1 Guide to Project Management
Guide To
Project Management
By WorkMonk.com
Guide to Project Management by WorkMonk.com
A
Guide To
Project Management
WorkMonk.com
Project Management
2 Guide to Project Management
This PDF is Downloaded from
WorkMonk is an Outsourcing Project for businesses all over the worldand service providers with zero risk
As a Client you get dedicated Project Managers who manages all the work including reporting, communication and splitting the work to various vendors.
You can use WorkMonk to
1. Outsource your Work. Keep your core competency and let WorkMonk do all the backend work.2. White Label WorkMonk work and services and resell it to your clients and in your local market.
What Kind of work WorkMonk
Web Development, Software Development, Mobile Development, SEO/SEM/SMO, Copywriting, Analytics, Business Intelligence,Legal Outsourcing and many more. http://workmonk.com/all_services
So go ahead and post the work at [email protected] or contact/call us from Chat with us option on the site to talk to us.
Feel free to use the information and distribute this pdf and use the content for noncommercial /commercial purpose.
Guide to Project Management by WorkMonk.com
This PDF is Downloaded from WorkMonk.com
WorkMonk is an Outsourcing Project Management and Quality Control platform for businesses all over the world, so you can work with highly skilled freelancers and service providers with zero risk.
As a Client you get dedicated Project Managers who manages all the work ommunication and splitting the work to various
to –
1. Outsource your Work. Keep your core competency and let WorkMonk do all the
2. White Label WorkMonk work and services and resell it to your clients and in
Monk can do ?
Web Development, Software Development, Mobile Development, SEO/SEM/SMO, Copywriting, Analytics, Business Intelligence, Data Mining
and many more. You can see all the WorkMonk Services at http://workmonk.com/all_services
ost the work at WorkMonk.com for Free or drop us an email to or contact/call us from http://workmonk.com/contact
option on the site to talk to us.
Feel free to use the information and distribute this pdf and use the content for noncommercial /commercial purpose.
Management and Quality Control platform so you can work with highly skilled freelancers
As a Client you get dedicated Project Managers who manages all the work ommunication and splitting the work to various
1. Outsource your Work. Keep your core competency and let WorkMonk do all the
2. White Label WorkMonk work and services and resell it to your clients and in
Data Mining, You can see all the WorkMonk Services at
for Free or drop us an email to http://workmonk.com/contact or use
Feel free to use the information and distribute this pdf and use the content for non-
3 Guide to Project Management
Contents
1. An Introduction to Project Management
2. Project Phases & Project Life Cycle
2.1. Project Life Cycle Stages
3. Project Stakeholders................................
3.1. Roles & Responsibilities of a Project Manager
4. Key General Management Skills
5. Project Processes................................
6. Process Groups ................................
7. Defining Project Scope Management
7.1. Scope Statement................................
7.2. Creating the Work Breakdown Structure
8. Estimating Cost and Developing Budget
8.1. Cost Estimating Inputs
8.2. Estimating Activity Durations
8.3. Analyzing Cost Estimating Results
8.4. Cost Budgeting ................................
8.5. Developing the project Budget
8.6. Earned Value Management
9. Creating the Network Diagram
9.1. Precedence Diagram Method
9.2. Arrow Diagramming Method
9.3. Conditional Diagramming Method
10. Creating the Project Schedule
10.1. Applying Mathematical Analysis
10.2. Examining the Project schedule
11. Project Integration Management
12. Project Quality Management................................
12.1. Implementing Quality Control
12.2. Charting Quality Control
Guide to Project Management by WorkMonk.com
An Introduction to Project Management .............................................................................................
Project Phases & Project Life Cycle................................................................................................
Project Life Cycle Stages................................................................................................
.............................................................................................................................
Roles & Responsibilities of a Project Manager ................................................................
Key General Management Skills ................................................................................................
................................................................................................................................
................................................................................................................................
Defining Project Scope Management................................................................................................
................................................................................................
g the Work Breakdown Structure ................................................................
Estimating Cost and Developing Budget.............................................................................................
................................................................................................
Estimating Activity Durations................................................................................................
Analyzing Cost Estimating Results...........................................................................................
................................................................................................
Developing the project Budget ...............................................................................................
Earned Value Management ................................................................................................
Creating the Network Diagram................................................................................................
Precedence Diagram Method ................................................................................................
Arrow Diagramming Method................................................................................................
Conditional Diagramming Method ................................................................
................................................................................................
Applying Mathematical Analysis .............................................................................................
Examining the Project schedule..............................................................................................
Project Integration Management ................................................................................................
................................................................................................
Implementing Quality Control ................................................................................................
Charting Quality Control ................................................................................................
............................. 5
.......................................5
............................................5
............................. 6
.........................................6
...........................................7
.................................. 7
.....................................8
................................... 8
.......................................................8
................................................. 9
.............................10
............................................10
..................................10
...........................10
........................................................10
...............................10
....................................11
...........................................11
.................................11
..................................11
.........................................................11
............................................11
.............................12
..............................12
.......................................12
..............................................12
................................13
.........................................13
4 Guide to Project Management
12.3. Evaluating Quality Costs
12.4. Implementing Quality Assurance
13. Project Human Resource Management
14. Project Communications Management
15. Project Risk Management................................
15.1. Analyzing Identified Risks
15.2. Risk Management Methods
15.3. Responding to Identified Risks
15.4. Iterative Risk Management
16. Why Projects Fails? ................................
Guide to Project Management by WorkMonk.com
Evaluating Quality Costs................................................................................................
Implementing Quality Assurance............................................................................................
Project Human Resource Management..............................................................................................
Project Communications Management..............................................................................................
................................................................................................
Analyzing Identified Risks................................................................................................
Risk Management Methods................................................................................................
Responding to Identified Risks................................................................................................
Iterative Risk Management................................................................................................
.............................................................................................................................
..........................................13
............................13
..............................13
..............................14
...................................................14
........................................14
....................................15
................................15
.....................................15
.............................15
5 Guide to Project Management
The primary purpose of this document is to provide a basic reference to anyone whoproject management.
1. An Introduction to Project ManagementProject Management is the supervision and control of the work Project management includes work processes that initiate, plan, execute, and close work. Work processes require tradeoffs among the scope, quality, cost, and schedule of the project. needed to complete the project, while the project manager schedules, monitors, and controls the various project tasks.Project Management is comprised of the following nine knowledge areas:
Project Integration ManagementProject Scope ManagementProject Time ManagementProject Cost ManagementProject Risk ManagementProject Quality Management Project Procurement Management Project Human Resource ManagementProject Communications Management
2. Project Phases & Project Life CycleProjects are temporary endeavors to create a unique product or service. All projects must have an end date. Between the project launch and the covewill have its deliverables. A project phase allows a project manager to see the project completing the project one phase at a time. Consider a project to chave several phases to complete from concept to completion: product description, prototype, revision, testing and so on. Each project will have its own logical phases to completion, goals and deliverables andphase allows a project to move into the next phase.The collection of the project phases, as a whole, is known as beginning, middle, and end of a project. cycle than nearing its end.
