CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

Acceptance Testing. Facility capacity testing at the time a project is expected to reach design capacity. The timing in which this takes place varies by type of facility. Acceptance testing may occur shortly after start-up of a process unit, 6 to 12 months on building or mechanical trains, or 2 to 3 years for a paper mill.

Addition (Add-on). - A new addition that ties in to an existing facility, often intended to expand capacity. Synonym: Expansion.

Alliance Partner. A participant in a long-term association with a non-affiliated organization, used to further the common interests of the members. The continued association is based upon mutual trust and the satisfactory performance of each participant, and the alliance as a whole, rather than a pure contractual obligation.

Automation/Integration (AI) Technology. The Automation and Integration Technology practice addresses the degree of automation/level of use and integration of automated systems for predefined tasks/work functions common to most projects.

Bar Coding. The use of automatic identification technology by labeling, identifying, and controlling items, materials, and equipment through the use of bar codes. A bar code can be defined as a self contained message with information encoded in the widths of bars and spaces in a printed pattern.

Change. A change is any event that results in a modification of the project work, schedule or cost. Owners and designers frequently initiate changes during design development to reflect changes in project scope or preferences for equipment and materials other than those originally specified. Contractors often initiate changes when interferences are encountered, when designs are found to be not constructable, or other design errors are found.

Change Management. Change Management is the process of incorporating a balanced change culture of recognition, planning and evaluation of project changes in an organization to effectively manage project changes.

Constructability. Constructability is the effective and timely integration of construction knowledge into the conceptual planning, design, construction and field operations of a project to achieve the overall project objectives in the best possible time and accuracy, at the most cost-effective levels.

Contingency. All costs in contingency accounts including but not limited to normal contingency, allowances, reserves, indirect costs for schedule contingency, escalation, etc.

Cost of Land. The cost of land includes the purchase price of the land obtained for project use. It does not include the cost of preparing the land for use, such as soil remediation, demolition of existing structures, site preparation, etc.

Cost of Quality Management. The sum of those costs associated with quality deviation prevention and appraisal activities. Examples include:

Quality System/Program Development Personnel Qualification Testing Formal Design Check/Review On/Off-Site Inspection

Direct Cost of Field Rework. The sum of those costs associated with actual performance of tasks involved in rework. Examples include:

Glossary of Terms Page 1

Page 2: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

Labor Materials Equipment Supervisory personnel Associated overhead cost

Electronic Data Interchange (EDI). EDI is a technology that permits the direct computer-to-computer exchange of data in a standard format. Data is transmitted in a standard industry format, checked for error, and imported directly into the receiving computer system without re-keying.

Expansion. - A new addition that ties in to an existing facility, often intended to expand capacity. Synonym: Addition.

Grass Roots (Green Field). A new facility from the foundations and up. A project requiring demolition of an existing facility before new construction begins is also classified as grass roots.

Integrated Database. An integrated database is a concept of organizing, storing, and managing all electronic data relating to a project in such a fashion that data is entered and stored once and then accessed and utilized by multiple users and applications. The users may include those involved with facility planning, design, procurement, construction, plant operations, and suppliers.

Materials Management. Materials management is an integrated process for planning and controlling all necessary efforts to make certain that the quality and quantity of materials and equipment are appropriately specified in a timely manner, are obtained at a reasonable cost, and are available when needed. The materials management systems combine and integrate the takeoff, vendor evaluation, purchasing, expediting, warehousing, distribution, and disposing of materials functions.

Mechanical Completion. The point in time when a plant is capable of being operated although some trim, insulation, and painting may still be needed. This occurs after completion of precommissioning. In some industries, mechanical completion may have the same general meaning as beneficial occupancy.

Modernization. A facility for which a substantial amount of the equipment, structure, or other components is replaced or modified, and which may expand capacity and/or improve the process or facility. Synonyms: Renovation, Upgrade.

Modularization . Modularization refers to the use of offsite construction. For the purposes of the benchmarking data, modularization includes all work that represents substantial offsite construction and assembly of components and areas of the finished project. Examples that would fall within this categorization include:

Skid assemblies of equipment and instrumentation that naturally ship to the site in one piece, and require minimal on-site reassembly.

Super-skids of assemblies of components that typically represent substantial portions of the plant, intended to be installed in a building.

Prefabricated modules comprising both industrial plant components and architecturally finished enclosures.

Glossary of Terms Page 2

Page 3: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

Modularization does not include offsite fabrication of components. Examples of work that would be excluded from the definition of modularization include:

Fabrication of the component pieces of a structural framework Fabrication of piping spool-pieces

Planning for Startup. Startup is the transitional phase between plant construction completion and commercial operations, including all of the activities that bridge these two phases. Planning for Startup consists of a sequence of activities that begins during requirements definition and extends through initial operations.

Pre-Project Planning. Pre-Project Planning involves the process of developing sufficient strategic information that owners can address risk and decide to commit resources to maximize the chance for a successful project. Pre-project planning includes putting together the project team, selecting technology, selecting project site, developing project scope, and developing project alternatives. Pre-project planning is often perceived as synonymous with front-end loading, front-end planning, feasibility analysis, and conceptual planning.

Project Budget at Authorization to Proceed. This is the estimated cost for your company’s portion of the project at authorization to proceed. If your contract had cost changes before authorization to proceed, then these changes should be included in the project budget. Do not include estimated costs for change orders received during project execution. .

Project Development Changes. Changes required to execute the original scope of work or obtain original process basis. Examples include:

Unforeseen site conditions that require a change in design / construction methods Changes required due to errors and omissions Acceleration Change in owner preferences Additional equipment or processes required to obtain original planned throughput Operability or maintainability changes

Project Change Management. Practices related to the management and control of both scope changes and project changes.

P&IDs (Piping and Instrumentation Diagrams). Schematic diagrams which show the layout and relationship of piping and instrumentation.

Quality Management. Quality Management incorporates all activities conducted to improve the efficiency, contract compliance and cost effectiveness of design, engineering, procurement, QA/QC, construction, and start-up elements of construction projects.

Renovation. A facility for which a substantial amount of the equipment, structure, or other components is replaced or modified, and which may expand capacity and/or improve the process or facility. Synonyms: Modernization, Upgrade.

Scope Changes. Changes in the base scope of work or process basis. Examples include: Feedstock change

Glossary of Terms Page 3

Page 4: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

Changed site location Changed throughput Addition of unrelated scope

Team Building. Team Building is a project-focused process that builds and develops shared goals, interdependence, trust and commitment, and accountability among team members and that seeks to improve team members problem-solving skills.

Total Actual Project Cost. This is the total actual cost of all work performed by your company, including costs attributable to work added or deducted by change orders.

Turnaround/Shutdown/Outage. The period during which a boiler, generating unit, transmission line, or other facility is shutdown and unable to perform its normal operations. The shutdown of a facility including for maintenance, inspection, testing, regulatory changes, or, in some cases, for refuelling is known as a planned shutdown. Turnaround is interchangeable with shutdown or outage depending on industry groups.

Upgrade. A facility for which a substantial amount of the equipment, structure, or other components is replaced or modified, and which may expand capacity and/or improve the process or facility. Synonyms: Modernization, Renovation.

Zero Accidents. Zero accident techniques include the site specific safety programs and implementation, auditing and incentive efforts to create a project environment and a level of training that embraces the mind set that all accidents are preventable and that zero accidents is an obtainable goal.

3D CAD modeling. Computer aided drafting system that provides three-dimensional views for checking physical interferences in addition to providing two and three dimensional drafting capabilities.

Glossary of Terms Page 4

Page 5: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

Project Phase Table

Project Phase Start/Stop Typical Activities & Products Typical Cost Elements

Pre-Project Planning

Typical Participants:• Owner Personnel• Planning Consultants• Constructability Consultant• Alliance / Partner

Start: Defined Business Need that requires facilities

Stop: Total Project Budget Authorized

• Options Analysis• Life-cycle Cost Analysis• Project Execution Plan• Appropriation Submittal Pkg• P&IDs and Site Layout• Project Scoping• Procurement Plan• Arch. Rendering

• Owner Planning Team Personnel Expenses

• Consultant Fees & Expenses • Environmental Permitting Costs• Project Manager / Construction

Manager Fees• Licensor Costs

Detail Design

Typical Participants:• Owner Personnel• Design Contractor• Constructability Expert• Alliance / Partner

Start: Design BasisStop: Release of all approved

drawings and specs for construction (or last package for fast-track)

• Drawing & spec preparation• Bill of material preparation• Procurement Status• Sequence of operations• Technical Review• Definitive Cost Estimate

• Owner Project Management Personnel

• Designer Fees• Project Manager / Construction

Manager Fees

Demolition / Abatement (see note below)

Typical Participants:• Owner Personnel• General Contractor • Demolition Contractor• Remediation / Abatement

Contractor

Start: Mobilization for demolition

Stop: Completion of demolition

• Remove existing facility or portion of facility to allow construction or renovation to proceed

• Perform cleanup or abatement / remediation

• Owner Project Management Personnel

• Project Manager / Construction Manager Fees

• General Contractor and/or Demolition Specialist Charges

• Abatement / Remediation Contractor Charges

Note: The demolition / abatement phase should be reported when the demolition / abatement work is a separate schedule activity (potentially paralleling the design and procurement phases) in preparation for new construction. Do not report the demolition / abatement phase if the work is integral with modernization or addition activities.

