Rajasthan State Road Development & Construction Corporation Ltd.
Unit-II, Bikaner
C-72, Sadul Ganj, Bikaner
ORGANISATIONAL CHART OF RSRDCC UNIT-II BIKANER
Resident Engineer
Sh. R. K.Mathur
A. A. O.
Sh. B. L. Darak
ARE
Sh. S. M. Swami
ARE
Sh. Sunil Gahlot
ARE
Sh. Sanjay Golwal
ARE
Sh. S. P. Mathur
ARE
Sh. M.G. Shrimali
S. No. Name of Work Client Deptt.
A& F Sanction Expenditure till date
Balance Work
ARE – I Sh. S. M. Swami
1 Laying Sewer Line for Police Qtrs. Police Dept. 38.16 Lacs 4.02 Lacs 34.14 Lacs
2 Water Supply arrangement for Police Qtrs. Police Dept. 53.18 Lacs 24.74 Lacs 28.44 Lacs
3 Const. of LSQ-II Police Line, Bikaner Police Dept. 142.72 Lacs 103.13 Lacs 18.87 Lacs
4 Const of LSQ-IV Police Line, Bikaner Police Dept. 220.24 Lacs 138.87 Lacs 48.33 Lacs
5 Const. of 40 Nos. LSQ X RAC, Bikaner Police Dept. 124.24 Lacs 91.91 Lacs 13.69 Lacs
ARE – II Sh Sunil Gahlot
1 Const. of LSQ & USQ at X RAC, Bikaner Police Dept. 469.22 Lacs 353.18 Lacs 45.66 Lacs
ARE – III Sh. Sanjay Golwal
1 Const. of LSQ III Police Line, Bikaner Police Dept. 191.94 Lacs 137.58 Lacs 25.56 Lacs
2 Protection work on New Bikaner Bye Pass BOT Project 45.69 Lacs 24.81 Lacs 20.88 Lacs
3 Const. of retaining wall on New Bikaner Bye Pass BOT Project 34.65 Lacs 34.65 Lacs 20.88 Lacs
ARE – III Sh. S. P. Mathur
1 Const. of LSQ & USQ at PMDS & JNV Bikaner Police Dept. 123.10 Lacs 103.10 Lacs 7.00 Lacs
2 Const. of 2 Nos. LSQ at JNV & 8 Nos. LSQ at PMDS
Police Dept. 29.48 Lacs 23.16 Lacs 6.32 Lacs
3 Const. of Bye Pass Zone I km 0/0 to 13/0 BOT Project 496.83 Lacs 477.08 Lacs 19.75
ARE – V Sh. M.G. Shrimali
1 Const. Bikaner Bye Pass km 13/0 to 26/0 Zone II BOT Project 496.92 Lacs 460.38 Lacs 36.54 Lacs
2 Supply of Grit to Hot Mix Plant for Bye Pass BOT Project 186.00 Lacs 164.00 Lacs 22.00 Lacs
3 Transportation of Bitumen of Bikaner Bye Pass BOT Project 52.00 Lacs 48.00 Lacs 4.00 Lacs
4. Road Furniture work BOT Project 86.00 Lacs 00.00 86.00 Lacs
Financial Work Load in Unit-II, Bikaner
S. No. Name of work Client Department
ModeActual/Tender
EstimatedCost
Remarks
1. Construction of LibraryBlock, Academic Block(Science) & CompoundWall in University of
Bikaner
MaharajaGangasinghUniversity,
Bikaner
Actual Plus 467.00Lacs
MOU Signed DrawingsSubmitted for Approval
2. Building of KendriyaShakari Bank at
Hanumangarh, Junction
Co-operativeBank
Actual Plus 325.00Lacs
Client department has principally agreed &
further negotiations are inprocess.
Proposed new worksRSRDCC Unit-II, bikaner
Important Works Completed by RSRDCC Unit-II, Bikaner During last 5 Year’s
1Construction of Married accommodation Project
For OR’s & JCO’s at Sriganganagar & Suratgarh. [Tendered work.]
Completion Cost Rs. 2814.00 Lacs.
2Stregthening & improvement of HanumangarhPillibanga Suratgarh road including ROB at LC
71 A at Hanumangarh Junction.Completion Cost Rs. 2736.43 Lacs.
3Construction of V.C. Secretariat, Examination Block,
Administrative Block and Guest Housing Buildings in University of Bikaner.
Completion Cost Rs. 564.00 Lacs.
4
Construction of Internal road, Entrance Plaza, Compound Wall, Water Supply arrangements and External
Electrification Work in the premises of University of Bikaner.
Completion Cost Rs. 179.00 Lacs.
5Construction of 5000 MT Godown, Office building,
Compound Wall, Internal road for RAJFED at Sriganganagar.
Completion Cost Rs. 121.00 Lacs.
