FM ILT overview 1
PACS SVR-II 18 January 2007
The PACS FM ILT Phase I
overview on actual test execution and analysis
Eckhard SturmMPE
FM ILT overview 2
PACS SVR-II 18 January 2007
• The PACS FM ILT started with warm short functional tests (SFT Warm) on October 12-18
• Cold tests were executed between October 31 and December 22, based on the test plan (B) that was introduced by U. Klaas in the previous presentation
• Phase I of the PACS FM ILT ended on January 4 with another SFT Warm
FM ILT overview 3
PACS SVR-II 18 January 2007
• Progress was very good! All planned tests were executed (sometimes ahead of schedule), except one test block (photometer set-ups III), which was replaced by further tests of the spectrometer (including red!)
• (Preliminary) analysis reports exist for most of the tests (see below and the following presentations, see also the SVR-II web page), but naturally some test data carry further information that still needs to be extracted.
FM ILT overview 4
PACS SVR-II 18 January 2007
• most of the mechanisms (grating, filter wheels, calibration sources, hetaers, flashers, OGSE mechanisms, xy-stage, etc.) are functional and perform as requested
• the bolometer and spectrometer detectors seem to be in spec (NEP)
• PSFs and spectral resolution seem to be in spec
• autonomous operations (long tests over night) were possible
• the Lens laser setup worked extremely well
• stable DECMEC (but QM)
• data analysis, mostly within PCSS, much more routine-like (and faster) than at CQM ILT
FM ILT overview 5
PACS SVR-II 18 January 2007
• the chopper is non-conformant
• the spectrometer slicer unit is non-conformant
• no DECMEC FM yet
FM ILT overview 6
PACS SVR-II 18 January 2007
• Original Plan was to warm up at the end of Phase I in order to replace the DECMEC QM with the DECMEC FM (see previous talk by U. Klaas)
• However, the chopper non-conformance required a full warm up and opening of the cryostat to inspect and possibly exchange the chopper
• The chopper performance was good enough to continue the planned tests of phase I without information loss
• In order to characterize the spectrometer as much as possible to detect potential major problems before opening the cryostat we decided to expand the spetrometer test program in phase I
• For tests of the red spectrometer we needed to connect the red Ge:Ga array to the blue DECMEC (switching cable connections at 40K).
FM ILT overview 7
PACS SVR-II 18 January 2007
The PACS ICC at work
FM ILT overview 8
PACS SVR-II 18 January 2007
FM ILT overview 9
PACS SVR-II 18 January 2007
Test block execution report status
SFT Warm complete - „SFT Warm Chopper and Internal Calibration Sources“
- “Functional and Performance Tests of Mechanisms“
Bolometer LTU tests complete - „Report on the FM ILT PhFPU functional tests“
SFT He I complete - „Report on the FM ILT PhFPU functional tests“
- „Functional and Performance Tests of Mechanisms“
- „SFT HeI Chopper and Internal CS on 31 October“
available / Name on SVR-II web page
OGSE characterisation Ia complete - „OGSE Characterisation during CQM/FM ILT“
Control Loop optimisation complete - „Functional and Performance Tests of Mechanisms“
- „Basic Drive Parameters Chopper.... “
- „Angular Calibration of Chopper (PCD 2.3.1)“
- pending: report on CS
FM ILT overview 10
PACS SVR-II 18 January 2007
Test block execution report status
SFT He II complete pending, but see briefing minutes (14 Nov)
Thermal behaviour complete (draft) - „Thermal
behaviour tests during FM-ILT...“
OGSE characterisation Ib complete - „Angular Calibration of Chopper (PCD 2.3.1)“
- „Further investigations of chopper angle....“
available / Name on SVR-II web page
Photometer set-ups I (basic) complete - „Are the three modes....correctly interpreted?“
„all tests successful“
See presentations by H. Feuchtgruber and M. Sauvage
photometer & spectrometer
Lens Laser tests complete pending, but initial results on leaks, PSF, spectral resolution, wavelength calibration; see briefing minutes and presentation by H. Feuchtgruber
Plus spec AOT mode tests plus addtional tests
FM ILT overview 11
PACS SVR-II 18 January 2007
Test block execution report status
Photometer set-ups II a/b complete pending, but initial results on optimal bias and NEP; see presentations by M. Sauvage and A. Poglitsch
Spectrometer calibration I complete pending, but see presentation by plus RED ! H. Feuchtgruber
OGSE characterisation IIa complete pending, but optimal focus position was plus spectrom. determined and used in the further tests (see focus! briefing minutes (8 Dec) and presentation by M. Sauvage
available / Name on SVR-II web page
(wavelength cal. vapour cell)
(optimal settings)
(photometer focus)
OGSE characterisation IIb partially pending, partially in - „Bolometer FOV Chopper Scans...“ (photometer)
FM ILT overview 12
PACS SVR-II 18 January 2007
Test block execution report status
Photometer set-ups III not done information partially in other tests
Spectrometer characteris. pending, but results are extracted; see presentations by H.
Feuchtgruber and A. Poglitsch
slicer NRB
available / Name on SVR-II web page
(FOV scans, AOT mode tests, grating
scans in different resolutions, i.e.
SED, low, medium, high resolution,
line scans, point source rasters, slicer
NRB investigations)
(signal dependencies, pixel offsets,
low frequency noise, time constants...)
Additional tests with blue *AND* red spectrometer:
FM ILT overview 13
PACS SVR-II 18 January 2007
The Christmas Event
PACS Observations of Ursa Major and Ursa Minor on 22 December 2006
All data rights: A. Poglitsch
FM ILT overview 14
PACS SVR-II 18 January 2007
• OGSE characterisation I (basic function & performance) : complete
• OGSE characterisation II & III: partially, needs to be repeated (partially)
• photometer set-ups I and II (basic and optimal settings): complete
• spectrometer initial characterisation
• AOT like tests
• autonomous tests
Summary:
FM ILT overview 15
PACS SVR-II 18 January 2007
Mechanisms characterised (except chopper)
Photometer: optimal settings, and basic characterisations of PSF, spatial distortion, NEP, FOV, ...
Spectrometer: basic characterisation of PSF, instrumental (line) profiles, wavelength calibration, spectral resolution, relative spectral response, leakage and ghosts, FOV, NEP, ...
slicer non-conformance
chopper non-conformance
Full calibration yet to be done for both photometer and spectrometer