Glossary of Terms Page 5

Page 6: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

Project Phase Table (Cont.)

Project Phase Start/Stop Typical Activities & Products Typical Cost Elements

Procurement

Typical Participants:• Owner personnel• Design Contractor• Alliance / Partner

Start: Procurement Plan for Engineered EquipmentStop: All engineered

equipment has been delivered to site

• Vendor Qualification• Vendor Inquiries• Bid Analysis• Purchasing• Expediting• Engineered Equipment• Transportation• Vendor QA/QC

• Owner project management personnel• Project Manager / Construction

Manager fees• Procurement & Expediting personnel • Engineered Equipment• Transportation• Shop QA / QC

Construction

Typical Participants:• Owner personnel• Design Contractor

(Inspection)• Construction Contractor and

its subcontractors

Start: Beginning of continuous substantial construction activity

Stop: Mechanical Completion

• Set up trailers• Site preparation• Procurement of bulks• Issue Subcontracts• Construction plan for

Methods/Sequencing• Build Facility & Install

Engineered Equipment• Complete Punchlist• Demobilize construction

equipment• Warehousing

• Owner project management personnel• Project Manager / Construction

Manager fees• Building permits• Inspection QA/QC• Construction labor, equipment &

supplies• Bulk materials• Construction equipment• Contractor management personnel• Warranties

Start-up / CommissioningNote: Does not usually apply to infrastructure or building type projects

Typical Participants:• Owner personnel• Design Contractor • Construction Contractor• Training Consultant• Equipment Vendors

Start: Mechanical CompletionStop: Custody transfer to

user/operator (steady state operation)

• Testing Systems• Training Operators• Documenting Results• Introduce Feedstocks and

obtain first Product• Hand-off to user/operator• Operating System• Functional Facility• Warranty Work

• Owner project management personnel• Project Manager / Construction

Manager fees• Consultant fees & expenses• Operator training expenses• Wasted feedstocks• Vendor fees

Glossary of Terms Page 6

Page 7: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

PDRI (Project Definition Rating Index) Buildings

SECTION I: BASIS OF PROJECT DECISION

A. BUSINESS STRATEGY

A1. Building Use

Identify and list building uses or functions. These may include uses such as:

· Retail · Institutional · Instructional · Medical · Storage · Food service · Recreational · Research · Multimedia · Office · Light manufacturing

A description of other options which could also meet the facility need should be defined. (As an example, was renovating existing space rather than building new space considered?) A listing of current facilities that will be vacated due to the new project should be produced.

A2. Business Justification

Identify driving forces for the project and specify what is most important from the viewpoint of the owner including both needs and expectations. Address items such as:

· Need date · Target consumers · Building utilization justification · Possible competitors · Level of amenities · Location · Sales or rental levels · Market capacity · Use flexibility · Number of lessons/occupant types · Support new business initiatives · Facility replacement/consolidation A3. Business Plan

A project strategy should be developed that supports the business justification in relation to the following items:

Glossary of Terms Page 7

Page 8: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

· Funding availability · Cost and financing · Schedule milestones (including known deadlines) · Types and sources of project funds · Related/resulting projects

A4. Economic Analysis

An economic model should be developed to determine the viability of the venture. The model should acknowledge uncertainty and outline the boundaries of the analysis. It should acknowledge items such as:

· Design life · Building ownership · Tax implications of investment including length of ownership · Long-term operating and maintenance costs · Resale/lease potential or in the case of institutional buildings, long-term use plans · Analysis of capital and operating cost versus sales or occupancy and profitability

A5. Facility Requirements

Facility size requirements are many times determined by applicable code and are often driven by occupancy. Note that this analysis is at the macro level. Some considerations are listed below:

· Number of occupants · Volume · Net and gross square footage by area uses · Support infrastructure · Classroom size · Linear feet of display space · Number of laboratory stations · Occupant accommodation requirements (i.e., number of hospital beds, number of desks, number of workstations, on-site child care, on-site medical care, cot space, etc.)

A6. Future Expansion/Alteration Considerations

The possibility of expansion and/or alteration of the site and building should be considered for facility design. These considerations consist of a list of items that will facilitate the expansion or evolution of building use including adaptability/flexibility.

Evaluation criteria may include:

· Provisions for site space in case of possible future expansion up or out · Technologically advanced facility requirements · Are departments or functional areas intended to “grow in place” during the future phase? · If there will not be a future expansion of the building, how will departments or areas expand?

Glossary of Terms Page 8

Page 9: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

· Are any functional areas more likely than others to move out of the building in the future to allow others to expand or move in? · Who will occupy the building in five, 10, 15, 20 years? · Flexibility or adaptability for future uses. · Future phasing plan

A7. Site Selection Considerations

Evaluation of sites should address issues relative to different locations (i.e., global, country, or local). This evaluation may take into consideration existing buildings or properties, as well as new locations. The selection criteria include items such as:

· General geographic location o Access to the targeted market area o Local availability and cost of skilled labor (e.g., construction, operation) o Available utilities o Existing facilities o Economic incentive zones o Tax · Land availability and developed costs · Legal constraints · Unusual financing requirements in region/locality · Domestic culture vs. international culture · Community relations · Labor relations · Government relations · Political issues/constraints · Education/training · Safety and health considerations · Environmental issues · Symbolic and aesthetic · Historic preservation · Weather/climate · Permitting Schedule

A8. Project Objectives Statement

This statement defines the project objectives and priorities for meeting the business strategy. It should be clear, concise, measurable, and specific to the project. It is desirable to obtain total agreement from the entire project team regarding these objectives and priorities to ensure alignment. Specifically, the priorities among cost, schedule, and value-added quality features should be clear. The objectives also should comply with any master plans if applicable.

B. OWNER PHILOSOPHIES

B1. Reliability Philosophy

Glossary of Terms Page 9

Page 10: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

A brief description of the project intent in terms of reliability should be defined. A list of the general design principles to be considered to achieve optimum/ideal operating performance from the facility/building should be addressed. Considerations may include:

· Critical systems redundancy · Architectural/structural/civil durability · Mechanical/electrical/plumbing reliability

B2. Maintenance Philosophy

A list of the general design principles to be considered to meet building maintenance requirements should be identified. This evaluation should include life cycle cost analysis of major facilities. Considerations may include:

· Daily occupancy loads · Maximum building occupancy requirements · Equipment monitoring requirements · Energy conservation programs · Selection of materials and finishes · Requirements for building finishes

B3. Operating Philosophy

A list of the general design issues that need to be considered to support routine operations should be developed. Issues may include:

· Operating schedule/hours · Provisions for building rental or occupancy assignments (i.e., by room, floor, suite) including flexibility of partitioning · Future renovation schedule · User finish out philosophy · Flexibility to change layout

B4. Design Philosophy

A listing of design philosophy issues should be developed. These issues should be directed at concerns such as the following:

· Design life · Aesthetic requirements · Compatibility with master plan · Theme · Image · Environmentally sustainable design (internal/external) · Quality of life

C. PROJECT REQUIREMENTS

Glossary of Terms Page 10

Page 11: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

C1. Value-Analysis Process

A structured value analysis approach should be in place to consider design and material alternatives in terms of their cost effectiveness. Items that impact the economic viability of the project should be considered. Items to evaluate include issues such as:

· Discretionary scope issues · Expensive materials of construction · Life-cycle analysis of construction methods and structure

C2. Project Design Criteria

Project design criteria are the requirements and guidelines which govern the design of the project. Any design review board or design review process should be clearly articulated. Evaluation criteria may include:

· Level of design detail required · Climatic data · Codes and standards o National o Local o Owner specific o International · Utilization of design standards o Owner’s o Contractor’s o Designer’s o Mixed · Level of design detail required · Donor or benefactor requirements · Sole source requirements for equipment or systems · Insurance underwriter requirements · Cultural preferences

C3. Evaluation of Existing Facilities

If existing facilities are available, then a condition assessment must be performed to determine if they will meet facility requirements. Evaluation criteria may include:

· Capacity · Power · Utilities (i.e., potable water, gas, oil) · Fire water · Waste treatment/disposal · Sanitary sewer · Telecommunications · Security · Storm water containment system/filtration · Access

Glossary of Terms Page 11

Page 12: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

o Rail o ADA or local standards o Roads · Parking areas · Type and size of buildings/structures · Amenities o Food service o Ambulatory access o Medical facilities o Recreation facilities including public outdoor spaces o Change rooms · Condition assessment of existing facilities and infrastructure · Other

C4. Scope of Work Overview

This work statement overview is a complete narrative description of the project that is discipline-oriented and supports development of the project schedule and project cost estimate. It sets the limits of work by each involved party and generally articulates their financial, task, and contractual responsibilities. It clearly states both assumptions and exclusions used to define the scope of work.

