Download - Project Execution Plan for Bridge Construction

Transcript
Page 1: Project Execution Plan for Bridge Construction

Bridge Construction, Project Execution PlanDetails of how a Bridge is constructed, and how the progress, safety and quality will be monitored and controlled. Also the measures to ensure that the site is environmentally friendly.

David H Moloney

8th August 2016

Brief Description

The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct an insitu concrete bridge.

This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge.

Project Execution Plan (PEP) details how a project will be executed, monitored and controlled. High in Educational Value and easily understood. Recommended for Continuing Professional Development (CPD)

This Presentation is innovative and has many beneficial uses.

Page 2: Project Execution Plan for Bridge Construction

Table of Contents

Page 3: Project Execution Plan for Bridge Construction

Introduction

Page 4: Project Execution Plan for Bridge Construction

Project Location & Nearby National Roads In

troduction

Page 5: Project Execution Plan for Bridge Construction

Location of Bridge on Site Muscat Airport, Oman

Intr

oduction

Page 6: Project Execution Plan for Bridge Construction

Description & Scope

Brief Description & Scope

Four span insitu post-tensioned deck, Piled foundations.

Construction of the Bridge and Handover.

Intr

oduction

Page 7: Project Execution Plan for Bridge Construction

General Items

Page 8: Project Execution Plan for Bridge Construction

Contractor’s Temporary Site Facilities

ⓒ David H Moloney

Genera

l Item

s

To see animations, see my YouTube Film

Page 9: Project Execution Plan for Bridge Construction

Welfare Facilities

ⓒ David H Moloney

Genera

l Item

s

Toilets – Washing

Canteen, Drying Room, Toilet & Generator

Page 10: Project Execution Plan for Bridge Construction

Temporary Roads & Entrances

ⓒ David H Moloney

Genera

l Item

s

Page 11: Project Execution Plan for Bridge Construction

Site Hoarding examples

ⓒ David H Moloney

Genera

l Item

s

Page 12: Project Execution Plan for Bridge Construction

Dust Suppression

ⓒ David H Moloney

Genera

l Item

s

Page 13: Project Execution Plan for Bridge Construction

Wheel Wash Drive-through

ⓒ David H Moloney

Genera

l Item

s

Page 14: Project Execution Plan for Bridge Construction

Temporary Electricity Supply & Tower Lights

ⓒ David H Moloney

Genera

l Item

s

Page 15: Project Execution Plan for Bridge Construction

Contractor’s Temporary Site Facilities

ⓒ David H Moloney

Genera

l Item

s

Brief Description

Contractors Site facilities comprise:Offices, Canteens, Toilets, Drying Rooms, Stores, Plant Yard, generators and Workshops.

Page 16: Project Execution Plan for Bridge Construction

Dewatering

ⓒ David H Moloney

Genera

l Item

s

Brief Description

Construction dewatering is the removal or drainage of

groundwater and or surface / rain water usually by

pumping to keep the works dry.

Page 17: Project Execution Plan for Bridge Construction

Dewatering

ⓒ David H Moloney

Genera

l Item

s

Brief Description

Construction dewatering is the removal or

drainage of groundwater and or surface /

rain water usually by pumping to keep the

works dry.

Page 18: Project Execution Plan for Bridge Construction

Dewatering

ⓒ David H Moloney

Genera

l Item

s

Page 19: Project Execution Plan for Bridge Construction

Temporary WorksG

enera

l Item

s

Page 20: Project Execution Plan for Bridge Construction

FalseworkG

enera

l Item

s

Brief Description

Falsework to support Bridge deck formwork until the deck is post-

tensioned and becomes self supporting

Page 21: Project Execution Plan for Bridge Construction

Sheet Pile Temporary Shaft

ⓒ David H Moloney

Genera

l Item

s

Brief Description

Sheet Pile Temporary shaft is used to enable an excavation for a deep structure.The construction sequence is:Install sheet-piles.Excavate and install bracing.Excavate to final level.Construct concrete structure.Backfill, remove bracing and sheet-piles

