1MICE CM15 Alain Blondel 8 June 2006
MICE CM 15
Collaboration meeting 8-11 June 2006 at Fermilabcomplete review of the project.
today: -- reviews and progress-- new collaborators -- goals of the meeting
thanks to Alan Bross, Malcolm Ellis, Jean-Sebastien Graulich and Jim Norem for organisation of the meeting and agenda
2MICE CM15 Alain Blondel 8 June 2006
MICE and the big picture
There is a lot of discussion on neutrinos among the highest priorities in particle physics:Neutrino masses ARE new physics and desserve a dedicated programme
Both the EP2010 and the CERN Council Strategy Document emphasizethe need for
1. a coordinated accelerator neutrino oscillation programme at an intercontinental level.
2. (especially in the CERN report:) high priority for related R&D(i.e. 5th) -- LHC commission to design luminosity -- preparation for LHC upgrade -- CLIC-- high performance magnets -- a strong participation in the R&D towards a high intensity neutrino facility
Of Course in MICE we are doing just that:
R&D towards a high intensity neutrino facility at an international level.
3MICE CM15 Alain Blondel 8 June 2006
main news on reviews
-- tracker review : 20 April 2006 good progress. Understanding of light loss at 10% level, procedures proposed to fix it and to implement quality control. Will go through construction of scintillating fiber planes and verify quality once the first one is ready (exp date: September) Pointed out the need for a good definition and methodology for MICE alignment.EXPECT TRACKER TO BE WELL ON TIME
-- Beam line review: to take place at the MICE collab. meeting Monday 12 June
-- Target review: to take place at the MICE collab. meeting Monday 12 Junetest was delayed to October 2006. This is only acceptable because start of MICE slipped… … no more slippage acceptable.
-- Spectrometer solenoid review: to take place todaySC wire has been purchased. Bids for construction of the magnet have been received. To be chosen by LBNL. Consistency of chosen offer with MICE requirements will be reviewed.
4MICE CM15 Alain Blondel 8 June 2006
D&S Reviewsa very important process in MICE!
5MICE CM15 Alain Blondel 8 June 2006
-- PID: Test beam in Frascati July 2006!
EMCal Kloe module in construction, more scintillator behind
TOF TOF0 BC420 counters and lightguides are ready. (Cheaper Ukrainian scintillator will also be tested)
Readout options 1) TDC+CF discriminator, 2) splitter+TDC +ADC ) will be tested.
-- PID Downstream PID change request (no more CKOV2 -- size of TOF2/EMCAL?)CKOV1 proposal now ready
-- DAQ: Readout in view of Frascati beam test in July 2006
on the longer run: use of ALICE framework (DATE)?
6MICE CM15 Alain Blondel 8 June 2006
New collaborators and funding news:
Japanese bid (by Y. Mori U. Kyoto) was not approved for 2006 (tracker, L.H2 absorber) will re-apply next year.
Italy: will be discussed after test beam if that is succesful (TOF, E-M-Cal)
UK: MICE phase II bid in preparation
7MICE CM15 Alain Blondel 8 June 2006
MICE RF power station from CERN
Request was submitted to CERN AB division and approved - 170kCHF and 3 man months
response from CERN DG:
Dear Steve,
- MICE: your memo of 13 April 2006 Contribution to the refurbushing and commissioning of two 200 MHz high power RF amplifiers
Agreement from the DG to use resources from CERN to the level of 3 man/month of CERN staff and 173 kCHF
and only if UK is contributing for CLIC
8MICE CM15 Alain Blondel 8 June 2006
New collaborators and funding news (ctd):
Better news:
-- excellent report by MUTAC!-- DOE has agreed to 300k$ of supplemental funds for the MUCOOL Coupling Coil (CC)(still waiting for the answer of NSF on the CC request)
New collaborators will apply to join MICE at the CM 15:
-- New Hampshire (U. Bravar et al.) simulation, optics, analysis
-- Cockcroft Inst.& Lancaster University (R. Seviour) RF cavity surface studies
-- ICST Harbin in People’s Republic of China (Lin Jia, Li Wang)
9MICE CM15 Alain Blondel 8 June 2006
Dr Lin Jia DirectorDr Li Wang Associate-Director
Dr Lin Jia (also US passport) will be joining the collaboration meeting in Fermilab to apply to the MICE CB
great credit to be given to Mike Green(LBNL) !
