman
2. Academician ( to be selected by the DC) – Member
3. Representative from PAPs (to be selected by the DC) – Member
4. Divisional EE – Convener
The members of the GRC to be selected by the DC and representatives from the PAPs are under
progress and will be completed by 30th June 2012.
45. The main functions of the GRC will be:
a. to provide support to PAPs on problems arising out of eligibility for RAP-provided
entitlements and assistance provided;
b. to record the grievances of the PAPs, and categorize, prioritize and solve them within one
month;
c. to inform PIU of serious cases within one week; and
d. to report to the aggrieved parties about the developments regarding their grievance and
decisions of the PIU, within one month.
46. The Grievance Committees will meet regularly during implementation of the RAP, at least once a
month. The committees will suggest corrective measures at the field level itself and fix
responsibilities for implementation of its decisions. However the NGOs will form the first level of
intervention in resolving PAP related grievances and attempt to motivate the PAP to facilitate
implementation of the R&R program. Details regarding registering complaints, response times,
communication modes, and mechanisms for appeal or approaching civil courts if other provisions
fail are:
1. At the first level intervention the NGO will attempt to resolve the grievance;
2. Next the CAO will attempt to address land related grievance and the ADSW will address the non-
land related grievances;
3. The third step will be to approach the Grievance Redressal Committee;
4. Next the PAP can approach the Regional Commissioner who is the Appellate Authority.
5. If all the above fails, the PAPs can approach the court.
It is the responsibility of the SDRC/NGO to inform the affected person’s decisions of the GRC to
make it effective.
Resettlement Colonies and Vendor Markets
47. In this package there is no requirement for resettlement colony, as more than 20 families are not
losing their residential structure in this stretch.
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
21
Protection of RoW
48. Section 5 of the KHA mentions the Highway Authority will exercise power and discharge duties in
accordance with provisions of the KHA for restriction of ribbon development along the highways
and for prevention and removal of encroachments. The Highway Authority under Section 7 has
power to fix boundary of building and control lines of highways. Section 21 mentions prevention of
unauthorized occupation of highway. Thus the onus of protecting the COI/RoW lies with the Project
Authority. Once the COI/Row has been identified and frozen, the COI/RoW has to be clearly
marked with boundary stones.
49. Any new encroachment into the area will be monitored by the concerned KSHIP Division from the
time the cut-off date is established and the baseline surveys are completed. The Divisional Engineers
shall visit the project roads periodically, at least once in three months, in order to ensure that no new
encroachments take place and submit quarterly reports in this regard. Any additional encroachments
noticed through periodical visits will be issued notices and their shifting will be done immediately.
To avoid future encroachments, it is proposed to construct drains at the edge of ROW and ROW
stones will also be laid.
50. The NGOs shall take photographs of the affected structures at the time of joint verification and also
after their shifting / demolition of the affected portion and prepare documentation of structures.
51. Those Non-titleholders already identified by the project will be issued Identity Cards by the PIU. All
new encroachers / squatters not present during the time of survey, will have to be verified by the
NGO/PIU. All squatter and encroachers have to be shifted from out of the COI and RoW. Those who
remain in the Row will not be eligible to entitlements.
Impacts on Municipal Towns
52. Verification for non - titleholders has already been completed on this package. All the persons
identified at the time of survey and verified by the NGOs at the time of joint verification but
subsequently shifted by the Municipalities will be extended assistance as per the RAP.
53. KSHIP shall address all the Municipalities in the Project Roads informing them of the Rehabilitation
and Resettlement Policy of the Government under KSHIP-II and the details of persons identified as
Project Affected Persons in their jurisdiction. If the Municipality wants to shift any of them for their
development works, they may do so after providing them assistance as per the R&R Policy of the
Government or inform the details of such persons to KSHIP for extending assistance under the project
54. In this package the project road passes through the Municipality areas of Mudhol and Chikkodi .
These Municipalities will be addressed informing them of the Rehabilitation and Resettlement policy
of Government under KSHIP-II project and the details of the persons identified as ‘Project Affected
Persons’ in their respective jurisdiction. In case the Municipalities desire to shift any of the Project
Affected Person on account of development work, they may do so after providing assistance to them
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
22
as per the R&R Policy of Government or to inform the details of such displaced persons to KSHIP for
extending assistance to them under the project.
Data Base Management
55. The database generated will be used for tracking progress of this package by PIU. The data in the HQ
will be updated based on the information sent by the division office. PIU will be responsible for
tracking payments, generation of ID cards etc through the Data Base Management Consultants. The
socio-economic data for all PAPs are recorded in the Data Base and will be used for monitoring and
impact evaluation and other purposes.
Compensation and R&R assistance payment:
56. All the compensation and R&R assistance will be directly credited to the individual Bank A/cs. The
deduction of income tax is not applicable for receipt of compensation. The NGO will assist in
opening of the Bank A/cs and the details of payments will be recorded in the individual identification
cards and Pass Books. In case where the house/shop plots are allotted, the titles to those will be
provided in the joint name of wife and husband.
Co –ordination between R&R and Civil works
57. The resettlement programme will be co-coordinated with the timing of civil works. The Civil works
for this package is expected to start in December 2012. R&R and land acquisition is estimated to be
completed by August 2012. Under the Annuity Packages all land has to be handed over at one stage.
This will be after issue of Notification under Section 19 of KHA. The timeline for key activities is
given below.
58. The implementation of RIP will be performed in coordination with the procurement process and civil
works. The key mile stone in the process includes: issue of bids, singing of concession agreement,
appointed date and handing over of second mile stone stretches within 3 month of appointed date. The
various land acquisition and resettlement implementation actions to be completed prior to those mile
stones are listed below with respective target dates. The completion of these actions will be certified
through certification and confirmation by the M&E consultants.
Table 4- 2: Time line for Key LA and R & R Activities
Tasks Target Date Prior to Event
I Land Acquisition
Land Acquisition Plans
Section 15 Notification (first
notification)
November, 2011 Issue of bids
Section 27 (negotiation ) August, 2012 Signing of concession
agreement
Section 28(award declaration)
Notification
September, 2012 Appointed Date
Section 19 Possession of land December, 2012 Appointed Date
Section 39 (compensation offer and November 2012 Appointed Date
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
23
payment )
Transfer/ No objection received for
Government land
December 2012 Appointed Date
II R&R Implementation activities
PIU Approval and Disclosure of
RIP
Mid June 2012 Issue of bids
Completion of additional joint
verification for identification of
additional PAPs
June 2012 Signing concession
agreement
Issue of ID cards May 2012 Issue of bids
Constitution of GRCs June 2012 Signing concession
agreement
Completion of structure valuation June, 2012 Signing of concession
agreement
Relocation of Community assets
completed
November, 2012 Appointed Date
Identification of alternative sites
and options
October , 2012 Signing Concession
agreement
Disbursement of assistance October, 2012 Appointed Date
Completion of allotment of
developed Sites and first
installment of construction grant
November, 2012 Appointed Date
III Resettlement
Relocation of PAPs March , 2013 Handing over second mile
stone stretches
Handing over of CPRs to
community
November,2012/March, 2013 Appointed Date/Second
miler stone stretches
Certification by M&E consultants
for site readiness
As needed
Prior to each event
Joint inspection of site: Prior to appointed date, representatives of KSHIP and developer will be
undertaken a joint site visit to ascertain the encumbrance free site on the ground and record any
encumbrance noticed and accordingly a time frame for mitigating those encumbrances within the agreed
time frame and accordingly measures will be taken to mitigation encumbrances.
Monitoring and R&R activities:
59. The R&R Monitoring indictors for physical progress are given in the table below.
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
24
Table 4- 3: Monitoring Indicators for Physical Progress
Sl. No Monitoring Indicators for
Physical Progress
Implementa
tion Target
Nos
Revised
Implementati
on Target
Progress
This
Month
Cumulati
ve
Progress
% against
Revised
Implementati
on Target
1 Land Acquired- private
76 Acres 07
¾ guntas
2 Land transferred –
Government 1.10
3 PAFs paid compensation for
land 681
4 Construction cost for
residential owners 1
5 Construction cost for
residential squatters 1
6 Construction shop/ or IGA for
Owners 1
7 Alternative plot or IGA for
Commercial squatter 213
8 Subsistence allowance for
squatters 220
9 Shifting allowance for
squatters 220
10 Community Assets 165
Additional Impacts
60. Any additional impacts identified during the implementation will be considered in
accordance with RAP and the project entitlement matrix given therein. Any observation on
additional impacts will be forwarded by the Division to the PIU. The NGO will follow up
the matter in the field. A note will be prepared for the concurrence of the CPO.