2.1. Project Life Cycle StagesInitiating: When a project is proposed, planned at a high level, and key participants, commit to it in broad terms.Planning: Starts after the initial commitment, includes detailed planning, and ends when all stakeholders accept the entire detailed plan.Executing: Includes authorizing, executing, monitoring, and controlling work until the customer accepts the project deliverables.Closing: All activities after customer acceptance to ensure project is completed, lessons are learned, resources are recognized, and contributions are rewarded.
Guide to Project Management by WorkMonk.com
The primary purpose of this document is to provide a basic reference to anyone who is interested in understanding
to Project ManagementProject Management is the supervision and control of the work that is required to complete the project vision. Project management includes work processes that initiate, plan, execute, and close work. Work processes require tradeoffs among the scope, quality, cost, and schedule of the project. The project team carries out the work
le the project manager schedules, monitors, and controls the various project
Project Management is comprised of the following nine knowledge areas:Project Management Knowledge Areas
Focuses on project plan development and execution.Deals with the planning, creation, protection and fulfillment of the project scope.Covers activities, their characteristics, and how they fit into the project schedule.Concerned with the planning, estimating, budgeting, and control of costs.Focuses on risk planning, analysis, monitoring, and control.Centers on quality planning, assurance and control.Involves planning, solicitation, contract administration, and contract closeout.Focuses on organizational planning, staff acquisition, and team development.Details on how communication can be improved.
Project Phases & Project Life CycleProjects are temporary endeavors to create a unique product or service. All projects must have an end date. Between the project launch and the coveted end date, project will pass through multiple phases and each phase will have its deliverables. A project phase allows a project manager to see the project as a whole and still focus on completing the project one phase at a time. Consider a project to create a new electronic gadget. This gadget will have several phases to complete from concept to completion: product description, prototype, revision, testing and
Each project will have its own logical phases to completion, goals and deliverables andphase allows a project to move into the next phase.
, as a whole, is known as the project life cycle. Project Life cycle define the beginning, middle, and end of a project. Projects have a greater risk and uncertainty in the early phases of the life
Project Life Cycle StagesWhen a project is proposed, planned at a high level, and key participants, commit to it in broad terms.Starts after the initial commitment, includes detailed planning, and ends when all stakeholders accept
Includes authorizing, executing, monitoring, and controlling work until the customer accepts the project
All activities after customer acceptance to ensure project is completed, lessons are learned, resources are recognized, and contributions are rewarded.
is interested in understanding
required to complete the project vision. Project management includes work processes that initiate, plan, execute, and close work. Work processes require
The project team carries out the work le the project manager schedules, monitors, and controls the various project
Deals with the planning, creation, protection and fulfillment of the project scope.Covers activities, their characteristics, and how they fit into the project schedule.Concerned with the planning, estimating, budgeting, and control of costs.
Involves planning, solicitation, contract administration, and contract closeout.Focuses on organizational planning, staff acquisition, and team development.
Projects are temporary endeavors to create a unique product or service. All projects must have an end date. ted end date, project will pass through multiple phases and each phase
as a whole and still focus on reate a new electronic gadget. This gadget will
have several phases to complete from concept to completion: product description, prototype, revision, testing and the completion of a
Project Life cycle define the Projects have a greater risk and uncertainty in the early phases of the life
When a project is proposed, planned at a high level, and key participants, commit to it in broad terms.Starts after the initial commitment, includes detailed planning, and ends when all stakeholders accept
Includes authorizing, executing, monitoring, and controlling work until the customer accepts the project
All activities after customer acceptance to ensure project is completed, lessons are learned, resources are
6 Guide to Project Management
Fig 1: Project Life Cycle Stages
Fig 2: Project Life Cycle for Quality Improvement Projects
3. Project StakeholdersStakeholders are those folks and organizations who are actively involved in the project, or will be affected by its outcome – in other words, people, groups, businesses, customers, and communities that hathe project.
Project Manager Person who is accountable for managing the project.Project Customer Person or group that will use the project deliverable.Performing Organization Entity that employs the Project Team Collection of individuals that will work together to ensure success of the project.Project Sponsor Has the power to authorize and sanction the project work and is ultimately
responsible fo
3.1. Roles & Responsibilities The project manager has primary responsibility for the quality of a project’s deliverables and its successful completion. To succeed, the project manager must work closely with the project resources are applied. The project manager also has responsibility for planning and ensuring that the project is successfully completed on time and within budget.Responsibilities:
Implement project policies and procedures Acquire resources through negotiation with project owners and resource managers.
Guide to Project Management by WorkMonk.com
Quality Improvement Projects
Stakeholders are those folks and organizations who are actively involved in the project, or will be affected by its in other words, people, groups, businesses, customers, and communities that have a vested interest in
Key Project StakeholdersPerson who is accountable for managing the project.Person or group that will use the project deliverable.Entity that employs the people responsible for completing the project work.Collection of individuals that will work together to ensure success of the project.Has the power to authorize and sanction the project work and is ultimately responsible for project success.
Roles & Responsibilities of a Project ManagerThe project manager has primary responsibility for the quality of a project’s deliverables and its successful completion. To succeed, the project manager must work closely with the project owner to ensure that adequate resources are applied. The project manager also has responsibility for planning and ensuring that the project is successfully completed on time and within budget.
Implement project policies and proceduresAcquire resources through negotiation with project owners and resource managers.
Stakeholders are those folks and organizations who are actively involved in the project, or will be affected by its ve a vested interest in
people responsible for completing the project work.Collection of individuals that will work together to ensure success of the project.Has the power to authorize and sanction the project work and is ultimately
The project manager has primary responsibility for the quality of a project’s deliverables and its successful owner to ensure that adequate
resources are applied. The project manager also has responsibility for planning and ensuring that the project is
7 Guide to Project Management
Ensure adequate technical proficiency to meet project requirements and arrange for training. Establish and maintain quality in project. Identify and procure tools to be used o Monitor project progress against schedule and budget plans Ensure resources are focused on correct activities. Engage with management to ensure project awareness and prompt issue resolution.
4. Key General Management SkillsThere is more to project management than just getting the work done. Inherent to the process of project management are general management skills that allow the project manager to complete the project with some level of efficiency and control.
Leading the project team Excellent communication skills Negotiating project terms and conditions Active problem solving Influencing the organization
Matrix Organization & Composite Organization
Organizational Type ProsStrong Matrix Project team
from 50 to 990% of its duration. The project manager has a high level of authority. This model provides good communication
Balanced Matrix The project manager has balanced project authority with management. This model allows efficient use of functional resources.
Weak Matrix The project manager has little project authority and acts as a project coordinator.
Composite Ideal for organizations with recurring projects, such as manufacturing. Everyone on the project knows who is in charge: the functional manager.
5. Project ProcessesProcesses are a series of actions with a common, parent goal, to create a result. Processes are not the individual activities, but the control of individual activities to comThere are two types of processes:Product Oriented Processes: These processes are the activities that complete a project’s phase and life cycle. In other words, product oriented processes within a project complete phases, which in tuThe processes within a project are unique to each project.Project Management Processes: These processes are the activities that are universal to all projects. These activities comprise the bulk of the project management body of knprojects from construction to technology.