10MICE CM15 Alain Blondel 8 June 2006
funding and manpower for engineering is available, funding for construction will need to be submitted to government. expected time to completion ~18-24 mo.
If this goes through, one of the main uncertainties for MICE phase II will have a solution in sight.
11MICE CM15 Alain Blondel 8 June 2006
PHASE II preparation
Some key issues are
-- LH2 R&D @ RAL (safety review was passed -- actions pending)
-- MUCOOL RF cavity R&D @ FNAL construction of 200 MHz cavity and power up have been major milestones for MICE
Operation of RF cavity in magnetic field is the most wide open scientific question in MICE RF noise, field emission, max field?
we will hear more about this and possibly first measurement results?
+ simulation and analysis work (step III, and following ones)
12MICE CM15 Alain Blondel 8 June 2006
of MICE and MANX
MANX LOI was submitted in may 2006 to Fermilab
MANX is a cooling system based on a helicoidal focusing channel a very challenging magnet (3-5m long SC) around L.He. absorbers. Claim of 500% cooling (vs 10% for MICE) incl. long. emittance reduction.
It is suggested that MANX can eventually be tested in the RAL muon beam, using the spectrometers and diagnostics of MICE Caveats:-- the matching of all this has not been completely demonstrated-- the gauge ‘how much beam is cooled’ may not be the same between MANX LOI and MICE-- re-acceleration of muons after such cooling requires matching to RF cavity modules such as those of MICE -- not demonstrated either -- MICE is an approved experiment (this was hard enough!) and will be completed as proposed
Given these caveats, we certainly support MANX and wish it success, as a possible follow-up on MICE. Looking forward to fruitful collaboration (more on this in this meeting)
« PHASE III: »
13MICE CM15 Alain Blondel 8 June 2006
NEWS since Osaka:The ISIS shut down has been delayed
NEW « FIRST BEAM DATE » FOR MICE: 1 October 2007
(this is infortunate for outside university groups for whom summer is ’special’)
15 March: The IMC has agreed yesterday to start the long shutdown in December 2006. This means that there will be an extra cycle 2006/5 this year, starting on 14 November and ending on 18 December 2006.
During the long shutdown, the new EPB to the second target station will be installed and the problems with some of the magnets in EPB1 will be addressed. This work and more will go on from January 2007 to August 2007. During September 2007 there will be commissioning of part of the EPB2 and TS1 with beam. The first user cycle 2007/1 is expected to start on 1 October 2007.Every effort should be made to carry out all proposals submitted & accepted in the current call before the end of 2006, so that we go with a clean slate into the long shutdown. There will be no Call for Proposals in October 2006. The proposal round in April 2007 with FAPs in June 2007 will determine the programme from October 2007 onwards. The user community will be informed of this in the current call for proposals.
14MICE CM15 Alain Blondel 8 June 2006
Thus we have *480* days to data taking
However:this increases the pressure on us to do everyting swiftly once we have the beam: less time for phase I and II!
Preparations (DAQ, reconstruction, Software, procedures and detectors) hace to be prepared longer in advance…
15MICE CM15 Alain Blondel 8 June 2006
STEP I: 1 October 2007 = 480 days away!
STEP II: soon after (a few months)
PHASE I
MAIN GOAL of meeting: Understand where we stand in our preparations for Steps I and II. -- beam line: target, optics, tuning and correction abilities, diffuser -- TOF, Cherenkov1, EMCAL (size of shield&TOF2&EMCAL must be decided)-- tracker-- spectrometer solenoid -- installation and cabling-- controls and monitoring-- trigger, DAQ and event processing-- software: upstream and downstream particle ID, reconstruction of tracks-- analysis: form run plan, reconstruction of « beam», emittance, transmission