Budget
61. The budget for land acquisition and R&R activities for this package is Rs.13.41 crores which forms a
part of the overall budget approved by the GoK. The details of the budget have been given in the
RAP. Any additional budget need, will be obtained through additional approvals.
Table 4- 4: Budget
Sl. No Category Total (INR)
1. Land Acquisition 75290000
2. Alternative site cost 12400000
3. Structure cost 3356101
4. R&R assistance 43070000
WEP 2 total 1,34,11,6101
.
Disclosure
62. The RIP will be disclosed on the KSHIP website and the document will be available in PIU HQ and
the respective PIU division office at Belgaum, and Taluk offices of Mudhol and Chikkodi . General
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
25
Consultations will also be done for the package and documented and recorded. As part of disclosure
of RIP, public consultations will be held at important, locations to explain the contents of the RIP and
make them understand the process of implementation of RAP and also information about whether the
document and the list of PAPs will be available for their information. The details of grievance redress
process will also be explained. In addition, the periodical progress reports and other studies carried
out in relation to R&R will also be disclosed in the website.
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
26
Annexure 1: Guidance Value as on July 2011
Table 4- 5: Guidance Value for Link 19A
Sl.
No. District Taluk
Village
Name
Dry Land Wet Land
Minimu
m
Maximu
m
Minimu
m
Maximu
m
1 Bagalkot Mudhol Mudhol 131500 149000 213000 244500
2 Bagalkot Mudhol Malali 74000 83000 146000 171500
3 Bagalkot Mudhol Mughalkhod 70500 83000 137000 170500
4 Bagalkot Mudhol Belagali 67000 76000 139500 175000
5 Bagalkot Mudhol Mahalingapur 126000 149000 205500 256500
Table 4- 6: Guidance Value for Link 19B
Sl.
No. District Taluk
Village
Name
Dry Land Wet Land
Minimum Maximum Minimum Maximum
1 Bagalkot Mudhol Bisanala 63500 70500 134500 170500
2 Bagalkot Mudhol Saidapura 115500 135000 190500 231000
3 Bagalkot Mudhol P.D Budni 129500 149000 223500 256500
4 Bagalkot Mudhol Kesarakoppa 65500 70000 137000 168000
5 Belgaum Raibagh Kappalaguddi 77000 87000 192000 225000
6 Belgaum Gokak Hallura 60500 72600 176000
7 Belgaum Gokak Mudalagi 72600 96200 193600
8 Belgaum Raibagh Kankanawadi 89000 98000 192000 225000
9 Belgaum Raibagh Jodahatti 57000 63000 94000 108000
10 Belgaum Raibagh Bendavada 64000 71000 87000 108000
11 Belgaum Raibagh Nippanala 77000 87000 174000 197000
12 Belgaum Chikkodi Kabbura 41000 59000 114000
13 Belgaum Raibagh Mantura 60000 69000 108000 123000
Table 4- 7: Guidance Value for Link 19C
Sl.
No. District Taluk
Village
Name
Dry Land Wet Land
Minimum Maximum Minimum Maximum
1 Belgaum Chikkodi Kabbura 41000 59000 114000
2 Belgaum Chikkodi Umrani 43000 60000 118000
3 Belgaum Chikkodi Itanala 53000 90000 151000
4 Belgaum Chikkodi Belakoda Away from Village
5 Belgaum Chikkodi Chikkodi 87000 130000 217000
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
27
Table 4-8: Guidance Value for Link 19D
Sl.
No. District Taluk
Village
Name
Dry Land Wet Land
Minimum Maximum Minimum Maximum
1 Belgaum Chikkodi Chikkodi 87000 130000 217000
2 Belgaum Nippani Pattankudi 92000 140000 235000
3 Belgaum Chikkodi Chinchani 89000 133000 222000
4 Belgaum Chikkodi Kothalli 40000 60000 118000
5 Belgaum Nippani Kutali 69000 101000 212000
6 Belgaum Chikkodi Navalihala 46000 90000 154000
7 Belgaum Nippani Nippani 152000 227000 303000
8 Belgaum Nippani Kodani 67000 92000 193000
9 Belgaum Chikkodi Peerawadi 33000 55000 121000
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
28
Annexure 2: Details of PAFs in link 19A
Table 4- 93: PAFs Structure details of link 19A
Sl.
No. Chainage Side Village Name
Occu.
Status Loss Type
1 2.660 RHS Soragav Parashurama S/o
Sadashiva Squatter Residential
2 10.615 RHS Mugalakhoda Somappa S/o
Ningappa Squatter Commercial
3 10.645 RHS Mugalakhoda Raju S/o Hasansab Squatter Residential/Commer
cial
4 13.240 LHS Belagali Thimmanna S/o
Tukarama Encroacher Commercial
5 13.280 LHS Belagali Vijay Kumar S/o
Tukarama Encroacher Residential
6 13.325 LHS Belagali Sadashiva S/o
Siddappa Nagarala Encroacher Residential
7 13.510 LHS Belagali Eshwarappa S/o
Bheemappa Encroacher Residential
8 14.477 LHS Ranna
Belagali
Yamanavva W/o
Maruthi Squatter Residential
9 14.505 RHS Ranna
Belagali
Paramanna S/o
Hanumantha Squatter Commercial
10 14.510 LHS Ranna
Belagali
Srimantha S/o
Nagappa Squatter Commercial
11 14.510 RHS Ranna
Belagali
Kallavva W/o
Lachumappa Squatter Commercial
12 14.530 LHS Ranna
Belagali
Dasthagirsab S/o
Allasab Squatter Commercial
13 14.543 RHS Ranna
Belagali
Dattathreya S/o
Baburao Squatter Commercial
14 14.644 RHS Ranna
Belagali
Mahalingappa S/o
Siddaramappa
Malkod
Encroacher Residential
15 14.720 RHS Ranna
Belagali
Siddappa S/o
Ramappa Konnura Encroacher Residential
16 14.725 LHS Ranna
Belagali Prakasha S/o Revappa Encroacher Commercial
17 14.727 LHS Ranna
Belagali
Channaparappa S/o
Rudrappa Mandi Squatter Commercial
18 14.729 LHS Ranna
Belagali
Santhosha S/o
Jakkappa Squatter Commercial
19 14.730 RHS Ranna
Belagali
Mahadeva S/o
Shivappa Squatter Commercial
20 14.731 LHS Ranna
Belagali
Mahalingeshwara
Temple Trust Encroacher Commercial
21 14.734 LHS Ranna
Belagali
Mahalingeshwara
Temple Trust Encroacher Commercial
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
29
Sl.
No. Chainage Side Village Name
Occu.
Status Loss Type
22 14.738 LHS Ranna
Belagali
Mahalingeshwara
Temple Trust Encroacher Commercial
23 14.745 RHS Ranna
Belagali
Mahalingappa S/o
Channappa Pujari Encroacher Residential
24 14.747 RHS Ranna
Belagali
Shivaiah S/o Basaiah
Matigudda Squatter Commercial
25 14.749 RHS Ranna
Belagali Mallappa Guravva Squatter Commercial
26 14.770 LHS Ranna
Belagali
Shivaputrappa S/o
Virupakshappa
Konnur
Squatter Commercial
27 14.795 LHS Ranna
Belagali
Dundaiah S/o
Gangaiah Squatter Commercial
28 14.800 RHS Ranna
Belagali
Mahadeva S/o
Balappa Jagadala Squatter Commercial
29 14.830 LHS Ranna
Belagali
Hanumantha S/o
Basappa Lokapura Squatter Commercial
30 14.834 RHS Ranna
Belagali
Sadashiva S/o
Mallappa Squatter Commercial
31 14.836 RHS Ranna
Belagali
Basappa S/o
Fakirappa Squatter Commercial
32 14.845 LHS Ranna
Belagali
Bheemappa S/o
Mallappa Squatter Commercial
33 17.093 LHS Mahalingapura Subhadra W/o
Mahalingappa Squatter Commercial
34 18.015 LHS Mahalingapura Mallappa Squatter Commercial
35 18.105 RHS Mahalingapura Shivananda S/o
Channa Basappa Squatter Commercial
36 18.108 RHS Mahalingapura Rachaiah S/o
Mallaiah Shiromata Squatter Commercial
37 18.125 LHS Mahalingapura Dasthagir S/o
Mohammad Squatter Commercial
38 18.160 RHS Mahalingapura Mahalingappa S/o
Gurulingappa Squatter Commercial
39 18.232 LHS Mahalingapura Noorandappa S/o
Veerabhadrappa Squatter Commercial
40 18.237 LHS Mahalingapura Smt Shankramma
Umesha S/o Matagi Squatter Commercial
41 18.392 RHS Mahalingapura Husainbee W/o
Janglisab Squatter Residential
42 18.423 RHS Mahalingapura Manjunatha S/o
Balakrishnappa Squatter Commercial
43 18.426 RHS Mahalingapura Mahadeva S/o
Girimallappa Squatter Commercial
44 18.493 LHS Mahalingapura Prakash S/o
Yamanappa Encroacher Commercial
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
30
Sl.
