The Project TeamThe Project Team
3
ObjectivesObjectives
� Project Status
� Schedule
� Construction Work Hours
� Sequence of Construction
Project Status
� Final Plans have been submitted for VDOT approval
� Right of Way Plans are approved to begin land acquisition
� Environmental Permits have been obtained
� Utility Relocations have been initiated
4
Project Schedule
July 2014 Design/Build Contract Awarded
March 2015 Begin Right of Way Acquisition
April 2015 Complete Design
Late April 2015 Begin Construction
Spring 2016 Project Complete
5
Construction Work Hours
� Two lanes of traffic will be maintained in all directions during peak hours
� Occasional lane closures will occur during non-peak hours under flagging operation
� Weekend night hours will be used if necessary for stormdrain construction, MOT lane shifts, paving, and signing and marking
6
Construction Work Hours
7
WEEKDAYSDAY-TIME HOURS
NIGHT-TIME HOURS
Monday-Thursday 9:30AM – 3:00PM 9:30PM – 5:00AM
Friday 9:30AM – 2:00PM 10:00PM – 8:00AM
Saturday Not Permitted 10:00PM – 8:00AM
Sunday Not Permitted 10:00PM – 5:00AM
Braddock Road and Pleasant Valley RoadExisting Condition
8
Braddock Road and Pleasant Valley RoadPhase 1
9
Braddock Road and Pleasant Valley RoadPhase 2
10
Braddock Road and Pleasant Valley RoadPhase 3
11
Braddock Road and Pleasant Valley RoadPhase 4
12
Braddock Road and Pleasant Valley RoadPhase 5
13
Braddock Road and Pleasant Valley RoadCompleted Project
14
15
http://www.virginiadot.org/projects/northernvirginia/braddock
_and_pleasant_valley.asp(this webpage will be updated throughout the project development)
Sam Patel
Fort Myer Construction Corp. Design/Build Project Manager
Chan Basnayake, P.E.
VDOT Design/Build Project Manager
For More Information About the Braddock Rd/Pleasant Valley Rd
Roundabout Project:
For More Information About the Braddock Rd/Pleasant Valley Rd
Roundabout Project:
16
Questions?
Top Related