PrecisionFarmingofHazelnutOrchards(PANTHEON)___________________________________________________________________________________________________________
PANTHEONDocumentD1.1_ProjectManagementGuidelines_Rel.01_20171129
SCADA for AgriculturePANTHEON
1
ProjectNumber:774571StartDateofProject:2017/11/01Duration:48months
TypeofdocumentD1.1.–V1.0
ProjectManagementGuidelines
Disseminationlevel PUBLICSubmissionDate 2017-11-30WorkPackage WP1Task T1.1Type ReportVersion 1.0Author AlessandroAlbinoFrezzaApprovedby AndreaGasparri+PMC
DISCLAIMER:Thesoleresponsibility forthecontentofthisdeliverable lieswiththeauthors. ItdoesnotnecessarilyreflecttheopinionoftheEuropeanUnion.NeithertheREAnortheEuropeanCommissionareresponsibleforanyusethatmaybemadeoftheinformationcontainedtherein.
Ref. Ares(2017)5841551 - 29/11/2017
PrecisionFarmingofHazelnutOrchards(PANTHEON)___________________________________________________________________________________________________________
PANTHEONDocumentD1.1_ProjectManagementGuidelines_Rel.01_20171129
SCADA for AgriculturePANTHEON
2
ExecutiveSummary
ThisdocumentaimsatprovidingaguidancetoPANTHEONpartnersonthewaytheyareexpectedtofulfiltheprojectmanagementrequirementssetoutbytheH2020GrantAgreementandestablishedbytheProjectManagementcommonbestpractices.
ThisreportisenvisionedasaworkingtoolfortheBeneficiariestobeusedduringthewholedurationof PANTHEON. Project’smemberswill refer to these guidelines to establish a day-to-day projectmanagementroutine.Thisdocumentisabriefcompendiumdescribingthegoverningstructureandtheservicestobeusedforthemanagementandadministrativecoordination.Italsodescribesthecommunicationstreamwithin theConsortiumand towards theECandoutlines theConsortium'sformal communication on PANTHEON’s activities and outcomes. It aims at complementing theprovisionsoftheabove-mentionedGrantAgreement.ItalsocomplieswiththeprovisionssetoutintheConsortiumAgreementadoptedbytheConsortium’sMembers.
H2020rulesandprovisionswillbestrictlyobservedduringtheimplementationoftheproject.
PANTHEON’sbasicadministrationwillfocusonthefollowingtasks:
• ManagementoftheConsortium;• CommunicationwithintheConsortiumaswellaswiththeEC;• Deliveryofguidelinesonqualityassuranceandreportwriting,includingtheprovisionof
varioustemplates;• Organizationofregularconferencecallsforallpartnersandprovisionofminutes,etc.;• Monitoringofresourceexpenditureandsubmissionofreportsanddeliverables
PANTHEON’SLegalandfinancialtaskscover:
• Managementofcontractualissuesandtimelydistributionofcorrespondingdocumentsandrelevantinformationtopartners(e.g.regardingGAandCA).
• CommunicationbetweenConsortiumpartnersandtheEConprojectandfunding-relatedmatters.
• Managementofbudgetanddistributionofpaymentstopartners,etc.
PrecisionFarmingofHazelnutOrchards(PANTHEON)___________________________________________________________________________________________________________
PANTHEONDocumentD1.1_ProjectManagementGuidelines_Rel.01_20171129
SCADA for AgriculturePANTHEON
3
TableofContent
1 GovernanceandCoordination..................................................................................................................4
2 PeriodicreportingtotheEC......................................................................................................................6
3 Projectdocumentsanddeliverables.........................................................................................................7
4 Financialmanagement............................................................................................................................10
4.1 Directpersonnelcosts.....................................................................................................................13
4.2 Indirectcosts...................................................................................................................................14
4.3 Ineligiblecosts.................................................................................................................................14
5 Monitoringofresourcesexpenditure.....................................................................................................15
6 Communication.......................................................................................................................................15
6.1 CommunicationwiththeEC............................................................................................................15
6.2 Internalcommunication..................................................................................................................16
6.3 Externalcommunication.................................................................................................................16
6.4 Conferencecalls..............................................................................................................................16
6.5 ProjectMeetings.............................................................................................................................17
6.6 Portal,ForumandRepository.........................................................................................................17
7 WP1-duedeliverables............................................................................................................................17
8 Keydocuments........................................................................................................................................17
PrecisionFarmingofHazelnutOrchards(PANTHEON)___________________________________________________________________________________________________________
PANTHEONDocumentD1.1_ProjectManagementGuidelines_Rel.01_20171129
SCADA for AgriculturePANTHEON
4
AbbreviationsandAcronyms
AMGA AnnotatedModelGrantAgreementBEN BeneficiaryCA ConsortiumAgreementCO CoordinatorDoA DescriptionofActionEC EuropeanCommissionFO FinancialOfficerFS FinancialStatementGA GrantAgreementKoM KickoffMeetingMS ManagementStaffPM PersonMonthPMC ProjectManagementCommitteePN PartnerPO ProjectOfficerPP ParticipantPortalPR PeriodicReportSyGMa SystemforGrantManagementTS TechnicalStaffUoR UseofResourcesWP WorkPackageWPL WorkPackageLeader
1 GovernanceandCoordinationPANTHEON is based on the close collaboration of 4 academic and 2 industrial partners from 4EuropeanCountries.Theirnameandacronymstobeusedwithintheinternalcommunicationstream,aswellastheirroleandfinancialparticipationtotheprojectareitemizedinthefollowingtable.
