Welcome to Webinar on
Accelerated Bridge Construction
Precast Substructures, Part 2 –
Comparison of Non-Seismic and
Seismic Connection Details
Sponsored by
Accelerated Bridge Construction Center
(ABC Center) at
Florida International University
Website: abc-utc.fiu.edu
Email: [email protected]
June 19, 2014 – 1:00 p.m. to 2:00 p.m. Eastern
Webinar Agenda
ABC Announcements (10 minutes)
Featured Presentation (35 minutes)
Precast Substructures, Part 2 –
Comparison of Non-Seismic and
Seismic Connection Details
M. Lee Marsh, Ph.D., P.E., President and CEO,
BergerABAM
Question and Answer (15 minutes)
Please post your questions in the chat box
2014 National Accelerated Bridge
Construction Conference
December 4-5, 2014 December 3 – workshops
Hyatt Regency, Miami, Florida
www.2014abc.fiu.edu
Conference at a Glance
- Conference is Co-Sponsored by 26 State DOTs
- U.S. Secretary of Transportation Anthony Foxx
invited keynote speaker
- Conference includes more than 170 technical
presentations
- Nine (9) workshops – Day before the
conference
- Opportunities exist for exhibits
Thursday Breakout Sessions – Early Afternoon Room A Room B Room C Room D Room E
Session #1 – Case Studies Session #2 – State Experience Session #3 – Bridge Deck Session #4 – Railroad
Session #5 – Guide, Specification, Tools
1:3
0 –
1:5
0
Folded Steel Plate Girder System Applications in Accelerated Bridge Construction - Part I Matthew Macey, CDR Bridge Systems LLC Carlos Duart, CDR Bridge Systems LLC
Prefabricated Bridge Construction Practice in Florida Robert Robertson, Florida Dept. of Transp. Thomas Andres, Florida Dept. of Transp. Jeffrey Ger, FHWA, Florida Division Dennis Fernandez, Florida Dept. of Transp.
Design and Construction of Prefabricated Steel Deck Ramps during the Alexander Hamilton Bridge Reconstruction Project, Bronx, New York
Bhadresh Patel, SJH Engineering, P.C. S Jayakumaran, SJH Engineering, P.C. Gary Dinmore, Halmar International, LLC
Making the Most of Traditional Techniques
Mansoor Ahsan, Bridgefarmer & Associates, Inc.
Comparing Total Cost of Bridge Construction Using ABC and Conventional Methods of Construction Mohammed Hadi, Florida International University Albert Gan, Florida International University
1:5
0 –
2:1
0
Application of Folded Plate Technology - Part II: Case of Boone County Nebraska Fouad Jaber, Nebraska Dept. of Roads Mark Traynowicz, Nebraska Dept. of Roads
Accelerated Bridge Construction in Utah - Owner Perspective Randy Park, Utah Dept. of Transp. Carmen Swanwick, Utah Dept. of Transp.
Deck Replacement with Full Depth Precast Post-Tensioned Panels: Challenges, Solutions, Prefabrication and Construction Performance
Jim Scoles, Morrison-Maierle, Inc. Hugh Boyle, H. Boyle Engineering, Inc. Lee Wegner, Hanson Structural Precast Eric Wells, Granite Construction
Inlet Centre Station Tunnel Jacking- Evergreen Line Rapid Transit Project, Vancouver, British Columbia, Canada Samson Chan, SNC Lavalin Inc.
Geotechnical and Foundation Opportunities for ABC Jerry DiMaggio, Applied Research Associates Inc.
2:1
0 –
2:3
0
Accelerated Bridge Construction: Implementation of GRS-IBS for 27th Street Bridge over Broad Branch Stream, Washington DC
Zahra Dorriz, DC Department of Transportation
Precast, Pretensioned, Rectangular Bent Caps Christopher Miller, Texas Dept. of Transp. John Holt, Texas Dept. of Transp. Victoria McCammon, Texas Dept. of Transp.
Overnight Deck Replacement of the I-190 Grand Island Bridge
Mark Horschel, Bergmann Associates Philip Gase, BGFMA
Practical Accelerated Bridge Construction for Railroad Bridge Project Delivery
Duncan Paterson, HDR Inc. Jon Winer, HDR Inc.
ABC, FHWA SHRP2 R04: Implementation across the USA
Finn Hubbard, Fish & Associates Inc.
2:3
0 –
2:5
0
Don’t Judge A Bridge By Its Length
William Castle, W.J. Castle, P.E. & Associates, P.C.
VDOT I-95 Accelerated Bridge Construction Project Scott Fisher, Virginia Dept. of Transp. Jorge Suarez, Michael Baker International Malcolm Kerley, NXL
Precast Prestresseed Full Depth Deck Panels for Bridge Decks over New and Existing Prestressed Concrete Girder Bridges
Terry Mackie, Tennessee Dept. of Transp.