No. Chainage Side Village Name
Occu.
Status Loss Type
45 18.497 LHS Mahalingapura Prakash S/o
Yamanappa Encroacher Commercial
46 18.500 LHS Mahalingapura Prakash S/o
Yamanappa Encroacher Commercial
47 18.535 LHS Mahalingapura Jamal S/o Gajabarsab
Tambuli Squatter Commercial
48 18.655 RHS Mahalingapura Eshwara S/o Rajanna
Kalal Squatter Commercial
49 18.710 RHS Mahalingapura Naganatha S/o
Shiddarama Squatter Commercial
50 18.893 LHS Mahalingapura Yamanappa
Geethjavva Uttara Squatter Residential
51 18.915 LHS Mahalingapura Sumithra W/o Prahlad Squatter Commercial
52 18.915 LHS Mahalingapura Kamala W/o
Kasheppa Uttura Squatter Residential
53 18.927 LHS Mahalingapura Sadashiva S/o
Bhimappa Mangadi Squatter Commercial
54 18.931 LHS Mahalingapura Gowramma W/o
Shambara Manga Encroacher Residential
55 18.940 LHS Mahalingapura Mahalingappa S/o
Santhappa Manga Encroacher Residential
56 18.947 RHS Mahalingapura Lalsab S/o Yakamsab Encroacher Residential/Commer
cial
57 18.955 LHS Mahalingapura Roopa Nimbevva
Alasappagola Squatter Residential
58 18.956 RHS Mahalingapura Bashasab S/o
Ajarathsab Squatter Commercial
59 18.965 LHS Mahalingapura Lalithavva W/o
Chikkappa Squatter Commercial
60 19.013 LHS Mahalingapura Devendra S/o
Parashurama Lathore Encroacher Residential
61 19.020 LHS Mahalingapura Lakshmana S/o
Ningappa Encroacher Residential
62 19.020 RHS Mahalingapura Bhimappa S/o
Yallappa Squatter Commercial
63 19.025 LHS Mahalingapura Yusuf Khan S/o
Rasulsab Jamadhar Encroacher
Residential/Commer
cial
64 19.040 LHS Mahalingapura Marembee W/o
Rajasab Encroacher Residential
65 19.040 RHS Mahalingapura Mahalingappa S/o
Bhimappa Encroacher Residential
66 19.052 LHS Mahalingapura Abdul Terdal Encroacher Residential
67 19.055 LHS Mahalingapura Sayavva W/o
Bhimappa Kanatti Encroacher Residential
68 19.062 LHS Mahalingapura Hanumanthappa S/o
Bhimappa Valikara Encroacher Residential
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
31
Sl.
No. Chainage Side Village Name
Occu.
Status Loss Type
69 19.062 RHS Mahalingapura Ramanna S/o
Lakshmana Encroacher Residential
70 19.066 RHS Mahalingapura Lakshmana S/o
Gangappa Encroacher Residential
71 19.075 LHS Mahalingapura Suresh S/o Sadashiva
Shinde Encroacher Commercial
72 19.080 LHS Mahalingapura Kulkarni Encroacher Commercial
73 19.097 LHS Mahalingapura Gajanana S/o Lathore Squatter Commercial
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
32
Annexure 3: Details of PAFs in link 19B
Table 4- 40 PAF Structure details of link 19B
Sl.
No. Chainage Side Village Name
Occu.
Status Loss Type
1 0.020 LHS Mahalingapura
Eshwarappa S/o
Mahalingappa
Asthagi
Encroacher Commercial
2 0.030 LHS Mahalingapura M C Betageri Encroacher Commercial
3 0.034 LHS Mahalingapura M C Betageri Encroacher Commercial
4 0.037 LHS Mahalingapura Godachavva
Murugappa Betageri Encroacher Commercial
5 0.038 RHS Mahalingapura Sadashiva S/o
Veerabhadrappa Encroacher Commercial
6 0.039 LHS Mahalingapura M C Betageri Encroacher Commercial
7 0.041 LHS Mahalingapura S N Nagamurthy Encroacher Commercial
8 0.060 RHS Mahalingapura Nasaruddin Encroacher Commercial
9 0.072 LHS Mahalingapura Malakajappa Kuri Owner Commercial
10 4.865 LHS Saidapura Gopala S/o
Channappa Squatter Commercial
11 5.415 RHS Saidapura Hanumantha S/o
Gulappa Squatter Commercial
12 7.368 RHS Saidapura Govinda S/o
Krishnappa Squatter Commercial
13 7.500 LHS Saidapura Honnavva W/o
Baramappa Squatter Commercial
14 7.503 LHS Saidapura Manjunatha S/o
Neelakantappa Squatter Commercial
15 8.007 RHS Saidapura
Rukkamma W/o
Ganapathi
Devaramani
Squatter Commercial
16 8.530 LHS Saidapura Shivalinga S/o
Devappa Squatter Commercial
17 11.570 LHS Hallur Eshwarappa S/o
Siddappa Squatter Commercial
18 12.782 RHS Hallur Basappa S/o
Pundalika Squatter Commercial
19 12.782 LHS Hallur Eshwara S/o
Lakshmana Squatter Commercial
20 12.785 RHS Hallur Shankar S/o
Lakshmana Squatter Commercial
21 12.820 RHS Hallur Bhimappa S/o
Giryappa Squatter Commercial
22 12.825 RHS Hallur Hanumantha S/o
Basappa Squatter Commercial
23 12.826 RHS Hallur Yakub S/o Khajasab Squatter Commercial
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
33
Sl.
No. Chainage Side Village Name
Occu.
Status Loss Type
24 12.828 LHS Hallur
Basavva S/o
Hanumantha
Lokkkannavar
Squatter Commercial
25 12.833 RHS Hallur Sathyappa S/o
Mahadevappa B Patil Squatter Commercial
26 12.848 RHS Hallur Hanumantha S/o
Channabasappa Squatter Commercial
27 14.895 RHS Gandhinagara Lakshmi W/o Erappa Squatter Residential
28 17.410 RHS Gurlapura
Cross Abubkar S/o Gaussab Squatter Commercial
29 17.418 RHS Gurlapura
Cross
Shekhar S/o
Mahadevappa Squatter Commercial
30 17.421 RHS Gurlapura
Cross Ramesh S/o Kallappa Squatter Commercial
31 17.430 RHS Gurlapura
Cross
Shrishaila S/o
Hanumantha Squatter Commercial
32 17.433 RHS Gurlapura
Cross
Prakasha S/o
Basappa Squatter Commercial
33 17.436 RHS Gurlapura
Cross
Gokula Borewell
Services Squatter Commercial
34 17.438 RHS Gurlapura
Cross
Shiddalinga S/o
Basappa Squatter Commercial
35 17.446 RHS Gurlapura
Cross
Mudukappa S/o
Hanumantha Squatter Commercial
36 17.448 RHS Gurlapura
Cross Erappa Squatter Commercial
37 17.450 RHS Gurlapura Hanumantha S/o
Ramappa Squatter Commercial
38 17.454 RHS Gurlapura
Cross
Shivabasava S/o
Basappa Squatter Commercial
39 17.464 RHS Gurlapura
Cross
Shivappa S/o
Mallappa Squatter Commercial
40 17.467 RHS Gurlapura
Cross
Murigendra S/o
Gurupadappa Squatter Commercial
41 17.469 RHS Gurlapura
Cross
Revappa S/o
Mallappa Squatter Commercial
42 17.476 RHS Gurlapura
Cross
Lingappa S/o
Channabasappa Squatter Commercial
44 17.480 RHS Gurlapura
Cross
Shivappa S/o
Mallappa Squatter Commercial
45 17.490 RHS Gurlapura
Cross
Balappa S/o
Basavaneppa Squatter Commercial
46 17.496 RHS Gurlapura
Cross
Basavaraja S/o
Mallappa Squatter Commercial
47 17.498 RHS Gurlapura
Cross Holleppa Shetty Squatter Commercial
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
34
Sl.