Guide to Project Management by WorkMonk.com
Ensure adequate technical proficiency to meet project requirements and arrange for training.Establish and maintain quality in project.Identify and procure tools to be used on the project.Monitor project progress against schedule and budget plans and raise concerns as appropriate.Ensure resources are focused on correct activities.Engage with management to ensure project awareness and prompt issue resolution.
agement SkillsThere is more to project management than just getting the work done. Inherent to the process of project management are general management skills that allow the project manager to complete the project with some
Excellent communication skillsNegotiating project terms and conditions
Composite Organization
ConsProject team may be assigned to a project from 50 to 990% of its duration. The project manager has a high level of authority. This model provides good communication
Competition among project teams still exists. Overall costs may also increase due to redundant administramong projects.
The project manager has balanced project authority with management. This model allows efficient use of functional resources.
The functional manager and the project manager may battle for project team members’ time. Project team may feel they are reporting to multiple bosses.
The project manager has little project authority and acts as a project coordinator.
The project is more a part of the functional department operations than a separate activity.resources may be divided amongst too many projects at once.
Ideal for organizations with recurring projects, such as manufacturing. Everyone on the project knows who is in charge: the functional manager.
The project manager has litauthority and may be known as a project expeditor.
Processes are a series of actions with a common, parent goal, to create a result. Processes are not the individual activities, but the control of individual activities to complete a project phase.
These processes are the activities that complete a project’s phase and life cycle. In other words, product oriented processes within a project complete phases, which in turn complete the project. The processes within a project are unique to each project.
These processes are the activities that are universal to all projects. These activities comprise the bulk of the project management body of knowledge and these processes are common to all projects from construction to technology.
Ensure adequate technical proficiency to meet project requirements and arrange for training.
and raise concerns as appropriate.
There is more to project management than just getting the work done. Inherent to the process of project management are general management skills that allow the project manager to complete the project with some
Competition among project teams still exists. Overall costs may also increase due to redundant administrative staff
The functional manager and the project manager may battle for project team
time. Project team may feel they are reporting to multiple bosses.The project is more a part of the functional department operations than a separate activity. Project team resources may be divided amongst too many projects at once.The project manager has little project authority and may be known as a
Processes are a series of actions with a common, parent goal, to create a result. Processes are not the individual
These processes are the activities that complete a project’s phase and life cycle. In rn complete the project.
These processes are the activities that are universal to all projects. These owledge and these processes are common to all
8 Guide to Project Management
The two process types are interrelated and interdependent. Thus, a project manager must be familiar with the product oriented processes in order to apply the project maproject manager should be familiar with both how a house is constructed and the various phases involved in that construction in order to effectively apply the project management processes.
6. Process GroupsThe process groups are a collection of activities that contribute to the control and implementation of the project management life cycle. The output of one process group will act as input for another process group.The following are five project managementInitiating: The project is authorized.Planning: Project objectives are determined, as well as how to reach those objectives with the given constraints.Executing: The project is executed utilizing acquired resources.Controlling: Project performance is monitored and measured to ensure the project plan is being implemented to design specifications and requirements.Closing: The project and its various phases are brought to a formal end.
7. Defining Project Scope ManagementProject scope management constitutes the processes that the project includes all of the work required, and only the work required, to complete the project successfully. Project Scope Management has several purposes:
It defines what work is needed to complete the project objec It determines what is included in the project. It serves as a guide to determine what work is not needed to complete the project objectives. It serves as point of reference for what is not included in the project. It guides the project manager on
The following table lists the inputs, tools and techniques, and outputs of scope planning.InputsProduct DescriptionProject CharterConstraintsAssumptions
7.1. Scope StatementThe scope statement is a document that describes the work, and only the required work, necessary to meet the project objectives. The scope statement establishes a common vision among the project stakeholders to establish the point and purpose of the project work. It is used as a baseline against which all future made to determine if proposed changes or work results are aligned with expectations. The scope statement, may, with adequate reason, be updated to reflect changes in the projereferences the following:Project Justification: Identifies the business needs of the project. It answers why the project has been authorized.Project’s Product: The scope statement reiterates the details of the project product.Project Deliverables: The high-level deliverables of the project should be identified. These deliverables, when predefined metrics are met, signal that project scope has been completed. When appropriate, it should also list what deliverables are excluded from the project deliverables. For ex: a project to create a new food product may state that it is not including the packaging of the food product as part of the project. Items and features not listed as part of the project deliverables should be assumed toProject Objectives: Project objectives are specific conditions that determine the success of a project. Conditions are typically cost, schedule, and quality metrics. Vague metrics, such as customer satisfaction, increase the risk for the project, as the metric “customer satisfaction” is subjective and not
Guide to Project Management by WorkMonk.com
The two process types are interrelated and interdependent. Thus, a project manager must be familiar with the product oriented processes in order to apply the project management processes. To use a real world example, a project manager should be familiar with both how a house is constructed and the various phases involved in that construction in order to effectively apply the project management processes.
The process groups are a collection of activities that contribute to the control and implementation of the project management life cycle. The output of one process group will act as input for another process group.The following are five project management process groups:
Project objectives are determined, as well as how to reach those objectives with the given constraints.The project is executed utilizing acquired resources.
performance is monitored and measured to ensure the project plan is being implemented to design specifications and requirements.
The project and its various phases are brought to a formal end.
Defining Project Scope Managementment constitutes the processes that the project includes all of the work required, and only
the work required, to complete the project successfully. Project Scope Management has several purposes:It defines what work is needed to complete the project objectives.It determines what is included in the project.It serves as a guide to determine what work is not needed to complete the project objectives.It serves as point of reference for what is not included in the project.It guides the project manager on decision to add, change, or remove the work of the project.
the inputs, tools and techniques, and outputs of scope planning.Tools and Techniques OutputsProduct Analysis Scope StatementBenefit/Cost Analysis Supporting DetailAlternatives Identification Scope Management PlanExpert Judgment
The scope statement is a document that describes the work, and only the required work, necessary to meet the project objectives. The scope statement establishes a common vision among the project stakeholders to establish
t work. It is used as a baseline against which all future project decisions are made to determine if proposed changes or work results are aligned with expectations. The scope statement, may, with adequate reason, be updated to reflect changes in the project work.
Identifies the business needs of the project. It answers why the project has been authorized.The scope statement reiterates the details of the project product.
level deliverables of the project should be identified. These deliverables, when predefined metrics are met, signal that project scope has been completed. When appropriate, it should also list
rom the project deliverables. For ex: a project to create a new food product may state that it is not including the packaging of the food product as part of the project. Items and features not listed as part of the project deliverables should be assumed to be excluded.
Project objectives are specific conditions that determine the success of a project. Conditions are typically cost, schedule, and quality metrics. Vague metrics, such as customer satisfaction, increase the risk for
ect, as the metric “customer satisfaction” is subjective and not quantified.
The two process types are interrelated and interdependent. Thus, a project manager must be familiar with the nagement processes. To use a real world example, a
project manager should be familiar with both how a house is constructed and the various phases involved in that
The process groups are a collection of activities that contribute to the control and implementation of the project management life cycle. The output of one process group will act as input for another process group.