Accelerated Bridge Construction for Busy Commuter Rail Service Matthew Paradis, HNTB Corp Patrick Kitto, Caltrain/SAMTRANS
Slide-In Bridge Construction Guide Michael Arens, Michael Baker International
2:5
0 –
3:1
0
Angus L. Macdonald Suspension Bridge: Erection Sequence And Major Erection Equipment
Dusan Radojevic, Buckland & Taylor Keith Kirkwood, Buckland & Taylor Jon Eppell, Halifax Harbour Bridges Peter Buckland, Buckland & Taylor
UDOT Experience Utilizing Slide-In Bridge Construction
Richard Hansen, Parsons Rebecca Nix, Utah Dept. of Transp.
Bayou Lafourche Bridge – A Cost-Effective Full Depth Precast Deck Solution
Eddie He, AccelBridge Justin Peltier, Huval & Associates Carl Gaudry, Louisiana Dept. of Transp. and Dev. Paul Vaught III, Louisiana DOTD
Rapid Replacement of Railroad Bridges
Using Heavy Lift Technology Darren Conboy, Jacobs Engineering Group Ernest Dobbs, Jr., Jacobs Engineering Group James Szczupaj, Jacobs Engineering Group
Development of Economical Short-Span Steel Bridge Standards
Karl Barth, West Virginia University Gregory Michaelson, West Virginia University Michael Barker, University of Wyoming Daniel Snyder, Steel Market Development Inst.
3:1
0 –
3:3
0
Interstate Accelerated Bridge Replacement in Utah: Minimizing User Impacts by Optimizing Construction Sequence and Methods Jim Higbee, Utah Dept. of Transp. Jason Klophaus, Klophaus and Associates Carmen Swanwick, Utah Dept. of Transp.
The Michigan Department of Transportation and the Implementation of Accelerated Bridge Construction Kyle Kopper, Michigan Dept. of Transp. Bradley Wagner, Michigan Depart. of Transp.
Innovative ABC System Using Steel and Concrete in Sandwich Form
Atorod Azizinamini, Department of CEE, Florida International University
Bridge Street ABC Railroad Bridge Replacement Project, Hartford Vermont
Adam Stockin, Parsons Brinckerhoff G. Keith Donington, Parsons Brinckerhoff
Accelerated Bridge Construction – The Minnesota DOT Experience Paul Rowekamp, Minnesota Dept. of Transp.
Thursday General Session Main Ballroom Main Ballroom
8:0
0
Welcome
Atorod Azizinamini, Director, ABC-UTC Mark Rosenberg, President, Florida International University AASHTO SCOBS Chair, AASHTO FHWA FDOT Secretary of Transportation, FDOT Kevin C. Womack, Associate Administrator, Research, Development and Technology, Office of the Assistant Secretary for Research and Technology, U.S. Department of Transportation
10:3
0
Contractor Perspective on Effective Implementation of ABC
Eric Wells, Granite Construction
10:5
0
Concrete Industry Perspective on Effective Implementation of ABC William Nickas, Precast/Prestressed Concrete Institute
8:3
0
Keynote Address
Anthony Foxx, U.S. Secretary of Transportation
11:1
0
Steel Industry Perspective on Effective Implementation of ABC
Bill McEleney, NSBA
9:0
0
Recognition of Travel Scholarship Contributors
Ed Power, HDR Carlos Duart, CDR Maguire
11:3
0
National Perspective on FHWA EDC1 & EDC2 Ben Beerman, FHWA
9:2
0
Moving Innovation into Practice Carmen Swanwick, Chair of T-4 Committee, AASHTO
11:5
0
Service Life Related Issues for ABC Bruce Johnson, Oregon Department of Transportation
9:4
0
History of ABC Mary Lou Ralls-Newman, Ralls Newman, LLC
12:1
0
Available ABC Resources Through University Transportation Center Atorod Azizinamini, Director, ABC-UTC
10: 00 – 10:30 Break
12: 20 – 1:30 Lunch
Thursday Breakout Sessions – Late Afternoon Room A Room B Room C Room D Room E
Session #6: Case Studies Session #7: Moving Technique &
Construction Session #8: Planning-Contract-
Outreach Session #9: Seismic
Session #10: Guide, Specification, Tools
4:0
0 –
4:2
0
U.S. Route 202 over Passaic River - Complete Bridge Replacement in 7 Days Using Accelerated Bridge Construction Techniques
Mark Sheptock, AmerCom Corporation Atly Botas, AmerCom Corporation
Design and Construction Challenges in Converting a Construct-in-Place Bridge to a Bridge Moved into Place using a Lateral Slide
Hugh Boyle, H. Boyle Engineering Justin Wiatrek, Texas Dept. of Transp. David Griffin, Texas Sterling Construction
Managing Emerging Exposures in Accelerated Bridge Design and Construction
Robert Hughes, Ames & Gough
Seismic Performance of Precast Girder-to-Cap Beam Connections Designed for ABC
Sri Sritharan, Iowa State University Justin Vander Werff, Dordt College Robert Peggar, Iowa State University Ron Bromenschenkel, Caltrans
Modular Panel Bridges Used Adjacent To Existing Bridge For Temporary Detour During Bridge Replacement
Andrew Boorman, Mabey Inc.
