Download - Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

Transcript
Page 1: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

1

Porous Pavement and Model Municipal Operations Center

Demonstration Project Phase II

Photo Document Project

County of San DiegoDEPARTMENT OF GENERAL

SERVICESAugust 1, 2008

1

Page 2: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

2

Order of Review• Overview of Phase I Results• Treatment Train

• Site Preparation• Construction• Post Construction

• Porous Pavement• Site Preparation• Construction• Post Construction• Rain Event

• Results to Date

2

Page 3: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

3

Overview of Phase I

3

Page 4: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

4

N

11

M12A

Porous Concrete

14,936 s.f.Porous Asphalt

40,126 s.f.

Pavers

7,896 s.f.

Reference Area.

7

Porous Pavement Center COC 62,958 s.f.

4

Page 5: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

5

Cost Summary – Porous Pavement7

Page 6: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

6

PHASE I PAVEMENT REPLACEMENT SQUARE FOOT COSTS

  Demolition &

Excavation Installation of Sub Base

Pavement Costs

Square Foot Costs*

Annual Est. Square Foot Maintenance

Costs Comments

Porous Asphalt $ 2.75 $ 1.88

$ 1.87

$ 6.50

$ 0.04

18" excavation/backfill. 3" porous asphalt.

Standard Asphalt $ 2.13 $ 1.04

$ 1.32

$ 4.49

$ 0.06

6"-Excavation/Backfill. 6"-Asphalt.

Porous Concrete $ 3.19 $ 1.88

$ 6.34

$ 11.41

$ 0.02

18"-Excavation/Backfill. 5-1/2" pervious concrete.

Standard Concrete $ 1.51

$ -

$ 3.42

$ 4.93

$ 0.01

No new base material. 6"-Reinforced Concrete

Porous Pavers $ 2.75 $ 1.88

$ 9.63

$ 14.26 TBD

18"-Excavation/Backfill. 3"-Paver.

*Square foot cost are based on actual cost received by the County of San Diego.

8

Page 7: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

7

Phase I Treatment Train Schematic

5

Page 8: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

8

Targeted Pollutants of Concern

•Suspended Solids

• Oil/Grease

• Metals (Copper, Zinc, Chromium, Cadmium)

• Organics

• NitrogenNote: These are consistent between Phase I and Phase II.

6

Page 9: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

9

Phase II

9

Page 10: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

10Current and Proposed Porous Pavement and Treatment Train Locations

10

Page 11: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

11

Phase II Expansion

• Three additional media filtration units• Three additional porous paving test plots (54,000 sf)

• One additional porous concrete test plot• Two additional porous asphalt test plots• Geogrid stabilization under 1/2 of each new porous asphalt test plot• 26,000 sf of roof runoff diverted to porous asphalt test beds

• Enhanced monitoring to evaluate current/expanded BMP effectiveness

11

Page 12: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

12Phase II Treatment Train Schematic

12

Page 13: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

13

PHASE 2 PAVEMENT

REPLACEMENT SQUARE FOOT

COSTS

18"-30" excavation/backfill. 3" porous asphalt.Porous Asphalt 3.39$ 3.40$ 2.01$ 8.80$ 0.04$

Standard Asphalt 2.13$ 1.04$ 1.32$ 4.49$ 0.06$

Porous Concrete 3.64$ 3.40$ 7.10$ 14.14$ 0.02$

Standard Concrete 1.51$ -$ 3.42$ 4.93$ 0.01$

18"-30" excavation/backfill. 3" porous asphalt.

6"-Excavation/Backfill. 6"-Asphalt.

18"-30" Excavation/Backfill. 5-1/2" pervious concrete.

No new base material. 6"-Reinforced Concrete

PHASE 1 PAVEMENT

REPLACEMENT SQUARE FOOT

COSTS

18"-Excavation/Backfill. 3"-PaverPorous Asphalt 2.75$ 1.88$ 1.87$ 6.50$ 0.02$

Porous Concrete 3.19$ 1.88$ 6.34$ 11.41$ 0.04$

18"-Excavation/Backfill. 3"-Paver

*Square foot cost are based on actual cost received by the County of San Diego.

