Purchasing Directors’ MeetingAugust 23, 2007
2
• Agenda• Bureau A Update• Bureau B Update• MyFloridaMarketPlace Update• MyGreenFlorida Update-EO 07-126• Next Meeting-Thursday October 18, 2007
Purchasing Directors’ MeetingAugust 23, 2007 Agenda
3
• Agenda• Bureau A Update• Bureau B Update• MyFloridaMarketPlace Update• MyGreenFlorida Update-EO 07-126• Next Meeting-Thursday October 18, 2007
Purchasing Directors’ MeetingBureau A Update
4
• Team 1, Transportation & Energy– Christopher Walker: Motor Vehicles Contract Strategy
• Team 2, Institutional Furnishings & Supplies
• Team 3, MRO & Law Enforcement
• Team 7, SPA & Special Programs– GSA Disaster Recovery Purchasing Program
Bureau A Contract and Project Updates
5
Fuel Card: (David Bennett)– Working with TransMontaigne to negotiate discounts for Aviation
fuel. Working with Comdata to create a fleet maintenance reporting system. Working with Comdata to convert DOT fueling sites.
ESCO ITN and New Program: (David Bennett)– Extended the Current ESCO contract to 12/31/07. Working with
DFS and Facilities to create new ESCO contract and Program.
Propane (Liquefied Petroleum Gas): (David Bennett)– Expires 10/31/07. Solicitation was launched in late July.
Responses are due on 8/28/07. Construction, Industrial & Agricultural Equipment: (Christopher
Walker)– Launched ITB 06/25/07; 17 responses were received. Anticipate
new contract in September.
Team 1 UpdatesTransportation & Energy
6
Executive Order 07-126
Team 1 is working with DEP and DMS Fleet on threeinitiatives:
1. Approve new vehicles with the greatest fuel efficiency in a given class.
2. Use biodiesel and ethanol fuels when locally available.
3. Determine feasibility of opening state-owned alternative fuel facilities to public and private fleets.
Team 1 UpdatesTransportation & Energy
7
Motor Vehicles Contract Strategy
• Historic Strategy/Process– Segmented Contracts– Single Award per Specification– Variable Specifications
• Future Strategy/Process– Consolidated Contract(s)– Single Award by Representative Model per Specification– Standardized Specifications– New Naming, Commodity Codes, and Structure Possible– Benefits!
• Efficient Specifications Development and Evaluation Allowing Timely Contracts• Increased Vendor Participation & Increased Competition• More “Green” Vehicles/Options• Increased Choices to Meet your Intended Needs
Team 1 UpdatesTransportation & Energy
8
Office Furniture & Files: (Brenda Wells)– Reviewed applications from 40 manufacturers for
addition to contract. We expect to post intended awards in September.
Carpet & Installed Flooring: (Brenda Wells)– Reviewing manufacturers for addition to contract.
Expect adjustments in October.
Floor Maintenance Machines: (Mina Barekat)– Expires November 2007. We are recommending
renewal.
Team 2 UpdatesFurnishings & Institutional Supplies
9
Hot Topics:
• Welcome Lori Potts!
Purchasing Specialist
921-2520
Team 2 UpdatesFurnishings & Institutional Supplies
10
NY H.I.R.E. (ACS): (Mark Lovell)– We will be transitioning management of this contract to
Donna Smith, Team 7.
MRO: (Chuck Beall)– Expires in November. We have recommended renewal.
Next action will be finalized and posted shortly.
Generators: (Chuck Beall)– Preparing follow-up survey to respondents from initial
survey.
Team 3 UpdatesMRO & Law Enforcement
11
Emergency Notification Pilot Project: (Donna Smith)– Working with Division of Emergency Management
SPAs in progress: (Gary McGee)– Communication Towers, Maintenance & Repair– Detention Equipment– Portable Air Conditioners
Team 7 UpdatesSPA & Special Services
12
Mobile Shredding Services - ACS
• DOR contract• Gary McGee will
manage the ACS.• Now available on the
State Purchasing web site.
Contractor ACS #Accu-Shred A100H
Cintas Corporation
A100D
Gilmore Services A100E
Hill’s Shred Express
A100B
Progressive Document Destruction
A100F
Secure Document Destruction
A100A
Secure On-Site Shredding
A100C
Shredquick, Inc. A100G
Team 7 UpdatesSPA & Special Services
13
Hot Topics:
• Employment Opportunity
Purchasing Specialist position
Open until filled – contact Ellen Potts for details.