No. Chainage Side Village Name
Occu.
Status Loss Type
48 17.500 RHS Gurlapura
Cross
Gurappa S/o
Karagulappa Squatter Commercial
49 17.506 RHS Gurlapura
Cross
Tangevva W/o
Karugolappa Squatter Commercial
50 17.512 RHS Gurlapura
Cross
Revappa S/o
Channappa Squatter Commercial
51 17.521 RHS Gurlapura
Cross
Basappa S/o
Rangappa Squatter Commercial
52 17.552 RHS Gurlapura Mahadeva S/o
Kallappa Squatter Commercial
53 17.892 LHS Gurlapura Shrishaila S/o
Basappa Nerli Owner Residential
54 17.905 LHS Gurlapura Boravva W/o
Shankarappa Owner Residential
55 20.125 RHS Maladoor
Yallappa
Shivabasappa
Mukkad
Squatter Commercial
56 23.570 RHS Kankanavadi Vittala S/o Yallappa Squatter Commercial
57 23.590 RHS Kankanavadi Denamma W/o
Fakrusab Squatter Commercial
58 23.655 RHS Kankanavadi Maruthi S/o Yallappa
Maradi Encroacher Commercial
59 23.660 RHS Kankanavadi Halappa S/o
Yankappa Squatter Commercial
60 23.665 RHS Kankanavadi Halappa S/o Amarani Squatter Commercial
61 23.665 LHS Kankanavadi Paraiah S/o Balaiah
Hiremata Squatter Commercial
62 23.680 LHS Kankanavadi Sadashiva S/o
Shankar Squatter Commercial
63 23.683 LHS Kankanavadi Pundalika S/o
Siddappa Squatter Commercial
64 23.686 LHS Kankanavadi Malappa S/o
Mutthappa Squatter Commercial
65 23.690 LHS Kankanavadi Balappa S/o Yallappa Squatter Commercial
66 23.724 RHS Kankanavadi Tammanna Squatter Commercial
67 23.727 RHS Kankanavadi Husain S/o Hanadaf Squatter Commercial
68 25.252 LHS Kankanavadi Bhimappa S/o
Mallappa Squatter Commercial
69 25.283 LHS Kankanavadi Chandramma W/o
Balappa Squatter Residential
70 26.650 LHS Kankanavadi Lakkappa S/o
Lakshmana Squatter Commercial
71 26.655 LHS Kankanavadi Balappa Squatter Residential/Commer
cial
72 28.940 LHS Nippanala Bhimappa S/o
Mallappa Squatter
Residential/Commer
cial
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
35
Sl.
No. Chainage Side Village Name
Occu.
Status Loss Type
73 29.380 LHS Nippanala
Kallappa S/o
Lakshmana Encroacher Cattle Shed
74 29.4 LHS Nippanala Basappa S/o
Lakshmana Encroacher Cattle Shed
75 29.730 RHS Nippanala Ramagoda S/o
Basappa Squatter Commercial
76 29.735 RHS Nippanala Kedari S/o Kadappa
Bastuvadi Squatter Commercial
77 29.749 LHS Nippanala Maruthi S/o Kallappa Squatter Commercial
78 29.755 LHS Nippanala Dastagirisab S/o
Shahbuddin Squatter Commercial
79 29.758 LHS Nippanala Krishnappa S/o
Bhimappa Kantikar Encroacher Commercial
80 30.550 RHS Nippanala Muthyappa S/o
Bheerappa Borgod Owner Residential
81 31.270 RHS Mantur Rangappa S/o
Ramappa Squatter Commercial
82 32.862 LHS Mantur Siddappa S/o
Narasappa Squatter Commercial
83 34.060 LHS Bendevadi
Cross
Mahadeva S/o
Kallappa Squatter Commercial
84 37.415 LHS Jodatti Pundalika S/o
Basappa Owner Residential
85 40.710 RHS Kabbur Lakshmana S/o
Krishnappa Bidare Owner Cattle Shed
86 40.920 RHS Kabbur Basayya S/o C
Basayya Owner Cattle Shed
87 42.362 RHS Kabbur Subhash Squatter Commercial
88 42.416 RHS Kabbur
Gundappa S/o Kati
Basappa
Kattappanavar
Squatter Commercial
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
36
Annexure 4 : Details of PAFs in Link 19C
Table 4- 51: PAF Structure details of link 19C
Sl.
No. Chainage Side Village Name
Occu.
Status Loss Type
1 0.010 LHS Kabbur Gaffar S/o
Mohiddinsab Squatter Commercial
2 0.011 RHS Kabbur Jannath W/o Ameer
Jamadar Squatter Commercial
3 0.013 LHS Kabbur Kallappa S/o
Shivaraya Squatter Commercial
4 0.015 LHS Kabbur Kallappa S/o Maruthi Squatter Commercial
5 0.015 RHS Kabbur Gaus S/o Malliksab Squatter Commercial
6 0.018 LHS Kabbur Anil S/o Siddarama Squatter Commercial
7 0.025 LHS Kabbur Sadashiva S/o Gopal Squatter Commercial
8 0.032 RHS Kabbur Kallamesh S/o
Yallappa Squatter Commercial
9 0.035 RHS Kabbur Shekhar S/o Manohar Squatter Commercial
10 0.090 LHS Kabbur Yasin S/o Usman
Jamam Squatter Commercial
11 0.098 LHS Kabbur Balasab S/o
Sidramasab Squatter Commercial
12 0.585 LHS Kabbur Srikantha S/o Vittala Squatter Commercial
13 1.160 LHS Kabbur Halappa S/o
Buddappa Encroacher Residential
14 1.650 LHS Kabbur Basappa S/o Siddappa Encroacher Residential
15 2.998 RHS Kabbur Vittala S/o Siddappa Encroacher Cattle Shed
16 3.742 LHS Bilagi Cross Siddarama S/o
Bhimappa Encroacher Residential
17 4.470 LHS Nagaramunoli Ningappa S/o
Ramappa Squatter Commercial
18 5.575 LHS Nagaramunoli Sudheesh S/o
Pundalika Squatter Commercial
19 5.625 LHS Nagaramunoli Ananda S/o Santhappa
Myagale Squatter Commercial
20 5.638 RHS Nagaramunoli Chitrasena S/o Babu Squatter Commercial
21 5.708 LHS Nagaramunoli Siddu S/o Ramappa Squatter Commercial
22 5.710 LHS Nagaramunoli Dastagir S/o Alisab Squatter Commercial
23 5.775 LHS Nagaramunoli Fakruddin S/o
Mirasab Jamadar Squatter Commercial
24 5.777 LHS Nagaramunoli Smt Kastrivva Shekar
Pujar Encroacher Residential
25 5.800 LHS Nagaramunoli Jayakumar S/o
Siddappa Squatter Commercial
26 5.810 LHS Nagaramunoli Mahesh S/o Shivappa Squatter Commercial
27 5.830 LHS Nagaramunoli Virupaksha S/o
Mallappa Encroacher Residential
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
37
Sl.
No. Chainage Side Village Name
Occu.
