z
MINIMIZINGYour Risk +
AVOIDINGLegal Problems
Presented by Don GregoryJanuary 19, 2017
z
TOP RISKSin Today’s Construction
1 Labor Shortage 30%
2 Contract Language22%
z
Conditional
BIDSYour first – and
perhaps last – chance to make the rules.
z
Did You Condition Your Bid?
This bid is conditioned upon the use of the ConsensusDOCS
750, AIA A401 or other subcontract language
acceptable to subcontractor
“
“
z
Use ASA bid proposal form or similar language:
Favorable Conditions of Proposal:
+ Beginning work constitutes acceptance of bid
+ Change in material price by 5% or more warrants equitable adjustment
+ Not required to name additional insureds
+ Favorable payment terms
z
Use ASA bid proposal form or similar language:
Favorable Conditions of Proposal:
+ Entitled to equitable adjustments for modifications to schedule, delays outside sub’s control
+ Entitled to rely on contract documents
+ Lien waivers exclude retainage and unbilled changes/claims
z
Conditional
BIDSCan be incorporated into
the Subcontract scope (attach as exhibit A)
ORRetain leverage for
subcontract revisions
z
Securing Equitable CONTRACT TERMS
z
Killer Contract Clauses
Contingent Payment
No Damage for Delay
Waiver of Lien + Bond Rights
Unconditional Lien Waivers
Before Payment
z
Killer Contract Clauses
Contingent Payment
No Damage for Delay
Waiver of Lien + Bond Rights
Unconditional Lien Waivers
Before Payment
z
Contingent Payment
Pay-If-Paid
Pay-When-
Paid
z
“Condition precedent”
z
Progress Payment
z
FinalPayment
z
To be enforceable, must be clear + unambiguous
Pay-If-Paid
z
If not drafted correctly, “benefit of the doubt” will go to subcontractor
Pay-If-Paid
z
Unenforceable by statute in:
WI SC
DE
z
Why have a mechanic’s lien statute when it can
be defeated with a Pay-If-Paid clause?
z
Lehrer McGovern Bovis, Inc. v. Bullock
Insulation, Inc.Lien waiver and pay-if-paid
provisions are unenforceable based upon public policy favoring the
statutory right to a mechanic's lien
z
Paid within a reasonable period of time
Pay-When-
Paid
z
If owner fails to pay, payment on demand
Pay-When-
Paid
z
Practical Pointers
Look for contracts with good payment terms
(Fixed payment terms, pay-when-paid)
Try to Insert Pay-When-Paid Language
(Use AIA A401 or ConsensusDOCS 750)
Modify Pay-If-Paid Language
z
Killer Contract Clauses
Contingent Payment
No Damage for Delay
Waiver of Lien + Bond Rights
Unconditional Lien Waivers
Before Payment
z
Not Enforceable Under Ohio’s Fairness
in Construction Contracting Act
z
z
Sole remedy is a time extension
Generally unenforceable if –statute/case considers it against public policy or extent or nature
of delay was not foreseeable
z
Killer Contract Clauses
Contingent Payment
No Damage for Delay
Waiver of Lien + Bond Rights
Unconditional Lien Waivers
Before Payment
z
Contrary to popular belief, in many states an
“upfront” lien wavier (without independent
consideration like payment) is ENFORCEABLE
z
Lien Waiver
Language
z
Killer Contract Clauses
Contingent Payment
No Damage for Delay
Waiver of Lien + Bond Rights
Unconditional Lien Waivers
Before Payment
z
z
Condition your lien waiver … followed by a trailing unconditional
lien waiver
SOLUTION
z
ConditionalWaivers
Use Conditional Waivers for Progress Payments
z
SigningWaivers
Be Careful When Signing Waivers for Partial Payment
z
ProperNOTICE
Nobody likes itEverybody needs it
z
Change OrdersIN WRITING
Avoid provisions that:allow one to direct additional work without agreement on price
make payment for additional work contingent upon payment by owner
allow “backcharges” without notice (ConsensusDOCS 750)
z
Proper Notice
Risk of Proceeding Without Change Order or Written Direction
z
Would love to perform the work without delay, but
YOUR contract makes me stop to get a change order
signed in advance!
z
LANGUAGETo Protect Yourself
“Unless you indicate otherwise, we will proceed with the additional work as we were directed in the progress
meeting earlier today and this e-mail shall serve as continued notice of our
intention to receive additional compensation for this change”
z
Don’t get burned by signing a change order with broad waiver language
z
BE CAREFULWhen Signing Change Orders
Change Orders should just waive costs for that specific change rather than all possible extra costs through
the date of the change order
z
Questions?Donald W. Gregory, DirectorKegler Brown Hill + [email protected]/gregory614-462-5416
Top Related