Project Progress – 22nd April,2014
STATUS REPORT OF MY HOME VIHANGA Block--”01” As On 22nd April,2014
1.Basement –II Slab Completed 2.Basement-I 2,3,4 Flats Slab Completed,1,5,6 Bar Bending Completed
STATUS REPORT OF MY HOME VIHANGA Block--”02”As On 22nd April,2014
1.Basement –II Slab Completed 2.Basement-I 2,3-Flats Shuttering Completed,1,4,5,6 flats Columns Completed
STATUS REPORT OF MY HOME VIHANGA Block--”03” As On 22nd April,2014
1.Footing work Completed2.Preparing for Grade Slab
STATUS REPORT OF MY HOME VIHANGA Block--”04” As On 22nd April,2014
1.Footing work Completed2.Preparing for Grade Slab
STATUS REPORT OF MY HOME VIHANGA Block--”05 & 06” As On 22nd April,2014
1.Earth Work In Progress
STATUS REPORT OF MY HOME VIHANGA Block--”07 & 08” As On 22nd April,2014
1.Earth Work In Progress
STATUS REPORT OF MY HOME VIHANGA Block--”09 & 10” As On 22nd April,2014
1.Earth Work In Progress
STATUS REPORT OF MY HOME VIHANGA Block--”11 & 12” As On 22nd April,2014
1.Earth Work In Progress
STATUS REPORT OF MY HOME VIHANGA Block--”13 & 14” As On 22nd April,2014
1.Earth Work In Progress
STATUS REPORT OF MY HOME VIHANGA Block--”15” As On 22nd April,2014
1.PCC-Started
STATUS REPORT OF MY HOME VIHANGA Block--”16” As On 22nd April,2014
1.Ready For PCC
STATUS REPORT OF MY HOME VIHANGA Block--”17” As On 22nd April,2014
1.Footing Competed2.Columns Bar Bending work In Progress
STATUS REPORT OF MY HOME VIHANGA Block--”18” As On 22nd April,2014
1.PCC Competed
STATUS REPORT OF MY HOME VIHANGA Block--”19” As On 22nd April,2014
1.Basement –II Slab Completed Except Flat No 1,6 2.Basement-II Flat No 1, 6 Shuttering work In Progress
STATUS REPORT OF MY HOME VIHANGA Block--”20” As On 22nd April,2014
1.Grade Slab Completed2.Columns Bar Bending Work In Progress