C5. Project Schedule

Ideally, the project schedule should be developed by the project team (owner, A/E, and construction contractor). It should include milestones, unusual schedule considerations and appropriate master schedule contingency time (float), procurement of long-lead or critical pacing equipment, and required submissions and approvals.

C6. Project Cost Estimate

The project cost estimate should address all costs necessary for completion of the project. This cost estimate may include the following:

· Construction contract estimate · Professional fees · Land cost · Furnishings · Administrative costs · Contingencies · Cost escalation for elements outside the project cost estimate · Startup costs including installation · Miscellaneous expenses including but not limited to: o Specialty consultants o Inspection and testing services o Bidding costs o Site clearance o Bringing utilities to the site o Environmental impact mitigation measures

Glossary of Terms Page 12

Page 13: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

o Local authority permit fees o Occupant moving and staging costs o Utility costs during construction (if paid by owner) o Interest on borrowed funds (cost of money) o Site surveys, soils tests o Availability of construction laydown and storage at site or in remote or rented facilities

SECTION II: BASIS OF DESIGN

D. SITE INFORMATION

D1. Site Layout

The facility should be sited on the selected property. Layout criteria may include items such as:

· Access (e.g., road, rail, marine, air) · Construction access · Historical/cultural · Trees and vegetation · Site massing and context constraints or guidelines (i.e., how a building will look in three dimensions at the site) · Access transportation parking, delivery/service, and pedestrian circulation considerations · Open space, street amenities, “urban context concerns” · Climate, wind, and sun orientation for natural lighting views, heat loss/gain, energy conservation, and aesthetic concerns

D2. Site Surveys

The site should be surveyed for the exact property boundaries, including limits of construction. A topography map with the overall plot and site plan is also needed. Evaluation criteria may include:

· Legal property descriptions with property lines · Easements · Rights-of-way · Drainage patterns · Deeds · Definition of final site elevation · Benchmark control systems · Setbacks · Access and curb cuts · Proximity to drainage ways and flood plains · Known below grade structures and utilities (both active and inactive) · Trees and vegetation · Existing facility locations and conditions · Solar/shadows

D3. Civil/Geotechnical Information

Glossary of Terms Page 13

Page 14: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

The civil/geotechnical site evaluation provides a basis for foundation, structural, and hydrological design. Evaluations of the proposed site should include items such as:

· Depth to bedrock · General site description (e.g., terrain, soils type, existing structures, spoil removal, areas of hazardous waste, etc.) · Expansive or collapse potential of soils · Fault line locations · Spoil area for excess soil (i.e., location of on-site area or off-site instructions) · Seismic requirements · Water table elevation · Flood plain analysis · Soil percolation rate and conductivity · Ground water flow rates and directions · Need for soil treatment or replacement · Description of foundation design options · Allowable bearing capacities · Pier/pile capacities · Paving design options · Overall site analysis

D4. Governing Regulatory Requirements

The local, state, and federal government permits necessary to construct and operate the facility should be identified. A work plan should be in place to prepare, submit, and track permit, regulatory, re-zoning, and code compliance for the project. It should include items such as:

· Construction · Unique requirements · Environmental · Structural calculations · Building height limits · Setback requirements · Fire · Building · Occupancy · Special · Signage · Historical issues · Accessibility · Demolition · Solar · Platting · Air/water · Transportation

The codes that will have a significant impact on the scope of the project should also be investigated and explained in detail. Particular attention should be paid to local requirements. Regulatory and code

Glossary of Terms Page 14

Page 15: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

requirements may affect the defined physical characteristics and project cost estimate. The project schedule may be affected by regulatory approval processes. For some technically complex buildings, regulations may change frequently.

D5. Environmental AssessmentAn environmental assessment should be performed for the site to evaluate issues that can impact the cost estimate or delay the project. These issues may include:

· Archeological · Location in an EPA air quality non-compliance zone · Location in a wet lands area · Environmental permits now in force · Existing contamination · Location of nearest residential area · Ground water monitoring in place · Downstream uses of ground water · Existing environmental problems with the site · Past/present use of site · Noise/vibration requirements · Air/water discharge requirements and options evaluated · Discharge limits of sanitary and storm sewers identified · Detention requirements · Endangered species · Erosion/sediment control

D6. Utility Sources with Supply Conditions

The availability/non-availability of site utilities needed to operate the facility with supply conditions of quantity, temperature, pressure, and quality should be evaluated. This may include items such as:

· Potable water · Drinking water · Cooling water · Fire water · Sewers · Instrument air · Facility air · Heating water · Gases · Steam · Electricity (voltage levels) · Communications (e.g., data, cable television, telephones) · Special requirement (e.g., deionized water or oxygen)

D7. Site Life Safety Considerations

Glossary of Terms Page 15

Page 16: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

Fire and life safety related items should be taken into account for the selected site. These items should include fire protection practices at the site, available firewater supply (amounts and conditions), and special safety requirements unique to the site. Evaluation criteria may include:

· Wind direction indicator devices (e.g., wind socks) · Fire monitors and hydrants · Flow testing · Access and evacuation plan · Available emergency medical facilities · Security considerations (site illumination, access control)

D8. Special Water and Waste Treatment Requirements

On-site or pretreatment of water and waste should be evaluated. Items for consideration may include:

· Wastewater treatment · Process waste · Sanitary waste · Waste disposal · Storm water containment and treatment

E. BUILDING PROGRAMMING

E1. Program Statement

The program statement identifies the levels of performance for the facility in terms of space planning and functional relationships. It should address the human, physical, and external aspects to be considered in the design. Each performance criteria should include these issues:

· A performance statement outlining what goals are to be attained (e.g., providing sufficient lighting levels to accomplish the specified task safely and efficiently) · A measure that must be achieved (e.g., 200 foot-candles at surface of surgical table) · A test which is an accepted approach to establish that the criterion has been met (e.g., using a standard light meter to do the job)

E2. Building Summary Space List

The summary space list includes all space requirements for the entire project. This list should address specific types and areas. Possible space listings include:

· Building population · Administrative offices · Lounges · Food Service Cafeteria · Conference rooms · Vending alcoves · Janitorial closets · Elevators

Glossary of Terms Page 16

Page 17: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

· Stairs · Loading docks · Dwelling units · Special technology considerations · Classrooms · Laboratories · Corridors · Storage facilities · Mechanical rooms · Electrical rooms · Parking space · Entry lobby · Restrooms · Data/computer areas

A room data sheet should correspond to each entry on the summary space list. Room data sheets are discussed in element E11. The room data sheet contains information that is necessary for the summary space list. This list is used to determine assignable (usable) and non-assignable (gross) areas.

E3. Overall Adjacency Diagrams

The overall adjacency diagrams depict the layout of each department or division of the entire building. They show the relationship of specific rooms, offices, and sections. The adjacency diagrams must adequately convey the overall relationships between functional areas within the facility. Note that these diagrams are sometimes known as “bubble diagrams” or “balloon diagrams.” They are also commonly expressed in an adjacency matrix.

E4. Stacking Diagrams

A stacking diagram portrays each department or functional unit vertically in a multi-story building. Stacking diagrams are drawn to scale, and they can help establish key design elements for the building. These diagrams are easily created with space lists and adjacency (or bubble) diagrams. Critical vertical relationships may relate to circulatory (stairs, elevators), structural elements, and mechanical or utility shafts. Stacking diagrams can establish building elements such as floor size. This type of diagram often combines functional adjacencies and space requirements and also shows how the project is sited.

E5. Growth and Phased Development

Provisions for future phases or anticipated use change must be considered during project programming. A successful initial phase necessitates a plan for the long term phases. The following phasing issues may be addressed.

· Guidelines to allow for additions (i.e., over-design of structural systems, joist layout, column spacing) · Technology needs as facility grows and expands or changes (e.g., mechanical systems, water demands) · Compare the additional costs involved with making the building “expandable” versus the probability of the future expansion occurring as envisioned.

Glossary of Terms Page 17

Page 18: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

· Provisions for infrastructure that allow for future expansion

E6. Circulation and Open Space Requirements

An important component of space programming is common-area open spaces, both interior and exterior. These areas include the items listed and considerations such as:

· Exterior o Service dock areas and access o Circulation to parking areas o Passenger drop-off areas o Pedestrian walkways o Courtyards, plazas, or parks o Landscape buffer areas o Unbuildable areas (e.g., wetlands or slopes) o Sidewalks or other pedestrian routes o Bicycle facilities o Lobbies and entries o Security considerations (e.g., card access or transmitters) o Snow removal plan o Postal and newspaper delivery o Waste removal o Fire and life-safety circulation considerations · Interior o Interior aisle ways and corridors o Vertical circulation (i.e., personnel and material transport including elevators and escalators) o Directional and location signage

E7. Functional Relationship Diagrams/Room by Room

Room by room functional relationship diagrams show the structure of adjacencies of a group of rooms. With these adjacency diagrams (also known as bubble diagrams), the architect can convert them into a floor plan with all the relationships. Each space detail sheet should have a minimum of one functional relationship diagram. Rooms are often represented by circles, bubbles, squares, or rectangles. Larger rooms are represented with bigger symbols. They are also commonly expressed in an adjacency matrix.

