ID Task Name Duration Start Finish Predecessors
105 Tv ledge 2 days Thu 19-05-11 Fri 20-05-11 104106 Light fixtures 1 day Mon 23-05-11 Mon 23-05-11 105107 Toilet fixtures,mirror 2 days Mon 23-05-11 Tue 24-05-11 130108 ROOM INTERIORS 167 days? Wed 15-06-11 Mon 30-01-12109 Preparation of tender document 4 days? Wed 15-06-11 Mon 20-06-11
110 Float enquiries 6 days? Tue 21-06-11 Mon 27-06-11 109111 Receive quotes 7 days Tue 28-06-11 Tue 05-07-11 110112 Consultants review 10 days Wed 06-07-11 Tue 19-07-11 111113 Final negotiation 2 days Wed 20-07-11 Thu 21-07-11 112114 Award contract 1 day Fri 22-07-11 Fri 22-07-11 113115 Supply 97 days? Mon 29-08-11 Mon 09-01-12116 Erection 97 days? Mon 05-09-11 Mon 16-01-12117 Rooms comissioning 8 days? Thu 19-01-12 Mon 30-01-12118 PUBLIC AREAS 1 day? Mon 18-04-11 Mon 18-04-11119 Finalisation of Concept 5 days? Mon 02-05-11 Fri 06-05-11120 Preparation of tender document 4 days? Wed 15-06-11 Mon 20-06-11 134121 Float enquiries 6 days? Tue 21-06-11 Mon 27-06-11 120
122 Receive quotes 7 days? Tue 28-06-11 Tue 05-07-11 121123 Consultants review 10 days? Wed 06-07-11 Tue 19-07-11 122124 Final negotiation 2 days? Wed 20-07-11 Thu 21-07-11 123125 Award contract 1 day Fri 22-07-11 Fri 22-07-11 124126 Supply 117 days? Mon 29-08-11 Mon 06-02-12127 Erection 66 days? Mon 21-11-11 Mon 20-02-12128 KITCHEN EQUIPMENT 1 day? Mon 18-04-11 Mon 18-04-11129 Finalisation of Concept 6 days? Mon 09-05-11 Mon 16-05-11130 Preparation of t ender doc ument-Im ported 4 days ? Tue 17-05-11 Fri 20-05-11131 Indian 3 days? Mon 23-05-11 Wed 25-05-11 87132 Float enquiries 6 days? Thu 26-05-11 Wed 01-06-11 131133 Receive quotes 5 days? Thu 02-06-11 Wed 08-06-11
134 Consultants review 5 days? Thu 09-06-11 Tue 14-06-11 133135 Final negotiation 7 days? Wed 15-06-11 Thu 23-06-11136 Award contract 1 day Fri 24-06-11 Fri 24-06-11137 Supply 31 days? Mon 03-10-11 Mon 14-11-11 70138 Erection 35 days? Mon 14-11-11 Fri 30-12-11139 Comissioning 7 days? Mon 16-01-12 Tue 24-01-12
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T05 Dec '10 12 Dec '10 19 Dec '10 26 Dec '10 02 Jan '11 09 Jan '11
TaskSplit
ProgressMilestone
SummaryProject Summary
External TasksExternal Milestone
Deadline
Page 3
Project: Work break down structure,JGDate: Tue 03-05-11
8/7/2019 Microsoft Office Project - Document Print
4/21
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S16 Jan '11 23 Jan '11 30 Jan '11 06 Feb '11 13 Feb '11 20 Feb '11 27 Feb '11 06 Mar '11 13 Mar '11 20
TaskSplit
ProgressMilestone
SummaryProject Summary
External TasksExternal Milestone
Deadline
Page 4
Project: Work break down structure,JGDate: Tue 03-05-11
8/7/2019 Microsoft Office Project - Document Print
5/21
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S16 Jan '11 23 Jan '11 30 Jan '11 06 Feb '11 13 Feb '11 20 Feb '11 27 Feb '11 06 Mar '11 13 Mar '11 20
TaskSplit
ProgressMilestone
SummaryProject Summary
External TasksExternal Milestone
Deadline
Page 5
Project: Work break down structure,JGDate: Tue 03-05-11
8/7/2019 Microsoft Office Project - Document Print
6/21
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S16 Jan '11 23 Jan '11 30 Jan '11 06 Feb '11 13 Feb '11 20 Feb '11 27 Feb '11 06 Mar '11 13 Mar '11 20
TaskSplit
ProgressMilestone
SummaryProject Summary
External TasksExternal Milestone
Deadline
Page 6
Project: Work break down structure,JGDate: Tue 03-05-11
8/7/2019 Microsoft Office Project - Document Print
7/21
Arch/Structural
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T Far '11 27 Mar '11 03 Apr '11 10 Apr '11 17 Apr '11 24 Apr '11 01 May '11 08 May '11 15 May '11 22 May '11
TaskSplit
ProgressMilestone
SummaryProject Summary
External TasksExternal Milestone
Deadline
Page 7
Project: Work break down structure,JGDate: Tue 03-05-11
8/7/2019 Microsoft Office Project - Document Print
8/21
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T Far '11 27 Mar '11 03 Apr '11 10 Apr '11 17 Apr '11 24 Apr '11 01 May '11 08 May '11 15 May '11 22 May '11
TaskSplit
ProgressMilestone
SummaryProject Summary
External TasksExternal Milestone
Deadline
Page 8
Project: Work break down structure,JGDate: Tue 03-05-11
8/7/2019 Microsoft Office Project - Document Print
9/21
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T Far '11 27 Mar '11 03 Apr '11 10 Apr '11 17 Apr '11 24 Apr '11 01 May '11 08 May '11 15 May '11 22 May '11