4:2
0 –
4:4
0
Rural SW Montana County Utilizes ABC Techniques to Replace WPA Era Bridge with a 90-Foot Modular Steel Structure and Precast Abutments in Four Days
James Carpita, Beaverhead County
The Michigan Department of Transportation’s Use of Bridge Lateral
Slides Part I
Bruce Campbell, Parsons Corp.
Using the Design Build Process to Achieve a State of Good Repair on
“Typical” Bridges
Deborah Chase, Greenman Pedersen, Inc.
Caltrans Accelerated Bridge Construction
Barton Newton, CalTrans
Nondestructive Testing to Determine Existing Bridge Foundation Conditions
Paul Fisk, NDT Corporation
4:4
0 –
5:0
0
AASHTO Bulb-Tee Multi-Girder Bridge Supported on GRS-IBS Foundation System
Ahmad Faqiri, Pennoni Associates Inc.
The Michigan Department of Transportation’s Use of Bridge Lateral Slides Part II
Kyle Kopper, Michigan Dept. of Transp. Bradley Wagner, Michigan Dept. of Transp. Corey Rogers, Michigan Dept. of Transp.
An ABC Screening Process for Toll Roads in New Jersey
Thomas Zink, Gannett Fleming, Inc. Agnieszka Lapinski, Gannett Fleming, Inc.
State-of-the-Art Report on Seismic Design of Precast Concrete Bridges
Bijan Khaleghi, Washington State Dept. of Transp.
3D Design and Fabrication for Prefabricated Bridge Substructures
Changsu Shim, Chung-Ang University Sungjun Park, Chung-Ang University Sung-Woong Ji, Chung-Ang University
5:0
0 –
5:2
0
Accelerated Bridge Concepts for the Sprain Parkway Bridges over Route 119 for NYSDOT
David Weiss, WSP USA Corp.
P-954 Flyover Tied Arch Bridge
Natalie McCombs, HNTB Marwan Nader, T.Y. Lin International
CDR Maguire Engineering Practice on ABC Project Design and Construction Yihui Peter Wu, CDR Maguire Inc. Carlos Duart, CDR Maguire Inc.
Quasi-Static Experimental Testing of Emulative and Low-Damage Seismic Technologies for Accelerated Bridge Construction in Seismic Areas
Mustafa Mashal, University of Canterbury Alessandro Palermo, University of Canterbury
Tolerances for Prefabricated Bridge Elements
Michael Culmo, CME Associates, Inc.
5:2
0 –
5:4
0
New Jersey Route 10 over the Passaic River Superstructure Replacement using Accelerated Bridge Construction Systems
Gerard Kroner, Hatch Mott MacDonald Jeff Smith, Hatch Mott MacDonald
Slide-In-Replacement of the Skagit River Collasped Span
Christopher Vanek, Parsons Brinckerhoff Victor Ryzhikov, Parsons Brinckerhoff Charles Rudie, Parsons Brinckerhoff John Poulson, Parsons Brinckerhoff
VTrans Programmatic Approach to Planning and Public Outreach for Accelerated Bridge Projects
Kristin Higgins, Vermont Agency of Transp. Wayne Symonds, Vermont Agency of Transp.
Circular Concrete Filled Tube Bridge Pier Connections for Accelerated Bridge Construction in Seismic Zones
Max Stephens, University of Washington Dawn Lehman, University of Washington Charles Roeder, University of Washington
Recent Advancements in Accelerated Bridge Construction Applications in California
Paul Chung, CalTrans Jian Qiao Fang, CalTrans
Thursday Breakout Sessions – Evening Room A Room B Room C Room D Room E
Session #11: Case Studies Session #12: Moving Technique &
Construction Session #13: Research
Session #14: Planning-Contract-Outreach
Session #15: Guide, Specification, Tools
7:3
0 –
7:5
0
Innovative Crossroads: ABC Bridge Project Features Roundabouts (Pecos Street Bridge Replacement)
Tamara Hunter-Maurer, Colorado Dept. of Transp. Tom Melton, Wilson & Company, Inc. David Paris, Kiewit Infrastructure
The Bridges of Rocky Ford: A Comparison of Two Lateral Bridge Slide Methods Jeffrey Dobmeier, Jacobs Engineering
Strut-and-Tie Model and Design Guidelines of ABC Joints
Z. John Ma, University of Tennessee-Knoxville
How to Build the Perfect ABC Team Amalia Deslis, Somers-Jaramillo & Associates
GeoTechTools - Geotechnical Solutions for Accelerated Bridge Construction
Vernon Schaefer, Iowa State University Ryan Berg, Ryan R. Berg & Associates
7:5
0 –
8:1
0
Challenges of Designing a Two-span
Continuous Precast Concrete Accelerated Bridge Reconstruction Ryan Adams, Greenman-Pedersen, Inc. Scott Deeck, New Jersey Dept. of Transp.