Page 22: Project Execution Plan for Bridge Construction

Sheet pile Temporary Shaft

ⓒ David H Moloney

Genera

l Item

s

3D Animation to show Sequence

Page 23: Project Execution Plan for Bridge Construction

Sheet pile Cofferdam for Piers

ⓒ David H Moloney

Genera

l Item

s

Page 24: Project Execution Plan for Bridge Construction

Traffic Management

ⓒ David H Moloney

Genera

l Item

s

Brief Description

Traffic management plans are necessary when working on or beside roads

Page 25: Project Execution Plan for Bridge Construction

Traffic Management – Work on Median

ⓒ David H Moloney

Genera

l Item

s

Page 26: Project Execution Plan for Bridge Construction

Earthworks

Page 27: Project Execution Plan for Bridge Construction

Much Shifting

Brief Description

Muck Shifting is the process of moving

large quantities of soil and rock. Eart

hw

ork

s

Page 28: Project Execution Plan for Bridge Construction

Excavate & Load, Cart, Tip & Return

Brief Description

Cycle Time for 7km haulage distance using an Excavator 45 tonne weight and Dumper with a 40 tonne capacity, the cycle time is 34 minutes

Eart

hw

ork

s

7 minutes

14 minutes

3 minutes

14 minutes 7 km

7 km

Page 29: Project Execution Plan for Bridge Construction

Loading Tipper TrucksE

art

hw

ork

s

Page 30: Project Execution Plan for Bridge Construction

Tipping & Spreading FillE

art

hw

ork

s

Page 31: Project Execution Plan for Bridge Construction

Spreading & CompactionE

art

hw

ork

s

Page 32: Project Execution Plan for Bridge Construction

Spreading & CompactionE

art

hw

ork

s

Page 33: Project Execution Plan for Bridge Construction

Excavation for Trench with Stepped FacesE

art

hw

ork

s

Page 34: Project Execution Plan for Bridge Construction

Excavation for Trench with Battered FacesE

art

hw

ork

s

Page 35: Project Execution Plan for Bridge Construction

Backfill TrenchE

art

hw

ork

s

Page 36: Project Execution Plan for Bridge Construction

Rock - Excavability

Brief Description

The excavability of rock depends

mainly on the rock strength and the

layer thickness. This diagram shows

excavation methods for rock of

various strengths and thicknesses,

with a free face.

ⓒ David H Moloney

Eart

hw

ork

s

Page 37: Project Execution Plan for Bridge Construction

Eart

hw

ork

s

Excavator with Hydraulic Rock-breaker

Page 38: Project Execution Plan for Bridge Construction

Excavator with Hydraulic Rock-breakerE

art

hw

ork

s

Page 39: Project Execution Plan for Bridge Construction

Mass Haul DiagramE

art

hw

ork

s

Brief Description

Shows the quantities and location of

excavation and fill quantities for

motorway.

Page 40: Project Execution Plan for Bridge Construction

Concrete

Page 41: Project Execution Plan for Bridge Construction

Concrete Full Scale Trial Castings of Pier

ⓒ David H Moloney

Brief Description

The full-scale trial casting(s) shall

demonstrate/document that all

requirements to the concrete and the

execution of the work are fulfilled

simultaneously using the actual

methods and performed by personnel as

for the future production.

Concre

te

BIM 3D Model Shutter Fibreglass

Page 42: Project Execution Plan for Bridge Construction

Concrete Full Scale Trial Castings of Bridge Deck

Brief Description

The full-scale trial casting(s) shall

demonstrate/document that all

requirements to the concrete and the

execution of the work are fulfilled

simultaneously using the actual

methods and performed by personnel as

for the future production.

Concre

te

Fresh Concrete Properties Tests

Air Content, Consistence, Density, Initial and Final Setting Time, Temperature

and Bleeding

Chloride Ion Content

Hardening and Hardened Concrete Properties Tests:

Density and Compressive Strength for 1, 3, 7, 14 and 28 Days

Concrete Core Compressive Strength

Tensile Splitting Strength

Modulus of Elasticity

Heat Development

Chloride Migration Coefficient (28 Days)

Reinforcement Cover Measurement Survey

Page 43: Project Execution Plan for Bridge Construction

Concrete Tests

ⓒ David H Moloney

Concre

te

Page 44: Project Execution Plan for Bridge Construction

Trial Grouting of Post-tensioning Duct

ⓒ David H Moloney

Brief Description

The full-scale trial of grouting operation shall

demonstrate/document that all requirements to the grout and the

execution of the work are fulfilled simultaneously using the actual

methods and performed by personnel as for the future production.

