Microtrenching is the optimal solution for deploying bothaccess- and backbone in especially urban areas all in onlyone handling.
Once the machine and the scheduling technique is fully de-
veloped and fine-tuned, our estimate is, that four men, workingin asphalt or concrete,could lay as much as 400-500meters perday.
GMPLASTis involved in tests in Ireland, Germany, France,Norway, Portugal, Israel, Malaysia and Iran and with the currentrate, we believe that 2012 will be the major breakthrough forthis technique. In order to be able to accommodate the varyingneeds from job to job, GMPLAST is working on developing thenecessary machinery with 3 different manufacturers.The widthand depth of the vertical cut is depending on whether the pur-
pose is backbone, access networks, or both.
Flatliner is perfect for microtrenching because it is flex-ible in deployment but stiff and stable on edge.
GMPLASTalready has more than 25 km Flatlinerimple-mented in microtrenching, and 4-5 projects in the planning. Aprevailing trend is the Comboflatliner, where Backbone andAccess tubes are combined in the same line. It saves time andallows a good soil compaction or fillers. On the subsequentpages are shown a series of pictures from various pilot projectsin several cases more kilometers long.
MICRO TRENCHING400-500 meters Flatliner laid per day
Trenching prices reduced by 50-70%
8/12/2019 microtrenching
3/12
37 years of innovation and knowledgeGM
GM PLAST A/S www.gm-plast.dk
MICRO TRENCHINGMachine Park
Easy, Safe and Cost-Efficient
In order to constantly be on top of the game,being thebest we can be, we aim to gather information andexperience from as many sources as possible. That is whywe prefer to work with a wide range of machinery.
At the moment we work with the three machines seenon this page. They all have have a different approach to thetask, but their common goal is to put FTTH into ground in aeasy, safe and cost-efficient manner as possible.
What they all came up with was Microtrenching, withvariations of course, since they all have different premisesconcerning underground , civic demands and legislationsetc.
8/12/2019 microtrenching
4/12
37 years of innovation and knowledgeGM
GM PLAST A/S www.gm-plast.dk
Flatliner Typ Flatliner green, 8 Micropipes, 14mm / 2mm - 696,96m
Flatliner Typ Flatliner orange / blue, 8 Micropipes, 12mm / 2mm - 1135,94m
Flatliner Typ Flatliner orange / yellow, 8 Micropipes, 12mm / 2mm - 116,99m
Single pipe direct connection to manhole, 1 Micropipes, 12mm / 2mm - 44,38m
Single pipe from Flatliner to homes connected, 1 Micropipes, 12mm / 2mm - 1636,84m
57 homes connected with 4xG.652 d fiber length without spare length - 8868,45m
Microtrenching in the street 1994,27mHomes passed113
MICRO TRENCHINGTJOME PROJECT - NORWAY
8/12/2019 microtrenching
5/12
37 years of innovation and knowledgeGM
GM PLAST A/S www.gm-plast.dk
Project Raadyrstien - NORWAY
Project Tjome- NORWAY
Project Voiebyen- NORWAY
8/12/2019 microtrenching
6/12
37 years of innovation and knowledgeGM
GM PLAST A/S www.gm-plast.dk
Microtrenching - precisionMICRO TRENCHING
8/12/2019 microtrenching
7/12
37 years of innovation and knowledgeGM
GM PLAST A/S www.gm-plast.dk
MICRO TRENCHINGFlatliner - compact on drums - easy to transportFlatliner - compact in trench - easy to handle
An extra topskin is applyed onto the Flatliner. This secures a very
flexible solution , that makes the folding easy.
20mm
30mm
40mm
60mm
8/12/2019 microtrenching
8/12
37 years of innovation and knowledgeGM
GM PLAST A/S www.gm-plast.dk
MICRO TRENCHINGUsing Flatliner
Foldable trenching
Different combinations , sizes and colours
(Colourcode)
Power Flatliner -fibre cable + 220V powercable in
one workflow
Power Flatliner is offering numerous advantages
when used e.g. CCTV
Up to 12 microducts in one handling.
Stabilisation sticks between the microducts give
the product a higher stability .They support also
the micro ducts in the case of cross or tensile.
8/12/2019 microtrenching
9/12
37 years of innovation and knowledgeGM
GM PLAST A/S www.gm-plast.dk
At GMwe know that even the best idea needs a lot of
nursing and a lot of helping along in order to be adapted
into the market.This is why we have decided to start the
GM Micro Trenching Academy.
The main purpose is to evolve and refine our own
knowledge , in order to secure and strengthen our posi-tion as market leader and first-mover in an ever changing
market.
Secondly we will also be able to offer schooling and su-
pervision to various microtrenching projects. Both here
at our testcenter in Hedensted, but also on-site in most
parts of the world.
We will be able to demonstrate and work with a various
range of different brands of Microtrenching machinery,
all acording to specified needs and problems.
Do not hesitate to contact us if you have any ques-
tions, challenges or just want to optimize your FTTH
roll-out at a minimum cost.
MICRO TRENCHING400-500 meters Flatliner laid per day
8/12/2019 microtrenching
10/12
37 years of innovation and knowledgeGM
GM PLAST A/S www.gm-plast.dk
FPT mainbox
FPT powerbox
FPT splitbox
hanged
AERIAL FLATLINER
FLATLINER
microtrenched
8/12/2019 microtrenching
11/12
37 years of innovation and knowledgeGM
GM PLAST A/S www.gm-plast.dk
FLATLINER- regular Flatliner can be both traditionally
trenched or microtrenched.
For areas where trenching is not possible we designed
AERIAL FLATLINER which can be hanged to ensure
the connection.
AERIAL FLATLINER - different combinations and num-
ber of microducts according to the customers project..........................