Huey P. Long Bridge Innovative Truss Erection Method Hans Hutton, HNTB
Hybrid Fiber Reinforced Concrete Composites for Accelerated Bridge Column Construction Will Nguyen, CEE, UC Berkeley William Trono, CEE, UC Berkeley Claudia Ostertag, CEE, UC Berkeley
Accelerated Bridge Construction – A Design-Build Perspective Eddie He, Parsons Steve Haines, Parsons
Prefabricated Precast Structures Speed Accelerated Bridge Construction Scott Aston, Contech Engineered Solutions Anthony Rotondo, Jr., FHWA
8:1
0 –
8:3
0
Small Work Windows and Tight Schedule Equals ABC
Paul Berthiaume, Greenman-Pedersen, Inc.
Railing Smart-Transporter System for Replacement of an Existing Bridge in 4 Hours Jung-hyun Kim, KOBEC Kwang-Soo You, KOBEC Changsu Shim, Chung-Ang University Shigehide Noda, NODA CRANE
Earthquake Shake Table Testing of a Self-centering ABC Bridge
Islam Mantawy, University of Nevada Reno Travis Thonstad, University of Washington David Sanders, University of Nevada Reno John Stanton, University of Washington Marc Eberhard, University of Washington
Every Day Counts! Slide-In Bridge Construction Outreach and Training Travis Boone, URS Corporation Joshua Laipply, Colorado Dept. of Transp.
Utah and Arizona ABC / PBES – Get the “Nuts And Bolts” Right, or the Plan Won't Come Together as Planned Predrag Milosavljevic, Stanley Consultants, Inc. Eric Huskey, Stanley Consultants, Inc.
8:3
0 –
8:5
0
60 Hours: New Hampshire's First Interstate Use of Accelerated Bridge Construction Tom Kendrick, McFarland Johnson, Inc. Ron Kleiner, Jr., New Hampshire DOT
Cost Effective Slide-In Bridge Construction in Maine Tom Kendrick, McFarland Johnson, Inc. Kim Suhr, Wyman & Simpson, Inc.
Dimensional Stability of Prebagged Cementitious Grouts for Prefabricated Bridge Element and System Connections Igor De la Varga, SES-TFHRC Benjamin Graybeal, FHWA-TFHRC
Completing the ABC Package: Public Outreach Tactics Amalia Deslis, Somers-Jaramillo & Associates
Transition from 2D Drawings to 3D Models in Automated Concrete Detailing Alexander Mabrich, Bentley Systems
Friday Breakout Sessions – Early Morning Room A Room B Room C Room D Room E
Session #16: Case Studies Session #17: Repair Session #18: Service Life Session #19:Seismic Session #20: Guide, Specification, Tools
Montour Run Bridge No. 6 Replacement - Thanksgiving Weekend 2012
Mark Pavlick, HDR, Inc.
Rehabilitation of Historic Wells Street Moveable Bridge, Chicago, Illinois – Part I
Dipal Vimawala, AECOM
Using GFRP Rebar as a Cost Effective Solution to Extend the Service Life of New and Replacement Bridge Decks: A Case Study of the I-635 Bridge Deck Replacement for the KDOT
Ryan Koch, Aslan FRP
A Precast Concrete Bridge Bent System for ABC in High Seismic Regions
Olafur Haraldsson, Univeristy of Washington John Stanton, Univeristy of Washington Marc Eberhard, Univeristy of Washington Bijan Khaleghi, Washington State DOT Lee Marsh, BergerABAM Engineers
SHRP2 – Contribution to ABC
Finn Hubbard, Fish & Associates, Inc.
Merging Hybrid Composite Beams and GRS-IBS Technology for a Cost Effective Accelerated Bridge Construction Solution
Dipali Patel, Whitney Bailey Cox & Magnani, LLC Mike Izzo, Whitney Bailey Cox & Magnani, LLC
Wells Street Bascule Bridge Fast Track Construction Engineering – Part II
Stan-lee Kaderbek, Collins Engineers, Inc. Jason Schneider, Collins Engineers, Inc. Anastasia Kotsakis, Collins Engineers, Inc. Kevin Becker, Walsh Construction Company
Galvanized Steel for Bridge Longevity
Kevin Irving, AZZ Galvanizing Services
Damage-free Earthquake-resistant Deconstructible Columns for ABC
Sebastian Varela, Univ. of Nevada, Reno M. Saiid Saiidi, Dept of CEE, Univ. of Nevada, Reno
ABC Design and Construction Guide
Mike Culmo, CME Associates, Inc.