Pre-trials were carried out in the site laboratory and by way of a

mock-up to check the following in accordance with BS EN 447:

i Fluidity

ii Bleeding and re-absorption

iii Compressive strength (3 cubes at 28 days, all > 30 N/mm2)

iv Mixing ratio (w/c < 0.40)

v Expansion (-1 % - +5 %). For grouts with expanding admixtures

there shall be no decrease in volume

Concre

te

Page 45: Project Execution Plan for Bridge Construction

Trial for Waterproofing to Bridge Deck

ⓒ David H Moloney

Brief Description

. The trial for the deck waterproofing

shall demonstrate/document that all

requirements to the waterproofing and

the execution of the work are fulfilled

simultaneously using the actual

methods and performed by personnel as

for the future production.

Concre

te

Page 46: Project Execution Plan for Bridge Construction

Trial for Waterproofing to Bridge Deck - TestsC

oncre

te

Page 47: Project Execution Plan for Bridge Construction

Concrete Batching Plant David H Moloney

ⓒ David H Moloney

Brief Description

Concrete batching plant comprises -

concrete mixer, control cabin, silos for

cement and fly ash, aggregate bins and

conveyor belt system to feed the mixer.

Also aggregate storage bays and water

storage tanks.

Concre

te

Page 48: Project Execution Plan for Bridge Construction

Concrete Batching Plant

ⓒ David H Moloney

Concre

te

Page 49: Project Execution Plan for Bridge Construction

Concrete Batching Plant 3Nr.

ⓒ David H Moloney

Concre

te

Page 50: Project Execution Plan for Bridge Construction

Concrete Batching Plant – Computer Controlled

ⓒ David H Moloney

Concre

te

Page 51: Project Execution Plan for Bridge Construction

Concrete Batching Plant - Liebherr Betomix AnimationC

oncre

te

Page 52: Project Execution Plan for Bridge Construction

Concrete Batching Plant David H Moloney

ⓒ David H Moloney

Brief Description

.

The mixing is computer controlled

and has a dynamic screen display,

showing the process. The material

storage capacity is, to match two

days concrete production.

Concre

te

Page 53: Project Execution Plan for Bridge Construction

Concrete Mix Proportions per Cu M

Brief Description

.

Details of Mix for C40

1. Concrete Grade C40

2. Cement Type = OPC

3. Slump =125mm

4. Max size aggregate = 20mm

5. Max water / Cementitious ration =0.42

Concre

te

Materials Qty Units

Cement 310 Kgs

Fly ash 100 Kgs

Micro-silica 12 Kgs

Washed Sand 670 Kgs

Fine Sand 106 Kgs

10mm Crushed aggregate 400 Kgs

20mm Crushed aggregates 725 Kgs

Water 145 Ltr.

Additive Rheobuild 7.5 Ltr.

Page 54: Project Execution Plan for Bridge Construction

Concrete MixG

enera

l Item

s

A concrete mix contains 5 major

elements: cement, water, coarse

aggregates, fine aggregates (sand) and

air in different proportion. Additional

elements such as pozzolanic materials (fly

ash, silica fumes or slag) and chemical

admixtures can also be incorporated to

the mix to increase its properties.

Page 55: Project Execution Plan for Bridge Construction

Quarry & Aggregate Production

ⓒ David H Moloney

Concre

te

Brief Description

Quarry and Aggregate Production. Rock is

blasted free from a quarry face and fragmented.

