Renewable Energy Committee Meeting

Discussion of 2008 Renewable Energy Program Plans

October 9, 2007

Page 2: Renewable Energy Committee Meeting Discussion of 2008 Renewable Energy  Program Plans

Today’s Overview

• Program Changes

• Budget (compared to 2007)

• MWh (compared to 2007)

• Other Goals (compared to 2007)

Page 3: Renewable Energy Committee Meeting Discussion of 2008 Renewable Energy  Program Plans

Purpose of Plan• Combines high level plan with program details

– One regulatory filing instead of two

• Components same as 2007 Compliance filing– Program designs– Budgets– Marketing plan– Goals

Page 4: Renewable Energy Committee Meeting Discussion of 2008 Renewable Energy  Program Plans

2008 Staff Proposed Budget(all $000)

Renewable Energy Proposed Allocation: Budget CORE $127,494 Other RE (CPC, RECs, DEP baseline, other) $5,000 EDA Programs $40,000Total $172,494

Page 5: Renewable Energy Committee Meeting Discussion of 2008 Renewable Energy  Program Plans

Renewable Budget Comparison

$151,611

$132,944

$935 $981 $842 $1,346 0$5,113

$19,400

$34,887

$0

$20,000

$40,000

$60,000

$80,000

$100,000

$120,000

$140,000

$160,000

Annual Budget(000)

CORE CPC REC RMDI EDA ProgramsInitiative

NJCEP Renewable Budget Comparison

2007

2008

Page 6: Renewable Energy Committee Meeting Discussion of 2008 Renewable Energy  Program Plans

Renewable Generation Comparison

34,000

38,021

83,243

38,000

56,999

51,600

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

MWh

CORE REC CPC RMDIInitaitive

NJCEP Renewable Programs Projected Annual New Generation

2007

2008

Page 7: Renewable Energy Committee Meeting Discussion of 2008 Renewable Energy  Program Plans

CORE Program Changes• Stop accepting new applications once each budget

category is subscribed (terminate queues)• $5 million dedicated for new wind and biomass

applications (pending funding approval) • Expected Performance Based Buy-down for wind• Develop new rebate program for 2009• Provide transition support

Page 8: Renewable Energy Committee Meeting Discussion of 2008 Renewable Energy  Program Plans

CORE ComparisonPY 2007 PY 2008

Budget $151 m(new + outstanding)

$127-$133 m(new + outstanding)

MWh ~34,000(24,000 solar &

10,000 non)

~38,000(29,400 solar &

8,500 non)

Number of Systems

714 1,373

Page 9: Renewable Energy Committee Meeting Discussion of 2008 Renewable Energy  Program Plans

CORE 08 Budget by Activity

Note: Includes projected $76 m carry-forward from 07 (including ~200 new approvals w O8 funds) and $22m carry-forward of commitments to be paid in 09

CORE Proposed 2008 Budget (all $000)

Administra-tion and Program Developmt $1,274

Sales, Call Centers, Marketing and Website $65Training $145

Rebates, Grants, and Other Direct Incentives $129,903

Rebate Processing, Inspections and Other Quality Control $1,557

Performnce Incentives tbd

Evaluation and Related Research $0Total $132,944

Page 10: Renewable Energy Committee Meeting Discussion of 2008 Renewable Energy  Program Plans

Proposed Allocation of New CORE Rebate Funds

(All numbers = 000's)

Preliminary 2008 CORE

Budget% of 2008

CORE BudgetBudget Category< 10 kw- non public $38,054 52.0%> 10 kw non public $0 0%Public - Non - schools $20,104 27%Public - Schools k-12 $8,616 12%Sunlit (HMFA affordable housing) $1,436 2%New Wind & Biomass $5,000 7%Total $73,210 100%

2008 CORE Budget AllocationAlternate for 10/9

Page 11: Renewable Energy Committee Meeting Discussion of 2008 Renewable Energy  Program Plans

REC Program Changes• Consolidate SREC-Only Pilot and REC

Facilitation into one program• Provide market analysis and information• Possibly have Market Manager administer/assist

w REC/SREC compliance and reporting• Significant volume increase

Page 12: Renewable Energy Committee Meeting Discussion of 2008 Renewable Energy  Program Plans

REC ComparisonPY 2007 PY 2008

Budget $842k $1,346k

MWh - ~83,000

Number of Registrations

20-50 expected

256 ytd

300-400

Page 13: Renewable Energy Committee Meeting Discussion of 2008 Renewable Energy  Program Plans

REC 08 Budget by ActivityREC Proposed 2008 Budget (all $000)

Administration and Program Development $727

Sales, Call Centers, Marketing and Website $30Training $0

Rebates, Grants, and Other Direct Incentives $0

Rebate Processing, Inspections and Other Quality Control $460

Performance Incentives tbdEvaluation and Related Research $129

Total $1,346

Page 14: Renewable Energy Committee Meeting Discussion of 2008 Renewable Energy  Program Plans

CPC Program Changes• Complete rule-making process to formally adopt

the program• Conduct competitive solicitation for Clean Power

Marketers (CPMs) and their offerings of renewable power products;

• Continued growth of the Community Partnership program, which enlists local communities in promoting the CPC program to its residents and businesses.

Page 15: Renewable Energy Committee Meeting Discussion of 2008 Renewable Energy  Program Plans

CPC Comparison

Budgets do not include ~$2m OCE marketingSavings/participant based on cumulative EDC data

9,000 new participants

6,000 (projected new

for 2007) –year end total

13,000

Number of Participants

~57,000~38,000MWh

$981k$935kBudget

PY 2008PY 2007

9,000 new participants

6,000 (projected new

for 2007) –year end total

13,000

Number of Participants

~57,000~38,000MWh

$981k$935kBudget

PY 2008PY 2007

Page 16: Renewable Energy Committee Meeting Discussion of 2008 Renewable Energy  Program Plans

CPC 08 Budget by ActivityCPC Proposed 2008 Budget (all $000)

Administration and Program Development $500

Sales, Call Centers, Marketing and Website $481Training $0

Rebates, Grants, and Other Direct Incentives $0

Rebate Processing, Inspections and Other Quality Control $0

Performance Incentives $0Evaluation and Related Research $0

Total $981

Page 17: Renewable Energy Committee Meeting Discussion of 2008 Renewable Energy  Program Plans

RMDI Program Changes• Market Manager role to include:

– Performance based solicitation ($4.6 m)– Market development activities in non-CORE segments

(e.g. grid supply & >700 kW)• Main element focused on MWh/1st yr production – delivered

capacity and milestones • Component to assist w pre-project

development

Page 18: Renewable Energy Committee Meeting Discussion of 2008 Renewable Energy  Program Plans

RMDI-EDA Support Comparison

PY 2007 PY 2008

Budget $19.4 m

“EDA”

$5.1m(RMDI only)

MWh - ~50,000 MWh

New

Capacity

- 7 to 12 MW

(primarily non-solar)

Page 19: Renewable Energy Committee Meeting Discussion of 2008 Renewable Energy  Program Plans

RMDI 08 Budget by Activity

Note: MM RMDI Activity Pending approval

RMDI Proposed 2008 Budget (all $000)

Administration and Program Development $384

Sales, Call Centers, Marketing and Website $129Training $0

Rebates, Grants, and Other Direct Incentives $4,600

Rebate Processing, Inspections and Other Quality Control $0

Performance Incentives $0Evaluation and Related Research $0

Total $5,113

Page 20: Renewable Energy Committee Meeting Discussion of 2008 Renewable Energy  Program Plans

Questions and Discussion