E8. Loading/Unloading/Storage Facilities Requirements

list of requirements identifying materials to be unloaded and stored and products to be loaded along with their specifications. This list should include items such as:

· Storage facilities to be provided and/or utilized · Refrigeration requirements and capabilities · Mail/small package delivery · Recycling requirements

Glossary of Terms Page 18

Page 19: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

E9. Transportation Requirements

Specifications for implementation of facility transportation (e.g., roadways, conveyers, elevators) as well as methods for receiving and shipping of materials (e.g., air, rail, truck, marine) should be identified. Provisions should be included for items such as:

· Facility access requirements based on transportation · Drive-in doors · Extended ramps for low clearance trailers · Rail car access doors · Service elevators · Loading docks · Temporary parking

E10. Building Finishes

Levels of interior and exterior finishes should be defined for the project. For example, the finishes may include categories such as:

Interior Schedule: · Type A o Floor: vinyl composition tile o Walls: painted · Type B o Floor: direct glue carpet o Walls: vinyl wall covering · Type C o Floor: carpet over pad o Walls: wood paneling Exterior Schedule: · Type 1 o Walls: brick o Trim: brick · Type 2 o Walls: overlapping masonry o Trim: cedar

Finishes and local design standards are further defined in category F.

E11. Room Data Sheets

Room data sheets contain the specific requirements for each room considering its functional needs. A room data sheet should correspond to each room on the building summary space list. The format of the room data sheet should be consistent. Possible issues to include on room data sheets are:

· Critical dimensions · Technical requirements (e.g., fireproof, explosion resistance, X-ray) · Furnishing requirements

Glossary of Terms Page 19

Page 20: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

· Equipment requirements · Audio/visual (A/V) data and communication provisions · Lighting requirements · Utility requirements · Security needs including access/hours of operation · Finish type · Environmental issues · Acoustics/vibration requirements · Life-safety

E12. Furnishings, Equipment, and Built-Ins

All moveable furnishings, equipment, and built-ins should be listed on the room data sheets. Moveable and fixed in place equipment should be distinguished. Building modifications, such as wide access doors or high ceilings, necessary for any equipment also need to be listed. Long delivery time items should be identified and ordered early. It is critical to identify the utility impact of equipment (e.g., electrical, cooling, special water or drains, venting, radio frequency shielding). Examples may include:

· Furniture · Kitchen equipment · Medical equipment · Material handling · Partitions New items and relocated existing items must be distinguished in the program. The items can be classified in the following categories.

New Items:

· Contractor furnished and contractor installed · Owner furnished and contractor installed · Owner furnished and owner installed

Existing Items:

· Relocated as is and contractor installed · Refurbished and installed by contractor · Relocated as is and owner installed · Refurbished and installed by owner

E13. Window Treatment

Any special fenestration window treatments for energy and/or light control should be noted in order to have proper use of natural light. Some examples include:

· Blocking of natural light · Glare reducing windows · Exterior louvers

Glossary of Terms Page 20

Page 21: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

· Interior blinds

F. BUILDING/PROJECT DESIGN PARAMETERS

F1. Civil/Site Design

Civil/site design issues should be addressed to provide a basis for facility design. Issues to address may include:

· Service and storage requirements · Elevation and profile views · High point elevations for grade, paving, and foundations · Location of equipment · Minimum overhead clearances · Storm drainage system · Location and route of underground utilities · Site utilities · Earth work · Subsurface work · Paving/curbs · Landscape/xeriscape · Fencing/site security

F2. Architectural Design

Architectural design issue should be addressed to provide a basis for facility design. These issues may include the following:

· Determination of metric (hard/soft) versus Imperial (English) units (Note: The term “hard” metric means that materials and equipment are identified on the drawings and have to be delivered in metric-sized unit dimensions such as 200mm by 400mm. “Soft” metric means that materials and equipment can be delivered using sizes that approximate the metric dimensions given on the drawings, such as three-inch length instead of eight cm. It is important to set these dimensions and not “mix and match.”)

· Requirements for building location/orientation horizontal and vertical · Access requirements · Nature/character of building design (e.g., aesthetics) · Construction materials · Acoustical considerations · American with Disabilities Act requirements or other local access requirements · Architectural Review Boards · Planning and zoning review boards · Circulation considerations · Seismic design considerations · Color/material standards · Hardware standards · Furniture, furnishings, and accessories criteria · Design grid

Glossary of Terms Page 21

Page 22: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

· Floor to floor height

F3. Structural Design

Structural design considerations should be addressed to provide a basis for the facility design. These considerations may include the following:

· Structural system (e.g., construction materials, constraints) · Seismic requirements · Foundation system · Corrosion control requirements/required protective coatings · Client specifications (e.g., basis for design loads, vibration, deflection) · Future expansion/flexibility considerations · Design loading parameter (e.g., live/dead loads, design loads, collateral load capacity, equipment/material loads, wind/snow loads, uplift) · Functional spatial constraints

F4. Mechanical Design

Mechanical design parameters should be developed to provide a basis for facility design. Items to consider include:

· Special ventilation or exhaust requirements · Equipment/space special requirements with respect to environmental conditions (e.g., air quality, special temperatures) · Energy conservation and life cycle costs · Acoustical requirements · Zoning and controls · Air circulation requirements · Outdoor design conditions (e.g., minimum and maximum yearly temperatures) · Indoor design conditions (e.g., temperature, humidity, pressure, air quality) · Building emissions control · Utility support requirements · System redundancy requirements · Plumbing requirements · Special piping requirements · Seismic requirements

F5. Electrical Design

Electrical design parameters provide the basis for facility design. Consider items such as:

· Power sources with available voltage and amperage · Special lighting considerations (e.g., lighting levels, color rendition) · Voice, data, and video communications requirements · Uninterruptable power source (UPS) and/or emergency power requirements · Energy consumption/conservation and life cycle cost · Ability to use daylight in lighting

Glossary of Terms Page 22

Page 23: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

· Seismic requirements · Lightning/grounding requirements

F6. Building Life Safety Requirements

Building life safety requirements are a necessity for building operations. They should be identified at this stage of the project. Possible safety requirements are listed below:

· Fire resistant requirements · Explosion resistant requirements · Area of refuge requirements in case of catastrophe · Safety and alarm requirements · Fire detection and/or suppression requirements · Eye wash stations · Safety showers · Deluge requirements and foam · Fume hoods · Handling of hazardous materials · Isolation facilities · Sterile environments · Emergency equipment access · Personnel shelters · Egress · Public address requirements · Data or communications protection in case of disaster or emergency · Fall hazard protection · Gas hazard detection

F7. Constructability Analysis

CII defines constructability as, “the optimum use of construction knowledge and experience in planning, design, procurement, and field operations to achieve overall project objectives. Maximum benefits occur when people with construction knowledge and experience become involved at the very beginning of a project.” Is there a structured approach for constructability analysis in place? Have provisions been made to provide this on an ongoing basis? This would include examining design options and details of construction that minimize construction costs while maintaining standards of safety, quality, and schedule. Elements of constructability during pre-project planning include:

· Constructability program in existence · Construction knowledge/experience used in project planning · Early construction involvement in contracting strategy development · Developing a construction-sensitive project schedule · Considering major construction methods in basic design approaches · Developing site layouts for efficient construction · Early identification of project team participants for constructability analysis · Usage of advanced information technologies

F8. Technological Sophistication

Glossary of Terms Page 23

Page 24: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

The requirements for intelligent or special building systems should be evaluated. Examples of these systems may include:

· Video conferencing · Internet connections · Advanced audio/visual (A/V) connections · Personnel sensing · Computer docking stations · “Smart” heating or air-conditioning · Intercommunication systems · Security systems · Communication systems · Conveyance systems

G. EQUIPMENT

G1. Equipment List

Project-specific equipment should be defined and listed. (Note: Building systems equipment is addressed in element F4 – Mechanical Design and F5 – Electrical Design). In situations where owners are furnishing equipment, the equipment should be properly defined and purchased. The list should define items such as:

· Process · Medical · Food service/vending · Trash disposal · Distributed control systems · Material handling · Existing sources and characteristics of equipment o Relative sizes o Weights o Location o Capacities o Materials of construction o Insulation and painting requirements o Equipment related access o Vendor, model, and serial number once identified o Equipment delivery time, if known G2. Equipment Location Drawings

Equipment location/arrangement drawings identify the specific location of each item of equipment in a project. These drawings should identify items such as:

· Plan and elevation views of equipment and platforms · Location of equipment rooms · Physical support requirement (e.g., installation bolt patterns)

Glossary of Terms Page 24

Page 25: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

· Coordinates or location of all major equipment

G3. Equipment Utility Requirements

This evaluation should consist of a tabulated list of utility requirements for all major equipment items such as:

· Power and/or all utility requirements · Flow diagrams · Design temperature and pressure · Diversity of use · Gas · Water

SECTION III: EXECUTION APPROACH

H. PROCUREMENT STRATEGY

H1. Identify Long-lead/Critical Equipment and Materials

Identify engineered equipment and material items with lead times that will impact the design for receipt of supplier information or impact the construction schedule with long delivery times.