Team 7 UpdatesSPA & Special Services
14
GSA Disaster Recovery Purchasingwww.gsa.gov/disasterrecovery
• Section 833 of the John Warner National Defense Authorization Act for fiscal year 2007 (Public Law 109-364)
• Opens all GSA Schedules to state and local governments
to facilitate recovery from a major disaster, terrorism, or nuclear, biological, chemical, or radiological attack.
• Intent of this program is to speed recovery from a disaster,
including advance purchases of items necessary within 72 hours after the disaster.
Team 7 UpdatesSPA & Special Services
15
Advantages
• Nation-wide vendor base– Access to vendors outside of the disaster area
– Access to multiple vendors per supply or service
• Pre-negotiated contracts save time for items rarely purchased, or purchased only in disaster recovery efforts.
• Vendors are required to accept P-cards for orders up to the micro-purchase threshold.
Team 7 UpdatesSPA & Special Services
16
Considerations
• Random pricing samples indicate savings of 5-20% on emergency related items.
• Only 61% of GSA vendors have agreed to service the Disaster Recovery program.
• You’ll be competing against FEMA.• GSA vendors have 5 days to accept or reject an order.
– P-card orders must be declined within 24 hours.• GSA does recommend a best value three quote system
– Survey at least three Schedule contractors through the online shopping service GSA Advantage!® or review the catalogs or pricelists of at least three Schedule contractors, and seek additional price reductions where appropriate;
Team 7 UpdatesSPA & Special Services
17
Major Consideration
Advance Purchasing Program:
• Normal purchasing procedures will apply – STCs will take precedence, quote processes, other agency procedures, etc.
• GSA will not monitor purchases, but FEMA can audit your purchases as part of the reimbursement process.
• No clear guidelines in Section 833 nor are there clear expectations from FEMA.
• State Purchasing will have no role in determining whether your advanced purchase may meet FEMA expectations.
• Agencies will assume all risk related to advance purchases.
Team 7 UpdatesSPA & Special Services
18
Next Steps
• GSA presentation at the Tallahassee NIGP Purchasing Conference– Monday, August 27 at 3:30 PM or– Tuesday, August 28 at 10:45 AM
• Review the GSA Disaster Recovery FAQs
• Agency feedback & ACS [email protected]
Team 7 UpdatesSPA & Special Services
19
• Agenda• Bureau A Update• Bureau B Update• MyFloridaMarketPlace Update• MyGreenFlorida Update-EO 07-126• Next Meeting-Thursday October 18, 2007
Purchasing Directors’ MeetingBureau B Update
20
Jeff Rackley – Lead Purchasing [email protected]
Jon Yeaton – Purchasing [email protected]
Thomas Ashby – Purchasing Specialist414-6131
Team 4 UpdatesIT & Telecommunications
21
• Live Scan Electronic Fingerprint Stations– Negotiations/Presentations have been delayed until Sept.
• U.S. Communities Technology Solutions and Products contracts with GTSI – Only for items and services not already on STCMaintenance is available on GTSI as well. (Handout)
• Verizon Wireless State Term Contract was recently renewed with a 5% reduction based on the PPI. Rate is now .057 per minute. Reminder: Text messaging is not included in base fees unless a bolt-on is used. Data Plan does not include text message.
Bolt–On Per additional Text 100 $2.99 $.02 For Inbound 250 $4.99 $.10 For Outbound1000 $9.992500 $19.99
Team 4 UpdatesIT & Telecommunications
22
Earl CamposPurchasing Analyst, Lead Starts 3/16/07Tel: 850.487.6592Email: [email protected]
Fran ShewanPurchasing AnalystTel: 850.488.4946Email: [email protected]
Beverly ButlerPurchasing Specialist Tel: 850.414.6740Email: [email protected]
Team 5
23
Air Travel Contract• City Pairs ITB bids opened 8/22/08: No Bids were received.• Outcome of this bid will dictate the approach to travel in general.
DFS is willing to work with us on utilizing a more modern and cost effective approach, possibly online travel services or a bundled service through a full service travel company.
Avis Contract• Negotiating Adding GPS devices to Contract.• In discussion with Avis on compliance with the recent Executive
Order.
Pharmaceuticals • Earl Campos
Team 5 Contract Updates
24
New Changes that have occurred:
Prime Vendor Contract 268-000-98-2 ended 8/1/07
MMCAP Contract 268-000-04-1 is currently in effect
What Does This Mean For Agencies?