Status Loss Type
28 5.860 LHS Nagaramunoli Baramappa S/o
Basappa Kore Squatter Commercial
29 5.864 LHS Nagaramunoli Subhash S/o Somappa Squatter Commercial
30 5.870 LHS Nagaramunoli Lakshmana S/o
Bhimappa Squatter Commercial
31 5.873 LHS Nagaramunoli Mallikarjuna S/o
Shivappa Squatter Commercial
32 5.880 LHS Nagaramunoli Shankara S/o
Ramappa Squatter Commercial
33 5.885 LHS Nagaramunoli Appasab S/o Kalisab Squatter Commercial
34 5.900 LHS Nagaramunoli Siddaruda S/o
Ramappa Squatter Commercial
35 12.405 LHS Umrani Smt Gangavva
Siddappa Dadugola Squatter Residential
36 12.413 RHS Umrani Appanna S/o
Narasappa Encroacher Residential
37 17.676 RHS Chikkodi Kempanna S/o
Bhimappa Squatter Commercial
38 17.716 RHS Chikkodi Basavaraj S/o
Gangadhara Encroacher
Boundary
Wall
39 18.060 RHS Chikkodi Tabaraka S/o Hyderali Encroacher Residential
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
38
Annexure 5: Details of PAFS in Link 19D
Table 4- 12: PAF Structure details of link 19D
Sl.
No. Chainage Side Village Name
Occu.
Status Loss Type
1 3.435 RHS Chikkodi Jothibha Malave Owner Commercial
2 6.000 LHS Chinchani Suresh S/o Rama
Nadoni Encroacher Residential
3 6.010 LHS Chinchani Annasab S/o Ramu
Nadoni Encroacher Residential
4 6.055 LHS Chinchani Sanjaya Dadu S/o
Bheema Nadoni Squatter Commercial
5 8.000 LHS Kuppanawadi Vijay S/o Annasab
Gulle Encroacher Residential
6 10.870 LHS Kothali Sanjeeva S/o Prakash
Mugdum Squatter Commercial
7 10.940 RHS Kutali
Balagowda S/o
Ramangowda
Demannanavar
Squatter Commercial
8 10.940 LHS Kothali Raju S/o Prakash
Mugdum Squatter Commercial
9 10.980 LHS Kothali Tategowda S/o
Annagowda Patil Tenant Commercial
10 10.990 LHS Kutali Sadashiva S/o Annappa
Chougala Squatter Commercial
11 11.000 LHS Kutali Mallappa S/o
Bheemappa Navi Squatter Commercial
12 11.010 LHS Kutali Gajanana S/o Shivappa
Chougala Squatter Commercial
13 11.020 LHS Kutali Appasaheb S/o
Mahadeva Mane Squatter Commercial
14 11.025 LHS Kutali
Suresh S/o
Veerupakshappa
Chougala
Squatter Commercial
15 11.080 LHS Kutali Bheemappa S/o
Devappa Kamagowda Squatter Commercial
16 11.280 LHS Kutali Shankar S/o Ramu
Mugdum Squatter Commercial
17 17.800 RHS Pattankudi Riaz S/o Iqbal Jari Squatter Commercial
18 17.820 RHS Pattankudi Vinayaka Y Shinde Squatter Commercial
19 17.840 LHS Pattankudi Sanjay S/o Keshav
Prabhalakar Squatter Commercial
20 17.850 LHS Pattankudi Elahi S/o Hasan Kamate Squatter Commercial
21 17.865 LHS Pattankudi Mahaveera S/o
Hucchannanavar Encroacher Residential
22 17.870 LHS Pattankudi Bhoopal S/o Rama
Hucchannanavar Encroacher Residential
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
39
Sl.
No. Chainage Side Village Name
Occu.
Status Loss Type
23 17.875 LHS Pattankudi Shanthabai W/o
Ramagonda Patil Encroacher Residential
24 17.880 LHS Pattankudi Gowrabai W/o Late
Appa Bankapura Encroacher Residential
25 17.885 LHS Pattankudi Tathoba Koth Encroacher Residential
26 17.895 LHS Pattankudi Srinivasa S/o
Panduranga Sasini Encroacher Residential
27 17.910 RHS Pattankudi Rajendra Sripala
Dumme Encroacher Residential
28 17.920 RHS Pattankudi Ashok S/o Vasantha
Bagal Encroacher Residential
29 17.926 RHS Pattankudi Shankar Ramjee Bagal Encroacher Residential
30 17.931 RHS Pattankudi Sriranga S/o Appa
Shelara Squatter Commercial
31 17.945 RHS Pattankudi Suresh S/o Ganapathi
Bagal Encroacher Commercial
32 17.945 RHS Pattankudi Raveendra S/o
Dadasaheb Punekar Encroacher Residential
33 17.960 RHS Pattankudi Bagavatha S/o Dondiba
Punekar Encroacher Residential
34 22.188 RHS Nippani Anil Sankapala Squatter Commercial
35 22.300 RHS Nippani Anasuya W/o Rajaram
Rapri Squatter Residential
36 22.520 LHS Nippani Umesh S/o Maruthi
Hegde Squatter Commercial
37 22.525 RHS Nippani Maruthi S/o Ningapp
Hegde Squatter Commercial
38 22.575 LHS Nippani Mahadeva S/o Annappa
Patil Squatter Commercial
39 22.620 RHS Nippani Balu S/o Datta Honne Squatter Commercial
40 22.625 RHS Nippani
Veepan S/o
Rameshwarlal
Vaishnava
Squatter Commercial
41 22.628 RHS Nippani Sushma Kamble C/o
Manorama Kamble Squatter Commercial
42 22.631 RHS Nippani Shekar S/o Gangaram
Teradali Squatter Commercial
43 22.632 LHS Nippani Raju S/o Siddappa
Kamate Squatter Commercial
44 22.634 RHS Nippani Vijay S/o Gundu
Tipukade Squatter Commercial
45 22.635 LHS Nippani Kallappa S/o Babu
Kamate Squatter Commercial
46 22.640 RHS Nippani Prabhakar S/o Pundalik
Kadam Squatter Commercial
47 22.646 RHS Nippani Hanumantha S/o
Lakshman Jalapura Squatter Commercial
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
40
Sl.
No. Chainage Side Village Name
Occu.
Status Loss Type
48 22.650 RHS Nippani Maruthi S/o Bheema
Rao Hakkule Squatter Commercial
49 22.653 RHS Nippani Sikandar S/o Babasab
Mujavar Squatter Commercial
50 22.656 RHS Nippani Ramachandra S/o
Annappa Tippukude Squatter Commercial
51 22.659 RHS Nippani
Mumtaz W/o Late
Mohammad Haneef
Mujavar
Squatter Commercial
52 22.661 RHS Nippani Vikas Kamble S/o
Shyama Rao Kamble Squatter Commercial
53 22.664 RHS Nippani Amol Kamble S/o
Prakash Kamble Squatter Commercial
54 23.110 RHS Nippani Vijay S/o Dattathreya
Tippe Squatter Commercial
55 23.113 RHS Nippani Sudhakar S/o
Lakshmana Jathrate Squatter Commercial
56 23.165 RHS Nippani Sagar S/o Narayana
Indalakar Squatter Commercial
57 23.168 RHS Nippani Rao Saheb S/o
Ramachandra Malhabad Squatter Commercial
58 23.172 RHS Nippani Samiulla S/o Iqbal
Mujavar Squatter Commercial
59 23.175 RHS Nippani Havasa bai W/o Ashok
Lakhe Squatter Commercial
60 23.178 RHS Nippani Marufa Babasab Bhavan Squatter Commercial
61 23.180 RHS Nippani Muksuda S/o Kareem
Muniyar Squatter Commercial
62 23.183 RHS Nippani Vittala Hadhikara Squatter Commercial
63 23.185 RHS Nippani Basavaraj S/o Veerappa
Ammanagi Squatter Commercial
64 23.198 RHS Nippani Raju S/o Panduranga
Suthara Squatter Commercial
65 23.201 RHS Nippani Ghanu Gosamvi Squatter Commercial
66 23.206 RHS Nippani Mamtaz W/o Daraveshi Squatter Commercial
67 23.210 RHS Nippani Bharathesh S/o Kallappa
Pangare Squatter Commercial
68 23.212 RHS Nippani Shivaji S/o Rama
Suryavamshi Squatter Commercial
69 23.215 RHS Nippani Dilip S/o Bamane Squatter Commercial
70 23.220 LHS Nippani Harish S/o Jasud 2
Commercial,
(O) Open
Land
71 23.222 RHS Nippani Mahadeva S/o Daadu
Kumbara Squatter Commercial
72 23.224 RHS Nippani Anil S/o Narayana
Kumbara Squatter Commercial
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
41
Sl.
No. Chainage Side Village Name
Occu.