Table1.Beneficiaries
Beneficiary Role COUNTRY TotalCost MaxGrantAmountUNIROMA3 CO IT 960.893,75 960.893,75FERRERO PN LUX 172.500,00 172.500,00ULB PN BE 515.750,00 515.750,00UNITUS PN IT 452.525,00 452.525,00TRIER PN DE 684.108,75 684.108,75SIGMA PN IT 358.675,00 358.675,00
Thegoverninganddecision-makingprocessoftheprojectwillinvolve:
i) the Project Coordinator/Principal Investigator (CO/PI) as responsible of the project’simplementation.TheCOchairstheProjectManagementCommittee(PMC)(seebelow).
PrecisionFarmingofHazelnutOrchards(PANTHEON)___________________________________________________________________________________________________________
PANTHEONDocumentD1.1_ProjectManagementGuidelines_Rel.01_20171129
SCADA for AgriculturePANTHEON
5
ii) thePM,supportingthePIandactingasanintermediatebetweentheConsortiumandtheEC;
iii) thePMCcomposedbyonerepresentativeforeachmemberoftheConsortium,includingtheWPLs.(Seetable2below).ThePMCisthedecision-makingbody.EachmemberofthePMCisexpectedtobedulyauthorizedtodeliberate,negotiateanddecideonallmattersrelatingPANTHEON.
iv) theWPLresponsibleoftheWPsandrelevanttasks,supportingtheCOineachformofcommunication from/to the research units in charge of the actual realization of theresearch. Their responsibilities includeamongstother things coordinating,monitoring,andassessingtheprogressoftheworkpackagemostlyintermsofscopeandschedule.
TheCOisresponsiblefortheoverallmanagement,communication,andcoordinationofPANTHEON.Asmentionedabove,healsochairsthePMCandservesastheonlyofficialchannelthatinteractswiththeEC,focusingonthesubmissionofdeliverables,theaspectsrelatingtothemanagementofthebudgetandonanyotherrelevantcontractualissuethatmightraiseduringtheimplementationoftheproject.
Moreindetail,theCOisresponsiblefor:
• establishingtheoverallcoordinationandthecommunicationbetweenprojectpartnersandstakeholders;
• ensuringareliable,efficientandeffectivecommunicationwiththeEC(PO+FO);• ensuringtheachievementoftheprojectgoalsasoutlinedinAnnex1totheGAontime;• ensuringthetimelyandaccuratehandlingofalltheadministrativeandfinancialtasks;• gathering,maintainingandsubmittingdeliverables,projectreportsandfinancialstatements;• supportingthedecision-makingprocessandtheadoptionofequitablesolutionsforresolving
conflicts;• ensuringthefullcompliancewiththetermsoftheECGAandtheCA.
Prof.AndreaGASPARRI ([email protected]) is therepresentativeof theCO(UNIROMATRE)andthePrincipalInvestigatorinchargeofcoordinatingandsupervisingallthescientificaspectsoftheproject.
Table2.MembersoftheProjectManagementCommittee
Beneficiary Name emailUNIROMA3 A.Gasparri [email protected] L.Giustarini [email protected] E.Garone [email protected] V.Cristofori [email protected] T.Udelhoven [email protected] E.Graziani [email protected]
PrecisionFarmingofHazelnutOrchards(PANTHEON)___________________________________________________________________________________________________________
PANTHEONDocumentD1.1_ProjectManagementGuidelines_Rel.01_20171129
SCADA for AgriculturePANTHEON
6
WP# WPTitle WPL1 Projectmanagement A.Gasparri2 Functionalspecifications L.Giustarini3 SCADAsub-systemsandrealization A.Gasparri4 Hazelnutremotesensing T.Udelhoven5 Agronomicdecisionmaking V.Cristofori6 Integration,testingandvalidation E.Graziani7 Disseminationandexploitation E.Garone
TheresponsibilitiesoftheWPLswillspecificallyfocusonthecoordinationofthefollowings:
• implementationoftheWP-relatedtasksinaccordancewiththeobjectivesset-outintheDoA;• coordinationandsupervisionoftheinvolvedpartners;• coordinationofthetimelydeliveryofdeliverables;• identificationandassessmentofunforeseenrisksandrelevantcommunicationtotheCO.
ThecollaborationwithintheConsortiumandwiththeECisbasedontheGA.RelevantfortheproperimplementationoftheprojectworkisAnnex1includingtheestimatedbudgetfortheAction(Annex2)
TheConsortium'sworkisbasedontheCAwhichhasbeendulypreparedontheDESCAModelbytheCO.TheCAwassignedandadoptedbyallthebeneficiarieson08.09.2017.