– Cardinal is still the distributor for pharmaceuticals
– Agencies will realize savings when invoices are paid quickly
– There are a number of Agencies that need to reconcile their invoices with the former Prime Vendor Contract
– State spend is approaching $207 million
– Agencies can sign up for EDI and have invoices paid within 15 days
Team 5 UpdatesPharmaceuticals
25
Terms to Know:• EDI – Electronic Data Interchange• DSO – Days Since Order
Contact Jay Francis - Florida MMCAP Coordinator at 850/922.4627x129 [email protected] if you have any questions about the Contract or setting up EDI
Team 5 UpdatesPharmaceuticals
26
Ommet Mbiza – 488-7804 – [email protected]
• Promoted to Team Lead
Michael Bailey – 487-0417 – [email protected]
• Promoted to Analyst over Property Insurance, PRIDE and RESPECT contracts
Specialist Position – Candidates currently being interviewed.
Team 6 UpdatesSpecial Programs
27
• Computer Assisted Legal Research – renewed for one year
• Purchasing Card Services – Re-procurement based on ASPIRE project suspension – Estimated release of ITN January 08
• Aviation Insurance Contract – Answers to Q&A posted 8/22 bids are due 8/31
• Boiler and Machinery Policy and Auto Policies are up for renewal in September
Team 6 UpdatesSpecial Programs
28
• Agenda• Bureau A Update• Bureau B Update• MyFloridaMarketPlace Update• MyGreenFlorida Update-EO 07-126• Next Meeting-Thursday October 18, 2007
Purchasing Directors’ MeetingMyFloridaMarketPlace Update
MyFloridaMarketPlace
State Purchasing Director Meeting
August 23, 2007
30
MyFloridaMarketPlace Activity Review
• User Queue Analysis – Change Request #32
• “A” Encumbrance Update
• Failed Purchase Order notification
• Catalog Enablement
• Shared Resource Center (SRC) Move
31
MFMP User Queue Analysis – Change Request 32
• Change Review Board Update– Focus for Q1 is the ‘User Queue Report’ enhancement
– Design Approval team approved the design of the report. The report provides insight into the time it takes individual approvers in a workflow to approve system transactions (i.e., Master Agreement Requests, Requisitions, and Invoice Reconciliations)
– The report also categorizes workflow approval times into:• Agency approval time• FLAIR approval time• Audit approval time
32
MFMP User Queue Analysis – Change Request 32
Requisition Approval by Agency and Approver
Number of Days to ApproveAgency Approver Type User Approvable 0 1 2 3 4 … TotalTotal 3 1 1 1 2 8
Departmental of Management Services 2 1 1 1 1 6Agency Approver 1 1 1 1 1 5
John 1 1 2PR111111 1 1PR333333 1 1
Jeff 1 1PR333333 1 1
Dan 1 1PR111111 1 1
Brandon 1 1PR111111 1 1
FLAIR Approver 1 1FLAIR 1 1
PR111111 1 1
Data: Avg approval time
• This mock-up provides a ‘general’ sense of what the report will look like
• Note: There will be additional day range columns. Specifically, the Design Approval Team finalized on the following day ranges for columns: 0, 1, 2, 3, 4, 5, 6-8, 9-12, 13-14, and >14
SAMPLE
33
MFMP “A” Encumbrance Update
• Agency Address Memo (DRAFT):
FLAIR EDITS FOR MYFLORIDAMARKETPLACE (MFMP) TRANSACTIONS
Effective August 31, 2007, edits will be reinstalled in FLAIR that will prohibit updating encumbrances or payables originating in MyFloridaMarketPlace directly thru FLAIR. These edits were in place until July of last year when they were temporarily suspended due to certified forward problems experienced by some agencies.
34
MFMP “A” Encumbrance Update
• Impacts of activity in FLAIR against MFMP initiated POs:
– General loss of tracking in MFMP: If changes are made directly to an encumbrance file in FLAIR that information will not be tracked in MFMP.
– Change Order Issues:
• Encumbrance amounts will be impacted: MFMP keeps a "running total" of the encumbrance amount. If a change is made directly in FLAIR, that change does not get accounted for in MFMP. When a change order is initiated and a transaction is sent to FLAIR, MFMP will always try to make encumbrance balances in the two systems match
• Encumbrance transaction may fail: When a change order is submitted to FLAIR, if the matching encumbrance is not found, the transaction will fail.