13

Page 14: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

14

TREATMENT TRAIN

Site Preparation14

Page 15: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

15

TREATMENT TRAIN

Site Preparation and Excavation

15

Page 16: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

16

TREATMENT TRAIN

Excavation Around Phase 1 Treatment Train

16

Page 17: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

17

TREATMENT TRAIN

CONSTRUCTION

17

Page 18: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

18

TREATMENT TRAIN

Installation of MFS and Storm Filter Chambers

20

Page 19: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

19

TREATMENT TRAIN

Installation of MFS and Storm Filter Chambers

21

Page 20: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

20

TREATMENT TRAIN

Installation of Diversion Pipe and Monitoring Boxes

26

Page 21: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

21

TREATMENT TRAIN

Backfilling Treatment Train

28

Page 22: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

22

TREATMENT TRAIN

Maintenance

30

Page 23: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

23

TREATMENT TRAIN

CONSTRUCTION

29

Page 24: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

24

TREATMENT TRAIN

MSF Unit Replacement Filter

31

Page 25: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

25

TREATMENT TRAIN

Filter Replacement of Phase 1 MSF Unit

32

Page 26: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

26

CDS PRE-TREATMENT CLEAN-OUT

After Three Rain Events33

Page 27: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

27

POROUS PAVEMENT

Site Preparation

34

Page 28: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

28

POROUS PAVEMENT

Excavation Engraving

35

Page 29: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

29

POROUS PAVEMENT

CONSTRUCTION

37

Page 30: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

30

POROUS PAVEMENT

Installation of Subsurface Overflow Drainage and Monitoring System

38

Page 31: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

31

POROUS PAVEMENT

CONSTRUCTION

39

Page 32: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

32

POROUS ASPHALT PROFILE 41

Page 33: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

33

POROUS PAVEMENT

Installation of Geotech Style Fabric and Aggregate

44

Page 34: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

34

POROUS PAVEMENT

Installation of Geogrip Re-enforcement

45

Page 35: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

35

POROUS PAVEMENT

Porous Asphalt Overlain Aggregate Bed

52

Page 36: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

36

POROUS PAVEMENT

Installation of Porous Asphalt

50

Page 37: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

37

POROUS ASPHALT PROFILE

46

Page 38: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

38

POROUS PAVEMENT

Installation of Porous Concrete

47

Page 39: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

39

POROUS PAVEMENT

Porous Concert Curing Process

48

Page 40: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

40

POROUS PAVEMENT

POST CONSTRUCTION

54

Page 41: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

41

POROUS PAVEMENT

Asphalt concrete Interface

55

Page 42: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

42

POROUS PAVEMENT

POST-CONSTRUCTION

56

Page 43: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

43

POROUS PAVEMENT

Porous Concrete Infiltration

57

Page 44: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

44

POROUS PAVEMENT

Porous Asphalt Infiltration

58

Page 45: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

45

POROUS PAVEMENT

Rain EventNovember 30, 2007

59

Page 46: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

46

POROUS PAVEMENT

RAIN EVENT (11/30/2007)

60

Page 47: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

47

POROUS PAVEMENT

RAIN EVENT (11/30/2007)

61

Page 48: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

48

POROUS PAVEMENT

RAIN EVENT (11/30/2007)

62

Page 49: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

49

POROUS PAVEMENT

RAIN EVENT (11/30/2007)

63

Page 50: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

50

Results to Date

64

Page 51: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

51

Porous Paving Treatments

• Rainfall and Runoff measured during 11 events during the 2005-2006 wet season.

• Events ranged from 0.23 inches to 1.07 inches during Phase I monitoring.

• All Three Porous Paving Treatments eliminated 100 percent of the runoff and associated contaminants.

65

Page 52: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

52

Infiltration Works!Porous Asphalt

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

Infil

trat

ion

Bas

in W

ater

Lev

el (f

t)

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

Rai

nfal

l Int

ensi

ty (I

nche

s/ho

ur)

Infiltration Basin Water Level

Rainfall Intensity

OVERFLOW LEVEL

66

Page 53: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

53

67

Page 54: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

54

68

Page 55: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

55

MFS Performance (Phase I)• Perlite used as Media• Initial data based upon only 3 events• Effective at further removal of sediment

• Coarse sediments (>63 µ) to <1.8 mg/L.• Fine sediments (<63 µ) to <14 mg/L

• Effective at further removal of contaminants strongly associated with particulate contaminants• e.g. Total Lead concentrations reduced 27-60

percent

69

Page 56: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II

56

70