PartnershavecopyofboththeGAandtheCA.TheGAisalsoaccessiblethroughthePP.AdditionalcopieswillbemadeavailableinthePANTHEONrepositorycurrentlyunderconstructionandduefordeliveryatM4(SeeCommunicationbelow).
2 PeriodicreportingtotheECThereportingprocessallowstheECtofollowtheprojectcloselyandtoensurethatitisimplementedasstatedintheGAandinconformitywiththecurrentfinancialprovisions.Thereportingprovidesanoverall sketchof theprogressof theproject versus theoriginal and revised (if any)plans. It alsoprovidesareviewoftheincurredcosts.
PANTHEONisdividedin3RPcoveringM1-12(P1),M13-30(P2)andM31-48(P3).TheCOmustsubmitaPeriodicReportwithin60daysfollowingtheendoneachRP.
ThePeriodicReportsmustincludeaperiodictechnicalreportandaperiodicfinancialreport(seeGAart.20–20.3).
AllreportsarecoordinatedandmonitoredbytheCOwhoalsowillprovideguidanceontherequiredcontentsandstyle.Theperiodicreportswilltypicallyinclude:
• theprogressdetailsperWP/task;• alistofpublications;
PrecisionFarmingofHazelnutOrchards(PANTHEON)___________________________________________________________________________________________________________
PANTHEONDocumentD1.1_ProjectManagementGuidelines_Rel.01_20171129
SCADA for AgriculturePANTHEON
7
• alistofdisseminationandnetworkingactivities;• adeliverableandmilestonetableand,• atablepresentingplannedversusactualresourceusage(PMs)perpartners.
GeneralscopeofthesereportsistoprovideanoverviewoftheprogressmadetowardstheobjectivesofeachWP/taskandoftheworkperformedandresultsachievedwithineachtimeframe.
Ifapplicable,thereportswillalsocontainfullexplanationsondeviationsfromtheworkplanandwilloutlinecorrectiveactions tobe taken.Furthermore, theywill summarize theactions for thenextphasesandillustratemajordisseminationandcooperationactivitiescarriedout.
Report writing will be mainly managed through the PANTHEON repository. While the CO isresponsibleforrequestingandreviewingthereports,forverifyingtheiraccuracyandcompletenessandsubmittingthemtotheEC,eachBeneficiarymustprovideingoodtimethedataneededforthesereports. Contributions are expected from all partnersmonitored through theWPLs. Revisions, ifrequiredforthereport'sfinalacceptance,aremanagedbytheCO.
3 ProjectdocumentsanddeliverablesAgeneraltemplateforthedeliverableshasbeendevelopedbytheCOandwillbemadeavailabletoallpartnersintherepository.DuringPANTHEON’simplementation,awiderangeofdocumentswillbewidelyused,eitherforinternaluse,forreportingtotheECorfordisseminationandexploitationpurposes.Thetablebelowshows,pereachitem,thepreparationandapprovalchain
27deliverablesareplannedforsubmissioninPANTHEON.Theyarelistedinthetablebelow.
PrecisionFarmingofHazelnutOrchards(PANTHEON)___________________________________________________________________________________________________________
PANTHEONDocumentD1.1_ProjectManagementGuidelines_Rel.01_20171129
SCADA for AgriculturePANTHEON
8
Dlv.# Title WP# Lead Type Diss.level DuedateD1.1 Project
managementguidelines
WP1 UNIROMA3 Report Public M1
D2.1 Requirements,specificationsandbenchmark
WP2 FERRERO Report Public M6
D2.2 Guidelines forcomponents anddocumentcompatibility
WP2 FERRERO Websites,patentsfiling
Public M8
D2.3 Real-world (1:1scale) hazelnutorchard for finaldemo
WP2 FERRERO Report Public M10
D3.1 Roboticprototypes
WP3 ULB Other Confidential M14
D3.2 Datamanagement
WP3 UNIROMA3 Other Public M30
D3.3 Communicationinfrastructure
WP3 SIGMA Other Public M16
D3.4 Userinterface WP3 SIGMA Other Public M24D3.5 Farm activities
plannerWP3 UNIROMA3 Other Public M26
D4.1 MultispectralLiDAR pointclouds
WP4 TRIER Other Public M14
D4.2 3Dtreemodels WP4 TRIER Other Public M28D4.3 Aerial
orthophoto-mosaic
WP4 TRIER Other Public M16
D4.4 Drought stressdetection
WP4 TRIER Other Public M22
D4.5 Pest and diseasedetection
WP4 TRIER Other Public M29
D4.6 Fruitdetection WP4 TRIER Other Public M46D5.1 Water
managementcontrol
WP5 UNITUS Other Public M10
D5.2 Suckers’managementcontrol
WP5 UNITUS Other Public M18
D5.3 Pruningmanagementprotocol
WP5 UNITUS Report Public M36
D5.4 Pestanddiseasesmonitoring andcontrol
WP5 UNITUS Report Public M39
PrecisionFarmingofHazelnutOrchards(PANTHEON)___________________________________________________________________________________________________________
PANTHEONDocumentD1.1_ProjectManagementGuidelines_Rel.01_20171129
SCADA for AgriculturePANTHEON
9
D5.5 Fruitdevelopmentand productionmonitoring
WP5 UNITUS Report Public M46
D6.1 Robotic vehiclesfieldvalidation
WP6 UNIROMA3 Demonstrator Public M30
D6.2 SCADA systemintegration andfieldvalidation
WP6 SIGMA Demonstrator Public M39
D6.3 Finaldemo WP6 SIGMA Demonstrator Public M48D7.1 Publicwebsite WP7 ULB Website Public M4D7.2 Data
managementplan–Opendatapilot
WP7 ULB ORDP Public M6
D7.3 PUDF WP7 ULB Websites,patent filings,etc.