Project objectives are determined, as well as how to reach those objectives with the given constraints.
performance is monitored and measured to ensure the project plan is being implemented to
ment constitutes the processes that the project includes all of the work required, and only the work required, to complete the project successfully. Project Scope Management has several purposes:
It serves as a guide to determine what work is not needed to complete the project objectives.
decision to add, change, or remove the work of the project.
Scope StatementSupporting DetailScope Management Plan
The scope statement is a document that describes the work, and only the required work, necessary to meet the project objectives. The scope statement establishes a common vision among the project stakeholders to establish
project decisions are
ct work. It includes or
Identifies the business needs of the project. It answers why the project has been authorized.
level deliverables of the project should be identified. These deliverables, when predefined metrics are met, signal that project scope has been completed. When appropriate, it should also list
rom the project deliverables. For ex: a project to create a new food product may state that it is not including the packaging of the food product as part of the project. Items and features not listed
Project objectives are specific conditions that determine the success of a project. Conditions are typically cost, schedule, and quality metrics. Vague metrics, such as customer satisfaction, increase the risk for
9 Guide to Project Management
The following table depicts the Inputs, Outputs and Tools and Techniques of Scope DefinitionInputs Tools and TechniquesScope Statement Work Breakdown Structure Constraints DecompositionAssumptionsOther planning outputsHistorical information
7.2. Creating the Work Breakdown StructureThe Work Breakdown Structure (WBS) is an organized collection of the project deliverable to be created by project work. A WBS breaks down into a deliverablecannot complete the activity alone. Tindividuals close to the work and will be completing the actual activities within the project phases. The smallest element in the WBS is called the Work Package. WBS also identifies the relationship between work packages.
Fig 3: A sample WBS for a technology project
Some essential elements about the WBS: Serves as the project scope baseline. One of the most important project management tools. Serves as the foundation for planning, estimating, and project control. Visualizes the entire project. Work not included in the WBS is not part of the project. Builds team consensus and buy Serves as a control mechanism to keep the project on track. Allows for accurate cost and time estimates. Serves as deterrent to scope change.
WBS is an input to five core processes:
PM Activities
Planning
Meetings
Schedule
Budgeting
Training
Development
Courseware
WBT
Handouts
Classes
WBS
Cost Estimating
Cost Budgeting
Resource Planning
Guide to Project Management by WorkMonk.com
The following table depicts the Inputs, Outputs and Tools and Techniques of Scope DefinitionTools and Techniques OutputsWork Breakdown Structure template Work Breakdown StructureDecomposition Scope statement updates
Creating the Work Breakdown StructureThe Work Breakdown Structure (WBS) is an organized collection of the project deliverable to be created by project
A WBS breaks down into a deliverable-oriented collection of manageable pieces. The project manager cannot complete the activity alone. The input and guidance of the project team is required as they are the individuals close to the work and will be completing the actual activities within the project phases. The smallest element in the WBS is called the Work Package. WBS also identifies the relationship between work
Fig 3: A sample WBS for a technology project
Some essential elements about the WBS:Serves as the project scope baseline.
most important project management tools.Serves as the foundation for planning, estimating, and project control.
Work not included in the WBS is not part of the project.Builds team consensus and buy-in to the project.
s as a control mechanism to keep the project on track.Allows for accurate cost and time estimates.Serves as deterrent to scope change.
OS Rollout
Testing
Planning
Scenario
Simulations
Pilots
Lab
Rollout
IT Dept
Sales
AA's
Education
HR
Accounting
Documentation
Courseware
Operations
Versioning
Issues
Knowledge Management
WBS
Resource Planning
Risk Management
Activity Definition
Work Breakdown StructureScope statement updates
The Work Breakdown Structure (WBS) is an organized collection of the project deliverable to be created by project The project manager
he input and guidance of the project team is required as they are the individuals close to the work and will be completing the actual activities within the project phases. The smallest element in the WBS is called the Work Package. WBS also identifies the relationship between work
10 Guide to Project Management
8. Estimating Cost and Developing BudgetCost estimating is the process of calculating the costs of the identified resources required to complete the project work. It relies on several project componentsrelies on historical information and policies from the performing organization.
8.1. Cost Estimating InputsUsing the Work Breakdown Structure:planning, risk management planning, and activity definition.Relying on Resource Requirements: The project will have some requirement for resources equipment must all be accounted for.Calculating Resource Rates: The estimator should know how much each resource costs. There are four categoriesof cost:Direct Costs: Attributed directly to the project work and cannot be shared among projects.Variable Costs: Costs that vary depending on the conditions applied in the project.Fixed Costs: Costs that remains constant throughout the project.Indirect Costs: Costs that are representative of more than one project.
8.2. Estimating Activity DurationsEstimates of the duration of the activities, which predict the length of the project, are needed for decisions on financing the project.
8.3. Analyzing Cost Estimating ResultsThe output of cost estimating is the actual cost estimates of the resources required to the complete the project work. The cost of the project is expressed in monetary terms so that the management can compare projects based on costs. The estimate can be presented n detail against the WBS components or summarized in terms of a grand total, by phases of the project, or by major deliverables. Each resource in the project must be accounted for and assigned to a cost category. Categories incluLabor Costs, Material Costs, Travel Costs, Supplies, Hardware Costs, Software Costs etc.
8.4. Cost BudgetingCost Budgeting is the process of assigning a cost to an individual work package. The aim is to assign costs to the work in the project so that the work may be measured for performance.
Cost Estimates Predicted costs for the project workWork Breakdown Structure Deliverable of the project as it’s what the project is buyingProject Schedule It’s needed to Risk Management Plan It provides the probability of identified risks and their associated costs.
8.5. Developing the project BudgetThe tools and techniques used to create the project cost estimates are Analogous Budgeting: Form of expert judgment that uses a topaccurate than other methods.Parametric Budgeting: Uses a parametric model to extrapolate what costs cost/unit). Also includes variables and points based on conditions.Bottom-up Budgeting: Most reliable approach, though it takes the longest to create. Starts at zero and requires each work package to be accounted forComputerized Tools: Software programs that are used in estimating can be used to help predict the project budget with some accuracy.
Guide to Project Management by WorkMonk.com
Estimating Cost and Developing BudgetCost estimating is the process of calculating the costs of the identified resources required to complete the project work. It relies on several project components from the Initiation and planning process groups. The process also relies on historical information and policies from the performing organization.
Using the Work Breakdown Structure: It’s an input to five major planning processes: cost estimating, planning, risk management planning, and activity definition.
The output of resource planning serves as a key input for estimating costl have some requirement for resources – the skills of the labor, the ability of materials, or the function of
The estimator should know how much each resource costs. There are four categories
Attributed directly to the project work and cannot be shared among projects.Costs that vary depending on the conditions applied in the project.
Costs that remains constant throughout the project.Costs that are representative of more than one project.