H2. Procurement Procedures and Plans

Procurement procedures and plans include specific guidelines, special requirements, or methodologies for accomplishing the purchasing, expediting, and delivery of equipment and materials required for the project. Evaluation criteria may include:

· Who will perform procurement? · Listing of approved vendors, if applicable · Client or contractor purchase orders · Reimbursement terms and conditions · Guidelines for supplier alliances, single source, or competitive bids · Guidelines for engineering/construction contracts · Who assumes responsibility for owner-purchased items? o Financial o Shop inspection o Expediting · Tax strategy o Depreciation capture o Local sales and use tax treatment o Investment tax credits · Definition of source inspection requirements and responsibilities · Definition of traffic/insurance responsibilities · Definition of procurement status reporting requirements · Additional/special owner accounting requirements · Definition of spare parts requirements

Glossary of Terms Page 25

Page 26: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

· Local regulations (e.g., tax restrictions, tax advantages) · Incentive/penalty strategy for contracts · Storage

J. DELIVERABLES

J1. CADD/Model Requirements

Computer Aided Drafting and Design (CADD) requirements should be defined. Evaluation criteria may include:

o Software system required by client (e.g., AutoCAD, Intergraph) o Will the project be required to be designed using 2D or 3D CADD? Will rendering be required? o If 3D CADD is to be used, will a walk-through simulation be required? o Owner/contractor standard symbols and details o How will data be received and returned to/from the owner? o Disk o Electronic transfer o Tape o Reproducibles o Full-size mock-ups

Physical model requirements depend upon the type needed for analysis, such as study models or design checks.

J2. Documentation/Deliverables

Documentation and deliverables required during project execution should be identified. If electronic media are to be used, format and application packages should be outlined. The following items may be included in a list of deliverables:

o Drawings and specifications o Project correspondence o Permits o Maintenance and operating information/startup procedures o Facility keys, keying schedules, and access codes o Project data books (quantity, format, contents, and completion date) o Equipment folders (quantity, format, contents, and completion date) o Design calculations (quantity, format, contents, and completion date) o Spare parts and maintenance stock (special forms) o Procuring documents/contract documents o Record (as-built) documents o Quality assurance documents o Project signage o Guarantees/warranties o Inspection documents o Certificates of inspection

Glossary of Terms Page 26

Page 27: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

o Shop drawings and samples o Bonds o Distribution matrix

K. PROJECT CONTROL

K1. Project Quality Assurance and Control

Quality assurance and quality control procedures need to be established. Responsibility for approvals needs to be developed. Electronic media requirements should be outlined. These issues may include:

o Responsibility during design and construction o Testing of materials and workmanship o ISO 9000 requirements o Submittals and shop drawing approach o Inspection reporting requirements o Progress photos o Reviewing changes and modifications o Communication documents (e.g., RFIs, RFQs) o Commissioning tests o Lessons-learned feedback

K2. Project Cost Control

Procedures for controlling project cost need to be outlined and responsibility assigned. Electronic media requirements should be identified. These may include cost control requirements such as:

o Financial (client/regulatory) o Phasing or area sub-accounting o Capital vs. non-capital expenditures o Report requirements o Payment schedules and procedures o Cash flow projections/draw down analysis o Cost code scheme/strategy o Costs for each project phase o Periodic control check estimates o Change order management procedure, including scope control

K3. Project Schedule Control

The project schedule is created to show progress and ensure that the project is completed on time. The schedule is necessary for design and construction of the building. A schedule format should be decided on at the beginning of the project. Typical items included in a project schedule are listed below.

o Milestones o Unusual schedule considerations o Required submissions and/or approvals o Required documentation and responsible party

Glossary of Terms Page 27

Page 28: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

o Baseline vs. progress to date o Long-lead or critical pacing equipment delivery o Critical path activities o Contingency or “float time” o Permitting or regulatory approvals o Activation and commissioning o Liquidated damages/incentives The owner must also identify how special project issues will be scheduled. These items may include:

o Selection, procurement, and installation of equipment o Design of interior spaces (including furniture and accessory selection) o Stages of the project that must be handled differently than the rest of the project o Tie-ins, service interruptions, and road closures

K4. Risk Management

Major project risks need to be identified, quantified, and management actions taken to mitigate problems developed. Pertinent elements may include:

o Design risks o Expertise o Experience o Work load o Teamwork orientation o Communication o Integration and coordination o Construction risks o Availability of craft labor and construction materials o Weather o Differing/unforeseen/difficult site conditions o Long-lead item delays o Strikes o Inflation o Scope growth o Management risks o Availability of designers o Critical quality issues o Bidders o Human error o Cost and schedule estimates o Timely decisions o Team chemistry o Insurance considerations

K5. Safety Procedures

Glossary of Terms Page 28

Page 29: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

Safety procedures and responsibilities must be identified for design consideration and construction. Safety issues to be addressed may include:

o Hazardous material handling o Interaction with the public o Working at elevations/fall hazards o Evacuation plans and procedures o Drug testing o First aid stations o Accident reporting and investigation o Pre-task planning o Safety orientation and planning o Safety incentives o Other special or unusual safety issues

L. PROJECT EXECUTION PLAN

L1. Project Organization

The project team should be identified including roles, responsibilities, and authority. Items to consider include:

o Core team members o Project manager assigned o Project sponsor assigned o Working relationships between participants o Communication channels o Organizational chart o Approval responsibilities/responsibility matrix

L2. Owner Approval Requirements All documents that require owner approval should be clearly defined. These may include:

o Milestones for drawing approval by phase o Comment o Approval o Bid issues (public or private) o Construction o Durations of approval cycle compatible with schedule o Individual(s) responsible for reconciling comments before return o Types of drawings/specifications o Purchase documents/general conditions and contract documents o Data sheets o Inquiries o Bid tabulations o Purchase orders o Supplier information

Glossary of Terms Page 29

Page 30: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

L3. Project Delivery Method

The methods of project design and construction delivery, including fee structure should be identified. Issues to consider include:

o Owner self-performed o Designer and constructor qualification selection process o Selected methods (e.g., design/build, CM at risk, competitive sealed proposal, bridging, design-bid-build) o Contracting strategies (e.g., lump sum, cost-plus) o Design/build scope package considerations

L4. Design/Construction Plan and ApproachThis is a documented plan identifying the specific approach to be used in designing and constructing the project. It should include items such as:

o Responsibility matrix o Subcontracting strategy o Work week plan/schedule o Organizational structure o Work Breakdown Structure (WBS) o Construction sequencing of events o Site logistics plan o Safety requirements/program o Identification of critical activities that have potential impact on facilities (i.e., existing facilities, crane usage, utility shut downs and tie-ins, testing) o Quality assurance/quality control (QA/QC) plan o Design and approvals sequencing of events o Equipment procurement and staging o Contractor meeting/reporting schedule o Partnering or strategic alliances o Alternative dispute resolution o Furnishings, equipment, and built-ins responsibility

L5. Substantial Completion Requirements

Substantial Completion (SC) is defined as the point in time when the building is ready to be occupied. The following may need to be addressed:

o Have specific requirements for SC responsibilities been developed? o Have warranty, permitting, insurance, and tax implications been considered? o Commissioning o Equipment/systems startup and testing o Occupancy phasing o Final code inspection o Calibration o Verification o Documentation

Glossary of Terms Page 30

Page 31: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

o Training o Acceptance o Landscape requirements o Punchlist completion plan and schedule o Substantial completion certificate

Glossary of Terms Page 31

Page 32: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

PDRI (Project Definition Rating Index) Industrial

SECTION I - BASIS OF PROJECT DECISION

A. MANUFACTURING OBJECTIVES CRITERIA

A1. Reliability Philosophy

A list of the general design principles to be considered to achieve dependable operating performance from the unit. Evaluation criteria should include:

· Justification of spare equipment · Control, alarm, and safety systems redundancy · Extent of providing surge and intermediate storage capacity to permit independent shutdown of portions of the plant · Mechanical / structural integrity of components (metallurgy, seals, types of couplings, bearing selection, etc.)

A2. Maintenance Philosophy

A list of the general design principles to be considered to meet unit up-time requirements. Evaluation criteria should include: · Scheduled unit / equipment shutdown frequencies and durations · Equipment access / monorails / cranes · Maximum weight or size requirements for available repair equipment · Equipment monitoring requirements (vibrations monitoring, etc.)