Public M46
D8.1 M–PODP–OEI–H- DU – GEN –EPQrequirements#1
WP8 UNIROMA3 Ethics Confidential M3
As the high-quality standard of the deliverables is a priority, the following steps, to be mainlyimplementedbyWPLsandtheCO,willhelptodefineasharedstructuredreviewingandapprovalprocess:
• Deliverables’mainauthorsandreviewersofthedeliverablestobesubmittedinthefirst12months of theproject,will be identifiedby the PMC in advanceby the secondmonthofimplementation of PANTHEON, following the technical discussion held during the KoMmeeting. Adjustments, ifneeded,willbeadoptedduringproject implementation.Authorsandreviewersfortheadditionaldeliverables[Year2+Year3+Year4]willbeidentifiedonayearlybasisbythePMC.Therewillbeatleastonereviewerperdeliverable;
• D1.1willbereviewedandapprovedbythePMCbeforeitssubmission(M1);• Theinternalworkscheduleforthetimelyproductionofthedeliverableswasapprovedduring
theKoM,specifyingtheexactdeadlinesforinternalreviewsandrevisionswithrespecttothedifferentapplicabledeadlinesforsubmission.Inprinciple,some6weekswillbedevotedtothe preparation of the deliverables; in addition, 1week/10 dayswill be dedicated to theinternalreview.Timingissubjecttovariationsaccordingtothecomplexityofthedeliverablesthemselves;
• ThefinalapprovalofthedeliverablesrestsintheresponsibilityoftheWPLandtheCO.
Thefollowingschemesummarizestheworkschedulementionedabove.
PrecisionFarmingofHazelnutOrchards(PANTHEON)___________________________________________________________________________________________________________
PANTHEONDocumentD1.1_ProjectManagementGuidelines_Rel.01_20171129
SCADA for AgriculturePANTHEON
10
Hereafteristheschedulingofthedeliverablestobesubmittedduringthe48monthslengthoftheproject.
4 FinancialmanagementTheCOoverseesthefinancialcontributionoftheECtoPANTHEON.TheCOtransferspaymentstothepartner'sbankaccountswithoutunjustifieddelayandinconformitywiththeruleslaidoutintheGAandCA.TheCOalsomonitorsthesubmissionoftheFS(Annex4oftheGA)andhandleswiththePMCanyrequestofre-allocationoffundingwithintheConsortium.
Thefollowingarethepaymentsmade/tobemadebytheECtotheCO:
• Onepre-financingpaymentmadewithin30dayseitherfromtheentryintoforceoftheGAorfrom10daysbeforethestartingdateoftheproject.[Paymentprocessed].
• Oneinterimpayment,madewithin90daysfromreceivingtheperiodicreportsattheendofP1 and P2. The amount of the interim payment is calculated by the EC following theapplication of the reimbursement rates (100%) and considering the limit of 90% of themaximumgrantamount.Thetotalamountofpre-financingandinterimpaymentsmustnotexceed90%ofthemaximumgrantamount.