Estimating Activity DurationsEstimates of the duration of the activities, which predict the length of the project, are needed for decisions on
Estimating ResultsThe output of cost estimating is the actual cost estimates of the resources required to the complete the project
The cost of the project is expressed in monetary terms so that the management can compare projects based estimate can be presented n detail against the WBS components or summarized in terms of a grand
total, by phases of the project, or by major deliverables. Each resource in the project must be accounted for and assigned to a cost category. Categories include the following:Labor Costs, Material Costs, Travel Costs, Supplies, Hardware Costs, Software Costs etc.
Cost Budgeting is the process of assigning a cost to an individual work package. The aim is to assign costs to the so that the work may be measured for performance.
Inputs to Cost BudgetingPredicted costs for the project workDeliverable of the project as it’s what the project is buyingIt’s needed to determine when the amount in the budget will be spent.It provides the probability of identified risks and their associated costs.
Developing the project BudgetThe tools and techniques used to create the project cost estimates are also used to create the project budget.
Form of expert judgment that uses a top-down approach to predict costs. Generally, it’s less
Uses a parametric model to extrapolate what costs will be for a project (ex: cost/hr and cost/unit). Also includes variables and points based on conditions.
Most reliable approach, though it takes the longest to create. Starts at zero and requires each work package to be accounted for.
Software programs that are used in estimating can be used to help predict the project budget
Cost estimating is the process of calculating the costs of the identified resources required to complete the project lanning process groups. The process also
s an input to five major planning processes: cost estimating, resource
estimating cost. The the skills of the labor, the ability of materials, or the function of
The estimator should know how much each resource costs. There are four categories
Estimates of the duration of the activities, which predict the length of the project, are needed for decisions on
The output of cost estimating is the actual cost estimates of the resources required to the complete the project The cost of the project is expressed in monetary terms so that the management can compare projects based
estimate can be presented n detail against the WBS components or summarized in terms of a grand total, by phases of the project, or by major deliverables. Each resource in the project must be accounted for and
Cost Budgeting is the process of assigning a cost to an individual work package. The aim is to assign costs to the
determine when the amount in the budget will be spent.It provides the probability of identified risks and their associated costs.
also used to create the project budget.down approach to predict costs. Generally, it’s less
will be for a project (ex: cost/hr and
Most reliable approach, though it takes the longest to create. Starts at zero and requires
Software programs that are used in estimating can be used to help predict the project budget
11 Guide to Project Management
8.6. Earned Value Management It is the process of measuring performance of project work against a plan to identify variances.Planned Value (PV): It is the work scheduled and the authorized budget to accomplish that work. For ex: if a project has a budget of $10,000 and month six represents 50% of the project work, the PV for that month is $5,000. PV is also known as Budget Cost of Work Schedule (BCWS).Earned Vale (EV): It is the physical work completed till date and the authorized budget for that work. For Ex: If a project has a budget of $10,000 and the work completed till date represents 25% of the entire project work, its EVis $2,500. EV is also known as Budgeted Cost of Work Performed (BCWP).Actual Cost (AC): It is the actual amount of monies the project has incurred till date. For ex: if a project has a budget of $10,000 and $5,000 has been spent on the project till date,known as Actual Cost of Work Performed (ACWP).
9. Creating the Network DiagramA network diagram shows the relationship of the work activities and how the work will progress from start to completion. A network diagram visualizes the project work. These diagrams can vary from being extremely complex to easy to create and configure.
9.1. Precedence Diagram MethodThe PDM is the most common method of arranging the project work visually. It puts the activities in boxes called nodes, and connects the boxes with arrows. The arrows represent the relationship and dependencies of work packages.
Relationships between activities in a PDM constitute one of four different types:Finish-to-Start (FS): It means task A must be completed before Task B.Start-to-Start (SS): It means Task A must start before Task B can start.Finish-to Finish (FF): It means Task A must complete before Task B does.Start-to-Finish (SF): It requires that Task A
9.2. Arrow Diagramming MethodADM approach uses arrows to represent the activities. The arrows are connected on nodes. ADM only uses finishto-start relationships. ADM is an example of Activity
9.3. Conditional Diagramming MethodCDMs are more complex and structure than ADM or PDM. CDM includes system dynamics and graphical evaluation and review technique (GERT). These models allow for loops and conditional branching. GERT also alloprobabilistic clarification of work package estimates.
10.Creating the Project ScheduleCreating the project schedule is part of the planning process group. It is calendar based and relies on the project network diagram and the accuracy of time estimatscope in the shortest amount of time possible without incurring exceptional costs, risks, or a loss of quality.
Start
C
Guide to Project Management by WorkMonk.com
Earned Value Management is the process of measuring performance of project work against a plan to identify variances.
It is the work scheduled and the authorized budget to accomplish that work. For ex: if a project has a budget of $10,000 and month six represents 50% of the project work, the PV for that month is $5,000. PV is
of Work Schedule (BCWS).It is the physical work completed till date and the authorized budget for that work. For Ex: If a
project has a budget of $10,000 and the work completed till date represents 25% of the entire project work, its EVis $2,500. EV is also known as Budgeted Cost of Work Performed (BCWP).
It is the actual amount of monies the project has incurred till date. For ex: if a project has a budget of $10,000 and $5,000 has been spent on the project till date, then the AC would be $5,000. AC is alknown as Actual Cost of Work Performed (ACWP).
Creating the Network DiagramA network diagram shows the relationship of the work activities and how the work will progress from start to
visualizes the project work. These diagrams can vary from being extremely complex to easy to create and configure.
Precedence Diagram MethodThe PDM is the most common method of arranging the project work visually. It puts the activities in boxes called
des, and connects the boxes with arrows. The arrows represent the relationship and dependencies of work
Relationships between activities in a PDM constitute one of four different types:It means task A must be completed before Task B.
It means Task A must start before Task B can start.It means Task A must complete before Task B does.
It requires that Task A to start so that Task B may finish.
Arrow Diagramming MethodADM approach uses arrows to represent the activities. The arrows are connected on nodes. ADM only uses finish
start relationships. ADM is an example of Activity-on-Arrow (AOA) networks.
Conditional Diagramming MethodCDMs are more complex and structure than ADM or PDM. CDM includes system dynamics and graphical evaluation and review technique (GERT). These models allow for loops and conditional branching. GERT also alloprobabilistic clarification of work package estimates.
Creating the Project ScheduleCreating the project schedule is part of the planning process group. It is calendar based and relies on the project network diagram and the accuracy of time estimates. The point of the project schedule is to complete the project scope in the shortest amount of time possible without incurring exceptional costs, risks, or a loss of quality.
A B
D
End
It is the work scheduled and the authorized budget to accomplish that work. For ex: if a project has a budget of $10,000 and month six represents 50% of the project work, the PV for that month is $5,000. PV is
It is the physical work completed till date and the authorized budget for that work. For Ex: If a project has a budget of $10,000 and the work completed till date represents 25% of the entire project work, its EV
It is the actual amount of monies the project has incurred till date. For ex: if a project has a the AC would be $5,000. AC is also
A network diagram shows the relationship of the work activities and how the work will progress from start to visualizes the project work. These diagrams can vary from being extremely
The PDM is the most common method of arranging the project work visually. It puts the activities in boxes called des, and connects the boxes with arrows. The arrows represent the relationship and dependencies of work
ADM approach uses arrows to represent the activities. The arrows are connected on nodes. ADM only uses finish-
CDMs are more complex and structure than ADM or PDM. CDM includes system dynamics and graphical evaluation and review technique (GERT). These models allow for loops and conditional branching. GERT also allows for
Creating the project schedule is part of the planning process group. It is calendar based and relies on the project es. The point of the project schedule is to complete the project
scope in the shortest amount of time possible without incurring exceptional costs, risks, or a loss of quality.