• Accounting information will be corrupted: If accounting information associated to an encumbrance is changed directly in FLAIR and a user later creates a change order, the change order will overwrite the accounting changes made directly in FLAIR.
35
MFMP “A” Encumbrance Update
• Potential Disbursement Processing Impacts:– MFMP invoice transactions may fail if the encumbrance has been
released in FLAIR but not recorded in MFMP by processing an IR. The interface will fail and the invoice payment cannot be completed from MFMP.
– Accounting information can be corrupted: The accounting information in MFMP “trumps” the FLAIR file.
• Impairs Reconciliation with FLAIR: With users having the ability to change encumbrance information in both FLAIR and MFMP it prevents encumbrance reconciliation between FLAIR and MFMP.
• Perpetuates inconsistent payment and accounting practices among agencies
36
MFMP Failed Purchase Order Notification
• The Customer Service Desk (CSD) identifies purchase orders failed to be sent to the vendor due to problems with the vendor’s contact information (email, phone, fax)
• The CSD will view the vendor contact information and attempt to send via an alternative method (e.g. if previously fax, they will try e-mail, etc.). Unless the vendor has already been flagged for having Invalid Data (ID) the CSD will attempt to send the order via fax or e-mail.
• If the order is still unsuccessfully sent, they will attempt to contact the vendor by phone and get current information from them, send the order and update the vendor’s information in Vendor Registration. – The agency will only receive notification that the purchase order has been
sent successfully if the purchase order had attachments. The agency will be notified in this communication to send the attachments directly to the vendor as they are unable to. NOTE: if there are no attachments then the agency is never notified.
• If, however, the CSD has not been able to contact the vendor the vendor will be marked with Invalid Data and the month and year this is effective. Ex: Geyer Painting Inc. ID: 08/07(001_Geyer Painting Inc. Tallahassee) .
37
MFMP Failed Purchase Order Notification
• The agency is then notified of the unsuccessful transmission of the purchase order and the CSD will cease attempting to contact the vendor to get the purchase order successfully sent.
• The agency is asked to assist in reaching out to the vendor to get them to update their information in Vendor Registration. While the agency can continue to use this vendor, unless the vendor’s information is updated, the purchase orders will continue to fail and the CSD is not required to assist in the transmission of the purchase order.
• An amended process is in development and will be provided to the Change Review Board (CRB) on August 30, 2007.
• A report request has been submitted to capture and report the failed purchase order information and make this available to the agencies. The fields may change dependent upon the CRB vote.
• We need the agencies assistance in reaching out to their vendors and asking them to update their vendor registration information.
38
MFMP Failed Purchase Order Notification
• FAILED PURCHASE ORDERS (Report Request)– Report Purpose: Assist the agencies in knowing what purchase
orders are failing to get to the vendor and why. What the time frame is from the point of failure to the time the agency has been notified the purchase order has successfully been sent.
– Report Fields: • Agency Name • Date PO failed to send
• OBO • Reason PO failed to send
• Vendor FEID • Date successfully sent to the vendor
• PUI • Method successfully sent to the vendor
• Vendor Name • Date agency notified
• DO #
39
MFMP Line Item Catalog Enablement Completed
• Mail Processing equipment (Contract Number: 600-760-07-1) – Leasing– Supplies
• Body Armor contract (Contract Number: 680-850-05-1): 8 out of the 10 catalogs loaded as line item
• PRIDE contracts (9 of 11) – Office Furniture (Contract Number: 425-001-05-P)– Metal Lockers (Contract Number: 425-540-95-P)– Cleaning Chemicals & Supplies (Contract Number: 485-000-06-P)– Shelving Metal (Contract Number: 450-130-96-P)– Fencing (Contract Number: 535-000-00-P)– Signage (Contract Number: 550-000-00-P)– Traffic Paint (Contract Number: 630-550-97-P)– Park Furniture (Contract Number: 650-000-98-P)– Mattresses (Contract Number: 850-500-95-P)
40
MFMP Line Item/Punchout Catalog Enablement In Progress
• Punchout activities:– VF Imagewear Punchout
– Identification of additional punchout site candidates
• Line Item Catalog Enablement:
– Detention Clothing (Contract Number: 200-050-06-P)- Targeted for next month
– Body Armor contract (Contract Number: 680-850-05-1): Currently working with Gator Hawk Armor, Inc. and Protective Apparel Corporation of America to load their contracts into MFMP
41
MFMP Shared Resource Center Move
• MFMP hardware and operations relocating to DMS Shared Resource Center• Relocation will occur 9/14 – 9/16• Testing involves performance, data migration, and functional verifications• Schedule of events:
– 9/14/07 6:00 PM Eastern: MFMP Shutdown– 9/14/07 6:00 PM – 9/16/07 8:00 AM Easter: Server relocation, configuration and
testing– 9/16/07 8:00 AM – 2:00 PM Eastern: Functional verification– 9/16/07 7:00 PM Eastern: Go/No go for production– 9/17/07 7:00 AM Eastern: MFMP return to production
• Communications will be distributed at key points during the weekend• Contingency plan for Monday, 9/17/07 will follow the upgrade approach
– In the unlikely event additional time is needed, Monday will be used – At 2:00 PM Eastern, if conditions persist, MFMP will revert back to Miami Data
Center
42
• Agenda• Bureau A Update• Bureau B Update• MyFloridaMarketPlace Update• MyGreenFlorida Update-EO 07-126• Next Meeting-Thursday October 18, 2007
Purchasing Directors’ MeetingMyGreenFlorida Update-EO 07-126
43
Governor Crist’s recent Executive Order has committed Florida to becoming a leader in reducing Greenhouse Gas emissions.