• Onepaymentofthebalancereimbursingtheremainingpartoftheeligiblecostsincurredbythebeneficiaries.Beingthetotalamountsofpreviouspaymentslowerthanthefinalgrantamount,theECwillpaythebalancewithin90daysfromreceivingthefinalreport(P3)
Draft sharedthroughPANtHEOnrepositoy
Drafting Writing Completing Internal RW Revision/FinalEditing
PDFtoCOforuploading toSyGMa
6weeksbeforedeadline 7- 10daysweekbeforedeadline
DEADLINE
Nov-17
Dec-17
Jan-18
Feb-18
Mar-18
Apr-1
8
May-18
Jun-18
Jul-1
8
Aug-18
Sep-18
Oct-18
Nov-18
Dec-18
Jan-19
Feb-19
Mar-19
Apr-1
9
May-19
Jun-19
Jul-1
9
Aug-19
Sep-19
Oct-19
UNIROMA3 FERRERO ULB UNITUS TRIER SIGMA
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 D1.1 D2.1 D3.1 D5.1 D4.1 D3.3D1.1 D8.1 D7.1 D2.1 D2.2 D2.3 D3.1 D3.3 D5.2 D4.4 D3.4 D3.2 D2.2 D7.1 D5.2 D4.2 D3.4
D7.2 D5.1 D4.1 D4.3 D3.5 D2.3 D7.2 D5.3 D4.3 D6.2D6.1 D7.3 D5.4 D4.4 D6.3D8.1 D5.5 D4.5
D4.6RP1
Nov-19
Dec-19
Jan-20
Feb-20
Mar-20
Apr-2
0
May-20
Jun-20
Jul-2
0
Aug-20
Sep-20
Oct-20
Nov-20
Dec-20
Jan-21
Feb-21
Mar-21
Apr-2
1
May-21
Jun-21
Jul-2
1
Aug-21
Sep-21
Oct-21
Nov-21
Dec-21
M25 M26 M27 M28 M29 M30 M31 M32 M33 M34 M35 M36 M37 M38 M39 M40 M41 M42 M43 M44 M45 M46 M47 M48 M49 M50D3.5 D4.2 D3.2 D5.3 D5.4 D4.6 D6.3
D4.5 D6.1 D6.2 D5.5D7.3
RP2 RP3
Year1 Year2
Year3 Year4
PrecisionFarmingofHazelnutOrchards(PANTHEON)___________________________________________________________________________________________________________
PANTHEONDocumentD1.1_ProjectManagementGuidelines_Rel.01_20171129
SCADA for AgriculturePANTHEON
11
ThemaximumgrantamountisEUR3.144.452,50.Theamountofthepre-financingsetoutintheGAisEUR1.677.041,33.AnamountofEUR157.222,63(5%ofthemaximumgrantamount)isretainedbytheECfromthepre-financingpaymentandtransferredintotheGuaranteeFund.Theactualpre-financingpaidbytheECisEUR1.519.818,70.Thedistributionofthepre-financingtothepartnershasbeenprocessedbytheCOon08.11.2017.
Table4showsthedistributionofthepre-financingtopartnersasprocessedbytheCO.
Table4.Overviewofpre-financingpaymentstopartners
Beneficiaries will be notified by the CO aboutupcomingpaymentswell inadvancewithall thenecessary information on the amounts to betransferred.
Supporting management activities provided bytheCO in this specific fieldwillmainly focus oncostreportingincludingthecollectionandreviewof partners’ Financial Statements (FS) and costexplanations.
This include the monitoring of the Use ofResources (UoR) and the preparation of therelevant UoR table providing a detailed
explanationofindividualcostitems.
AdditionalinformationontheineligibilityandeligibilityofcostsislaidinArt.6oftheGA.TheUoRmonitoring table is requested for the mere purpose of validating these costs as coherent andcongruous.SuchamonitoringhelpstheECtounderstandapartner'scostclaimbetter.Thefollowingisapreliminary,illustrativeandnotlimitingexample/templateoftheUoR:
Typeofcosts FocusofexplanationsPersonnelcosts Listname,jobtitle,cosandperson/monthper
staffmember.LinkthecoststotheWPOtherdirectcosts–Travels List cost per travel, name and number of
participants,placeofdestination,dateoftravelandtravelpurpose(providespecialjustificationfortraveloutsideEU).LinkthecoststotheWP
Otherdirectcosts–Durableequipment Specify whether the equipment has beenacquiredexclusivelyforPANTHEON(ortowhatextenttheequipmentisusedintheproject)andwhat is used for. Specify depreciationmethodology, according to the financialregulationsofyourOrganization.LinkthecoststotheWPs
PrecisionFarmingofHazelnutOrchards(PANTHEON)___________________________________________________________________________________________________________
PANTHEONDocumentD1.1_ProjectManagementGuidelines_Rel.01_20171129
SCADA for AgriculturePANTHEON
12
DuringthecostreportingtheCOwillprovidesupport:
• byfacilitatingthecollectionoffinancialfiguresfortherelevantreportingperiod;• byinformingaboutrequireddocumentssuchasCertificatesoftheFinancialStatement(CFS
Annex5oftheGA);• byclarifyinghowtoenterfiguresintoSyGMainthePP;• and by reviewing the cost explanations for consistency and completeness. Advicewill be
offered via email and/or by exploiting the NeXTcloud platform (described below). Whenfinalized,beneficiariesentertheirfinancialinformationintoSyGMa,electronicallysigntheFSandsubmitthemtotheCO.RevisionsrequestedbytheECwillbeorganizedandsubmittedwithoutdelayviatheCO.
Thefollowingisadescriptionofthemostrelevantfinancialaspectstobeconsideredclassifiedby:
A. EligibleDirectCostsB. IndirectCostsC. IneligibleCosts
Eligibleactualdirectcostsmustmeetthefollowingcriteria:
i. theymustbeactuallyincurredbythebeneficiary;theymustbeincurredintheperiodsetout
inArticle3oftheGrantAgreement,apartfromcostsrelatingtothesubmissionoftheperiodicreportforthelastreportingperiodandthefinalreport;
ii. theymustbeindicatedintheestimatedbudgetsetoutinAnnex2;iii. theymustbeincurredinconnectionwiththeactionasdescribedinAnnex1andnecessary
foritsimplementation;iv. theymustbeidentifiableandverifiable,inparticularrecordedinthebeneficiary’saccounts
inaccordancewiththeaccountingstandardsapplicableinthecountrywherethebeneficiaryisestablishedandwiththebeneficiary’susualcostaccountingpractices;
v. theymustcomplywiththeapplicablenationallawontaxes,labourandsocialsecurity;vi. theymust be reasonable, justified andmust complywith the principle of sound financial
management,inparticularregardingeconomyandefficiency.