12 Guide to Project Management
10.1. Applying Mathematical AnalysisMathematical analysis is the process of factorinwith the project network diagrams. Three common methods for mathematical analysis are:Program Evaluation and Review Technique (PERT): activities will end. It uses “Pessimistic”, “Optimistic” and “completed.Formula: (O+4M+P)/6Graphical Evaluation and Review Techniqueof activities and is based on probable estimates. Activities within GERT are dependent on other upstream activities. For ex: the results of work package may determine if additional testing is needed, rework is required, or the project may continue as planned.Critical Path Method (CPM): It is the most commonly used method for calculating finish time of a project. It uses a “forward” pass and “backward” pass to reveal which activities are considered critical. Activities on the critical path should not be delayed; else the project end date will be delayed. The critical path is defined as the path with the longest duration to complete. Activities not on the critical path have some float (slack) that allows some amount of delay without delaying the project end date.Three different kinds of float:Free Float: Total time a single activity can be delayed without delaying the early start of any successor activities.Total Slack: Total time for which an activity can be delayed without delaying project comProject Slack: Total time the project can be delayed without passing the customer expected completion date.
10.2. Examining the Project scheduleProject schedule can be presented in many different formats:Project Network Diagrams: Illustrates the flowproject end date and dates associated with each project activity.Bar Charts: Shows the start and end dates for the project, and are listed down the left hand side and a time scale is shown along the bottom. interrelationships of activities and if one activity is These are easy to read and these scheduling bar charts are also called Gantt Charts.Milestone Charts: These plot out the high level deliverables and external interfaces, such as customer walk through, against a calendar. These are similar to Gantt charts, but with less detail regarding i
11.Project Integration ManagementIt is the art and science of ensuring that your project moves forward, that your plan is fully developed and properly implemented. It is made up of the dayparts of the project work together.
It requires expertise, as the project manager will have to negotiate with the stakeholders for a resolution to competing objectives.
It requires proper organization as project manager will have to develop, coproject plan.
It requires the ability to accomplish the project plan. It required leadership, record
changes throughout the project implementation. It requires flexibility and adaptability throughout the project execution.
12.Project Quality ManagementQuality management is the process to ensure the project is completed with no deviatiThere are several quality management philosophies:
Guide to Project Management by WorkMonk.com
Applying Mathematical AnalysisMathematical analysis is the process of factoring theoretical early and latest start and finish dates for each activity with the project network diagrams. Three common methods for mathematical analysis are:Program Evaluation and Review Technique (PERT): PERT uses a weighted average method to predict wh
It uses “Pessimistic”, “Optimistic” and “Most likely” estimate to predict when the project will be
Graphical Evaluation and Review Technique (GERT): GERT uses conditional advancement, branching, of activities and is based on probable estimates. Activities within GERT are dependent on other upstream activities. For ex: the results of work package may determine if additional testing is needed, rework is required, or the
It is the most commonly used method for calculating finish time of a project. It uses a “forward” pass and “backward” pass to reveal which activities are considered critical. Activities on the critical path
d not be delayed; else the project end date will be delayed. The critical path is defined as the path with the Activities not on the critical path have some float (slack) that allows some amount of
roject end date.
Total time a single activity can be delayed without delaying the early start of any successor activities.Total time for which an activity can be delayed without delaying project completion.
Total time the project can be delayed without passing the customer expected completion date.
Examining the Project scheduleProject schedule can be presented in many different formats:
Illustrates the flow of work, relationship between activities, critical path, and expected project end date and dates associated with each project activity.
Shows the start and end dates for the project, and the activity duration against a calendar. listed down the left hand side and a time scale is shown along the bottom. But these do not show
interrelationships of activities and if one activity is delayed, it is not obvious that how will it affect other activities. scheduling bar charts are also called Gantt Charts.
These plot out the high level deliverables and external interfaces, such as customer walk through, against a calendar. These are similar to Gantt charts, but with less detail regarding individual activities.
Project Integration Managementart and science of ensuring that your project moves forward, that your plan is fully developed and properly
is made up of the day-to-day processes the project manager relies on to ensure that all of the
requires expertise, as the project manager will have to negotiate with the stakeholders for a resolution
It requires proper organization as project manager will have to develop, co-ordinate, and record the
It requires the ability to accomplish the project plan.It required leadership, record-keeping, and political savvy as there may be a need to deal with potential changes throughout the project implementation. It requires flexibility and adaptability throughout the project execution.
Project Quality ManagementQuality management is the process to ensure the project is completed with no deviations from the requirements. There are several quality management philosophies:
g theoretical early and latest start and finish dates for each activity
PERT uses a weighted average method to predict when the ikely” estimate to predict when the project will be
GERT uses conditional advancement, branching, and looping of activities and is based on probable estimates. Activities within GERT are dependent on other upstream activities. For ex: the results of work package may determine if additional testing is needed, rework is required, or the
It is the most commonly used method for calculating finish time of a project. It uses a “forward” pass and “backward” pass to reveal which activities are considered critical. Activities on the critical path
d not be delayed; else the project end date will be delayed. The critical path is defined as the path with the Activities not on the critical path have some float (slack) that allows some amount of
Total time a single activity can be delayed without delaying the early start of any successor activities.pletion.
Total time the project can be delayed without passing the customer expected completion date.
of work, relationship between activities, critical path, and expected
he activity duration against a calendar. Activities But these do not show
, it is not obvious that how will it affect other activities.
These plot out the high level deliverables and external interfaces, such as customer walk ndividual activities.
art and science of ensuring that your project moves forward, that your plan is fully developed and properly to ensure that all of the
requires expertise, as the project manager will have to negotiate with the stakeholders for a resolution
ordinate, and record the
o deal with potential
ons from the requirements.
13 Guide to Project Management
Total Quality Management: The organization strives for constant improvement for products and business practices.Kaizen: The organization applies small changes to products and prand provide overall quality improvement.Marginal Analysis: The cost of quality is not greater than the increased sales because of the level of quality implemented. Ideally, the revenue generated because of thequality.
12.1. Implementing Quality Control Quality control monitors specific results within a project. Concerned that the results must satisfy relevant quality standards. Can rely on root cause analysis used to Completed through inspection.
12.2. Charting Quality ControlFishbone Diagram: It’s a cause effect diagram that illustrates the factors which may issues or problems. It’s also known as Ishikawa diagraFlow Charts: They demonstrate how a system works from start to finish, and how system components are integrated.Pareto Charts: These histograms are related to Pareto’s 80/20 rule which says “80% of the problems come from 20% of the issues.” This diagram charts the problems, categories, and frequency. Project team should first solve the larger problems and then move to smaller issues.Control Charts: These charts plot out the results of the inspections against a mean to examine performance against expected results. Upper and lower control limits are typically set +or the control limit value are considered out of coto determine why the result occurred.
