Project Management Strategy – ETP Pre-treatment Plant –II
22nd February 2013
ETP Pre-treatment Plant-II
• BCS 4:3 Template 2010 • June 2011Page 2
Agenda
Project Execution Strategy
Project Scope- PFD , Equipment Lay-out
Timeline
Concerns & mitigation measures
Strategy
A Way Forward
Project Execution Strategy
• BCS 4:3 Template 2010 • June 2011Page 3
Concept Development
completed as an integrated Team with TISS, BTS,
GermanyDetail Engineering
is outsourced
Procurement being done in-
house
Civil construction management being outsourced- BTSI
Overall project management being
done in-house
Project Scope- PFD
• BCS 4:3 Template 2010 • June 2011Page 4
PFD ETP Upgrade Phase2 RevB
Equipment Lay-out
• BCS 4:3 Template 2010 • June 2011Page 5
3-D View
• BCS 4:3 Template 2010 • June 2011Page 6
3-D View
• BCS 4:3 Template 2010 • June 2011Page 7
Page 8 • Investment Committee • PROJECT TITLE • YYYY-MM-DD
Project scope in Brief CSA :
Building (RCC + Structure), Green-field, 30m X 12m X 21m Pipe Rack, ~100m ~140MT Steel
Equipment 45nos., MS-GL Equipment ( 8nos) Alloy-20 Pumps ( 2nos., Imported – ITT, Korea) SS904L HE ( 2nos.,ALFALAVAL) Graphite HE ( 2nos.,Imported – GAB Neumann, Germany)
Page 9 • Investment Committee • PROJECT TITLE • YYYY-MM-DD
Project scope in Brief Piping
500NB to 25NB IBR Piping, lined piping
PCS More than 400KW Power requirement PCT : PLC with i/os ---
Timeline
• BCS 4:3 Template 2010 • June 2011Page 10
Page 11 • Investment Committee • PROJECT TITLE • YYYY-MM-DD
Concerns & Mitigating Measures1. Delivery of Long lead items :
ALFA LAVAL : Heat Exchangers’ SS904L tubes delayed by more than 2 weeks , Tubes delivery expected by end of week10 (10th March 2013) as confirmed by M/s. ALFA LAVAL (scheduled delivery 14th April 2013)
Mitigation: In this event of delay, ALFA LAVAL air-freighting the Tubes to make-up the
delay ( confirmed by ALFA LAVAL)
2. Delay in Start-up of Construction : Delay of 6-8weeks in start-up of construction of HTDS Facility/building Mitigation:
Introduced strong Bonus Clause in CSA construction Close monitoring of Construction schedule
3. Disposal of impacted earth :
Presentation • 2 May 2023 • Slide 12
Project Management Strategy
Defining the Building completion date from start to maintain overall Project
Timeline
Implemented Bonus cum LD clause for Civil contractor for Target completion
Design Management :
Expediting the Design & details for Building
Remove the complexities from the design to speed-up the Building
Construction
Two shifts Construction Management from beginning even with smaller Project
Team
Construction Time : 8AM till 11PM ( Monday to Saturday)
Presentation • 2 May 2023 • Slide 13
Construction Strategy
Every week meeting within Project & Operational Team to discuss status & a
way forward
Defining & tracking the BOQ of services from day1
Use of WH Bay4 space for soil storage to continue with HTDS Construction
Shed & water-cooler for skilled people for civil contract people to have better
working environment in view of approaching summer
Saturday evening meeting with all contractor site in-charges
Involvement of all site maintenance contractors to meet the target
completion & to utilize the knowledge of plant maintenance
A Way Forward
• BCS 4:3 Template 2010 • June 2011Page 14
Close monitoring of Construction
Long Delivery items’ expediting
Detail Engineering Piping& PCT
Thank you!