The blasted rock is crushed and screened to

produce different size ranges of aggregates

Page 56: Project Execution Plan for Bridge Construction

Quarry & Aggregate Production

ⓒ David H Moloney

Concre

te

Page 57: Project Execution Plan for Bridge Construction

Reinforcement Cutting & Bending Yard

ⓒ David H Moloney

Concre

te

Brief Description

Reinforcement in 12 m lengths. Delivery in 3 ton Bundles

Page 58: Project Execution Plan for Bridge Construction

Reinforcement Cutting & Bending

ⓒ David H Moloney

Concre

te

Page 59: Project Execution Plan for Bridge Construction

Reinforcement Cutting & Bending

ⓒ David H Moloney

Concre

te

Page 60: Project Execution Plan for Bridge Construction

Reinforcement Cutting & Bending Yard David H Moloney

ⓒ David H Moloney

Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine

Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site

Concre

te

Page 61: Project Execution Plan for Bridge Construction

Reinforced Wall Construction Sequence

ⓒ David H Moloney

Concre

te

Brief Description

The sequence to construct a reinforced concrete wall is as

follows:

Tie the reinforcement.

Erect stop-ends and the wall shutters.

Pour and vibrate the concrete mix.

Remove the shutters after the concrete has hardened.

.

Cycle Time Pour per Day

Page 62: Project Execution Plan for Bridge Construction

Reinforced Wall Construction Sequence

ⓒ David H Moloney

Concre

te

Page 63: Project Execution Plan for Bridge Construction

Vibrating Concrete

ⓒ David H Moloney

Concre

te

Page 64: Project Execution Plan for Bridge Construction

Bridge & Post-tensioningC

oncre

te

Brief Description

The sequence to post-tension a bridge

deck is as follows;

Fix the ducts and anchorages.

Install the stressing strand.

Concrete the deck.

Stress the strands and lock at

anchorages.

Grout the ducts.

Page 65: Project Execution Plan for Bridge Construction

Bridge & Post-tensioningC

oncre

te

Page 66: Project Execution Plan for Bridge Construction

Bridge & Post-tensioningC

oncre

te

Page 67: Project Execution Plan for Bridge Construction

Bridge Concrete DeckC

oncre

te

Page 68: Project Execution Plan for Bridge Construction

Bridge Concrete DeckC

oncre

te

Page 69: Project Execution Plan for Bridge Construction

Bridge Post Tensioning Deck – Install StrandC

oncre

te

Page 70: Project Execution Plan for Bridge Construction

Bridge Post Tensioning DeckC

oncre

te

Page 71: Project Execution Plan for Bridge Construction

Bridge Construction Sequence David H Moloney

ⓒ David H Moloney

Concre

te

Page 72: Project Execution Plan for Bridge Construction

Piling

Page 73: Project Execution Plan for Bridge Construction

Piling Construction - Plant & Methods

Brief Description

Piling Plant, Equipment and Material;

Crawler Crane, Piling Hammer, Temporary Casing,

Piling Rig, Concrete Pump, Concrete Mixer Trucks,

Tremie Pipe and Reinforcement Cage

Pili

ng

Page 74: Project Execution Plan for Bridge Construction

Piling Construction - Plant, Methods & SequenceP

iling

Page 75: Project Execution Plan for Bridge Construction

Piling Construction - Plant & MethodsP

iling

Page 76: Project Execution Plan for Bridge Construction

Piling Construction - Vertical PilesP

iling

Page 77: Project Execution Plan for Bridge Construction

Piling Construction - Raking PilesP

iling

Page 78: Project Execution Plan for Bridge Construction

Piling Construction - Raking PilesP

iling

Page 79: Project Execution Plan for Bridge Construction

Pile Load Test

ⓒ David H Moloney

Pili

ng

Brief Description

A jack is used to load the pile in steps and

gauges measure any settlement.

Page 80: Project Execution Plan for Bridge Construction

Pile Load Test

ⓒ David H Moloney

Pili

ng

Page 81: Project Execution Plan for Bridge Construction

Roads & Pavings

Page 82: Project Execution Plan for Bridge Construction

Asphalt Batching YardR

oad

s &

Pavin

gs

Brief Description

Asphalt Batching Yard

Capacity of main batching plant is

250 tonnes per hour .