A3. Operating Philosophy

A list of the general design principles that need to be considered to support the routine scheduled production from the unit in order to achieve the projected overall on-stream time or service factor.

Evaluation criteria should include:

· Level of operator coverage and automatic control to be provided · Operating time sequence (ranging from continuous operation to five day, day shift only) · Necessary level of segregation and clean out between batches or runs · Desired unit turndown capability · Design requirements for routine startup and shutdown

B. BUSINESS OBJECTIVES

B1. Products

A list of product(s) to be manufactured and their specifications. It should address items such as:

· Chemical composition

Glossary of Terms Page 32

Page 33: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

· Allowable impurities · Physical form · By-products · Raw materials · Wastes

B2. Market Strategy

Has a market strategy been developed and clearly communicated? It must identify the driving forces (other than safety) for the project and specify what is most important from the viewpoint of the business group. It should address items such as:

· Cost · Schedule · Quality

B3. Project Strategy

Has a project strategy been defined that supports the market strategy in relation to the following items:

· Cost · Schedule · Quality B4. Affordability / Feasibility

Have items that may improve the affordability of the project been considered? These should include incremental cost criteria such as:

· Consideration of feedstock availability and transport to the job site · Performing an analysis of capital and operating cost versus sales and profitability

Results of these studies should be communicated to the project team.

B5. CapacitiesThe design output of a given specification product from the unit. Capacities are usually defined as:

· On-stream factors · Yield · Design rate B6. Future Expansion Considerations

A list of items to be considered in the unit design that will facilitate future expansion. Evaluation criteria should include:

· Providing space for a possible new reactor train

Glossary of Terms Page 33

Page 34: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

· Providing tie-ins to permit a duplicate or mirror image unit that can be added without necessitating a shutdown · Guidelines for over design of structural systems to allow for additions

B7. Expected Project Life Cycle

This is the time period that the unit is expected to be able to satisfy the products and capacities required. Have requirements for ultimate disposal and dismantling been considered? These requirements should include:

· Cost of ultimate dismantling and disposal · Dismantling equipment requirements · Presence of contaminants · Disposal of hazardous materials · Possible future uses

B8. Social Issues

Evaluation of various social issues such as:

· Domestic culture vs. international culture · Community relations · Labor relations · Government relations · Education / training · Safety and health considerations

C. BASIC DATA RESEARCH & DEVELOPMENT

C1. Technology

The chemistry used to convert the raw materials supplied to the unit into the finished product. Proven technology involves least risk, while experimental technology has a potential for change. Technology can be evaluated as:

· Existing / proven · Duplicate · New · Experimental

C2. Processes

A particular, specific sequence of steps to change the raw materials into the finished product. Proven processes involve the least risk, while experimental processes have a potential for change. Processes can be evaluated as:

· Existing / proven · Duplicate

Glossary of Terms Page 34

Page 35: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

· New · Experimental

D. PROJECT SCOPE

D1. Project Objectives Statement (Y/N) This is a mission statement that defines the project objectives and priorities for meeting the business objectives. It is important to obtain total agreement from the entire project team regarding these objectives and priorities to ensure alignment.

D2. Project Design Criteria The requirements and guidelines which govern the design of the project. Evaluation criteria should include:

· Level of design detail required · Climatic data · Codes & standards · National · Local · Utilization of engineering standards · Owner's · Contractor's · Mixed

D3. Site Characteristics Available vs. Required (Y/N)

An assessment of the available vs. the required site characteristics. Evaluation criteria should include:

· Capacity · Utilities · Power · Fire water · Pipe racks · Flare systems · Waste treatment / disposal · Cooling water · Storm water containment system · Type of buildings / structures · Amenities · Food service · Recreation facilities · Change rooms · Ambulatory access · Medical facilities · Product shipping facilities · Material receiving facilities · Material storage facilities · Product storage facilities

Glossary of Terms Page 35

Page 36: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

· Security

D4. Dismantling and Demolition Requirements

Has a scope of work been defined for the dismantling of existing equipment and/or piping which may be necessary for completing new construction? Evaluation criteria should include:

· Timing · Permits · Approval · Safety requirements · Hazardous operations · Plant / operations requirements · Narrative (scope of work) for each system · Are the systems that will be dismantled... · Named & marked on process flow diagrams · Named & marked on P&ID's · Denoted on line lists and equipment lists · Denoted on piping plans or photo-drawings

D5. Lead / Discipline Scope of Work

This is a complete narrative description of the project, generally discipline oriented. This should be developed through the use of the Work Breakdown Structure (WBS) (Halpin et al. 1987).

D6. Project Schedule (Y/N)

Has the project milestone schedule been developed, analyzed, and agreed upon by the major project participants? This should involve obtaining early constructability input from:

· Operations · Engineering · Construction

E. VALUE ENGINEERING

E1. Process Simplification (Y/N)

Identify activities (through studies, reviews, etc.) for reducing the number of steps or the amount of equipment needed in the process in order to optimize performance.

E2. Design & Material Alternatives Considered / Rejected (Y/N)

Is there a structured approach in place to consider design and material alternatives? Has it been implemented?

E3. Design For Constructability Analysis

Glossary of Terms Page 36

Page 37: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

Is there a structured approach for constructability analysis in place? Have provisions been made to provide this on an ongoing basis? This would include examining design options that minimize construction costs while maintaining standards of safety, quality, and schedule. CII defines constructability as, "the optimum use of construction knowledge and experience in planning, design, procurement, and field operations to achieve overall project objectives. Maximum benefits occur when people with construction knowledge and experience become involved at the very beginning of a project" (CII 1986).

SECTION II - FRONT END DEFINITION

F. SITE INFORMATION

F1. Site Location (Y/N)

Has the geographical location of the proposed project been defined? This involves an assessment of the relative strengths and weaknesses of alternate site locations. A site that meets owner requirements and maximizes benefits for the owner company should be selected. Evaluation of sites may address issues relative to different types of sites (i.e. global country, local, "inside the fence," or "inside the building"). This decision should consider the long-term needs of the owner company (CII 1995). The selection criteria should include items such as:

· General geographic location o Access to the targeted market area o Near sources of raw materials o Local availability and cost of skilled labor (e.g. construction, operation, etc.) o Available utilities o Existing facilities · Land availability and costs · Access (e.g. road, rail, marine, air, etc.) · Construction access and feasibility · Political constraints · Legal constraints · Regulatory constraints · Financing requirements · Social issues · Weather · Climate

F2. Surveys & Soil Tests

Survey and soil test evaluations of the proposed site should include items such as:

· Topography map · Overall plant plot plan · General site description (e.g. terrain, existing structures, spoil removal, areas of hazardous waste, etc.) · Definition of final site elevation · Benchmark control system

Glossary of Terms Page 37

Page 38: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

· Spoil area (i.e. location of on-site area or off-site instructions) · Seismic requirements · Water table · Soil percolation rate & conductivity · Existing contamination · Ground water flow rates and directions · Downstream uses of ground water · Need for soil treatment or replacement · Description of foundation types · Allowable bearing capacities · Pier / pile capacities F3. Environmental Assessment

Evaluation of the site by characteristics such as:

· Location in an EPA air quality non-compliance zone · Location in a wet lands area · Environmental permits now in force · Location of nearest residential area · Ground water monitoring in place · Containment requirements · Existing environmental problems with the site · Past / present use of site

F4. Permit Requirements

Is there a permitting plan in place? The local, state, and federal government permits necessary to construct and operate the unit should be identified. These should include items such as:

· Construction · Fire · Local · Building · Environmental · Occupancy · Transportation · Special

F5. Utility Sources With Supply Conditions

Has a list been made identifying availability / nonavailability of site utilities needed to operate the unit with supply conditions of temperature, pressure, and quality? This should include items such as:

· Potable water · Instrument air · Drinking water · Plant air

Glossary of Terms Page 38

Page 39: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

· Cooling water · Gases · Fire water · Steam · Sewers · Condensate · Electricity (voltage levels)

F6. Fire Protection & Safety Considerations

A list of fire and safety related items to be taken into account in the design of the facility. These items should include fire protection practices at the site, available firewater supply (amounts and conditions), special safety requirements unique to the site, etc. Evaluation criteria should include:

· Eye wash stations · Deluge requirements · Safety showers · Wind direction indicator · Fire monitors & hydrants devices (i.e. wind socks) · Foam · Alarm systems · Evacuation plan · Medical facilities · Security fencing

G. PROCESS / MECHANICAL

G1. Process Flow Sheets

Drawings that provide the process description of the unit. Evaluation criteria should include:

· Major equipment items · Flow of materials to and from the major equipment items · Primary control loops for the major equipment items · Sufficient information to allow sizing of all process lines

G2. Heat & Material Balances

Heat balances are tables of heat input and output for major equipment items (including all heat exchangers) within the unit. Material balances are tables of material input and output for all equipment items within the unit. The documentation of these balances should include:

· Special heat balance tables for reaction systems · Information on the conditions (e.g. temperature and pressure) · Volumetric amount (GPM, ACFM, etc.)

