Replacement cable routeThe replacement cable route will run along the existing cable route on Tarro Avenue, Eastern Avenue and Kennedy Street, crossing Weston Street, Tower Street and Burns Road.
The southernmost section will access an existing easement through the Georges River National Park.
Environmental and health standardsAusgrid plans its infrastructure in line with relevant environmental and health standards for the protection of both the environment and the community.
This includes designing and operating all new equipment to minimise construction impacts, minimising tree trimming and removal and managing issues such as dust, noise and vibration during construction. The final REF has more details on how these impacts have been assessed.
Working with youAusgrid understands there will be temporary impacts during construction, particularly on residents and businesses living or working close to the route which we will work to minimise.
You will receive a letter approximately one week before work begins near you which will include information on local impacts.
Your feedback is welcome at any time throughout the project to help Ausgrid and our contractors manage potential community impacts during the construction phase effectively.
Project updateAusgrid has now appointed Taihan and Garde as our contractors to replace the existing 132,000 volt underground electricity cables that run between our substation in Tarro Avenue, Revesby and Transgrid’s Sydney South substation located in George’s River National Park at Picnic Point.
As outlined in our previous newsletters, the existing cables are more than 35 years old and must be replaced to maintain a safe and reliable power supply to customers in the area.
Pre-construction activities will start in early November 2018. Trenching to install the new cables in roads will start from mid November 2018 and will continue for about six months.
This newsletter includes a graphic over the page which is indicative of the general construction process. There is also information on what to expect during construction.
You have received this newsletter because you live or work near the replacement cable route shown on the map on the back page.
Community engagement
Ausgrid has been liaising with the community and Canterbury Bankstown Council since early 2018. Feedback from community members, Council and key stakeholders has been considered to refine the cable route and reduce construction impacts.
Thank you to everyone who has provided feedback to date, most recently on the Review of Environmental Factors (REF) which was on public exhibition for comment from Friday 7 September 2018 to Friday 28 September 2018.
A drop in session to discuss the REF was also held at the Revesby Workers Club on Monday 17 September 2018 for interested community members to discuss the REF and ask questions.
While Ausgrid received no formal submissions during the REF stage, we considered all feedback received via phone calls, emails and face-to-face meetings to date as part of the process of assessing the project for construction approval.
The final REF and a summary of consultation completed to date, including the most commonly asked questions and our responses are available on our project web page ausgrid.com.au/picnicpointrevesby.
Community Newsletter 3 – November 2018
Picnic Point to Revesby cable project
A similar cable project in progress
Key dates
Early 2018
Preliminary investigations and obtaining early feedback from key stakeholders.
May – September 2018
Site investigations, REF prepared and displayed for public comment.
Early November 2018
Further site investigations, start of construction.
Early 2020
Target project completion.
Late October 2018
Project approved for construction, contractor engaged and program prepared.
Mid - late 2019
Finish installing new cables in streets, start retiring existing cables.
April 2018
Obtaining feedback from community on the preferred cable route to inform project.
Contacting usYou are welcome to contact us with any enquiries:
Call 1800 604 765 (free call from fixed phones) Email [email protected] ausgrid.com.au/picnicpointrevesby
Interpreter service 131 450
Picnic Point to Revesby replacement cable route
PA N A N IA
EAST HILLS
PICNICPOINT Georges River
National Park
Sydney South
Substation
RevesbySubstation
R E V E S B Y
REVESBYHEIGHTS
PADSTOWHEIGHTS
ALFORDS POINT
SANDY POINT
PLEASURE POINT
VOYAGER POINT
PADSTOW
BankstownCity YMCA
Kelso ParkNorth
Picnic PointHigh School
Picnic PointPrimary
Revesby WorkersClub
RevesbyPresbyterian Church
Burns Road Burns Road
Prince Street
Taloma Street
Tower Street
Tompson Road
Rowland Street
Gorman
Avenue
Richard St
Paul Street
Ferndale Road
Henr
y Law
son
Driv
e
Weston Street
Weston Street
Kenn
edy
Stre
et
East
ern
Ave
Cond
on A
ve
Tarr
o Av
e
Wol
long
bar
Ave
Vict
or A
venu
eA
pex
Aven
ue
Picn
ic P
oint
Roa
d
Ram
say
Road
Lam
beth
Str
eet
The
Rive
r Roa
dTh
e Ri
ver R
oad
Brett Street
Parkview Ave
LochinvarR oad
Legend
Substation
Existing 132kV cables
New132kV cables
N
What to expect during constructionBelow is a summary of the type of activities that can be expected during this project.