Page 83: Project Execution Plan for Bridge Construction

Asphalt Batching YardR

oad

s &

Pavin

gs

Page 84: Project Execution Plan for Bridge Construction

Asphalt Batching YardR

oad

s &

Pavin

gs

Page 85: Project Execution Plan for Bridge Construction

Asphalt Batching YardR

oad

s &

Pavin

gs

Page 86: Project Execution Plan for Bridge Construction

Asphalt Batching YardR

oad

s &

Pavin

gs

Page 87: Project Execution Plan for Bridge Construction

Asphalt Batching YardR

oad

s &

Pavin

gs

Page 88: Project Execution Plan for Bridge Construction

Road Construction

Brief Description

Sequence, methods and plant to construct a

motorway on a high embankment

Road

s &

Pavin

gs

Page 89: Project Execution Plan for Bridge Construction

Road ConstructionR

oad

s &

Pavin

gs

Page 90: Project Execution Plan for Bridge Construction

Road ConstructionR

oad

s &

Pavin

gs

Page 91: Project Execution Plan for Bridge Construction

Asphalt Pavement - TestsR

oads &

Pavin

gs

Page 92: Project Execution Plan for Bridge Construction

Miscellaneous Works

Page 93: Project Execution Plan for Bridge Construction

FencingM

iscella

ne

ous

Brief Description

Fencing.

Sequence of construction;

1. Clear and grade the ground.

2. Fix corner and straining posts.

3. Fix intermediate posts.

4. Fix line wire, chain-link and razor wire.

5. Construct concrete ground beam

Page 94: Project Execution Plan for Bridge Construction

FencingM

iscella

ne

ous

Page 95: Project Execution Plan for Bridge Construction

FencingM

iscella

ne

ous

Page 96: Project Execution Plan for Bridge Construction

FencingM

iscella

ne

ous

Page 97: Project Execution Plan for Bridge Construction

FencingM

iscella

ne

ous

Page 98: Project Execution Plan for Bridge Construction

Setting out & Surveying

Page 99: Project Execution Plan for Bridge Construction

Setting out & Surveying

Page 100: Project Execution Plan for Bridge Construction

Setting out & Surveying

Page 101: Project Execution Plan for Bridge Construction

Safety & Environmental

Page 102: Project Execution Plan for Bridge Construction

Emergency Phone Numbers & Response H

ealth,

Safe

ty &

Environm

ent

Page 103: Project Execution Plan for Bridge Construction

HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of

current HSE Issues and historical trends

Health,

Safe

ty &

Environm

ent

Page 104: Project Execution Plan for Bridge Construction

Site Safety Posters examplesH

ealth,

Safe

ty &

Environm

ent

Page 105: Project Execution Plan for Bridge Construction

Trench - Safety Measures

ⓒ David H Moloney

Health,

Safe

ty &

Environm

ent

Page 106: Project Execution Plan for Bridge Construction

Safety Training on Site M

iscella

ne

ous

The purpose of safety training is to provide the knowledge necessary to

perform a job safely

Page 107: Project Execution Plan for Bridge Construction

Safety Training Matrix M

iscella

ne

ous

The purpose of safety training is to provide the knowledge necessary to

perform a job safely

Page 108: Project Execution Plan for Bridge Construction

Emergency Response Drill H

SE

Drills and exercises are used to rehearse anticipated emergency scenarios

Page 109: Project Execution Plan for Bridge Construction

Safety DocumentsH

ealth,

Safe

ty &

Environm

ent

Safe System of Work.

To provide a safe system of work is a legal requirement. What this means is that before you ask an employee to do a

job. You ensure that he has received training, has the appropriate personal protective equipment, the work area is safe

and he is unlikely to be injured or cause damage by carrying out the assigned task.

Project Management Plan for Health, Safety, Security and Environment. also Known as (HSSE Plan)

The Project HSSE Management Plan details how safety on site will be managed.

Project Procedures for Health, Safety, Security & Environment

Details the safe way to undertake a task

Methods Statements

Are prepared in advance of starting work, to plan a Safe System of Work on site for all activities that carries a risk. The

contents of a Method Statement, typically include:- Scope & Location of the Works, Programme, Roles & Responsibilities

of Staff. Resources, Work Methodologies and Risk Assessment.