12.3. Evaluating Quality Costs The cost of quality is the amount of money the organization must spend on the quality standards. The cost of nonconformance
demands. Optimal quality is reached when the cost of quality meets or exceeds the incremental cost to achieve
quality.
12.4. Implementing Quality Assurance Monitors overall results. May use a QA program to set quality standards. Represents the implementation of the quality plan.
13.Project Human Resource ManagementProject Human Resource Management is the ability to lead, direct, and orchestrate the project team, the customers, project partners, contributors, and any other stakeholders to achieve the desired results for the project purpose.
It focuses on utilizing the people involved in the project in the most effective way. Because projects are often similar, the project managers can rely on
historical projects. Staffing Management plan describes the process that the project manager must follow to bring resources
onto a project, or to dismiss them when the resources are no longer needed. The policies and procedures of the performing organization should be documented within the staffing
management plan to ensure the guidelines are followed as management intends.
Guide to Project Management by WorkMonk.com
The organization strives for constant improvement for products and business
The organization applies small changes to products and processes to improve consistency, reduce costs, and provide overall quality improvement.
The cost of quality is not greater than the increased sales because of the level of quality implemented. Ideally, the revenue generated because of the quality improvements far exceeds the cost of the
Implementing Quality ControlQuality control monitors specific results within a project.
oncerned that the results must satisfy relevant quality standards.cause analysis used to eliminate unsatisfactory results.
ompleted through inspection.
Charting Quality ControlIt’s a cause effect diagram that illustrates the factors which may be contributing to quality
issues or problems. It’s also known as Ishikawa diagram.They demonstrate how a system works from start to finish, and how system components are
These histograms are related to Pareto’s 80/20 rule which says “80% of the problems come from m charts the problems, categories, and frequency. Project team should first solve
the larger problems and then move to smaller issues.These charts plot out the results of the inspections against a mean to examine performance
against expected results. Upper and lower control limits are typically set +or – 3/6 sigma. Results that are beyond the control limit value are considered out of control and they have an assignable cause that requires investigation to determine why the result occurred.
Evaluating Quality CostsThe cost of quality is the amount of money the organization must spend on the quality standards.The cost of nonconformance to quality is the money or event attributed to not satisfying the quality
Optimal quality is reached when the cost of quality meets or exceeds the incremental cost to achieve
Implementing Quality Assurance
e a QA program to set quality standards.Represents the implementation of the quality plan.
Project Human Resource ManagementProject Human Resource Management is the ability to lead, direct, and orchestrate the project team, the
s, contributors, and any other stakeholders to achieve the desired results for the project
It focuses on utilizing the people involved in the project in the most effective way.Because projects are often similar, the project managers can rely on templates to re-create the success of
Staffing Management plan describes the process that the project manager must follow to bring resources onto a project, or to dismiss them when the resources are no longer needed.
rocedures of the performing organization should be documented within the staffing to ensure the guidelines are followed as management intends.
The organization strives for constant improvement for products and business
ocesses to improve consistency, reduce costs,
The cost of quality is not greater than the increased sales because of the level of quality quality improvements far exceeds the cost of the
be contributing to quality
They demonstrate how a system works from start to finish, and how system components are
These histograms are related to Pareto’s 80/20 rule which says “80% of the problems come from m charts the problems, categories, and frequency. Project team should first solve
These charts plot out the results of the inspections against a mean to examine performance 3/6 sigma. Results that are beyond
ntrol and they have an assignable cause that requires investigation
The cost of quality is the amount of money the organization must spend on the quality standards.to quality is the money or event attributed to not satisfying the quality
Optimal quality is reached when the cost of quality meets or exceeds the incremental cost to achieve
Project Human Resource Management is the ability to lead, direct, and orchestrate the project team, the s, contributors, and any other stakeholders to achieve the desired results for the project
create the success of
Staffing Management plan describes the process that the project manager must follow to bring resources
rocedures of the performing organization should be documented within the staffing
14 Guide to Project Management
The project manager should not forget to involve other stakeholders: customers, management, indivcontributors, project sponsor, and any other stakeholder unique to the project.
Organizational planning calls on the project manager to identify the roles and responsibilities of the project and the reporting relationship within the organization.
Reporting relationships can be internal (management) or external (customer/community). The relationships and the procedure to communicate with these projects interfaces must be documented.
Project performance improvements must be noted in an honest appraisal effort and contributions to the project.
Special care to involve the project team must be given when the team is scattered geographically.
14.Project Communications ManagementThe most important skill a project manager should possProject Communications Management centers on determining who needs what information and when? And accordingly it produces a plan to provide the needed information.PCM includes generating, collecting, disseminating, and stosuccessful communication. It is the key link between people, ideas and information.PCM includes four processes, which may overlap each other and other knowledge areas. The four processes are:Communication Planning: The planning manager will need to identify the stakeholders and their communications needs and determine how to fulfill their requirements.Information Distribution: The project manager will need to get the correct information on ththe appropriate stakeholders.Performance Reporting: The project manager will rely on EVM and other performance measurement to create status reports, measure performance, and forecast project conditions.Administrative Closure: The project manager will need a routine of documentation, communication, and information distribution to close out a phase or a project.
15.Project Risk ManagementRisks are uncertain events that can affect a project’s objectives for good or bad. Risk management pldetermining how the risk management activities within the project will take place. It is basically the determination of how to manage project risks. Risk management planning is accomplished through planning meetings with the project team, management, customers, and other key stakeholders. The output of risk management planning is the risk management plan.Risks can be placed into following major categories:
Technical Risks Quality or Performance Risks Project Management Risks Organizational Risks External Risks
Project files from published information and previous projects can serve as input to risk identification.The Delphi technique allows participants to identify risk anonymously without fear of embarrassment. A survey allows results to be shared with all participants for comments on each other’s anonymous inputs. Rounds of surveying and analysis can create consensus on the major project risks.Triggers are warning signs that a risk is about to happen or risk has happened.
15.1. Analyzing Identified Risks Risks can be ranked by ordinal ranking by using such indicators as very low, low, moderate, high, and very
high.
Guide to Project Management by WorkMonk.com
The project manager should not forget to involve other stakeholders: customers, management, indivcontributors, project sponsor, and any other stakeholder unique to the project.Organizational planning calls on the project manager to identify the roles and responsibilities of the project and the reporting relationship within the organization.
orting relationships can be internal (management) or external (customer/community). The relationships and the procedure to communicate with these projects interfaces must be documented.Project performance improvements must be noted in an honest appraisal of the project team members’ effort and contributions to the project.Special care to involve the project team must be given when the team is scattered geographically.
Project Communications ManagementThe most important skill a project manager should possess is effective communication. Project Communications Management centers on determining who needs what information and when? And accordingly it produces a plan to provide the needed information.PCM includes generating, collecting, disseminating, and storing communication. Successful projects require successful communication. It is the key link between people, ideas and information.PCM includes four processes, which may overlap each other and other knowledge areas. The four processes are:
The planning manager will need to identify the stakeholders and their communications needs and determine how to fulfill their requirements.