TaskSplit
ProgressMilestone
SummaryProject Summary
External TasksExternal Milestone
Deadline
Page 9
Project: Work break down structure,JGDate: Tue 03-05-11
8/7/2019 Microsoft Office Project - Document Print
10/21
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W29 May '11 05 Jun '11 12 Jun '11 19 Jun '11 26 Jun '11 03 Jul '11 10 Jul '11 17 Jul '11 24 Jul '11 31 Jul '11
TaskSplit
ProgressMilestone
SummaryProject Summary
External TasksExternal Milestone
Deadline
Page 10
Project: Work break down structure,JGDate: Tue 03-05-11
8/7/2019 Microsoft Office Project - Document Print
11/21
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W29 May '11 05 Jun '11 12 Jun '11 19 Jun '11 26 Jun '11 03 Jul '11 10 Jul '11 17 Jul '11 24 Jul '11 31 Jul '11
TaskSplit
ProgressMilestone
SummaryProject Summary
External TasksExternal Milestone
Deadline
Page 11
Project: Work break down structure,JGDate: Tue 03-05-11
8/7/2019 Microsoft Office Project - Document Print
12/21
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W29 May '11 05 Jun '11 12 Jun '11 19 Jun '11 26 Jun '11 03 Jul '11 10 Jul '11 17 Jul '11 24 Jul '11 31 Jul '11
TaskSplit
ProgressMilestone
SummaryProject Summary
External TasksExternal Milestone
Deadline
Page 12
Project: Work break down structure,JGDate: Tue 03-05-11
8/7/2019 Microsoft Office Project - Document Print
13/21
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M07 Aug '11 14 Aug '11 21 Aug '11 28 Aug '11 04 Sep '11 11 Sep '11 18 Sep '11 25 Sep '11 02 Oct '11 09 Oct '
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 13
Project: Work break down structure,JGDate: Tue 03-05-11
8/7/2019 Microsoft Office Project - Document Print
14/21
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M07 Aug '11 14 Aug '11 21 Aug '11 28 Aug '11 04 Sep '11 11 Sep '11 18 Sep '11 25 Sep '11 02 Oct '11 09 Oct '
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 14
Project: Work break down structure,JGDate: Tue 03-05-11
8/7/2019 Microsoft Office Project - Document Print
15/21
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M07 Aug '11 14 Aug '11 21 Aug '11 28 Aug '11 04 Sep '11 11 Sep '11 18 Sep '11 25 Sep '11 02 Oct '11 09 Oct '
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 15
Project: Work break down structure,JGDate: Tue 03-05-11
8/7/2019 Microsoft Office Project - Document Print
16/21
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S1 16 Oct '11 23 Oct '11 30 Oct '11 06 Nov '11 13 Nov '11 20 Nov '11 27 Nov '11 04 Dec '11 11 Dec '11
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 16
Project: Work break down structure,JGDate: Tue 03-05-11
8/7/2019 Microsoft Office Project - Document Print
17/21
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S1 16 Oct '11 23 Oct '11 30 Oct '11 06 Nov '11 13 Nov '11 20 Nov '11 27 Nov '11 04 Dec '11 11 Dec '11
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 17
Project: Work break down structure,JGDate: Tue 03-05-11
8/7/2019 Microsoft Office Project - Document Print
18/21
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S1 16 Oct '11 23 Oct '11 30 Oct '11 06 Nov '11 13 Nov '11 20 Nov '11 27 Nov '11 04 Dec '11 11 Dec '11
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 18
Project: Work break down structure,JGDate: Tue 03-05-11
8/7/2019 Microsoft Office Project - Document Print
19/21
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T18 Dec '11 25 Dec '11 01 Jan '12 08 Jan '12 15 Jan '12 22 Jan '12 29 Jan '12 05 Feb '12 12 Feb '12 19 Feb '12
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 19
Project: Work break down structure,JGDate: Tue 03-05-11
8/7/2019 Microsoft Office Project - Document Print
20/21
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T18 Dec '11 25 Dec '11 01 Jan '12 08 Jan '12 15 Jan '12 22 Jan '12 29 Jan '12 05 Feb '12 12 Feb '12 19 Feb '12
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 20
Project: Work break down structure,JGDate: Tue 03-05-11
8/7/2019 Microsoft Office Project - Document Print
21/21
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T18 Dec '11 25 Dec '11 01 Jan '12 08 Jan '12 15 Jan '12 22 Jan '12 29 Jan '12 05 Feb '12 12 Feb '12 19 Feb '12
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 21
Project: Work break down structure,JGDate: Tue 03-05-11