Status Loss Type
73 23.227 RHS Nippani Chandrakantha S/o
Krishna Surangi Squatter Commercial
74 23.230 RHS Nippani Aslam S/o Mohiddin
Bhagavan Squatter Commercial
75 23.234 RHS Nippani Dilip S/o Ramu
Desamane Squatter Commercial
76 23.237 RHS Nippani Kurlinga S/o Shivarudra
Udase Squatter Commercial
77 23.240 RHS Nippani Bala Saheb S/o Bairu
Ravuth Squatter Commercial
78 23.244 RHS Nippani Jubeera S/o Aslam
Bhagavan Squatter Commercial
79 23.250 RHS Nippani Juneed S/o Aslam
Bhagavan Squatter Commercial
80 23.325 LHS Nippani Faruk S/o Ismail Mulla Squatter Commercial
81 23.340 LHS Nippani Mahesh S/o Shivaji
Suthara Squatter Commercial
82 23.345 LHS Nippani Pradeep S/o Jadav Squatter Commercial
83 23.350 LHS Nippani Dasthagir S/o Moulasab Squatter Commercial
84 23.353 LHS Nippani Prabhakar S/o
Panduranga Patade Squatter Commercial
85 23.359 LHS Nippani Ashoka Neevut Ravut Squatter Commercial
86 23.362 LHS Nippani Manohar S/o Ravut N Squatter Commercial
87 23.365 RHS Nippani Anil S/o Maruthi
Manjrekar Squatter Commercial
88 23.365 LHS Nippani
Vimala W/o
Chandrakantha
Karavekara
Squatter Commercial
89 23.390 LHS Nippani Umesha S/o Shivaputra
Chougale Squatter Commercial
90 23.400 LHS Nippani Ananda S/o Bairu
Sangapala Squatter Commercial
91 23.440 LHS Nippani Sabuddin S/o Abubakar
Mujavar Squatter Commercial
92 23.445 RHS Nippani Sachin S/o Raghunatha
Patil Squatter Commercial
93 23.450 LHS Nippani Chandu S/o Sakarama
Patil Encroacher Commercial
94 23.480 LHS Nippani Arun S/o Vittal Rao
Savanth Encroacher Commercial
95 23.485 RHS Nippani Preveen Batle Encroacher Commercial
96 23.500 LHS Nippani Arun S/o Vittalrao
Savanth Encroacher Commercial
97 23.520 RHS Nippani Mohan S/o
Ramachandra Kade Squatter Commercial
98 24.025 RHS Nippani Alla Baksh S/o Hazarath
Hazukhan Squatter Commercial
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
42
Sl.
No. Chainage Side Village Name
Occu.
Status Loss Type
99 24.028 RHS Nippani Ashoka S/o Keraba
Shindhe Squatter Commercial
100 24.032 RHS Nippani
Srikanth S/o
Parashurama
Mathivaddara
Squatter Commercial
101 24.036 RHS Nippani Vinoda S/o Ekanatha
Suthara Squatter Commercial
102 24.038 RHS Nippani Vijay S/o Dondiba
Savantha Squatter Commercial
103 24.040 RHS Nippani Chandrakantha S/o
Panduranga Maane Squatter Commercial
104 24.042 RHS Nippani Vinayaka S/o Ganapathi
Rao Squatter Commercial
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
43
Annexure 6: Details of Community Structure
Table 4- 6: Community Asset Details of link 19A (Mudhol - Mahalingapura )
Area in Sq.m
Sl.
No.
Chain
age Side District Taluk Village Typeof Asset Owner Type
Total
Struc
ture
Affec
ted
Strct
ure
% of
Str.
Getti
ng
Affec
ted
1 0.210 LHS Bagalkot Mudhol Mudhol Hand Pump Panchayat 13.50 2.25 16.67
2 0.240 LHS Bagalkot Mudhol Mudhol Arch Community 48.00 24.00 50.00
3 1.870 LHS Bagalkot Mudhol Mudhol Bore Well Panchayat 13.50 2.25 16.67
4 2.622 RHS Bagalkot Mudhol Soragav Temple Community 45.00 15.00 33.33
5 2.635 RHS Bagalkot Mudhol Soragav Hand Pump Panchayat 16.50 2.25 13.64
6 2.645 LHS Bagalkot Mudhol Soragav Bus Stand Panchayat 49.00 28.00 57.14
7 2.960 LHS Bagalkot Mudhol Soragav Bore Well Panchayat 12.75 2.25 17.65
8 2.980 RHS Bagalkot Mudhol Soragav Well & Pump
House
Panchayat 34.00 14.00 41.18
9 4.025 LHS Bagalkot Mudhol Soragav Temple Community 33.00 6.00 18.18
10 6.450 RHS Bagalkot Mudhol Soragav Bore Well Panchayat 13.50 2.25 16.67
11 7.100 LHS Bagalkot Mudhol Malali Temple Community 10.00 1.00 10.00
12 8.092 RHS Bagalkot Mudhol Mugalkhod Hand Pump Panchayat 12.00 2.25 18.75
13 8.280 LHS Bagalkot Mudhol Mugalkhod Ashrama Community 48.00 4.00 8.33
14 8.315 LHS Bagalkot Mudhol Mugalkhod Shrine Community 7.50 1.00 13.33
15 9.182 LHS Bagalkot Mudhol Mugalkhod Hand Pump Panchayat 13.50 2.25 16.67
16 11.920 RHS Bagalkot Mudhol Belagali Bore Well Panchayat 7.50 2.25 30.00
17 13.320 LHS Bagalkot Mudhol Ranna
Belagali Temple
Community 63.00 35.00 55.56
18 13.725 RHS Bagalkot Mudhol Belagali Hand Pump Panchayat 15.00 2.25 15.00
19 14.345 RHS Bagalkot Mudhol Ranna
Belagali Hand Pump
Panchayat 10.50 2.25 21.43
20 14.425 RHS Bagalkot Mudhol Ranna
Belagali Temple
Community 20.00 12.00 60.00
21 14.550 LHS Bagalkot Mudhol Ranna
Belagali Circle
Community 10.00 4.00 40.00
22 14.550 RHS Bagalkot Mudhol Ranna
Belagali
Mini Water
Supply Tank
Panchayat 9.00 2.25 25.00
23 14.562 RHS Bagalkot Mudhol Ranna
Belagali Water Tap
Panchayat 7.50 2.25 30.00
24 14.670 RHS Bagalkot Mudhol Ranna
Belagali Water Tap
Panchayat 7.50 2.25 30.00
25 14.720 LHS Bagalkot Mudhol Ranna
Belagali High School
Panchayat 45.00 4.50 10.00
26 14.740 LHS Bagalkot Mudhol Ranna
Belagali Temple
Community 96.00 32.00 33.33
27 14.740 RHS Bagalkot Mudhol Ranna Water Tap Panchayat 12.00 2.25 18.75
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
44
Belagali
28 14.800 RHS Bagalkot Mudhol Ranna
Belagali
Mini Water
Supply Tank
Panchayat 7.80 2.25 28.85
29 14.955 RHS Bagalkot Mudhol Ranna
Belagali Temple
Community 12.00 2.25 18.75
30 15.410 LHS Bagalkot Mudhol Ranna
Belagali Temple
Community 9.00 1.00 11.11
31 17.485 LHS Bagalkot Mudhol Mahalingapu
ra Laboratory
Private 18.00 4.00 22.22
32 18.463 LHS Bagalkot Mudhol Mahalingapu
ra
Mini Water
Supply Tank
Panchayat 10.50 2.25 21.43
33 18.465 LHS Bagalkot Mudhol Mahalingapu
ra Temple
Community 14.00 4.00 28.57
34 18.475 LHS Bagalkot Mudhol Mahalingapu
ra Circle
Community 4.00 4.00 100.0
0
35 18.882 RHS Bagalkot Mudhol Mahalingapu
ra Toilet
Panchayat 164.0
0
16.00 9.76
36 18.885 LHS Bagalkot Mudhol Mahalingapu
ra Anganavadi
Panchayat 27.75 2.25 8.11
37 18.968 LHS Bagalkot Mudhol Mahalingapu
ra Circle
Community 104.2
5
30.75 29.50
38 18.995 LHS Bagalkot Mudhol Mahalingapu
ra
Mini Water
Supply Tank
Panchayat 9.75 2.25 23.08
39 19.119 LHS Bagalkot Mudhol Mahalingapu
ra Toilet
Panchayat 28.00 8.00 28.57
Table 4- 7 Community Asset Details of link 19B (Mahalingapura - Kabbur)
Area in Sq.m
Sl.