The project manager will need to get the correct information on the correct schedule to
The project manager will rely on EVM and other performance measurement to create status reports, measure performance, and forecast project conditions.
oject manager will need a routine of documentation, communication, and information distribution to close out a phase or a project.
Project Risk ManagementRisks are uncertain events that can affect a project’s objectives for good or bad. Risk management pldetermining how the risk management activities within the project will take place. It is basically the determination of how to manage project risks. Risk management planning is accomplished through planning meetings with the
ent, customers, and other key stakeholders. The output of risk management planning is
major categories:
Project files from published information and previous projects can serve as input to risk identification.allows participants to identify risk anonymously without fear of embarrassment. A survey ared with all participants for comments on each other’s anonymous inputs. Rounds of
surveying and analysis can create consensus on the major project risks.Triggers are warning signs that a risk is about to happen or risk has happened.
RisksRisks can be ranked by ordinal ranking by using such indicators as very low, low, moderate, high, and very
The project manager should not forget to involve other stakeholders: customers, management, individual
Organizational planning calls on the project manager to identify the roles and responsibilities of the
orting relationships can be internal (management) or external (customer/community). The relationships and the procedure to communicate with these projects interfaces must be documented.
of the project team members’
Special care to involve the project team must be given when the team is scattered geographically.
Project Communications Management centers on determining who needs what information and when? And
Successful projects require
PCM includes four processes, which may overlap each other and other knowledge areas. The four processes are:The planning manager will need to identify the stakeholders and their communications
e correct schedule to
The project manager will rely on EVM and other performance measurement to create
oject manager will need a routine of documentation, communication, and
Risks are uncertain events that can affect a project’s objectives for good or bad. Risk management planning is determining how the risk management activities within the project will take place. It is basically the determination of how to manage project risks. Risk management planning is accomplished through planning meetings with the
ent, customers, and other key stakeholders. The output of risk management planning is
Project files from published information and previous projects can serve as input to risk identification.allows participants to identify risk anonymously without fear of embarrassment. A survey ared with all participants for comments on each other’s anonymous inputs. Rounds of
Risks can be ranked by ordinal ranking by using such indicators as very low, low, moderate, high, and very
15 Guide to Project Management
Risks can also be analyzed using a cardinal ranking system of numerical values that are assigned to each risk based on its impact and pr
An overall project risk ranking can be used to compare the current projects with other projects in the organization.
The risks can be moved into quantitative analysis for further study. Risks are assigned numeric values.
15.2. Risk Management MethodsThe Monte Carlo Simulation can determine the likelihood of the project’s success, predict the costs of a specific risk exposure, and identify realistic time, scope, and cost objectives. Interviews with stakeholders and subject matter experts are an excellent start for quantitative risk analysis.Decision Trees help determine the cost, benefit, and value of multiple decisions. They are based on he cost of the decision and the probability of completing an objective.
15.3. Responding to Identified Risks Risk thresholds, defined in risk management planning, describe the acceptable level of risk within a
company. Risk owners are the individuals or groups that are responsible for a risk response, and should participate
in the risk response planning. Risk avoidance changes the project plan to avoid the risk. Risk transference moves the risk consequence to a third party. Risk Mitigation involves actions designed to reduce likelihood of a risk occurring, reduce the impact of a
risk on the project objectives, or both. Risk Acceptance acknowledges the risk exists but the risk is not worthy of a more in Residual Risks are risks that remain after avoidance, transference, mitigation, and acceptance.
15.4. Iterative Risk Management Identified risks must be tracked, Issue logs, action-item lists, jeopardy warnings, and escalation notices are all types of communication
reports the project team and risk owners must use to document and track identified risks. Risk response audits measure the success
quality values gained or lost by the risk responses. Earned Value analysis can measure project performance, but it can also predict and signal pending risks
within the project.
16.Why Projects Fails? Not enough resources are available for project completion. Not enough time has been given to the project. Project expectations are unclear. Changes in the scope are not understood or agreed upon by all parties involved. Stakeholders disagree regarding expectations for the project. Adequate project planning is not used. Lack of effective leadership and management. Ambiguous communications and conflicts among team members.
Efficient Project management with effective management skills projects also successful and result in utmost customer satisfaction.
Guide to Project Management by WorkMonk.com
Risks can also be analyzed using a cardinal ranking system of numerical values that are assigned to each risk based on its impact and probability.An overall project risk ranking can be used to compare the current projects with other projects in the
The risks can be moved into quantitative analysis for further study.Risks are assigned numeric values.
Risk Management Methodscan determine the likelihood of the project’s success, predict the costs of a specific
risk exposure, and identify realistic time, scope, and cost objectives. Interviews with stakeholders and subject ent start for quantitative risk analysis.
help determine the cost, benefit, and value of multiple decisions. They are based on he cost of the decision and the probability of completing an objective.
Responding to Identified Risksolds, defined in risk management planning, describe the acceptable level of risk within a
Risk owners are the individuals or groups that are responsible for a risk response, and should participate
changes the project plan to avoid the risk.Risk transference moves the risk consequence to a third party.Risk Mitigation involves actions designed to reduce likelihood of a risk occurring, reduce the impact of a risk on the project objectives, or both.
isk Acceptance acknowledges the risk exists but the risk is not worthy of a more in-depth response.Residual Risks are risks that remain after avoidance, transference, mitigation, and acceptance.
Iterative Risk ManagementIdentified risks must be tracked, monitored for warning signs, and documented.
item lists, jeopardy warnings, and escalation notices are all types of communication reports the project team and risk owners must use to document and track identified risks.
dits measure the success of the responses and the effectiveness of the cost, scope, and quality values gained or lost by the risk responses.Earned Value analysis can measure project performance, but it can also predict and signal pending risks
Not enough resources are available for project completion.Not enough time has been given to the project.Project expectations are unclear.Changes in the scope are not understood or agreed upon by all parties involved.
lders disagree regarding expectations for the project.Adequate project planning is not used.Lack of effective leadership and management.Ambiguous communications and conflicts among team members.
Project management with effective management skills can make even the most difficult and compprojects also successful and result in utmost customer satisfaction.
Risks can also be analyzed using a cardinal ranking system of numerical values that are assigned to each
An overall project risk ranking can be used to compare the current projects with other projects in the
can determine the likelihood of the project’s success, predict the costs of a specific risk exposure, and identify realistic time, scope, and cost objectives. Interviews with stakeholders and subject
help determine the cost, benefit, and value of multiple decisions. They are based on he cost of the
olds, defined in risk management planning, describe the acceptable level of risk within a
Risk owners are the individuals or groups that are responsible for a risk response, and should participate
Risk Mitigation involves actions designed to reduce likelihood of a risk occurring, reduce the impact of a
depth response.Residual Risks are risks that remain after avoidance, transference, mitigation, and acceptance.
item lists, jeopardy warnings, and escalation notices are all types of communication reports the project team and risk owners must use to document and track identified risks.
of the responses and the effectiveness of the cost, scope, and
Earned Value analysis can measure project performance, but it can also predict and signal pending risks
can make even the most difficult and complex