Costsareeligibleiftheycomplywiththeabovegeneralconditionsandthespecificconditionssetoutbelowforeachofthefollowingbudgetcategories:
• directpersonnelcosts;• directcostsofsubcontracting;• otherdirectcosts;• indirectcosts;• notapplicable.
Direct costsarecosts thataredirectly linked to theaction implementationandcan thereforebeattributedtoitdirectly.Theymustnotincludeanyindirectcosts(seenextsectionbelow).
PrecisionFarmingofHazelnutOrchards(PANTHEON)___________________________________________________________________________________________________________
PANTHEONDocumentD1.1_ProjectManagementGuidelines_Rel.01_20171129
SCADA for AgriculturePANTHEON
13
Indirectcostsarecoststhatarenotdirectlylinkedtotheactionimplementationandthereforecannotbeattributeddirectlytoit.
4.1 DirectpersonnelcostsOnlythecostsoftheactualhoursworkedbythepersonsdirectlycarryingoutworkundertheprojectmaybecharged.Suchpersonsmust:
o Bedirectlyhiredbythebeneficiaryinaccordancewithitsnationallegislation;o Workunderthesoletechnicalsupervisionandresponsibilityofthebeneficiary,ando Beremuneratedinaccordancewiththenormalpracticesofthebeneficiary.
Beneficiariesmustkeeprecordsofthehoursworkedfortheaction(e.g.time-sheets,etc.)byeachteammember.ThetimesheetsshouldhavethetimeallocationbyWP/taskandshouldbeproducedbythepersoninvolvedintheproject.
Directcostsofsubcontracting
Asubcontractorisatypeofthirdparty,i.e.alegalentitywhichisnotabeneficiaryoftheGA,andisnotasignatorytoit.Itappearsintheprojectbecauseoneofthebeneficiariesappealstoitsservicestocarryoutpartofthework,usuallyforspecializedjobsthatcannotcarryoutitselforbecauseitismoreefficienttousetheservicesofaspecializedorganization.
o Subcontractmustbedescribedincludingprojectname,projectnumber,durationandcontentof activity subcontracted, calculation of costs, signatures of all parties involved, dates ofsigningthecontract,etc.);
o The proof of payment to the subcontracted person or institution must be kept in thebeneficiary’saccountingrecords.
Subcontracting is only allowed if previously specified in the GA. Adding a subcontractor duringPANTHEONimplementationrequiresanamendmenttotheGA.
Travelcostsandrelatedsubsistenceallowances
Travelandsubsistencecostsmayrelatetothepersonnelofthebeneficiariesaswellastoexternalexperts thatparticipate in theactiononanadhocbasis (e.g. attending specificmeetings), if theexperts’participationisenvisagedintheGA.Inthiscase,thebeneficiarymayreimbursetheexpertsor handle the travel arrangements itself (andbe invoiceddirectly). As an internal rule, travellingoutsideofEuropemustbecommunicatedtotheCO.Alltravelcostsmustbelimitedtotheneedsoftheaction.Moreover,theymustbeadequatelyrecordedandjustified.
Depreciationcostsofequipment
Thedepreciableamountofanassetmustbeallocatedonasystematicbasisoveritsusefullife(i.e.theperiodduringwhich theasset isexpected tobeusable;depreciatedequipmentcosts cannotexceedtheequipment’spurchaseprice;depreciationcannotbespreadoveraperiodlongerthantheequipment’susefullife).Thedepreciationcostsmustbecalculatedforeachreportingperiod.
PrecisionFarmingofHazelnutOrchards(PANTHEON)___________________________________________________________________________________________________________
PANTHEONDocumentD1.1_ProjectManagementGuidelines_Rel.01_20171129
SCADA for AgriculturePANTHEON
14
Costsofothergoodsandservices
Suchgoodsandservicesinclude,for instance,consumablesandsupplies,dissemination(includingopenaccess),protectionofresults,certificatesonthefinancialstatements(requiredbytheGAforpartners receiving an EC contribution exceeding the 325KE), certificates on the methodology,translationsandpublications.