Slide 1 of 2

Page 110: Project Execution Plan for Bridge Construction

Safety DocumentsH

ealth,

Safe

ty &

Environm

ent

Safety Risk Assessments

Are prepared to identify and evaluate risks, to adopt control measures to reduce or eliminate risks.

COSHH Sheet

The purpose of the Control Of Substances Hazardous to Health sheet is to identify how to prevent or adequately control

workers exposure to hazardous substances.

Permit to Work.

Is a management system used to control high risk activities by ensuring safety measures are in place prior to starting

work.

Types of work for which permits will be required include:

Excavation and the digging of trenches.

Working at height, including on roofs.

Working in confined spaces, for example entering a manhole.

Hot work, which is welding, soldering or cutting steel with angle grinders or by gas torch.

Slide 2 of 2

Page 111: Project Execution Plan for Bridge Construction

Hazardous Substances Symbols H

ealth,

Safe

ty &

Environm

ent

COSHH stands for the Control of Substances Hazardous to Health

Shown are the new hazard symbols

Page 112: Project Execution Plan for Bridge Construction

Safety PrecautionsH

ealth,

Safe

ty &

Environm

ent

Page 113: Project Execution Plan for Bridge Construction

Signs Examples H

ealth,

Safe

ty &

Environm

ent

Page 114: Project Execution Plan for Bridge Construction

Environmentally Friendly Site Air, Noise, Water & Soil PollutionH

ealth,

Safe

ty &

Environm

ent

Page 115: Project Execution Plan for Bridge Construction

Segregation of Waste H

ealth,

Safe

ty &

Environm

ent

Segregation of waste for proper disposal and recycling. Less waste goes to landfill and hazardous waste is treated to make it safe.

Colour Code for Skips & Bins

Page 116: Project Execution Plan for Bridge Construction

Water Pollution PreventionH

ealth,

Safe

ty &

Environm

ent

Page 117: Project Execution Plan for Bridge Construction

Concrete Washout & Settlement TanksH

ealth,

Safe

ty &

Environm

ent

Page 118: Project Execution Plan for Bridge Construction

Existing Underground Utilities

ⓒ David H Moloney

Brief Description

Before digging establish the

location and route of

underground utilities.

Locator to find Utilities

Spray Paint to mark pavement

Health,

Safe

ty &

Environm

ent

Page 119: Project Execution Plan for Bridge Construction

Existing Underground Utilities & Overhead Cables - Safety Measures

ⓒ David H Moloney

Health,

Safe

ty &

Environm

ent

Page 120: Project Execution Plan for Bridge Construction

Trench - Safety Measures H

ealth,

Safe

ty &

Environm

ent

Page 121: Project Execution Plan for Bridge Construction

Trench - Safety Measures

ⓒ David H Moloney

Health,

Safe

ty &

Environm

ent

Page 122: Project Execution Plan for Bridge Construction

Quality Assurance

Page 123: Project Execution Plan for Bridge Construction

Quality Assurance Dashboard Dashboard is a single page, graphical representation of

current statistics and historical trends

Page 124: Project Execution Plan for Bridge Construction

Runway Asphalt Pavement - TestsR

oads &

Pavin

gs

Page 125: Project Execution Plan for Bridge Construction

Quality Assurance Tests

Page 126: Project Execution Plan for Bridge Construction

Runway Concrete Pavement - TestsR

oads &

Pavin

gs

Page 127: Project Execution Plan for Bridge Construction

Runway LaboratoryR

oads &

Pavin

gs

Page 128: Project Execution Plan for Bridge Construction

Laboratory

ⓒ David H Moloney

Asphalt P

avin

g

Page 129: Project Execution Plan for Bridge Construction

Administration

Page 130: Project Execution Plan for Bridge Construction

Staff Directory

Brief Description

List of staff and their

contact details

Page 131: Project Execution Plan for Bridge Construction

Daily Work Record

Brief Description

Daily Work Records showing the

allocation of resources, materials and

work activities carried out daily.