6Widening and Strengthening of Sriganganagar
Hanumangarh road km 0/500 to 56/0 [BOTProject ] Tendered Work.
Completion Cost Rs. 1594.50 Lacs.
Completion Cost Rs. 1081.79 Lacs.
Completion Cost Rs. 475.00 Lacs
Foundation Stone laid by Hon’ble PWM on 27.5.2005Inaugurated by Hon’le Ex-Minister on 20.9.2008
Completion Cost Rs. 195.93 Lacs
Foundation Stone laid by Hon’ble Governor on 24.4.2005Inaugurated by Hon’ble Chief Minister on 14.8.2008
Completion Cost Rs. 179.00 Lacs
Completion Cost Rs. 121.00 Lacs
No. of Quarter : LSQ 156 nos., USQ 3 nos.
Total Cost : 737.76 Lacs
Location : Xth RAC, Bikaner
Date of Start : 3.3.2008
Stipulated Date of Completion : 2.2.2009
Expenditure till Date : 611.19 Lacs
Likely Completion Date : December, 2009
No. of Quarter : 40 nos. LSQ
Total Cost : 185.60 Lacs
Location : Xth RAC, Bikaner
Date of Start : 13.05.2008
Stipulated Date of Completion : 12.04.2009
Expenditure till Date : 156.68 Lacs
Likely Completion Date : December, 2009
No. of Quarter : 34nos. LSQ & 6nos. USQ
Total Cost : 185.60 Lacs
Location : PMDS and JNV Police Station
Date of Start : 03.03.2008
Stipulated Date of Completion : 02.02.2009
Expenditure till Date : 172.77 Lacs
Likely Completion Date : December, 2009
No. of Quarter : 10 Nos. LSQ
Total Cost : 46.40 Lacs
Location : PMDS and JNV Police Station
Date of Start : 11.10.2008
Stipulated Date of Completion : 10.07.2009
Expenditure till Date : 39.38 Lacs
Likely Completion Date : December, 2009
No. of Quarter : 48 Nos. LSQ
Total Cost : 222.72 Lacs
Location : Police Line, Bikaner
Date of Start : 19.04.2008
Stipulated Date of Completion : 18.03.2009
Expenditure till Date : 179.68 Lacs
Likely Completion Date : December, 2009
No. of Quarter : 60 Nos. LSQ
Total Cost : 278.40 Lacs
Location : Police Line, Bikaner
Date of Start : 11.10.2008
Stipulated Date of Completion : 10.07.2009
Expenditure till Date : 234.70 Lacs
Likely Completion Date : Jan., 2009
No. of Quarter : 72 Nos. LSQ
Total Cost : 334.08 Lacs
Location : Police Line, Bikaner
Date of Start : 13.05.2008
Stipulated Date of Completion : 12.04.2009
Expenditure till Date : 251.05 Lacs
Likely Completion Date : Jan., 2009
No. of Quarter : P&L&J of Sewer Line for Police Housing Project
Total Cost : 38.17 Lacs
Location : Police Housing Premises, Bikaner
Date of Start : 07.06.2009
Stipulated Date of Completion : 06.10.2009
Expenditure till Date : 4.39 Lacs
Likely Completion Date : Dec., 2009
Bottlenecks if Any : Permission to Lay Line and connect with the existing sewer system of Karni Nagar Colony was accorded in Sept.
2009 by Nagar Nigam after great pursuance.
No. of Quarter : Const. of OHSR, CWR & P&L&J of Distribution System
Total Cost : 53.19 Lacs
Location : Police Housing Premises, Bikaner
Date of Start : 07.06.2009
Stipulated Date of Completion : 06.12.2009
Expenditure till Date : 26.98 Lacs
Likely Completion Date : Dec., 2009
Bottlenecks if Any : PHED department has not yet approved the scheme of
Rs.81.55 Lacs for providing water supply to the Police Housing Premises.
Name of Work : Const. of New Bikaner Bye-Pass connecting NH-15 Bikaner-Jaisalmer Road to NH-15 Bikaner- Sriganganagar road Km 0/0 to 26/0.
Total Cost : 4169.93 Lacs.Off Take Point : Km 0/0 of Bye Pass is at NH-15
Bikaner- Jaisalmer road in km 17/500End Point : Km 26/0 of Bye Pass meets NH-15
Bikaner- Sri –Ganganagar road in km 14/600
Date of Start : 28.7.2009Stipulated Date of Completion : 31.3.2010Expenditure till Date : Rs.2211.61 Lacs.Likely Completion date : 15.1.2009
Bituminous Concrete work in Progress in km 0/0 to 1/0 of Bye Pass
Rotary at SH-03 Chhattargarh Road Km 10/775 of Bye Pass
Bikaner Bye Pass Km 1/0
Toll Plaza in Km 0/0 to 1/0 of Bikaner Bye Pass