ABC Techniques in Rural Montana – 3 Replacement Bridges on the Lewis & Clark Highway
Jim Scoles, Morrison-Maierle, Inc. Andy Cullison, Morrison-Maierle, Inc. Keely Matson, Morrison-Maierle, Inc. Kent Barnes, Montana Dept. of Transp.
Accelerated Repair of the Eggner’s Ferry Bridge
Aaron Stover, Michael Baker International
Standardized Steel Orthotropic Decks for
Improved Manufacturability, Accelerated Construction and 100 Years’ Service Life
Soguata Roy, Lehigh University Soham Mukherjee, Lehigh University
An ABC Bridge Bent that Self-centers After an Earthquake
Travis Thonstad, University of Washington Olafur Haraldsson, University of Washington John Stanton, University of Washington Marc Eberhard, University of Washington
NCHRP ABC Research Products
Waseem Dekelbab, National Cooperative Highway Research Program, Transportation Research Board
ABC Solutions for the Colorado River Pathway Bridges
Jared Olsen, Horrocks Engineers Larry Reasch, Horrocks Engineers Matt Horrocks, Horrocks Engineers Dave Dillman, Horrocks Engineers
Well Road Bridge Replacement Using Self-Propelled Modular Transporters
Rachel Mertz, Modjeski and Masters, Inc. Mark Bucci, Louisiana Dept. of Transp. and Dev.
Corrosion Protection Plan Requirements in APD: Toward a Best-Practice Approach
Peter Elza, Parsons Corporation
Extending Application of SDCL in Seismic Areas
Ramin Taghinezhad, Dept of CEE, FIU Alireza Mohammadi, Dept of CEE, FIU Atorod Azizinamini, Dept of CEE, FIU
Developing next generation of ABC decision-making tools
Ben Tang, Oregon Department of Transportation
New York’s I-84 Bridge Slide: Design Challenges and Lessons Learned
Bala Sivakumar, HNTB Corp Steven Lin, HNTB Corp Cristina Brosio, HNTB Corp
Implementation of Accelerated Construction Methods for the Rehabilitation of New York Avenue Bridge Over Railroad Tracks
Inmar Badwan, T.Y. Lin International Amir Arab, T.Y. Lin International Ali Shakeri, DDOT IPMA Bijan Naderi, Fort Myer Construction Corporation
Performance of Post-Tensioned Curved-Strand Connections in Transverse Joints of Precast Deck
Zane Wells, Utah State University Paul Barr, Utah State University Patrick James, Utah State University Marv Halling, Utah State University
An Earthquake-Resistant Column Base Pipe Pin Connection for ABC
Ali Mehrsoroush, Dept. of CEE, UNR M. Saiid Saiidi, Dept. of CEE, UNR
Data Base as a Tool for Selecting Best ABC Alternative
Mohamadreza Shafieifar, Dept of CEE, FIU Jawad Gull, Dept of CEE, FIU Atorod Azizinamini, Dept of CEE, FIU
Accelerated Bridge Construction Techniques, Considerations, and Lessons Learned for Rapid Replacement of Bascule Bridge Spans
Timothy Davis, PCL Civil Constructors, Inc.
Accelerated Bridge Construction
Methods Employed in the Rehabilitation of the Pulaski Skyway
Andrew Foden, Parsons Brinckerhoff Christopher Gentz, Parsons Brinckerhoff Nat Kasbekar, New Jersey Dept. of Transp. Scott Thorn, New Jersey Dept. of Transp.
Development of Service Life Design
Guide for ABC Projects
Jawad Gull, Dept. of CEE, FIU Atorod Azizinamini, Dept. of CEE, FIU
Seismic Performance of Grouted Splice Precast Column Joints with Shifted Plastic Hinge Mechanisms
Haider Al-Jelawy, Dept. of CECE, UCF Zachary B. Haber, Professional Service Industries Kevin R. Mackie, Dept. of CECE, UCF
The Genetic Makeup of Accelerated
Bridge Technology
Mark Joosten, Acrow Corporation of America Eugene Sobecki, Acrow Corporation of America
Friday Breakout Sessions – Late Morning Room A Room B Room C Room D Room E
Session #21: Case Studies Session #22: Research Session #23: State Experience Session #24: New ABC Systems Session #25: Tappan Zee Bridge
10:3
0 –
10:5
0
Milton Madison Bridge Replacement - Part 1 Murray Johnson, Buckland & Taylor Tom Bolte, Burgess & Niple Inc.