Governor’s Justification for EO 07-126• Florida’s 1,350 miles of coastline make it more vulnerable to rising ocean levels and
violent weather• Global climate change is one of the most important issues facing State of Florida this
century• Florida has committed to becoming a leader in reducing greenhouse gas (GHG) emissions
which are changing Earth’s climate (targeting 10% reduction of current emissions by 2012 and 40% by 2025)
• Immediate actions are available and required to reduce GHG emissions in Florida• Florida’s state government is largest employer in Florida, spends more than $1 billion in
annual commodity purchases, and has 16.8 million square feet of office space statewide• Florida state government must led by example in the fight against global climate change
by reducing GHG emissions and demonstrating the economic value of such reductions (e.g., returns to taxpayers through reduced energy costs)
Source: Governor Crist’s Executive Order 07-126, dated July 13, 2007
Executive Order 07-126 Background
44
The Governor directed his agencies to undertake several immediate actions...
Source: Governor Crist’s Executive Order 07-126, dated July 13, 2007
Segment Directive Due Date Status
State Purchasing
Develop the Florida Climate Friendly Products List 10/1/07 Started
Incorporate best possible environmental performance in Rental Vehicles STC Started
General
Conduct GHG emissions assessment (for both facilities and fleets) 10/1/07 Started
Incorporate energy consumption and GHG emissions as performance criteria in outsourcing projects business cases
Started
Facilities
Adopt US Green Building Council’s LEED standards (NC and EB) Done
Enter into new leases with Energy Star rated facilities
Develop energy conservation measures and guidelines for facilities Started
Develop and implement a model solar project
Contract with only DEP Green Lodging certified meeting facilities 1/1/08 Started
Fleet
Certify that all vehicles are meeting maintenance schedules 8/13/07 Done
Provide inventory of alternative motor vehicle fueling facilities 10/1/07 Ready
Approve only new vehicles with the greatest fuel efficiency in class
Use biodiesel and ethanol fuels when locally available
Determine feasibility of opening state-owned alternative fuel facilities to private fleet / public
… and encouraged all non-Governor’s agencies to implement these actions to help reduce State Government’s GHG emissions.
Executive Order 07-126 Requirements
45
DMS and DEP have formed a project team to address EO 07-126 requirements.
Selected Completed Activities• Developed a detailed project workplan, stakeholders map and communication plan• Conducted initial meetings with key stakeholders to engage their support in addressing EO 07-
126 requirements• Confirmed Greenhouse Gas (GHG) Protocol templates for building the Carbon Scorecard and
collected centrally available fleet and facility data• Worked with DEP to develop assessment criteria to determine existing green standards (e.g.,
Energy Star, Green Seal) can be used by vendors to certify their products as green• Developed and kicked off process with DMS State Purchasing to confirm applicable green
standards for their managed categories and then identify current State Term Contract items that qualify as green (building the Florida Climate Friendly Product List)
• Determined needed enhancements to MyFloridaMarketPlace and Aravo content management tool to accommodate flagging green products / vendors
Andrew CollinsDEP Senior
Executive Assistant
Roz IngramDMS Fleet Division
Director
Dean IzzoDMS Facilities
Division Director
Charles CovingtonState Purchasing
Director
Josh YaffinEO 07-126
Project DirectorJim Bard
MFMP
Jan DeLaneyDEP Environmental
Manager
Executive Order 07-126 Project Team
46
DMS and DEP are coordinating the required development of the Florida Governmental Carbon Scorecard for the Governor’s agencies.