Howtobesurecostsareeligible:
o Theymustbeactuallyincurredbythebeneficiaryo Theymustbeincurredintheperiodofdurationoftheaction.Thereisonlyoneexception
costsrelatingtothesubmissionoftheperiodicreportforthelastreportingperiodandthefinalreport.
o TheymustbeindicatedintheestimatedbudgetsetoutinAnnex2ofGAo TheymustbeincurredinconnectionwiththeactionasdescribedinAnnex1andnecessary
foritsimplementation(necessarytoachievetheaction'sobjectives)o Theymustbeidentifiableandverifiable,inparticularrecordedinthebeneficiary'saccounts
accordingtotheaccountingstandardsapplicable inthecountryandwiththebeneficiary'susualcostaccountingpractices(comedirectlyfromthebeneficiaryaccountsandsupportedbydocumentation)
o Theymustcomplywithnationallawsontaxes,labourandsocialsecurityo Andfinally,theymustbereasonable,justifiedandmustcomplywiththeprincipleofsound
financial management in particular regarding economy and efficiency (in line withhousekeepingpracticewhenspendingpublicmoneyandnotbeexcessive).
IMPORTANT: Keep Records used to Proof eligibility and pay attention to the requirements forpersonnelcostsrecordsandhourlyratecalculation(article6)
4.2 IndirectcostsAreallthoseeligiblecostswhichcannotbeidentifiedbythebeneficiaryasbeingdirectlyattributedtotheproject.Theymustbecalculatedbyapplyinga25%flat-ratetothebeneficiary’seligibledirectcosts,minus:
o costsofsubcontractingando costsofin-kindcontributionsprovidedbythirdpartieswhicharenotusedonthe
beneficiary’spremises
4.3 IneligiblecostsArethosecoststhatdonotcomplywiththeconditionssetoutinArticle6.1to6.4ofGA,inparticular:
o costsrelatedtoreturnoncapital;o debtanddebtservicecharges;o provisionsforfuturelossesordebts;o interestowed;o doubtfuldebts;o currencyexchangelosses;
PrecisionFarmingofHazelnutOrchards(PANTHEON)___________________________________________________________________________________________________________
PANTHEONDocumentD1.1_ProjectManagementGuidelines_Rel.01_20171129
SCADA for AgriculturePANTHEON
15
o bankcostschargedbythebeneficiary’sbankfortransfersfromtheAgency;o excessiveorrecklessexpenditure;o deductibleVAT;o costsincurredduringsuspensionoftheimplementationoftheaction(seeArticle49).
Accordingly,declaredcoststhatareineligiblewillberejected.ReadingtheH2020annotatedModelGrantAgreement is strongly recommended–namely thearticles relatedtoeligibleand ineligiblecosts - that can be found in the following link:http://ec.europa.eu/research/participants/data/ref/h2020/grants_manual/amga/h2020amga_en.pdf.
DuringtheimplementationofthePANTHEONorafterwards,theECchecks,reviews,investigatesandauditstheproperimplementationoftheprojectanditscompliancewiththeGA.TheECmayorderanaudittothegrantduringtheprojectoratanytimeupto2yearsafterthefinalpayment.Anyclaimed ineligible costswill be recovered or deducted from the next payment. In the context ofchecks,reviews,auditsorinvestigations,partnersmustmakeavailablerecordsandothersupportingdocumentationthatprovestheproperimplementationoftheactionandthatthecoststheydeclareaseligible(foraperiodoffiveyearsafterthepaymentofthebalance).
5 MonitoringofresourcesexpenditureTheallocationofresourceswillbecontrolledonahalf-yearbasisbytheCO.Partnerswillbeaskedtoreport thedistributionof PMs for their organization,which is reviewedby theCOmainly to seewhethertheeffortsareinlinewiththeDoA.
ThisdatacollectionwillallowtheCOtotrackthemanpowerallocationperpartnerthroughouttheproject and provides a detailed summary of planned versus actual PM deployed for controllingpurposes.Eachpartnerwillalsobeaskedtojustifyanymajorover/underuseofPMtomakesurethatthedeviationsfromtheplannedschemewillnotresultinanoveralldelayoftheprojectorotherwisejeopardizetheproject'sobjectives.
6 Communication6.1 CommunicationwiththeEC.TheCOwillactassoleintermediaryforallcommunicationsbetweentheprojectpartnersandtheEC.
TheCOwillmanageallthecorrespondencewiththePOandtheFOonthefollowingtopics:
• the preparation, completion and submission of the PR (point 2 above) and FS for theConsortium,
• thepreparation,completionandsubmissionofdeliverables• projectand funding relatedmatters requiring specific feedbackandagreementby thePO
and/ortheFO.
The interaction between the CO and PO/FO will be mainly handled through the EC’s GrantmanagementSystemforH2020calledSyGMa.SyGMawillallowthemanagementofallprocedures
PrecisionFarmingofHazelnutOrchards(PANTHEON)___________________________________________________________________________________________________________
PANTHEONDocumentD1.1_ProjectManagementGuidelines_Rel.01_20171129
SCADA for AgriculturePANTHEON
16
relating to the submission of deliverables and reports, to the payment execution and auditimplementationaswellastotheenteringofanypotentialamendmenttotheGA.
6.2 Internalcommunication.ReferenceshallbemadetotheidentifiedscientificandadministrativecontactsperBeneficiary.
6.3 ExternalcommunicationIt is important tonote thatvisibilityofEU funding ismandatorywhilepromotingprojectactions.Pleaseusealways:
• The EU emblem - High-resolution emblems can be found here: http://europa.eu/about-eu/basic-information/symbols/flag/
• The following text: “Project PANTHEON is funded by the EuropeanUnion's Horizon 2020ResearchandInnovationProgramme,underGrantAgreementnumber774571”.
