MiMinneapolis Community and Technical College Workforce Project
WORKFORCE PROJECT TEAM
Scott EricksonMike Christenson
Roger BrozRoger Wolff – Pegasus Group, Owner’s RepresentativeSteve Albertson – Cuningham Group, Project Architect
Chris Frank – Mortenson, Project ManagerLane Schoening – Mortenson, Superintendent
Jerry Wallerius – Braun Intertec, Asbestos Abatement ConsultantGreg Olson – Braun Intertec, Air Monitoring Consultant
GEN FUND PROJECTS
$12,144,242
HEAPR PROJECTS (including Kitchen remodeling)
$14,329,234
BONDS PROJECTS (including Library, Colocation and Science building projects)
$46,080,327
REVENUE PROJECTS (Student Center project)
$9,599,823
MCTC Mobilization Mobilize, Temp partitions, & set-up construction office
August August AugustExterior Partitions 6 7 8 9 10 13 14 15 16 17 20 21 22 23 24
MCTC to relocate bike racks at dumpster route prior to Aug 6th
Install construction signage and safety cones x Yard truck delivery x Build exterior partitions and fencing x x x Set scaffold and dumpster x x x
Set Up Construction office Install plan tables racks and furniture x x x x x x x x x x x x x xSet up "E systems" and phone x x x x x
Install temp partitions Install partitions Plaza level at freight elevator x x x Install partitions Plaza level at elevators x x Install partitions Skyway level at elevators x x
Install temp partitions Install partitions 4th level x x x Install partitions 5th level x x x All temp partitions to include signage
All construction areas to have dust collection
Mats at main entry/exit point