Strengthening Transverse Connections of Prefabricated Concrete Hollow Core Slab Beam Bridges using Transverse Post-tensioned Bars Yanling Leng, New Mexico State University Jinquan Zhang, RIOH, Ministry of Trans China Ruinian Jiang, New Mexico State University Sonya Copper, New Mexico State University Haifang He, RIOH, Ministry of Trans, China
Upcoming ABC initiative in Pennsylvania Tom Macioce, PennDOT
Hydro-Brace Steel Pile Repair System
William Castle, W.J. Castle, P.E. & Associates, P.C.
Precast Pile Tub Foundations Design for Tappan Zee Bridge (Part 1) Nicholas Burdette, HDR Inc.
10:5
0 –
11:1
0
Milton Madison Bridge Replacement: Part 2 Murray Johnson, Buckland & Taylor Tom Bolte, Burgess & Niple Inc.
Strength and Fatigue Resistance of Clustered Shear Studs
Jason Provines, PSI, Inc. Justin Ocel, Federal Highway Administration
Upcoming ABC Initiative in Oklahoma
Bob Rusch, Oklahoma Dept. of Transp.
Development of a Press-Brake-Formed Modular Steel Tub Girder for Accelerated Bridge Construction
Karl Barth, West Virginia University Gregory Michaelson, West Virginia University Lindsay Kelly, West Virginia University Michael Barker, University of Wyoming Daniel Snyder, Steel Market Development Institute
Precast Pile Tub Foundations Details for Tappan Zee Bridge (Part 2) Nick Hatinger, HDR Inc.
11:1
0 –
11:3
0
Accelerated Bridge Construction of Martin Luther King Jr. Memorial Bridge – City of Bluefield, WV Faheem Ahmad, E. L. Robinson Engineering Co. Ahmed Mongi, West Virginia Division of Highways
Field-Cast Connections for Prefabricated Bridge Elements Jiqiu Yuan, PSI, Inc., Turner-Fairbank HRC Benjamin Graybeal, FHWA, Turner-Fairbank HRC Sorin Marcu, PSI, Inc., Turner-Fairbank HRC
Re-Decking of I-84 Bridges over UPRR and Northside Blvd. in Nampa, Idaho
Kenneth Clausen, Idaho Transportation Dept.
Rapidly Deployable Plate and Tube Modular Workhorse Bridges of 120 ft or Less in Length Christopher Hahin, Illinois Dept. of Transp.
Precast Pier Cap Design for Tappan Zee Bridge (Part 1)
Mike Lamont, HDR Inc.
11:3
0 –
11:5
0
Accelerated Bridge Construction for the Replacement of the Bridge on Route 10 over the Manhan River in Easthampton, Massachusetts
Paul White, Lafarge
Pile-to-Pile Cap Connections for Accelerated Bridge Construction Justin Dahlberg, Bridge Engg. Center - ISU James Nelson, Iowa Dept. of Transp. Ahmad Abu-Hawash, Iowa Dept. of Transp. Brent Phares, Bridge Engg. Center - ISU
Prefabricated Decked Girders for Accelerated Bridge Construction in Washington State Lara Khaleghi, Parsons Transportation Group, Irvine, California
The Design of Prefabricated SPS Bridge Decks for US Bridges Angelo Ferro, Intelligent Eng. (Canada) Ltd. Alain-Philippe Beauger, Intelligent Eng. (Can) Ltd. Zachary McNeil, Intelligent Eng. (Canada) Ltd.
Precast Pier Cap Details for Tappan Zee Bridge (Part 2)
Sreenath Kotamala, HDR Inc.
11:5
0 –
12:1
0
Examining Accelerated Bridge Construction Techniques in the Clayton Street Bridge Replacement Aboud Alzaim, The Louis Berger Group, Inc. Malek Al-Khatib, The Louis Berger Group, Inc. Daniel Deng, The Louis Berger Group, Inc.
Laboratory Investigation of ABC Connection Details using Grouted Couplers Travis Hosteng, Bridge Engg. Center - ISU Brent Phares, Bridge Engg. Center - ISU Ahmad Abu-Hawash, Iowa Dept. of Transp. Dean Bierwagen, Iowa Dept. of Transp.
I-40 Inner Loop Bridges in Downtown Nashville Accelerated Bridge Construction Project utilizing CM/GC Project Delivery
Lia Obaid, Tennessee Dept. of Transp. Terry Mackie, Tennessee Dept. of Transp. Ted Kniazewycz, Gresham, Smith and Partners
Dorland J. Henderson Memorial Bridge/Manahawkin Bay Bridge Rehabilitation with Fast Curing MMA Polymer Materials Michael Stenko, Transpo Industries Inc.
Precast Concrete Deck Panels for Tappan Zee Bridge Mike LaViolette, HDR Inc.