Forscientificdisseminationactivities,thefollowingtextshouldbealwaysused:
• “Thisworkhasbeen supportedby the EuropeanCommissionunder the grant agreementnumber774571–ProjectPANTHEON.”
6.4 ConferencecallsPANTHEONwillsetaconferencecallplatformtobeusedasmaincollectivecommunicationtool.ThisfunctionalitywillbepartoftheportalbasedontheNextcloudtechnologywhichhasbeendevelopedwithintheConsortium.SeeSection6.6forfurtherdetailsonthePortal.
AgeneralcallconferencewillbeorganizedbytheCOinprincipleevery3months.WPLsarerequiredtoparticipateortoberepresentedbyadeputy.ThesecallswillbeannouncedbytheCOviaemailaweekbefore.TheCOwilldraftandsendtheagendatwo-to-threedaysinadvance.
Everypartnerisexpectedtoparticipateinthesecallsinanactiveandreliablemanner.Ifanyoneisunabletobepresent,theyoughttogivepriornoticetotheCOandsendfeedbacktorelevantpointsraisedintheagenda.
Theagendawilltypicallyfocuson:
• progresswithineachworkpackagewithafocusonduedeliverables;• recentandcomingeventsattendedbyPANTHEONmembers;• management,reporting;• dissemination,networkingorganizationofreviewandplenarymeetings,etc.
Inaddition,callswillbescheduledonaregularbasistodiscusstechnicalandscientificissuesrelatingtoindividualWPs.
PrecisionFarmingofHazelnutOrchards(PANTHEON)___________________________________________________________________________________________________________
PANTHEONDocumentD1.1_ProjectManagementGuidelines_Rel.01_20171129
SCADA for AgriculturePANTHEON
17
6.5 ProjectMeetingsPANTHEONwillholdoneplenarymeetingtwiceayeartodiscussongoingwork,achievementsandnew actions. Eachmeeting will be organized by one of the partner who will be responsible formanagingontime issuessuchasvenue,agenda,co-locatedevents likecommunitymeetupswithstakeholdersand/orinvitationsofexternalguests.
6.6 Portal,ForumandRepositoryAportalincludingarepositorybasedontheNextcloudtechnologyhasbeendeveloped.Nextcloudisasuiteofclient-serversoftwareforcreatingandusingfilehostingservices,itisfreeandopen-source,allowinganyonetoinstallandoperateitonaprivateserver.
It also offers additional functionalities for enhancing collaborations such as video calls, sharedcalendars and instant messaging. Regarding specifically the repository functionality, Nextcloudallowseachusertohavehis/herownaccountwithspaceforprivatefiles,draft,inprogressdocumentandsoon.
Thesharedfolderfeatureallowstheworkgrouptoaccessallrequiredresources(inputs)andproducethenecessaryprojectartefacts(output).Sharingandauthorizationleveliscustomizableasneeded.AspartofthePantheonproject,theportaladministratorwillorganizeasetofdefaultfolders,sharedbetweenworkgroups,forfileexchange.
Thefolderstructurecanmodelmilestones/projectphases,adoptapartitioningdrivenbyWP,splitinworkgroupsoramixofthesestrategies.Thestructureshouldbedynamic,flexibleanditwilladjustovertimebasedonworkgroupneeds.
Finally, it has also been implemented a Forum devoted to the collection of all the technicaldiscussionsandcontributionsfocusedonthespecificnecessitiesofeachactivity.
7 WP1-duedeliverablesThefollowingisthemaindeliverableduewithinWP1:
Ø D.1.1:ProjectManagementGuidelinesM1
Inaddition,WP1willdelivertherequestedTechnicalandFinancialReportsatM12,M30andM48.
8 KeydocumentsGrantAgreement(No.774571)–ThecontractconcludedbetweentheEC(representingtheEU)andthebeneficiariesunderwhich theparties receive the rights andobligations (e.g. the rightof theUnion'sfinancialcontributionandtheobligationtocarryouttheresearchanddevelopmentwork).TheGAconsistsofthebasictextandannexes,includingAnnex1–Descriptionoftheaction(DoA).TheDoA(Annex1partA)isakeydocumenttobetakenintoaccountgiventhatitcompilesaspecificdescription of the tasks that will be carried out along the project and the expected results,deliverablesandmilestonestobeobtained.
PrecisionFarmingofHazelnutOrchards(PANTHEON)___________________________________________________________________________________________________________
PANTHEONDocumentD1.1_ProjectManagementGuidelines_Rel.01_20171129
SCADA for AgriculturePANTHEON
18
ConsortiumAgreement - the internalagreementsignedbetweenthemembersof theconsortiumestablishing their rights and obligations with respect to the implementation of the action incompliancewiththegrantagreement.
AllPANTHEONpartnershaveonecopyofthesedocuments,andtheywillbemadeavailableontheproject’srepository.
[ENDofD1.1]