Activity Owner
8/1
3/2
00
7
8/2
0/2
00
7
8/2
7/2
00
7
9/3
/2007
9/1
0/2
00
7
9/1
7/2
00
7
9/2
4/2
00
7
10/1
/200
7
Confirm specific GHG Protocol templates and required activity data needed to create Scorecard
DEP / DMS
Request and compile activity data from central fleet and facility databases
DEP / DMS
Send compiled data to agencies for validation and completion of missing data
DEP / DMS
Review data and make any corrections to fleet data in EMIS and provide any missing / corrected facility data to DMS
Governor's Agencies
Based on updated fleet and facility data, build Scorecard and submit to Governor’s Office
DEP / DMS
Missing data or that agencies may need to address could include:• Total square footage and occupancy type of any leased fixed space over 3,000 square feet
that the agency directly manages but that is not in FACT (if any)• Electricity usage (in kWh) between July 2006 and June 2007 for state-owned or leased
fixed space that the agency directly manages and pays for electricity (if any)• Fleet fuel usage not previously entered into EMIS for July 2006 and June 2007 time period• Critical fleet information data in EMIS (e.g., fuel type) and FACT (e.g., square footage,
occupancy type)
Developing Carbon Scorecard
47
DMS will work closely with DEP to confirm green product standards and then use the approved standards to identify qualifying STC products by end of September.
Consolidate Green Items
into FCFPL and Send to
Governor’s Office
Identify STC Items
that Meet Approved
Green Standards
Determine Green
Standards for
STC Items
DMS Purchasing
Teams
STC Vendors
• Work with vendors to identify / confirm appropriate independent green standards for specific category (e.g., Energy Star, Green Seal)
• Using Aravo tool, request vendors identify current STC catalog items that meet approved green standards and validate recycled item flags
• Facilitate review of standards with DEP. Purchasing Teams are requested to submit proposed standards to Jim Bard as soon as available
• Provide report of green flagged items to Charles Covington for submission to Governor’s Office as the Florida Climate Friendly Products List
Aug 20 – Sep 7 Sep 10 – Sep 21 Sep 24 – Sep 28
MFMP
• Provide input to PA/PS on appropriate green standards for category
• Within Aravo tool, identify current STC items that meet approved green standards and indicate which standard (new fields). Validate recycle flags on catalogs.
DEP • Review and approve standards
Building the Florida Climate Friendly Product List
48
To support the consistent and justifiable identification, evaluation and approval of green standards across all categories, DEP has identified four assessment criteria that all standards must meet in order to be approved.
Assessment Criteria for Green Standards Definition
Rating Independence / Enforcement Organization that issues and governs the standard is deemed impartial and independent from the products and vendors being reviewed
3rd Party or Buyer Verifiable DMS, DEP, buyers and public have access to a list of certified products to verify vendors’ claims of meeting standard
Geographically Applicable The standard is relevant to products and services being purchased from vendors in the State of Florida
Reasonable to Deploy Adopting and utilizing the standard in Florida is workable for the vendors, buyers and the State from a process and usability perspective
Assessment Criteria for Green Standards
49
Conduct Pilot and
Gather Feedback
DMS State Purchasing will also pilot flagging the identified green items and vendors in MFMP to help users find and select green products and to streamline the ongoing maintenance of the Florida Climate Friendly Products List.
Flag Green Items and
Vendors in MFMP
DMS Purchasing
Teams
MFMP
• Work with STC vendors and MFMP to have green items / vendors flagged in MFMP catalog / vendor punchout site
• Develop process to identify green products to non-MFMP users
• Issue communication to MFMP users about green flag and collect user feedback
• Develop and execute reports
Sep 24 – Oct 26 Oct 29 – Dec 28
• Assist in getting green items / vendors flagged in MFMP catalog
STC Vendors
• Work with DMS and MFMP to have green items / vendors flagged in MFMP catalog / vendor punchout site
• Execute process to identify green products to non-MFMP users
MyGreenFlorida Pilot Approach
50
• Agenda• Bureau A Update• Bureau B Update• MyFloridaMarketPlace Update• MyGreenFlorida Update-EO 07-126• Next Meeting-Thursday October 18, 2007
Purchasing Directors’ MeetingNext Meeting
Top Related