No.
Chain
age Side District Taluk Village Typeof Asset
Owner
Type
Total
Structur
e
Affecte
d
Strctur
e
% of
Str.
Getti
ng
Affec
ted
1 0.030 RHS Bagalkot Mudhol Mahalingapura Malige Panchayat 38.10 10.80 28.35
2 0.455 RHS Bagalkot Mudhol Mahalingapura Temple Community 5.50 1.00 18.18
3 1.13 LHS Bagalkot Mudhol Mahalingapura Pond Panchayat 45.00 10.00 22.22
4 3.548 LHS Bagalkot Mudhol Mahalingapura Temple Community 35.00 14.00 40.00
5 3.575 RHS Bagalkot Mudhol Mahalingapura Bore Well Panchayat 26.25 2.25 8.57
6 3.890 RHS Bagalkot Mudhol Mahalingapura Hand Pump Panchayat 10.50 2.25 21.43
7 4.530 LHS Bagalkot Mudhol Saidapura Temple Community 14.00 4.00 28.57
8 4.806 RHS Bagalkot Mudhol Basavanagara Bore Well Panchayat 13.50 0.75 5.56
9 4.815 LHS Bagalkot Mudhol Saidapura Temple Community 33.00 24.00 72.73
10 4.882 LHS Bagalkot Mudhol Saidapura Hand Pump Panchayat 6.00 2.25 37.50
11 5.480 RHS Bagalkot Mudhol Busanala Hand Pump Panchayat 15.00 1.50 10.00
12 6.716 LHS Bagalkot Mudhol Saidapura Hand Pump &
Water Tap
Panchayat 13.50 1.50 11.11
13 7.000 LHS Bagalkot Mudhol Saidapura Bore Well Panchayat 12.00 2.25 18.75
14 7.015 LHS Bagalkot Mudhol Saidapura Pump House Panchayat 12.00 2.25 18.75
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
45
15 7.355 RHS Bagalkot Mudhol Saidapura Mini Water
Supply Tank
Panchayat 46.00 6.00 13.04
16 7.360 RHS Bagalkot Mudhol Saidapura Arch Community 66.00 9.00 13.64
17 7.385 RHS Bagalkot Mudhol Saidapura Temple Community 60.00 15.00 25.00
18 7.475 RHS Bagalkot Mudhol Saidapura Water Tap Panchayat 11.25 0.75 6.67
19 7.495 RHS Bagalkot Mudhol Saidapura Bore Well &
Pump House
Panchayat 10.50 1.50 14.29
20 7.990 RHS Bagalkot Mudhol Saidapura Mini Water
Supply Tank
Panchayat 10.50 2.25 21.43
21 8.508 LHS Bagalkot Mudhol Mahalingapura Hand Pump Panchayat 8.25 3.38 40.91
22 9.400 RHS Belgaum Raybag Kappalagudi Hand Pump Panchayat 20.25 1.50 7.41
23 9.680 RHS Belgaum Raybag Kappalagudi Primaty
School
Panchayat 154.00 112.00 72.73
24 9.700 RHS Belgaum Raybag Kappalagudi Hand Pump Panchayat 18.00 2.25 12.50
25 10.570 LHS Belgaum Raybag Kappalagudi Aralikatte Community 22.00 16.00 72.73
26 11.115 RHS Belgaum Raybag Kappalagudi Hand Pump Panchayat 12.00 2.25 18.75
27 12.775 RHS Belgaum Gokak Hallur Hand Pump Panchayat 15.00 0.75 5.00
28 12.810 RHS Belgaum Gokak Hallur Temple Community 24.00 12.00 50.00
29 13.330 LHS Belgaum Gokak Hallur Temple Community 20.00 16.00 80.00
30 14.803 RHS Belgaum Gokak Gandhinagara Bus Stand Panchayat 56.00 28.00 50.00
31 14.812 RHS Belgaum Gokak Gandhinagara Milk Dairy Government 24.00 9.00 37.50
32 14.83 RHS Belgaum Gokak Gandhinagara Aralikatte Community 24.00 9.00 37.50
33 17.467 RHS Belgaum Gokak Gurlapura
Cross Bus Stand
Panchayat 60.00 40.00 66.67
34 17.487 LHS Belgaum Gokak Gurlapura
Cross Bore Well
Panchayat 9.00 2.25 25.00
35 17.488 LHS Belgaum Gokak Gurlapura
Cross
Mini Water
Supply Tank
Panchayat 15.00 2.25 15.00
36 20.072 LHS Belgaum Gokak Maldoor Temple Community 32.00 2.00 6.25
37 21.86 LHS Belgaum Raybag Kankanavadi Temple Community 27.00 9.00 33.33
38 22.010 RHS Belgaum Raybag Kankanavadi Bore Well &
Hand Pump
Panchayat 15.00 1.50 10.00
39 23.090 RHS Belgaum Raybag Kankanavadi Bore Well &
Hand Pump
Panchayat 13.50 2.25 16.67
40 23.186 RHS Belgaum Raybag Kankanavadi Hand Pump Panchayat 15.00 0.75 5.00
41 23.280 RHS Belgaum Raybag Kankanavadi Bore Well Panchayat 13.50 1.50 11.11
42 24.085 LHS Belgaum Raybag Kankanavadi Hand Pump Panchayat 14.25 1.50 10.53
43 24.1 LHS Belgaum Raybag Kankanavadi Toilet Pvt. Trust 44.00 4.00 9.09
44 26.595 LHS Belgaum Raybag Kankanavadi Hand Pump Panchayat 16.50 1.50 9.09
45 27.802 LHS Belgaum Raybag Hippanal Hand Pump Panchayat 15.00 2.25 15.00
46 28.152 RHS Belgaum Raybag Nippanal Temple Community 32.00 16.00 50.00
47 28.410 RHS Belgaum Raybag Nippanal Hand Pump Panchayat 15.00 2.25 15.00
48 29.432 RHS Belgaum Raybag Nippanal Bore Well Panchayat 9.00 2.25 25.00
49 29.448 LHS Belgaum Raybag Nippanal Mini Water
Supply Tank
Panchayat 10.50 2.25 21.43
50 29.74 LHS Belgaum Raybag Nippanal Circle Community 16.00 1.00 6.25
51 29.8 LHS Belgaum Raybag Nippanal Hand Pump Panchayat 30.00 2.25 7.50
52 29.805
LHS Belgaum Raybag Nippanal Stage
(Rangamandir
a)
Community
140.00 64.00 45.71
53 31.435 RHS Belgaum Raybag Mantoor Hand Pump Panchayat 13.50 2.25 16.67
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
46
54 31.813 RHS Belgaum Raybag Mantoor Temple Community 28.00 16.00 57.14
55 32.855 LHS Belgaum Raybag Mantoor Hand Pump Panchayat 16.50 2.25 13.64
56 32.858 LHS Belgaum Raybag MantoorMTR/
RBG/HP/L/
Mini Water
Supply Tank Panchayat
18.00 2.25 12.50
57 32.868 LHS Belgaum Raybag Mantoor Bus Stand Panchayat 63.00 28.00 44.44
58 34.038 LHS Belgaum Raybag Bendevad
Cross Hand Pump
Panchayat 15.00 1.50 10.00
59 34.053 LHS Belgaum Raybag Bendevad
Cross
Bus Stand Panchayat
51.00 15.00 29.41
60 37.614 LHS Belgaum Raybag Jodatti Cross Bus Stand Panchayat 54.00 27.00 50.00
61 38.862 LHS Belgaum Raybag Jodatti Bus Stand Panchayat 52.50 24.50 46.67
62 39.160 LHS Belgaum Chikko
di
Jodatti Cross Hand Pump
Panchayat 10.50 2.25 21.43
63 39.96 RHS Belgaum Chikko
di
Ganesh Nagar Hand Pump Panchayat
15.00 2.25 15.00
64 40.660 RHS Belgaum Chikko
di
Kabbur Pump House
Panchayat 30.00 6.00 20.00
65 40.660 LHS Belgaum Chikko
di
Kabbur Compound
Wall
Community 48.00 3.00 6.25
Table 4-15: Community Asset Details of link 19C (Kabbur - Chikodi)
Area in Sq.m
Sl.