G3. Piping and Instrumentation Diagrams (P&ID's)

Glossary of Terms Page 39

Page 40: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

These are often referred to by different companies as:

EFD's - Engineering Flow Diagrams MFD's - Mechanical Flow Diagrams PMCD's - Process & Mechanical Control Diagrams

In general, P&ID's are considered to be a critical element within the scope definition package of an industrial project. Since incomplete information on P&ID's is frequently identified as a source of project escalation, it is important to understand their level of completeness. It often requires several iterations, or passes, to obtain all of the necessary information from each discipline specialist. During each iteration, additional information is added to the P&ID's. Thus, it is unlikely for P&ID's to be completely defined in a project's scope definition package.

VALVES

o Process needed valves o Valves needed for maintenance o Bypasses, blocks, and bleeds o Drains, vents, freeze protection, etc. o Type of valve designated o Non-line sized valves indicated o Control valves sized o Miscellaneous designated valves added o Valve tags added (not always done) o Valve design details added (as necessary)

PIPING SPECIALTY ITEMS

o Identification of items o Numbering of items (usually by piping) o Specialty item design details (as necessary)

UTILITIES

o Main connections and continuations o Remaining connections and continuations o Overall distribution and control o Utilities design details

INSTRUMENTATION

o Elements, loops, and functions o Primary elements o Local panel or control house location o Control panel or CRT location o Computer inputs and outputs o Process steam traps (may be specialty items) o Hard wired interlocks

Glossary of Terms Page 40

Page 41: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

o Motor controls (need schematics) o Type of primary elements o Instrument numbers o Uniform logic control details o Indicator lights o Instrumentation design details (as necessary)

SAFETY SYSTEMS

o Process Safety Management Hazard Analysis review o Key process relief valves o Remaining relief valves o Failure mode of control valves o Car sealed valves (as necessary) o Relief valve sizes (instrumentation / process check) o Relief system line sizes o System design details (as necessary)

SPECIAL NOTATIONS

o Identification of sloped lines o Barometric legs (seals) o Critical elevations and dimensions o Vendor or designer supplied notes o Critical locations (valves, etc.) o Notes on venting or draining o Vessel trim notes o Startup and shutdown notes o Design detail notes (as necessary)

G4. Process Safety Management (PSM)

This refers to OSHA Regulation 1910.119 compliance requirements. Has the owner clearly communicated the requirements, methodology, and responsibility for the various activities?

G5. Utility Flow Diagrams

Utility flow diagrams are similar to P&ID's in that they show all utility lines from generation or supply (i.e. pipeline). They are generally laid out in a manner to represent the geographical layout of the plant. Utility flow diagrams are evaluated using the same criteria as P&ID's.

G6. Specifications

General specifications for the design, performance, manufacturing, material, and code requirements should include items such as:

o Classes of equipment (e.g. pumps, exchangers, vessels, etc.)

Glossary of Terms Page 41

Page 42: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

o Process pipe heating o Process o Freeze o Jacketed o Process pipe cooling o Jacketed o Traced o Piping o Protective coating o Insulation o Valves o Bolts / gaskets

G7. Piping System Requirements

Pipe stress criteria should be provided to establish guidelines for analysis of piping systems and equipment such as:

o Allowable forces and moments on equipment o Graphical representation of piping line sizes that require analysis based on:

o Temperature o Pressure o Cyclic conditions o Flex o Stress o Pulsation o Seismic

G8. Plot Plan

The plot plan will show the location of new work in relation to adjoining units. It should include items such as:

o Plant grid system with coordinates o Unit limits o Gates & fences o Off-site facilities o Tank farms o Roads & access ways o Roads o Rail facilities o Green space o Buildings o Major pipe racks o Laydown areas o Construction / fabrication areas

Glossary of Terms Page 42

Page 43: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

G9. Mechanical Equipment List

The mechanical equipment list should identify all mechanical equipment by tag number, in summary format, to support the project. The list should define items such as:

o Existing sources o Modified o Dismantled o Relocated o Rerated o New sources o Purchased new o Purchased used o Relative sizes o Weights o Location o Capacities o Materials o Power requirements o Flow diagrams o Design temperature and pressure o Insulation & painting requirements o Equipment related ladders and platforms

G10.Line List

The line list designates all pipe lines in the project (including utilities). It should include items such as:

o Unique number for each line o Size o Termination o Origin o Reference drawing o Normal and upset operating o Temperature o Pressure o Design temperature & pressure o Test requirements o Pipe specifications o Insulation requirements o Paint requirements

G11.Tie-in List

A list of all piping tie-ins to existing lines. It should include items such as:

o Location o Insulation removal requirements

Glossary of Terms Page 43

Page 44: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

o Decontamination requirements o Reference drawings o Pipe specifications o Timing / schedule o Type of tie-in / size o Hot tap o Cold cut o Flange o Screwed o Weld o Cut & weld

G12.Piping Specialty Items List

This list is used to specify in-line piping items not covered by piping material specifications. It should identify all special items by tag number, in summary format. It should include items such as:

o Tag numbers o Full purchase description o Quantities o Materials of construction o Piping plans referenced o P&ID's referenced o Piping details o Line / equipment numbers

G13.Instrument Index

This is a complete listing of all instruments by tag number. Evaluation criteria should include:

o Tag number o Instrument type o Service o P&ID number o Manufacturer o Model number o Line number o Relieving devices (e.g. relief valves, rupture disks, etc.)

H. EQUIPMENT SCOPE

H1. Equipment Status

Has the equipment been defined, inquired, bid tabbed, or purchased? This includes all engineered equipment such as:

o Process o Electrical

Glossary of Terms Page 44

Page 45: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

o Mechanical o HVAC o Instruments o Specialty items o Distributed control systems

Evaluation criteria should include:

o Equipment data sheets - how complete? o Number of items inquired o Number of items with approved bid tabs o Number of items purchased

H2. Equipment Location Drawings

Equipment location / arrangement drawings identify the specific location of each item of equipment in a project. These drawings should identify items such as:

o Elevation views of equipment and platforms o Top of steel for platforms and pipe racks o Paving and foundation elevations o Coordinates of all equipment H3. Equipment Utility Requirements

This should consist of a tabulated list of utility requirements for all equipment items.

I. CIVIL, STRUCTURAL, & ARCHITECTURAL

I1. Civil / Structural Requirements

Civil / structural requirements should include the following:

o Structural drawings o Pipe racks / supports o Elevation views o Top of steel for platforms o High point elevations for grade, paving, and foundations o Location of equipment and offices o Construction materials (e.g. concrete, steel, client standards, etc.) o Physical requirements o Seismic requirements o Minimum clearances o Fireproofing requirements o Corrosion control requirements / required protective coatings o Enclosure requirements (e.g. open, closed, covered, etc.) o Secondary containment o Dikes

Glossary of Terms Page 45

Page 46: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

o Storm sewers o Client specifications (e.g. basis for design loads, etc.) o Future expansion considerations

I2. Architectural Requirements

The following checklist should be used in defining building requirements.

o Building use (e.g. activities, functions, etc.) o Space use program indicating space types, areas required, and the functional relationships between spaces and number of occupants o Service, storage, and parking requirements o Special equipment requirements o Requirements for building location / orientation o Nature / character of building design (e.g. aesthetics, etc.) o Construction materials o Interior finishes o Fire resistant requirements o Explosion resistant requirements o "Safe haven" requirements o Acoustical considerations o Safety, security, and maintenance requirements o Fire detection and / or suppression requirements o Utility requirements (i.e. sources and tie-in locations) o HVAC requirements o Electrical requirements o Power sources with available voltage & amperage o Special lighting considerations o Voice and data communications requirements o UPS and / or emergency power requirements o Outdoor design conditions (e.g. minimum and maximum yearly temperatures) o Indoor design conditions (e.g. temperature, humidity, pressure, air quality, etc.) o Special outdoor conditions o Special ventilation or exhaust requirements o Equipment / space special requirements with respect to environmental conditions (e.g. air quality, special temperatures, etc.) o Americans With Disabilities Act requirements

J. INFRASTRUCTURE

J1. Water Treatment Requirements

Items for consideration should include:

o Wastewater treatment o Process waste o Sanitary waste o Waste disposal

Glossary of Terms Page 46

Page 47: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

o Storm water containment & treatment

J2. Loading / Unloading / Storage Facilities Requirements

A list of requirements identifying raw materials to be unloaded and stored, products to be loaded along with their specifications, and Material Safety Data Sheets. This list should include items such as:

o Instantaneous and overall loading / unloading rates o Details on supply and / or receipt of containers and vessels o Storage facilities to be provided and / or utilized o Specification of any required special isolation provisions o Double wall diking and drainage o Emergency detection (e.g. hydrocarbon detectors/alarms) o Leak detection devices or alarms

J3. Transportation Requirements (Y/N)

Specifications identifying implementation of "in-plant" transportation (e.g. roadways, concrete, asphalt, rock, etc.) as well as methods for receiving / shipping of materials (e.g. rail, truck, marine, etc.).