Site investigations
Ausgrid’s contractors will soon start site investigations to assess ground conditions and pinpoint existing services such as electricity, gas and water. This will help to confirm the final position of the new cables in the roadway and the location of joint bays and associated pits.
Trenching and laying conduits
The most common activity will be digging 1.3 metre wide trenches in roads and laying conduits to house the new cables. There will be a number of crews doing this work at multiple locations. This will start once site investigations have finished.
Typically, trenching and temporary restoration takes about a few days outside each property, depending on the ground and weather conditions.
Joint bays and other associated pits
Underground joint bays will be excavated approximately every 1100 metres along the route. These will be used to pull through and join sections of cable together.
Each joint bay will be about 3 metres wide and 10 metres long and will be in place for 2-4 months.
There will also be smaller pits associated with controlling and monitoring the cables, and to assist with cable installation. Some of these pits would be located in the nature reserve next to the road.
The project team will discuss the proposed location of the joint bays and pits with surrounding neighbours after our contractors have prepared their construction plans.
Cable installation
After the conduits have been installed, cables will be brought to the joint bay locations on large cable drums. The cables are pulled through the joint bays and into the conduits.
Traffic and parking changes
Traffic control will be used so that our work is safe for drivers, pedestrians and workers on site. Temporary parking restrictions will be in place during work and there will be resident only access in some streets when work is in progress.
Access to properties will be maintained unless we make alternative arrangements with you in advance.
Construction hours and expected impacts
Like all construction work, there will be some noise, vibration and dust which we will work to reduce.
Ausgrid standard work hours are 7am to 6pm on weekdays and between 8am and 1pm on Saturdays.
Nearby properties will be notified when work is planned outside normal hours and why the different hours are required.
Construction in school zones will be carried out during school holidays to ensure minimal impact on schools along the cable route.
Reinstatement of roads and other areas
Restoration of all affected areas to their previous condition is typically a two-step process. Following trenching and cable installation in roads, a temporary surface will be laid over the trench so that the road can return to normal use. The temporary road surface remains in place until the cables have been pulled through the conduits (pipes) joined and tested.
The excavated sections will then be reinstated permanently in consultation with the Canterbury Bankstown Council or other relevant road authority.
Your power supply
Ausgrid does not plan to interrupt your power supply during this work.
Underground 132,000 volt cable installation
STOP
SLOW
SLOW
STOP
SLOW
SLOW
Jointbay
Jointbay
Trench
Road
Plasticconduits
3m wide
12m long
Typically 600 – 900 metres between joint bays
but only 30 metres are dug up at any one time
2.5mdeep
1.3m
JOINT BAY
JOINT BAY DURINGCABLE INSTALLATION
COVEREDJOINT BAYDURING
JOINTING WORK
SEALEDJOINT BAY
TRENCH
RESURFACEDROAD
Not to scale
Construction stages
2–4 weeksTime it takes to complete work outside most properties.
Cable installation
• The 132,000 volt cables are pulled through the pipes and connected at the joint bays.
• At a later date, cable drums will be set up at joint bay locations.
• Underground joint bays would be constructedevery 1100m along the route.
• Between construction of the joint bay and connection of the cables, joint bays are either backfilled temporarily, barricaded or enclosed. Once cables are connected, the section of road is resurfaced.
• The joint bays are used to connect the cable sections.
2–4 monthsOverall time it takes to work at each joint bay location.
Underground joint bays• Trenching can occur on more than one site on a project simultaneously.
• The section of the road would then be permanentlyreinstated at the end of the project in consultationwith the Council.
• Plastic conduits (pipes) will then be placed in the trenches and then the area is backfilled with a special kind of concrete.
1–3 daysTime it takes to complete work outside most properties.
Trenching and conduit installation
The projectUNDERGROUNDJOINT BAY
The new cables will mainly be installed under thesurface of local roads along the route.
The proposed route aims to minimise impact on the community by avoiding major roads where possible and essential services such as existing underground electricity cables, water and sewerage pipes and gas mains.
Sealed trench through park.Work occurs quicker in parkland areas. Once construction is finished, the park is restored to its original state.
Trenches are backfilled and the affected section of roadway will be permanently resurfaced.
132,000 volt cables are drawn through conduits and connected at joint bays.
Truck removing spoil from excavation site.
Open trench showing plastic conduits.
Trench excavationOnce the plastic conduits are placed in the trench, the trenches are filled with a special kind of concrete with high thermal conductivity.
Road is resurfaced.
Traffic controllers work to maintain traffic flow and safety around the construction site.
Underground 132,000 volt cable installation
• Cable connection takes one to two weeks.