N
o.
Chain
age Side District Taluk Village Typeof Asset
Owner
Type
Total
Struct
ure
Affected
Strcture
% of
Str.
Getting
Affecte
d
1 4.420 LHS Belgaum Chikkodi Nagarmunoli Mini Water
Supply Tank Panchayat
10.50 2.25 21.43
2 5.423 LHS Belgaum Chikkodi Nagarmunoli Toilet Panchayat 34.50 1.50 4.35
3 5.660 LHS Belgaum Chikkodi Nagarmunoli Water Tap Panchayat 8.00 1.00 12.50
4 5.810 LHS Belgaum Chikkodi Nagarmunoli Bus Stand Panchayat 49.00 21.00 42.86
5 6.160 LHS Belgaum Chikkodi Nagarmunoli Bore Well Panchayat 13.50 2.25 16.67
6 6.823 LHS Belgaum Chikkodi Nagarmunoli Mini Water
Supply Tank
Panchayat 13.50 1.50 11.11
7 8.850 LHS Belgaum Chikkodi Itnal Cross Bus Stand Panchayat 56.00 21.00 37.50
8 10.290 LHS Belgaum Chikkodi Bengoda
Cross Bus Stand
Panchayat 73.50 10.50 14.29
9 12.238 LHS Belgaum Chikkodi Umrani Hand Pump Panchayat 15.00 2.25 15.00
10 12.340 LHS Belgaum Chikkodi Umrani Compound
Wall
Panchayat 585.00 22.50 3.85
11 12.888 LHS Belgaum Chikkodi Umrani Temple Communit
y
42.50 27.50 64.71
12 12.942 LHS Belgaum Chikkodi Umrani Hand Pump Panchayat 13.50 2.25 16.67
13 12.950 LHS Belgaum Chikkodi Umrani
Temple Communit
y
60.00 32.00 53.33
14 13.700 LHS Belgaum Chikkodi Umrani Bore Well &
Pump House Panchayat
12.00 2.25 18.75
15 13.900 LHS Belgaum Chikkodi Umrani Mini Water
Supply Tank Panchayat
16.50 1.50 9.09
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
47
16 15.660 LHS Belgaum Chikkodi Umrani
Temple Communit
y
40.00 30.00 75.00
17 17.785 LHS Belgaum Chikkodi Chikkodi Water Tank Panchayat 32.00 16.00 50.00
18 17.789 LHS Belgaum Chikkodi Chikkodi Compound
Wall
Governme
nt
1200.0
0
50.00 4.17
19 17.840 LHS Belgaum Chikkodi Chikkodi Bore Hole Panchayat 10.50 2.25 21.43
20 18.000 LHS Belgaum Chikkodi Chikkodi Mini Water
Supply Tank Panchayat
15.00 2.25 15.00
21 0.003 RHS Belgaum Chikkodi Kabbur Bus Stand Panchayat 34.00 2.00 5.88
22 3.871 RHS Belgaum Chikkodi Belagali
Cross Bus Stand
Panchayat 31.50 28.00 88.89
23 15.065 RHS Belgaum Chikkodi Umrani Bus Stand Panchayat 15.00 2.25 15.00
24 15.920 RHS Belgaum Chikkodi Chikkodi Compound
Wall
Governme
nt
30.75 5.25 17.07
25 17.680 RHS Belgaum Chikkodi Chikkodi Compound
Wall
Panchayat 634.50 23.50 3.70
26 18.073 RHS Belgaum Chikkodi Chikkodi
Temple Communit
y
162.00 54.00 33.33
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
48
Table 4- 86: Community Asset Details of link 19D (Chikodi - Nippani (NH4))
Area in Sq.m
Sl.
No.
Chaina
ge Side District Taluk Village
Typeof
Asset Owner Type
Total
Land
Affec
ted
Land
% of
Land
Getti
ng
Affec
ted
Total
Struc
ture
Affec
ted
Strct
ure
% of
Str.
Getti
ng
Affec
ted
1 0.085 LHS Belgaum Chikkodi Chikkodi Compound
Wall
Government 160.0
0
8.00 5.00
2 0.140 LHS Belgaum Chikkodi Chikkodi Public Toilet Panchayat 22.50 5.00 22.22
3 0.930 LHS Belgaum Chikkodi Chikkodi Compound
Wall
Government 492.2
5
27.50 5.59
4 1.130 LHS Belgaum Chikkodi Chikkodi Bus Stand Panchayat 62.45 20.70 33.15
5 3.080 LHS Belgaum Chikkodi Chikkodi Government
Land
Government 3300.
00
3300.
00
100.0
0
6 3.480 LHS Belgaum Chikkodi Chinchani Bus Stand Panchayat 35.10 33.60 95.73
7 3.480 LHS Belgaum Chikkodi Chinchani Government
Land Government
3190 3190 100.00
8 5.040 LHS Belgaum Chikkodi Chinchani Hand Pump Panchayat 13.95 2.25 16.13
9 6.040 LHS Belgaum Chikkodi Chinchani Mini Water
Supply Tank Panchayat 22.80 4.00 17.54
10 6.660 LHS Belgaum Chikkodi Chinchani Hand Pump Panchayat 12.30 2.25 18.29
11 12.300 LHS Belgaum Chikkodi Dulaganawadi Bus Stand
Panchayat 107.1
0 38.25 35.71
12 16.500 LHS Belgaum Chikkodi Pattankudi Temple Community 43.74 3.06 7.00
13 17.845 LHS Belgaum Chikkodi Pattankudi Bus Stand Panchayat 40.20 12.00 29.85
14 17.860 LHS Belgaum Chikkodi Pattankudi Flag Pole Community 3.75 0.25 6.67
15 22.295 LHS Belgaum Chikkodi Nippani Primaty
School Government
310.0
0
15.50 5.00
16 23.360 LHS Belgaum Chikkodi Nippani Mini Water
Supply Tank Panchayat
11.60 4.00 34.48
17 23.390 LHS Belgaum Chikkodi Nippani Temple Community 18.00 10.50 58.33
18 23.460 LHS Belgaum Chikkodi Nippani Basement Pvt. Trust 63.00 0.00 0.00
19 0.020 RHS Belgaum Chikkodi Chikkodi Bus Stand Panchayat 70.92 21.60 30.46
20 0.075 RHS Belgaum Chikkodi Chikkodi Sign Board Private 9.60 1.00 10.42
21 0.860 RHS Belgaum Chikkodi Chikkodi Compound
Wall Government
408.0
0
20.00 4.90
22 0.900 RHS Belgaum Chikkodi Chikkodi Compound
Wall Government
170.0
0
10.00 5.88
23 3.440 RHS Belgaum Chikkodi Chikkodi Bore Well Private 4.00 0.25 6.25
24 4.820 RHS Belgaum Chikkodi Chinchani Temple Community 12.45 2.25 18.07
25 5.380 RHS Belgaum Chikkodi Chinchani Temple Community 18.00 4.00 22.22
26 9.690 RHS Belgaum Chikkodi Kothali Shrine Community 5.00 1.00 20.00
27 10.420 RHS Belgaum Chikkodi Kothali Mini Water
Supply Tank Panchayat 15.00 6.25 41.67
28 10.430 RHS Belgaum Chikkodi Kothali Mini Water
Supply Tank
Panchayat 13.00 4.00 30.77
29 10.980 RHS Belgaum Chikkodi Kutali Bus Stand Panchayat 52.79 27.60 52.29
30 13.980 RHS Belgaum Chikkodi Dulaganawadi Bus Stand Panchayat 91.30 44.00 48.19
31 15.540 RHS Belgaum Chikkodi Pattankudi Bus Stand Panchayat 58.10 28.00 48.19
32 17.810 RHS Belgaum Chikkodi Pattankudi Bus Stand Panchayat 36.00 24.00 66.67
33 21.380 RHS Belgaum Chikkodi Nippani Pump House Panchayat 36.00 20.25 56.25
Karnataka State Highways Improvement Project –II Resettlement Implementation Plan WAP-2
(Mudhol - Nippani)
49
34 22.638 RHS Belgaum Chikkodi Nippani Bus Stand Panchayat 46.40 23.20 50.00
35 23.170 RHS Belgaum Chikkodi Nippani Mini Water
Supply Tank Panchayat
16.00 6.25 39.06
Top Related