K. INSTRUMENT & ELECTRICAL

K1. Control Philosophy

The control philosophy describes the general nature of the process and identifies overall control systems hardware, software, simulation, and testing requirements. It should outline items such as:

o Continuous o Batch o Redundancy requirements o Classification of interlocks (e.g. process, safety, etc.) o Software functional descriptions o Manual or automatic controls o Alarm conditions o On / off controls o Block diagrams o Emergency shut down o Controls startup

K2. Logic Diagrams (Y/N)

The logic diagrams provide a method of depicting interlock and sequencing systems for the startup, operation, alarm, and shutdown of equipment and processes.

K3. Electrical Area Classifications

Glossary of Terms Page 47

Page 48: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

The electrical area classification plot plan is provided to show the environment in which electrical and instrument equipment is to be installed. This area classification will follow the guidelines as set forth in the latest edition of the National Electric Code. Installation locations should include the following:

o General purpose o Hazardous o Class I: Gasses and vapors o Class II: Combustible dusts o Class III: Easily ignitable fibers o Corrosive locations

K4. Substation Requirements / Power Sources Identified

Substation requirements should include the following:

o Number of substations required o Electrical equipment rating required for each substation o Specifications for all major electrical substation equipment o Infrastructure required for each substation considering building type and environment, fencing, access, and substation yard materials

Clearly define power sources for the project in relation to:

o Location, voltage level, available power o Electrical equipment available o Electrical ratings and routes of power feeds from their sources to the project substations o Specifications for special power sources should be described and provided (e.g. emergency generators or in-plant generation) o Temporary construction power sources

K5. Electric Single Line Diagrams

A single line diagram indicates the components, devices, or parts of an electrical power distribution system. Single line diagrams are intended to portray the major system layout from the public utility's incoming transmission line to the motor starter bus. Depending on the size of the electrical system, the single line diagrams should include several levels of distribution such as:

o Incoming utility with owner substation / distribution to high and medium voltage motors and substations o Unit substations and 480V distribution o Motor control centers with distribution to motors, lighting panels, etc.

K6. Instrument & Electrical Specifications

These specifications should include items such as:

o Distributed Control System (DCS) o Instrument data sheets

Glossary of Terms Page 48

Page 49: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

o Motor control and transformers o Power and control components o Power and control wiring (splicing requirements) o Cathodic protection o Lightning protection o Grounding o Electrical trace o Installation standards o Lighting standards o Civil requirements for electrical installation o Protection / warning for underground cabling o Special slabs or foundations for electrical equipment o Concrete-embedded conduit

SECTION III - EXECUTION APPROACH

L. PROCUREMENT STRATEGY

L1. Identify Long Lead / Critical Equipment and Materials

Identify engineered equipment and material items with lead times that will impact the detailed engineering for receipt of vendor information or impact the construction schedule with long delivery times.

L2. Procurement Procedures and Plans

Specific guidelines, special requirements, or methodologies for accomplishing the purchasing, expediting, and delivery of equipment and materials required for the project. Evaluation criteria should include:

o Listing of approved vendors o Client or contractor paper? o Reimbursement terms and conditions o Guidelines for supplier alliances, single source, or competitive bids o Guidelines for engineered / field contracts o Who assumes responsibility for owner-purchased items? o Financial o Shop inspection o Expediting o Tax strategy o Engineered o Field materials o Labor o Definition of source inspection requirements and responsibilities o Definition of traffic / insurance responsibilities o Definition of procurement status reporting requirements o Additional / special owner accounting requirements o Definition of spare parts requirements o Local regulations (e.g. tax restrictions, tax advantages, etc.)

Glossary of Terms Page 49

Page 50: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

L3. Procurement Responsibility Matrix (Y/N)

Has a procurement responsibility matrix been developed?

M. DELIVERABLES

M1. CADD / Model Requirements

Computer Aided Drafting and Design (CADD) requirements should be defined. Evaluation criteria should include:

o Software system required by client (e.g. Autocad, Intergraph, etc.) o Will the project be required to be designed using 2D or 3D CADD? o If 3D CADD is to be used, will a walk through simulation be required? o Application software (e.g. ADEV Pro-series, Cadpipe, PDS, etc.) o Owner / contractor standard symbols and details o How will data be received and returned to / from the owner? o Disk o Electronic transfer o Tape o Reproducibles

Physical model requirements depend upon the type required, such as:

o Study model o Design check o Block model o Operator training

M2. Deliverables Defined

The following items should be included in a list of deliverables:

o Drawings o Project correspondence o Project Process Safety Management (PSM) documents o Permits o Project data books (quantity, format, contents, and completion date) o Equipment folders (quantity, format, contents, and completion date) o Design calculations (quantity, format, contents, and completion date) o Spare parts special forms o Loop folder (quantity, format, contents, and completion date) o Procuring documents o ISO's / field erection details o As-built documents o Quality assurance documents

M3. Distribution Matrix (Y/N)

Glossary of Terms Page 50

Page 51: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

A distribution matrix identifies most correspondence and all deliverables. It denotes who is required to receive copies of all documents at the various stages of the project.

N. PROJECT CONTROL

N1. Project Control Requirements

Has a method for measuring and reporting progress been established? Evaluation criteria should include:

o Change management procedures o Cost control procedures o Schedule / percent complete control procedures o Cash flow projections o Report requirements

N2. Project Accounting Requirements

Have all project specific accounting requirements been identified such as:

o Financial (client / regulatory) o Phasing or area sub-accounting o Capital vs. non-capital o Report requirements o Payment schedules

N3. Risk Analysis (Y/N)

Has a risk analysis for cost and schedule been performed?

P. PROJECT EXECUTION PLAN

P1. Owner Approval Requirements

Has owner clearly defined all documents that require owner approval such as:

o Milestones for drawing approval o Comment o Approval o Bid issues o Construction o Durations of approval cycle compatible with schedule o Individual(s) responsible for reconciling comments before return o Types of drawings o Purchase documents o Data sheets o Inquiries o Bid tabs

Glossary of Terms Page 51

Page 52: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

o PO's o Vendor information

P2. Engineering / Construction Plan & Approach

This is a documented plan identifying the methodology to be used in engineering and constructing the project. It should include items such as:

o Responsibility matrix o Contracting strategies (e.g. lump sum, cost-plus, etc.) o Subcontracting strategy o Work week plan / schedule o Organizational structure o Work Breakdown Structure (WBS) o Construction sequencing of events o Safety requirements / program o Identification of critical lifts and their potential impact on operating units o QA / QC plan

P3. Shut Down / Turn-Around Requirements (Y/N)

Have any required shut downs or turn-arounds been identified, including definitions of the scope of work to be accomplished during such down times, scheduled instructions for the down time, and timing of outages?

P4. Pre-Commissioning Turnover Sequence Requirements

This defines the owner's required sequence for turnover of the project for pre-commissioning and startup activation. It should include items such as:

o Sequence of turnover o Contractor's required level of involvement in pre-commissioning o Contractor's required level of involvement in training o Contractor's required level of involvement in testing o Clear definition of mechanical / electrical acceptance Requirements

P5. Startup Requirements

Have the startup requirements been defined and responsibility established?

P6. Training Requirements

Have the training requirements been defined and responsibility established?

Glossary of Terms Page 52

Page 53: PDRI (Project Definition Rating Index) Buildings.doc

CII Benchmarking & Metrics(Project Questionnaire Version 9.0)

Glossary of Terms

Addendum: Productivity Metrics GlossaryGlossary of Terms

Construction Productivity Metrics

Construction Productivity Concrete Section:

Installed Neat Quantity of concrete: concrete that is required for the specified slab, foundation, or structure provided in the project’s plans and specifications and does not include any quantity of concrete that is used due to rework.

Concrete Structures: This includes concrete structures, columns, beams, cooling tower basins, trenches, formed elevated slabs/structures, and retaining walls.

Construction Productivity Electrical Section:

UPS: Uninterrupted Power Supply System

MCC: Motor-Control Centers

DCS: Distributed Control System

PLC: Programmable Logic Control

Construction Productivity Piping Section:

NDE: Non-destructive evaluation

Hot piping: piping which has a design temperature greater than 250 degrees Fahrenheit.

Cold piping: piping which has a design temperature less than minus 20 degrees Fahrenheit.

Construction Productivity Insulation Section:

ELF: Equivalent Linear Feet of insulation applied to piping. Multiple layers count only one time in linear footage.

Engineering Productivity Metrics

IFC Drawing: Issued for Construction drawings

Engineering Productivity Instrumentation Section:

I/O (count): The I/O that comes over digital communication interfaces from outside of the control system. For such interfaces, count the addressable points. For Fieldbus interfaces, count only the devices.

Glossary of Terms Page 53