Friday Breakout Sessions – Afternoon Room A Room B Room C Room D Room E
Session #26: Case Studies Session #27: State Experience Session #28: Moving Techniques
and Construction Session #29: New ABC Systems
Session #30: Light Weight and High Performance Concrete
1:1
0 –
1:3
0
New Jersey Route 36 Highlands Bridge Replacement: True Accelerated Bridge Construction.
Suhail Albhaisi, Jacobs Engineering Satsih Patel, Jacobs Engineering
Emergency Replacement of Bridges Geetha Chandar, Texas Dept. of Transp. John Holt, Texas Dept. of Transp. Jamie Farris, Texas Dept. of Transp. Mark Steves, Texas Dept. of Transp.
Quick Railing Installation system SMART LIFTER Shigehide Noda, NODA CRANE Nobuyuki Noda, NODA CRANE
A New Type of Precast Bridge Deck Connection
Dong-Ho Shin, Daewoo Inst. of Const. Tech. Se-Jin Park, Daewoo Inst. of Const. Tech. Hyun-Chul Oh, Daewoo Inst. of Const. Tech. In-Kyu Kim, Daewoo Inst. of Const. Tech. Young-Jin Kim, Daewoo Inst. of Const. Tech.
Hodder Avenue Underpass – An Innovative Modular Construction Approach with Ultra-High Performance Fibre-Reinforced Concrete
Eileen Li, Hatch Mott MacDonald Liang Guo, Hatch Mott MacDonald Biljana Rajlic, Hatch Mott MacDonald Philip Murray, Hatch Mott MacDonald
1:3
0 - 1
:50
Meeting the Goals of ABC with Buried Bridges
Matthew Richie, Simpson Gumpertz & Heger Jesse Beaver, Simpson Gumpertz & Heger
Korean National Modular Bridge Research Project Chan-Hee Park, RIST Gwang-il Cho, RIST Pil-Goo Lee, RIST
Replacement of the BNSF Approach Spans over the Mississippi River
David Rogowski, Genesis Structures Inc. Josh Crain, Genesis Structures Inc.
Precast GFRP-bar Reinforced Bridge System for Accelerated Bridge Construction
Zhibin Lin, North Dakota State University Mostafa Fakharifar, Missouri Univ. of Sci. & Tech. Fujian Tang, Missouri Univ. of Sci. & Tech. Genda Chen, Missouri Univ. of Sci. & Tech.
Internal Curing with Lightweight Aggregate for ABC Projects
Reid Castrodale, Expanded Shale Clay and Slate Institute
1:5
0 - 2
:10
Accelerated Construction of a Prefabricated Structural Deck for a Runway Safety Area Extension over Boston Harbor
Darren Conboy, Jacobs Engineering Group Stephen Berkeley, Jacobs Engineering Group Steven Halloran, Jacobs Engineering Group
Precast Bent Caps and Full Depth Deck Panels for US90 over Little River and Hurricane Creek Steven Nolan, Florida Dept. of Transp.
Construction Techniques - ABC Lateral-Slide Method Vincent Siefert, Siefert Associates, LLC Kevin O'Neill, Siefert Associates, LLC Chuck Neth, Siefert Associates, LLC
Innovative Precast Concrete Adjacent-Box-Beam System Implemented in St. Clair Bridge Chuanbing Sun, eConstruct.USA Amgad Girgis, eConstruct.USA Maher Tadros, eConstruct.USA Kyle Kopper, Michigan Dept. of Transp. Talia Belill, DLZ
Recent ABC Projects using Lightweight Concrete
Reid Castrodale, Expanded Shale Clay and Slate Institute
2:1
0 –
2:3
0
Sabula Accelerated Bridge Construction Case Study: US 52 Over Mississippi River Overflow James Nelson, Iowa DOT
Accelerated Bridge Construction (ABC) Gaining Momentum
Jugesh Kapur, Burns & McDonnell
Bridge Designer/Heavy Lift Coordination for Accelerated Bridge Construction Projects
Steve Haines, Parsons Matt Boben, Mammoet USA
NU Precast Deck Second Generation Fouad Jaber, Nebraska Department of Roads
Durability of Lightweight Concrete for ABC Reid Castrodale, Expanded Shale Clay and Slate Institute
2:3
0 –
2:5
0
A Signature Bridge on the Fast Track Theodore (Tad) Molas, Parsons Brinckerhoff Adrian Moon, Parsons Brinckerhoff
VTrans Fast 4 on VT Route 73 - Using Accelerated Bridge Construction and Road Closures to Expedite Project Delivery in Rural Communities
Jennifer Fitch, Vermont Agency of Transportation Scott Burbank, Vanasse Hangen Brustlin, Inc. Greg Goodrich, Vanasse Hangen Brustlin, Inc.
Accelerated Bridge Construction for the Skagit River Truss Bridge Collapse and Rebuilt
Bijan Khaleghi, Washington State Dept. of Transp.
New Processing Equipment Allows Bridge Construction 12 Months a Year
Charles Smail, Shelter Structures, Inc.