Page 132: Project Execution Plan for Bridge Construction

Organogram

Brief Description

Shown are the line and

lateral relationships

between the various team

members and their relative

position in the site

organisation.

Page 133: Project Execution Plan for Bridge Construction

Staff Responsibility Matrix

Page 134: Project Execution Plan for Bridge Construction

Filing System

Page 135: Project Execution Plan for Bridge Construction

Quotations Comparison Sheet

Page 136: Project Execution Plan for Bridge Construction

Programme & Progress Monitoring

Page 137: Project Execution Plan for Bridge Construction

Progress Monthly, Monitoring & Reporting - DashboardDashboard is a single page, graphical representation of current

progress and historical trends

Page 138: Project Execution Plan for Bridge Construction

Programme for Construction

Gantt Charts to plan and schedule projects

Page 139: Project Execution Plan for Bridge Construction

Bridge Construction Stages, Images & TimelineC

oncre

te

Page 140: Project Execution Plan for Bridge Construction

Bridge Construction Stages, Images & TimelineC

oncre

te

Page 141: Project Execution Plan for Bridge Construction

Bridge Construction Stages, Images & TimelineC

oncre

te

Page 142: Project Execution Plan for Bridge Construction

Bridge Construction Stages, Images & TimelineC

oncre

te

Page 143: Project Execution Plan for Bridge Construction

Bridge Construction Stages, Images & TimelineC

oncre

te

Page 144: Project Execution Plan for Bridge Construction

Bridge Construction Stages, Images & TimelineC

oncre

te

Page 145: Project Execution Plan for Bridge Construction

Bridge Construction Stages, Images & TimelineC

oncre

te

Page 146: Project Execution Plan for Bridge Construction

Bridge Construction Stages, Images & TimelineC

oncre

te

Page 147: Project Execution Plan for Bridge Construction

Bridge Construction Stages, Images & TimelineC

oncre

te

Page 148: Project Execution Plan for Bridge Construction

Bridge Construction Stages, Images & TimelineC

oncre

te

Page 149: Project Execution Plan for Bridge Construction

Bridge Construction Stages, Images & TimelineC

oncre

te

Page 150: Project Execution Plan for Bridge Construction

Time Chainage Diagram

Brief Description

The chart has two axis: one for time and the other for location

A legend explains meaning of the colours, symbols and line types

Legend

Page 151: Project Execution Plan for Bridge Construction

Histogram Charts for Resources & Outputs

Manpower per Discipline

Concrete per Location

Man-hours for each month of the Project

Quantity for each month of the Project

ⓒ David H Moloney

Brief Description

Histograms shows resources etc. for each month of a project.

Page 152: Project Execution Plan for Bridge Construction

Plant & Equipment List & Worker’s Job Titles

ⓒ David H Moloney

Page 153: Project Execution Plan for Bridge Construction

Other Bridge Projects

Page 154: Project Execution Plan for Bridge Construction

Other Projects – Kuwait Causeway

Brief Description Marine Piling for Causeway in Kuwait

Page 155: Project Execution Plan for Bridge Construction

Other Projects – Kuwait Causeway

Brief Description Full Deck Span Precast 1,800 tonnes by 60m long

Precast Yard Straddle Carriers loading Deck onto Multi Wheeled Transporters

Multi Wheeled Transporters moving deck to Jetty

Jetty for loading Barge Barge Crane Placing Deck Barge Crane Placing Deck

Page 156: Project Execution Plan for Bridge Construction

Other Projects

Brief Description St. Croix Crossing, Minnesota, USA. Extradosed bridge design

Page 157: Project Execution Plan for Bridge Construction

Other Projects - Dubai Metro Viaduct

Brief Description

Precast Yard for Viaduct Segments Transport Viaduct SegmentsOverhead Launching Gantry to

place Viaduct Segments

Construction Sequence

Completed Project

Page 158: Project Execution Plan for Bridge Construction

Other Projects - Dubai Metro Programme

Brief Description

Page 159: Project Execution Plan for Bridge Construction

Production by David H Moloney

My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