Hodder Avenue Underpass – Different Applications of Ultra High Performance Concrete (UHPC) Result in a first-of-its-kind Bridge
Kyle Nachuk, Lafarge
2:5
0 –
3:1
0
King Road Grade Separation Bridge Jacking Jeffrey Long, Hatch Mott MacDonald Jeb Pittsinger, Hatch Mott MacDonald
Eastbound Nalley Valley Interchange Marketing Substructures for Precast Bridge Elements Patrick Gallagher, Washington State DOT
Jacking of Railroad Bridges/ Underpasses without Stopping Trains
Riccardo Castracani, Petrucco USA LLC
A New Steel Solution for Short Span ABC Bridge Replacements in Massachusetts Thomas Zink, Gannett Fleming, Inc. Agnieszka Lapinski, Gannett Fleming, Inc.
Illinois’ First Precast Deck Panel Bridge with UHPC Joints
David Liu, TranSystems Jayme Schiff, Bureau of Bridges and Structures,
Illinois Department of Transportation
Visit www.2014abc.fiu.edu To see list of 170 technical
presentations and speakers
Nine 4-hour Workshops – December 3
1 - GeoTechTools – Geotechnical Solutions for ABC
2 - GRS-IBS – Geosynthetic Reinforced Soil Integrated Bridge System
for ABC
3 - Lightweight Concrete – A Tool for ABC, Part I
4 - Lightweight Concrete – A Tool for ABC, Part II
5 - Design Management (DM) Guide for Design-Build (DB) and
Construction Manager / General Contractor (CM/GC) Projects
6 - Rapid Replacement of Bridges using the SHRP2 R04 ABC Toolkit
7 - Lateral Slide Bridges: Overview for Owners, Designers, and
Contractors
8 - Design of Concrete bridges using AASHTO LRFD Bridge Design
Specification
9 - Design of Steel bridges using AASHTO LRFD Bridge Design
Specification
Awards to be given at the Conference
- An ad-hoc award committee – Five State bridge
Engineers to be the judge
- More detailed information – July 2014 webinar
www.2014abc.fiu.edu
Hotel Reservations
- A block of rooms at the Miami Hyatt Regency, at
a special Conference rate, is available
www.2014abc.fiu.edu
Registration Information
- Please visit www.2014abc.fiu.edu to:
- Register online
- Make your hotel reservation
- View complete conference and workshop
descriptions
- Information for exhibiting
- How to contribute to development of travel
scholarship
www.2014abc.fiu.edu
ENGINEERING NEWS-RECORD
(ENR) REGIONAL BEST PROJECTS
2014 AWARDS PROGRAM
Best Projects in the U.S. & Puerto Rico
Projects completed July 1, 2013 – June 30, 2014
Call for Entries Deadline: June 30, 2014
http://enr.construction.com/bestprojects/2014/
NCSEA 17TH ANNUAL
EXCELLENCE IN STRUCTURAL
ENGINEERING AWARDS PROGRAM
Projects completed Jan. 1, 2011 – Dec. 31, 2013
Bridge categories:
New Bridge and Transportation Structures
Forensic/Renovation/Retrofit/Rehab Structures
Call for Entries Deadline: July 11, 2014
http://www.ncsea.com/awards/
excellenceinstructuralengineeringawards/
2015 TRB Annual Meeting
Call for ABC Papers – due August 1
http://www.trb.org/AnnualMeeting2015/
AnnualMeeting2015.aspx
Lateral Slide Showcase August 14, 2014
US-131 North/Southbound bridge over 3 Mile Road
(Grand Rapids)
Julia Tanner/MDOT
517.335.2177
http://www.ctt.mtu.edu/sites/ctt/files/flyers/2014_BridgeSlideShowcase.pdf
MassDOT LRFD Bridge Manual – Part III
Prefabricated Bridge Elements
Ch. 1 – Precast Abutments
Ch. 2 – Precast Integral Abutments
Ch. 3 – Precast Approach Slabs
Ch. 4 – Precast Piers
Ch. 5 – Precast Concrete Deck Panels
Ch. 6 – Precast Tolerances
Web Search: “MassDOT Manual Part III”
Next Webinar
Tuesday, July 29, 2014 (1:00 – 2:00 p.m. Eastern)
Featured Presentation
Performance of ABC Bridges in Utah
by
Carmen Swanwick, P.E.,
Chief Structural Engineer,
Utah Department of Transportation
To register, visit: www.abc-utc.fiu.edu
Webinar Agenda
ABC Announcements (10 minutes)
Featured Presentation (35 minutes)
Precast Substructures, Part 2 –
Comparison of Non-Seismic and
Seismic Connection Details
M. Lee Marsh, Ph.D., P.E., President and CEO,
BergerABAM
Question and Answer (15 minutes)